Agenda Item
b. Contract ~ Capital Improvement Project (CIP): RFQu No. 26-752-005 ~ Dunwoody High School Stadium Improvements Project ~ Construction Management at Risk (CMAR) ~ SmithBuilt Construction Company (Not to Exceed $5,000) ~ Updated 8.7.2026
Summary: Presented by: Mr. Darrell P. Stallings, Chief of Capital Improvements, Division of Capital Improvements
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve the award of RFQu No. 26-752-005 for Construction Management At-Risk Services (“CM@Risk”) for the Dunwoody High School Stadium Improvements Project to SmithBuilt Construction for a not-to exceed amount of $5,000 for pre-construction services.
Pre-construction services will only move forward after receipt of a $5,000 donation for pre-construction services from The Dunwoody High School Community Association, Inc., subject to approval by the Interim Superintendent, in accordance with Board Policy DFK.
Why: Approval of this award will allow the Construction Manager to develop a Guaranteed Maximum Price (GMP) for construction of the project. After development and approval of the GMP by the DeKalb County Board of Education and the Dunwoody High School Community Association, Inc. the parties will enter into a final binding agreement as outlined in the Memorandum of Understanding of August 11, 2025.
The project will provide a safe and healthy learning environment for students and staff.
Details: As Project Sponsor, The Dunwoody High School Community Association, Inc. will provide funding for design and construction of the project. The DeKalb County Board of Education will provide project management and testing and inspection services for quality assurance. After execution of the agreement and receipt of full funding from The Dunwoody High School Community Association, Inc. to the DeKalb County School District, a separate Board Action Item will be presented to authorize the Construction Manager At-Risk to proceed with construction.
Specific details related to the scope of work for this Request for Qualifications can be found on the District’s solicitation website at http://www.dekalbschoolsga.org/solicitations/.
The scope of the additions includes the following:
Addition of bleachers, press box, public address system, and audio/visual equipment
Addition of new concession stands with restroom facilities and storage areas
The project architect is Bianchi Architecture and Interior Design, under contract directly with The Dunwoody High School Community Association, Inc. The design drawings and permitting process are in the final stages. The DCSD Evaluation committee has completed the procurement process and recommends SmithBuilt Construction Group as the Construction Manager at Risk.
The SmithBuilt Construction Company will be responsible for the Construction Management At-Risk services as set forth in the proposal documents. The DeKalb County School District’s Standard Form of Construction Management Contract will be used. The award of this contract will allow for the commencement of the pre-construction phase of the construction management services for this project.
The SmithBuilt Construction Company is located at 2300 Lakeview Pkwy Ste 200, Alpharetta, GA 30009.
Financial impact: The District will accept the donation of $5,000 from the Dunwoody Community Association, LLC. to fund the Dunwoody High School Stadium Improvement project.
Contact: Mr. Darrell Stallings, Chief of Capital Improvement, Division of Capital Improvements, 404.861.0533
Mr. Erick Hofstetter, Chief of Operations, Division of Operations, 678.676.1470
Mr. Byron Schueneman, Chief Financial Officer, Division of Finance, 678.676.0133
Mr. Artis Johnson, HPM Program Director, Division of Operations, 404.790.8985
Effective: Upon Board Approval and a Fully Executed Contract
Status: Approved by the Office of Legal Affairs
,
MEMORANDUM OF UNDERSTANDING
between
DEKALB COUNTY BOARD OF EDUCATION
and
THE DUNWOODY HIGH SCHOOL COMMUNITY ASSOCIATION, INC., A GEORGIA (501c3) NON-
PROFIT CORPORATION
This Memorandum of Understanding (“MOU”) is entered into this __11th____ day of
__August________, 2025 (“Effective Date”) between the DeKalb County Board of Education
(“DCBOE”) and The Dunwoody High School Community Association, Inc.(“Project Sponsor”) is
hereby entered into for the purpose of memorializing preliminary discussions concerning the ___
Dunwoody Additional Seating _________________ (“Project”). This MOU is not intended to create
legal obligations on either Party but contemplates that further legally binding agreements would be
entered into by the Parties in the event that both Parties desire to continue with the Project as set
forth herein.
PROJECT SPONSOR: The Dunwoody High School Community Association, Inc.
a Georgia (501c3) Non-profit Corporation.
I. MOU SUMMARY:
A. The Dunwoody High School Community Association, Inc desires to donate 100% time and
materials for designing and constructing a Bleacher Seating System at the existing athletic
field located at Dunwoody High School, 5035 Vermack Road, Dunwoody, GA 30338 of the
DeKalb County School District.
