Revised RFQu 26-752-005 CM at Risk Dunwoody HS Stadium Improvements (1)

AID 2047649 · View on Simbli

Agenda Item

b. Contract ~ Capital Improvement Project (CIP): RFQu No. 26-752-005 ~ Dunwoody High School Stadium Improvements Project ~ Construction Management at Risk (CMAR) ~ SmithBuilt Construction Company (Not to Exceed $5,000) ~ Updated 8.7.2026

Summary: Presented by: Mr. Darrell P. Stallings, Chief of Capital Improvements, Division of Capital Improvements
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve the award of RFQu No. 26-752-005 for Construction Management At-Risk Services (“CM@Risk”) for the Dunwoody High School Stadium Improvements Project to SmithBuilt Construction for a not-to exceed amount of $5,000 for pre-construction services.

Pre-construction services will only move forward after receipt of a $5,000 donation for pre-construction services from The Dunwoody High School Community Association, Inc., subject to approval by the Interim Superintendent, in accordance with Board Policy DFK.
Why: Approval of this award will allow the Construction Manager to develop a Guaranteed Maximum Price (GMP) for construction of the project. After development and approval of the GMP by the DeKalb County Board of Education and the Dunwoody High School Community Association, Inc. the parties will enter into a final binding agreement as outlined in the Memorandum of Understanding of August 11, 2025.

The project will provide a safe and healthy learning environment for students and staff.
Details: As Project Sponsor, The Dunwoody High School Community Association, Inc. will provide funding for design and construction of the project. The DeKalb County Board of Education will provide project management and testing and inspection services for quality assurance. After execution of the agreement and receipt of full funding from The Dunwoody High School Community Association, Inc. to the DeKalb County School District, a separate Board Action Item will be presented to authorize the Construction Manager At-Risk to proceed with construction.

Specific details related to the scope of work for this Request for Qualifications can be found on the District’s solicitation website at http://www.dekalbschoolsga.org/solicitations/.

The scope of the additions includes the following:

Addition of bleachers, press box, public address system, and audio/visual equipment
Addition of new concession stands with restroom facilities and storage areas

The project architect is Bianchi Architecture and Interior Design, under contract directly with The Dunwoody High School Community Association, Inc. The design drawings and permitting process are in the final stages. The DCSD Evaluation committee has completed the procurement process and recommends SmithBuilt Construction Group as the Construction Manager at Risk.

The SmithBuilt Construction Company will be responsible for the Construction Management At-Risk services as set forth in the proposal documents. The DeKalb County School District’s Standard Form of Construction Management Contract will be used. The award of this contract will allow for the commencement of the pre-construction phase of the construction management services for this project.

The SmithBuilt Construction Company is located at 2300 Lakeview Pkwy Ste 200, Alpharetta, GA 30009.
Financial impact: The District will accept the donation of $5,000 from the Dunwoody Community Association, LLC. to fund the Dunwoody High School Stadium Improvement project.
Contact: Mr. Darrell Stallings, Chief of Capital Improvement, Division of Capital Improvements, 404.861.0533
Mr. Erick Hofstetter, Chief of Operations, Division of Operations, 678.676.1470
Mr. Byron Schueneman, Chief Financial Officer, Division of Finance, 678.676.0133
Mr. Artis Johnson, HPM Program Director, Division of Operations, 404.790.8985
Effective: Upon Board Approval and a Fully Executed Contract
Status: Approved by the Office of Legal Affairs
DeKalb County School District                                                       Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                            Project No. N/A
April 2, 2026                                                                                      Page 1 of 21


                                      DeKalb County Board of Education
                                      Operations Division
                                      Sam A. Moss Service Center
                                      1780 Montreal Road
                                      Tucker, GA 30084-6705

                          Revised Request for Qualifications (RFQu) No. 26-752-005
                                                     for
                                    Construction Management at Risk
                               Dunwoody High School Stadium Improvements
Project:                        Dunwoody High School Stadium Improvements
DCSD Project Nos.:              N/A
Owner:                          DeKalb County Board of Education (the “Board”)
Solicitation Timeline Summary
              EVENT                           DATE(S)              TIME                        LOCATION