B. The Dunwoody High School Community Association, Inc. desires support and future
approval of this donation from DCBOE prior to making any time and material investments
necessary to complete the Design phase of the PROJECT
II. The DCBOE and PROJECT SPONSOR agree as follows:
A. Will work collaboratively to meet the goals of the PROJECT through this MOU
B. Understand this MOU serves as a non-binding agreement with donation stipulations
included in this document
C. Will require a final approved binding agreement at a future date inclusive of PROJECT
SPONSOR 100% funding evidence and commitment of the Project along with a complete
set of plans. The construction plans for the Project, once approved (the “Approved Plans”)
shall be deemed DCBOE and DCSB’s approval that, once constructed, the Project is
permitted for use of the stadium for varsity home football games for Dunwoody High
School.
D. All procedures, practices, obligations, donations, and other requests will, as applicable or
required, be in accordance with and in compliance with all DCBOE policies and regulations
including, but not limited to:
1
1) Board Policy DFK: Gifts and Bequests
2) Board Policy DJE: Purchasing
3) Board Policy FDC: Naming Facilities
4) Board Policy KG: Use of School Facilities
5) Board Policy KJ: Advertising in the Schools
III. The PROJECT SPONSOR will undertake and complete the following tasks:
A. Provide development for the complete scope of the PROJECT, at no cost to DCBOE.
B. The goal of the construction of a Bleacher Seating System is to provide additional capacity
at the existing athletic field, the football/soccer, track complex more specifically and to
allow the stadium to host Dunwoody High School home football games.
C. Contract(s) with one or more vendors for the design and construction of the new Bleacher
Seating System, to include all infrastructure and other physical plant improvements set
forth in the approved plans and as may be required by law (concrete, electric, data,
plumbing, ADA, etc.) to receive a certificate of occupancy or similar approval.
1) Enter into a written agreement with one or more vendors for the complete Project
scope.
2) Identify the responsible party as the PROJECT SPONSOR on all forms.
3) Submit these written agreements and any proposed construction plans to the DCSD
Capital Improvements Office in advance for approval of all plans and other required
documents (each, once approved, is an “Approved Contract”).
D. Obtain and pay-for required construction and related permits from local authorities.
E. Be responsible for maintenance, utilities, and repairs to the PROJECT through and until
completion and close out.
F. Be responsible for and be obligated to payment of maintenance costs and up-keep of the
new bleacher seating system and other physical plant improvements, including the new
power meter and any associated monthly power costs through project completion.
G. Transfer all warranties to the DCSD related to the PROJECT
H. Provide all architectural, engineering, and construction documents to the DCSD Capital
Improvements Office at project close-out.
I. Provide all PROJECT financial records to the DCSD upon request and at project close-out.
J. Provide and maintain insurance as required by DCBOE, including “all-risk” property
insurance in an amount equal to the replacement cost of the Project. Ensure contractors
performing the construction, installation and/or maintenance portion of the Project have
and maintain liability and workers compensation insurance in amounts acceptable to
DCBOE. All insurers shall be licensed to do business in the State of Georgia. DCBOE shall
be named as an additional insured on all liability and property insurance policies.
K. Comply with all applicable laws, regulations, and other legal requirements applicable to the
Project including without limitation the Georgia Public Construction Works law, O.C.G.A.
§36-91-1, et. seq., the Georgia Security and Immigration Compliance Act, O.C.G.A. §13-10-
91, et. seq., Georgia Board of Education Rule FED (2), all applicable Georgia contractor
licensing laws, and DCBOE policies. Project Sponsor acknowledges that such laws,
regulations, and legal requirements may require, among other actions, public
advertisement and competitive bidding of the construction and installation portion of the
2
Project, performance and payment bonds for the Project, the provision of an e-verify
affidavit by Project Sponsor and the collection of executed e-verify affidavits from all
contractors and subcontractors of Project Sponsor.
L. Indemnify and hold harmless DCBOE and DeKalb County School District (“DCSD”) from
and against any and all claims of every kind or nature arising out of or in connection with the
construction of the Project, except to the extent caused by the negligence or gross conduct
of DCBOE or DCSD or any of their agents, employees, contractors or representatives.
M. PROJECT DRAWINGS AND SPECIFICATIONS: Any and all agreements, drawings and/or
specifications shall be supplied by the PROJECT SPONSOR’S vendor to the DCSD Capital
Programs Office for written approval before commencement of any work.