  Solicitation Opens                         April 2, 2026                          http://dekalbschoolsga.ionwave.net
  Mandatory Pre-Submittal
                                            April 21, 2026        2:00 PM                      Via Teams
  Conference
                                                                                         Dunwoody High School
  Mandatory Site Visit                      April 23, 2026       10:00 AM
                                                                                 5035 Vermack Rd., Dunwoody, GA 30338

  Final Questions Due                       April 29, 2026        2:00 PM        dcsd-op-bidquestion@dekalbschoolsga.org

  Final Addendum                             May 7, 2026          2:00 PM           http://dekalbschoolsga.ionwave.net
  Statement of Qualifications
                                            May 14, 2026          2:00 PM          http://dekalbschoolsga.ionwave.net
  Due Date & Time
                                                                                 Public Acknowledgement of RFQu will be
  Public Acknowledgement                    May 15, 2026                          posted to the DCSD website by close of
                                                                                                 business.
  Selection Committee
                                           May 18-22, 2026
  Evaluation

  Shortlist Finalist Notified                    N/A

  Interviews Conducted                           N/A
  Anticipated Board Review
                                            July 13, 2026
  and Approval

  Anticipated Notice of Award               July 22, 2026

  Anticipated Notice to
                                            August 3, 2026
  Proceed
DeKalb County School District                                                    Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                         Project No. N/A
April 2, 2026                                                                                   Page 2 of 21
                               Request for Qualifications and
                                  Evaluation Procedures

                         Construction Management at Risk Services
                       Negotiated Fee / Guaranteed Maximum Price


Qualifications will be received electronically on the DeKalb County School District website at
https://dekalbschoolsga.ionwave.net for CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR
DUNWOODY HIGH SCHOOL STADIUM IMPROVEMENTS, until 2:00 p.m. EST, Thursday, May 14, 2026.
Qualifications received after the specified time will not be considered. All potential respondents must register
as a vendor at http://dekalbschoolsga.ionwave.net. NOTE: A virtual mandatory pre-submittal conference will
be held on Tuesday, April 21, 2026, 2:00 p.m., EST, via TEAMS. Attendees must provide the following
information by 5:00 p.m., EST on Monday, April 20, 2026:

    1.   Individual Name and Title
    2.   Company Name
    3.   Telephone Number
    4.   Email Address

This information must be sent to dcsd-op-solicitation@dekalbschoolsga.org. A meeting link will be sent to all
registered attendees no later than 1:30 p.m., EST on Tuesday, April 21, 2026.

This document shall serve to provide interested parties with specific information as to the Procedures for
Selection of Construction Management at Risk Services for the DeKalb County School District.
DeKalb County School District                                                                           Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                                                Project No. N/A
April 2, 2026                                                                                                          Page 3 of 21
 Table of Contents

 Section           Description                                                                                                        PAGE

                   Request for Qualifications:

 1.0               Project Description ............................................................................................... 4
 2.0               Scope of Services ................................................................................................ 4
 3.0               Requirements of Construction Manager............................................................... 6
 4.0               Statement of Qualifications .................................................................................. 7
 5.0               Initial Screening Criteria ....................................................................................... 10
 6.0               Interview and Presentation .................................................................................. 13
 7.0               Selection Process ................................................................................................ 16
 8.0               Schedule .............................................................................................................. 17
 9.0               General Instructions ............................................................................................. 18
 10.0              Terms and Conditions .......................................................................................... 19
                   RFQu Advertisement ........................................................................................... 21


 Attachments (separate file from RFQu)
 Attachment A      Construction Manager Checklist and Certification
 Attachment B1     Corporate Certificate
 Attachment B2     Partnership Certificate
 Attachment B3     Entity Certificate
 Attachment C      Offeror’s and Individuals’ Affidavit of Noncollusion
 Attachment D      Conflict of Interest Disclosure Affidavit
 Attachment E      Consent to Release Information
 Attachment F      Immigration and Security Certification
 Attachment G      No Submittal Response
 Attachment H      Standard Form of Construction Management Contract Dunwoody HS


 Exhibits (separate file from RFQu)
 Exhibit A – Proposal Evaluation Form
     DeKalb County School District                                                      Revised RFQu No. 26-752-005
     CM at Risk Dunwoody High School Stadium Improvements                                           Project No. N/A
     April 2, 2026                                                                                     Page 4 of 21
                       REQUEST FOR CONSTRUCTION MANAGER QUALIFICATIONS

     PROJECT NAME: Dunwoody High School Stadium Improvements

     PROJECT LOCATION: Dunwoody HS – 5035 Vermack Rd., Dunwoody GA 30338
     RFQu NUMBER: 26-752-005

      1.0    PROJECT DESCRIPTION

               1.1     DeKalb County School District, Georgia is interested in entering into a contract with a
                       qualified firm to perform Construction Management at Risk Services as outlined in the
                       contract to be entered into, the form of said contract being attached hereto for Stadium
                       Improvements listed below in the Scope of Services. The CM is responsible for the
                       successful, timely, and economical completion of the construction Project.

               1.2     The Contract(s) shall be subject to the limitations and restrictions of Georgia
                       Code.

               1.3     DCSD has determined that the stipulated fee for the Pre-Construction Phase
                       Services for this project will be a maximum fee of $5,000.00. This fee is all
                       inclusive and incorporates all services provided during the pre-construction
                       phase for this project.

      2.0      SCOPE OF SERVICES
      Dunwoody High School Stadium Improvements

      This project was initiated by Dunwoody High School Community Association, Inc and is known as
      Dunwoody High School Stadium Improvements. The anticipated scope of this project is the installation of
      a new bleacher seating system in the Dunwoody High School football stadium at 5035 Vermack Road,
      Dunwoody, GA 30338.

A.   Stadium improvements include but are not limited to:
           • Installation of a new bleacher seating system.
           • New press box.
           • Improvements/modifications to concrete sidewalks, fencing, electrical, and data.
           • Improvements/modifications to concession stand and bathrooms.

B.   Pre-Construction Phase Services shall include but are not limited to: attending any and all design and
     preconstruction conferences, assisting and cooperating with the Design Professional with respect to the
     design of the Project, reviewing and commenting on design documents, constructability review, advertising
     & conducting pre-bid conference, providing cost estimates & GMP development, preparing construction
     schedule and incorporating design schedule into a single project schedule, refining general requirements
     and general conditions, and documenting “as-is” conditions (including offsite utilities from which
     connections are to be made).

C.   Construction Phase Services include, but are not limited to, furnishing, and paying for all management,
     supervision, financing, labor, materials, tools, fuel, supplies, utilities, equipment, and services of every kind
     and type necessary to diligently, timely and fully perform and complete the construction of the entire
     Project in a good and workmanlike manner in accordance with the Construction Documents.
     DeKalb County School District                                                 Revised RFQu No. 26-752-005
     CM at Risk Dunwoody High School Stadium Improvements                                      Project No. N/A
     April 2, 2026                                                                                Page 5 of 21


D.   Access and operation of Dunwoody High School by DCSD shall not be impacted.

E.   Management of portable classroom installation on site for swing space to be included in CMaR scope and
     GMP.

      A Guaranteed Maximum Price for the Dunwoody High School Stadium Improvements project will be
      agreed upon and approved by the Board of Education and may include early release packages. The
      estimated construction budget for this project will be $2,200,000 and subject to change. The Construction
      Management Firm is to provide all construction management services to deliver to the owner a safe,
      finished, and fully functioning high school facility within the estimated construction budget.

      Target Schedule:
      100% CD Submittal Date: April 2, 2026
      Final GMP Approval: December 2026
      Construction Notice to Proceed Date: January 2027
      Construction: Winter/Spring 2027
      Substantial Completion Date: July 2027



      3.0    REQUIREMENTS OF CONSTRUCTION MANAGER (CM)

              3.1     Firms must meet the following requirements:

                      3.1.1   Requirements of the Request for Qualifications (RFQu).

                      3.1.2   It is preferable that the CM has experience providing construction management
                              at risk for K-12 public school programs.

                      3.1.3   CM’s must be authorized to do business in the State of Georgia and must
                              possess professional service registrations, and general construction licenses
                              in accordance with applicable statutes, regulations, and rules.

                      3.1.4   CM's must be knowledgeable of the requirements of Georgia Code.

                      3.1.5   CM's must be able to demonstrate financial strength appropriate to the scale of
                              Project to be managed.

                      3.1.6   Statements of Qualifications must be submitted to the School District on or before
                              the time and date and at the place indicated in the RFQu.