IV. DCBOE will:
A. Pledge support and commitment to approve donation upon final approval of design plans
and PROJECT SPONSOR 100% funding assurance
B. Provide a DCSD Capital Improvements Project Manager to assist, guide, and approve all
required plans, scope, sequence and capital improvement procedures, at no cost to the The
Dunwoody High School Community Association, Inc.
C. Provide access to copies of any existing plans, surveys, and other related engineering and
construction related documents supporting the proposed construction area as indicated on
Exhibit A (attached) (DHS New Seating Map 6-23-2025.pdf).
D. Provide related DCSD design and educational specifications.
E. Provide an approved testing & inspections firm to ensure compliance with direct and
indirect construction tasks for quality assurance at no cost to the PROJECT SPONSOR
F. Confirm that DCBOE is the sole governing body for which approval of the PROJECT is
necessary on behalf of the owner of the underlying property.
G. In the season immediately following completion of the Project, DCBOE and DCSD shall
schedule GHSA events for Dunwoody High School varsity football at the stadium.
V. PROJECT SCOPE:
A. The stadium Location and general layout will be in general conformance with Exhibit A
(attached) (DHS New Seating Map 6-23-2025.pdf)
B. Seating capacity of approximately 2,000 seats
C. The project will include a press box and all audio/visual equipment, public address system,
data systems, and required needed infrastructure to make the public address system
operational
D. Ancillary features such as sidewalks, stairs, fencing, plazas, lighting, signage, and other
components necessary to integrate the stadium into the surrounding area are permitted but
not required unless required by law.
E. Additional structures including, but not limited to, storage areas, concession stands, and
restrooms are permitted but not required as part of the initial stadium construction.
3
Neither DCSD nor DCBOE may require the addition of any discretionary scope of work to
the Project following approval of the Approved Plans, except as may be required to comply
with applicable laws and/or to address unforeseen site conditions.
F. The project may incorporate signage, monuments, or other features to recognize and
display donor names in accordance with the provisions of DCBOE Policy KJ: Advertising in
the Schools and associated policies and regulations.
VI. PROJECT FUNDING:
A. Approximately $1,750,000.00 inclusive of all design, construction, equipment, permitting,
and installation costs, which sum shall be funded 100% through and by the The Dunwoody
High School Community Association, Inc.
B. The DCBOE and the DCSD will not have any obligation to fund any part of the construction
of PROJECT.
C. DCBOE acknowledge that the PROJECT SPONSOR intends to name the Project in honor of
an individual or family. DCBOE shall have the right to approve the proposed name of the
PROJECT prior to commencement of construction for the Project in accordance with
DCBOE Board Policy FDC: Naming Facilities and all associated policies and regulations.
VII. PROJECT TIME:
A. Construction and Installation: Approximately 12 months from approval of the Approved
Plans and Approved Contracts by DCSD Capital Programs Office.
B. Maintenance: Ongoing through the customary capital life of the bleacher seating system.
VIII. PROJECT OWNERSHIP AND OPERATIONAL COST:
A. Upon completion and close out of the PROJECT, any and all capital, physical plant, and
grounds improvements completed during this project by the PROJECT SPONSOR will
transfer ownership and operational costs to the DCSD. The improvements will be added to
the asset inventory where required.
B. The assets will be placed on an operational maintenance plan by DCSD to always keep it in
safe and in operational conditions. Ongoing maintenance costs will be budgeted by DCSD
for the customary capital life of the improvements.
IX. TERM:
This MOU shall have a term of twelve (12) months from the Effective Date of this Agreement but the
parties may renew this MOU for up to two (2) additional one-year terms upon approval of DCBOE.
X. RIGHT TO TERMINATE: If either party reasonably determines that the PROJECT is no longer
feasible or cannot be completed as contemplated by this MOU, that party shall provide written
4
notice to the other party of the condition giving rise to the concern. If the condition is not cured
by the other party to the complaining party’s reasonable satisfaction within 10-days of receipt
of said written notice, the complaining party may terminate this MOU upon 30-days written
notice to the other party.
XI. NON-BINDING:
This MOU is not intended to create any legally binding obligations or liabilities between the
Parties but shall serve as a statement of preliminary understanding and intent to collaborate.
Any binding obligations will arise only upon execution of separate, definitive agreements or
contracts specifically addressing those obligations.
This MEMORANDUM OF UNDERSTANDING is hereby agreed to by:
1. Project Sponsor: ____________________________________ Date___________
President/Authorized Officer
2. Superintendent of Schools ______________________________ Date____________
3. Board Chair ______________________________ Date____________
5