                      3.1.7   Statements of Qualifications shall be submitted electronically in accordance with
                              the requirements contained in the RFQu and should be limited to not more than
                              30 (8.5-inch x 11 inch) pages printed on one side, including covers and dividers,
                              and excluding financial information. Oversize pages will be counted as two
                              pages. Submissions in excess of 30 pages will not be disqualified; however,
                              clarity, conciseness, and brevity of this document will be part of the evaluation
                              criteria.
DeKalb County School District                                                  Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                       Project No. N/A
April 2, 2026                                                                                 Page 6 of 21


                3.1.8    Statements of Qualification which have not been received by the DeKalb County
                         School District on or before the scheduled receipt time as set forth in the RFQu
                         will not be considered.

                3.1.9    The selected Construction Manager will be required to meet the insurance
                         requirements of DCSD.

                3.1.10 A pre-negotiation meeting and negotiation meeting will be conducted on the
                         date and at the place to be specified at a later date. If agreement is not reached
                         on this date, DCSD will terminate negotiations and proceed to the next highest
                         ranked firm. We will proceed with the number two ranked firm in the event that
                         negotiations are being terminated with the number one ranked firm. At the school
                         district's sole option, the negotiation cutoff date may be extended.

                3.1.11 Costs of participating in the selection process, including presentations to the
                         Selection Committee, are solely those of the CM; DCSD will assume no
                         responsibility for any costs.

                3.1.12 DCSD reserves the right to waive informalities and to terminate the selection
                         process.


       4.0     STATEMENT OF QUALIFICATIONS
               Required Information and Format

       Electronic statements of qualifications shall be submitted to the website
       https://dekalbschoolsga.ionwave.net and include the following:

                    1) Letter of Introduction - To be included with Technical Proposal under “Response
                       Attachments”.
                    2) Table of Contents - To be included with Technical Proposal under “Response
                       Attachments”.
                    3) Compliance - To be included with Technical Proposal under “Response
                       Attachments”.
                    4) Successful Related Building Experience – To be included with Technical Proposal
                       under “Response Attachments”.
                    5) Proposed Project Staff and their Functions - To be included with Technical
                       Proposal under “Response Attachments”.
                    6) Project Approach - To be included with Technical Proposal under “Response
                       Attachments”.
                    6) Current Workload - To be included with Technical Proposal under “Response
                       Attachments”.
        4.1     Letter of introduction and interest signed by an officer or partner of the responding firm.
                Letter shall include specific reason(s) why firm would be the best choice for the project
                listed. Letter shall include name of entity submitting, contact name, phone number, e-
                mail address, fax number and address of firm submitting.
        4.2     Table of Contents
DeKalb County School District                                                 Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                      Project No. N/A
April 2, 2026                                                                                Page 7 of 21
           4.3  Compliance Information
               This is a compliance section and carries no evaluation points. Firms must meet
               minimum criteria as specified to receive further consideration. Submittals shall
               include the following:
               4.3.1   The CM must be properly certified by the Georgia Secretary of State to do
                       business in Georgia at the time of submission.

                       4.3.1.1 State the legal name of the entity submitting and if CM submitting is a
                               corporation, joint venture, or partnership. Note: It is understood that if
                               selected for this project the stated entity name will be used in all legal
                               contracting documents derived from this selection.

                       4.3.1.2 Provide a copy of certification for proper incorporation or registration from
                               Georgia Secretary of State. In the alternative, joint ventures and
                               partnerships should provide a copy of their joint venture or partnership
                               agreement and certification from the Georgia Secretary of State
                               establishing that each joint venture partner or partner is authorized to do
                               business in Georgia.

               4.3.2   The CM must be properly registered, licensed, and certified at the time of
                       submission:

                       4.3.2.1 Provide copy of current Georgia Professional Registration Certificate for
                               general contractor.

                       4.3.2.2 If CM is a joint venture, provide copy of the joint venture agreement and
                               either:

                                    a. Copy of current Georgia Professional Registration Certificate of
                                       the joint venture; or

                                    b. A copy of the current Georgia Professional Registration Certificate of
                                         one of the joint venture partners.

               4.3.3   The CM must have been in continuous business for a minimum of five
                       years. Note: If CM is a joint venture, at least one of the companies
                       comprising the joint venture or partnership must have been in continuous
                       business for a minimum of five years.

                       4.3.3.1 State number of years in business. If the CM is a joint venture, state both
                               the number of years that the joint venture has been in business, as well
                               as the number of years that each joint venture partners has been in
                               business.

                       4.3.3.2 State the location, address, and telephone number of CM’s offices. If the
                               CM is a joint venture or partnership, identify the location, address, and
                               telephone number of the principal place of business of the joint venture
                               or partnership designated with the Georgia Division of Corporations.
               4.3.3.3 Submit the names of owners, officers, or principals in charge.
DeKalb County School District                                                    Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                         Project No. N/A
April 2, 2026                                                                                   Page 8 of 21

               4.3.4    The CM must identify any existing or potential conflicts of interest and disclose
                        any representation of parties or other relationships that might be considered a
                        conflict of interest with regard to this selection. "Conflict" or "conflict of interest"
                        means a situation in which regard for a private interest tends to lead to disregard
                        of a public duty or interest.

                        4.3.4.1 If any conflicts of interest issues are identified, provide a detailed plan
                                 of action on how any existing or potential conflicts of interest will be
                                 mitigated in the case your firm is recommended for this project. DCSD
                                 at its sole discretion shall determine the adequacy of the plan and
                                 whether the conflict will disqualify the firm from consideration for the
                                 RFQu. If DCSD determines that the firm will be disqualified due to the
                                 conflict, the firm’s proposal will not be evaluated or considered by the
                                 Selection Committee

               4.3.5   Financial Capabilities and Cost Control Measures (Y/N):
                       The CM must demonstrate they have the necessary financial resources to
                       complete the project, their capabilities to control costs and their history of working
                       proactively to avoid litigation with Owners.
                                 4.3.5.1 Financial Statement: Include a copy of their most current audited
                                          financial statement. If the CM is a joint venture or partnership
                                          all firms comprising the submitting entity will be required to
                                          submit the previously requested documentation.
                                 4.3.5.2 Bonding Capacity: Evidence of sufficient bonding capacity to
                                        bond $2,200,000. The CM must submit a letter from their insurer
                                        stating their current bonding capacity for a single job and their
                                        aggregate capacity. (The firm will be required to bond on the
                                        guaranteed maximum price for the Project).
              4.3.6    Litigation/Insurance Claims/Convictions (Y/N)

                       4.3.6.1 Submit all litigation of any kind involving Construction Manager, its officers,
                               or directors with a project owner where the total amount in controversy
                               exceeds $100,000.00 within the last five years. If the CM is a joint
                               venture or partnership submit litigation involving all firms comprising
                               the submitting entity. State the court and location of the litigation.

                       4.3.6.2 Insurance Claims: State the number of claims, total worker’s compensation
                               dollars incurred for those claims, and loss cost per man hour for the
                               last five projects your firm has completed. This information should
                               include all claims including, but limited to, the firm’s personnel, and sub-
                               contractors and/or sub-consultants. In addition, firms shall include
                               information about their safety programs.

                       4.3.6.3 Convictions: Include a statement as to whether or not the CM (and in the
                               case of a joint venture, each of the partners in the joint venture) or any of
                               its officers has been convicted or entered a guilty plea (or plea of nolo
                               contendere) in any court within the two (2) years prior to the date of
                               application of a violation of any State or Federal statue concerning
                               competitive bidding or competitive proposals or the restraint of trade.
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                               Page 9 of 21

5.0            INITIAL SCREENING CRITERIA

               5.1     Individual Review: Proposal Evaluation Committee (“PEC”) members shall use the
                       Proposal Evaluation Form (Exhibit A) for the RFQu to document their review and
                       evaluation of each Proposal in accordance with the criteria listed below, within
                       their respective areas of experience and knowledge.

                       5.1.1 Successful Related Building Experience (30 points):
                             Past experience, including examples of renovations, refurbishment,
                             repairs, and new construction projects completed by the firm.
                             Consideration will be given to the successful completion of previous
                             projects comparable in design, scope, and complexity. This will include
                             e valuating the firm’s performance and quality of work on previous
                             projects.

                               5.1.1.1 List the projects which best illustrate the experience of the firm
                                       which utilized the current staff which is being assigned to this
                                       Project. (List no more than 10 projects and do not list projects
                                       which were not completed by your firm or completed more
                                       than ten years ago). Include the following for each project:

                                       a. Name and location of the project.
                                       b. The nature of the firm's responsibility on the project.
                                       c. Project owner's representative name, address,
                                            telephone, and facsimile number.
                                       d. Project user's representative name, address and
                                            telephone number.
                                       e. Date project was completed. Provide comparison of
                                            original schedule completion to actual completion date.
                                       f. Size of project (construction gross square feet).
                                       g. Cost of project (construction cost). Provide comparison of
                                          original contract amount with final contract amount
                                       h. Work for which firm's staff was responsible.
                                       i. Firm's project manager and other key professionals
                                          involved on the project and who of that staff would be
                                          assigned to the Project covered by this RFQu.

                       5.1.2   Proposed Project Staff and their Functions (25 points):
                               The quality, experience and quantity of staff and their functions will be
                               evaluated by the Committee.

                               5.1.2.1 The firm shall name the actual staff to be assigned to this
                                       Project, describe their ability, experience, and indicate the
                                       function of each within their organization and their proposed role
                                       on this Project. It is the intent that the proposed staff shall be
                                       assigned to this Project unless otherwise approved by Owner.
                                       The staff shall be present at the time of interview.

                               5.1.2.2 Organization Chart: Develop an organization chart as it
                                       relates to the Project indicating key personnel and their
                                       relationship.
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 10 of 21
                               5.1.2.3 Give brief resumes of key persons to be assigned to the
                                       Project including, but not limited to, the following:

                                       a. Name and title.
                                       b. How many years with this firm? For sub-consultants, list
                                          prior projects your firm has worked with sub-consultant.
                                       c. How many years with other firms?
                                       d. Experience including types of projects, size of projects (dollar
                                          value and square footage of project), and specific project
                                          involvement.
                                       e. Education.
                                       f. Active registrations (if any).
                                       g. If submitting as a joint venture or partnership, include the
                                          assigned staff for the joint venture or partnership and
                                          indicate which of the joint ventures or partners employs the
                                          staff member.
                      5.1.3   Project Approach (20 points):
                              5.1.3.1 The firm shall provide information regarding its knowledge of
                                      working on active school campuses, local codes and ordinances,
                                      local subcontractors, and suppliers as an indication of its ability to
                                      deliver quality workmanship in an effective and timely manner.
                              5.1.3.2 The firm shall demonstrate verbally and graphically its plan for
                                      performing the Project, documenting the services to be provided
                                      and showing the interrelationships of all parties, including the
                                      District’s consultants, departments (IT, FF&E, Transportation,
                                      Nutrition, etc.) local authorities, architects, and Program Manager,
                                      to name a few. As part of its services, the firm shall indicate
                                      knowledge and experience in the evaluation of building systems,
                                      construction techniques, and the recommendation of materials to
                                      create the optimum value in meeting the design and budget
                                      requirements.
                              5.1.3.3 Schedule: The anticipated construction Notice to Proceed is
                                      January 2027 with a Substantial Completion of Date of July 2027.
                                      Use the dates shown and develop a Preliminary Schedule that you
                                      plan on using to construct this project.
                              5.1.3.4 QA/QC: Describe your experience and technical expertise your firm
                                      will employ with regard to safety, cost and quality assurance and
                                      quality control.

                  5.1.4        Current Workload (10 points):

                               As part of the evaluation criteria, the Committee will review the firms and
                               their sub-consultants’ current workload. If the submitting firm is a joint
                               venture, the Committee will review the current workload of each of the
                               firms comprising the submitting entity. A maximum of ten points will be
                               awarded based on an evaluation of the firm’s total workload and capacity
                               to perform the work.
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 11 of 21


                              5.1.4.1 Firms and their sub-consultant(s) shall provide a list of
                                      outstanding projects, client names, status of completion,
                                      anticipated completion date, and dollars committed on open
                                      project workload. Furthermore, if the submitting firm is a joint
                                      venture, they shall also include projects for each firm
                                      comprising the joint venture.
                                       Definition of sub-consultant as it relates to this selection
                                       process: An individual and/or firm contracted or to be
                                       contracted by the submitting entity to provide services related
                                       to or part of those which this will be required as part of this
                                       selection process.

                       5.1.5 Equitable Distribution (Maximum 15 points):
                             In an effort to consider the equitable distribution of work, the Selection
                             Process Facilitator shall evaluate data showing dollar amounts of contracts
                             and projects awarded by DCSD to the submitting firm(s). The dollar amount
                             of projects awarded will reflect the estimated construction value listed on
                             the RFQu awarded to each firm. The projects taken into account in the
                             calculation will be those awarded by DCSD within two years from this RFQu
                             bid opening. For those projects already under contract, the awarded
                             amount will be replaced by the GMP and/or Bid amount(s) contracted, not
                             including change orders. For projects recommended but not yet awarded,
                             the contract value will reflect the estimated fee based on the budget listed
                             within the RFQu for which the firm was selected. In the case of submittals
                             received by joint ventures, the projects awarded to each of the firms
                             comprising the joint venture will be included in the calculation of the projects
                             awarded by DCSD. Furthermore, this calculation will include all projects
                             awarded to the submitting firm, either as a joint venture or as a separate
                             entity, whereby the submitting firm(s) was one of the entities included in the
                             award and/or contract.
                             5.1.5.1 The chart below will be used to award a maximum of 15 points
                                     based on dollar amount of projects currently under contract, as
                                     well as those awarded by DCSD, but not yet under contract and
                                     those recommended but not yet awarded. This single score will be
                                     allocated to each firm by the Selection Process Facilitator and
                                     added to the cumulative score the committee members.


                             Contract Value Awarded/ Recommended by DCSD                  Point Value
                            0 to $5,000,000                                                15 points
                            $5,000,001 to $10,000,000                                      13 points
                            $10,000,001 to $20,000,000                                     11 points
                            $20,000,001 to $30,000,000                                      9 points
                            $30,000,001 to $50,000,000                                      7 points
                            Greater than $50,000,000                                        0 points
DeKalb County School District                                         Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                Project No. N/A
April 2, 2026                                                                         Page 12 of 21
                5.2     Group Review. The PEC members shall meet and discuss the Proposals. The
                       goal of this review is to allow each PEC member the opportunity to fully discuss
                       the Proposals and to identify any information in the proposals deemed by
                       the PEC member to be significant to the evaluation. At the conclusion of
                       this meeting, each PEC member shall render his or her final scores for each
                       proposal and submit his or her Proposal Evaluation Form to the Selection
                       Process Facilitator.

                       5.2.1   The Selection Process Facilitator shall combine the evaluation scores
                               submitted by all PEC members and shall determine the five (5) highest
                               scoring firms (unless otherwise determined) based on the total
                               evaluation scores received. In the event of a tied score for fifth place, all
                               such tied firms shall be included in the short list.

                       5.2.2   Short List Recommendation. The Selection Process Facilitator shall
                               forward the PEC’s short list recommendation to the Chief Operations
                               Officer (“the COO”). The COO, in his or her sole discretion, can either
                               accept the short list recommendation or reject the short list
                               recommendation. If the COO accepts the recommendation, the selection
                               process proceeds as noted below. If the COO rejects the short list
                               recommendation, he or she, in his or her sole discretion, can proceed
                               in any of the following methods: directing the Selection Process
                               Facilitator to recommence the selection process at whatever stage
                               the COO deems appropriate (including the Individual Review stage or
                               the Group Review stage); pursuing the project by any other alternative
                               method permitted under Georgia law; or abandoning the project all
                               together. If the COO elects to pursue the project by an alternative method
                               or abandon the project, DCSD shall provide public notice of this decision.

                       5.2.3   Notice of Short List. Once the PEC’s short list recommendation has been
                               accepted by the COO, the Selection Process Facilitator will notify all
                               submitting firms of whether or not they appear on the short list and shall
                               provide public notice of the short-listed firms.

                       5.2.4   The short-listed firms shall then be invited for interviews before the PEC,
                               which will be scheduled within three (3) business days of notification.

        6.0     INTERVIEW AND PRESENTATION

                6.1    At the time of its scheduled interview, each short-listed firm shall provide
                       additional information about its firm and operations as may be required by DCSD.
                       This additional information shall include, but is not limited to, the following:

                       6.1.1. References (10 points):
                               The CM must demonstrate a positive relationship with prior clients on
                               similar projects.

                               6.1.1.1 The CM shall submit written recommendations from previous
                                       owners and discuss their strategy to provide a positive working
                                       relationship with DCSD. This strategy must include actual
                                       examples of how the CM has demonstrated their cooperation
                                       with other Owners. DCSD reserves the option of contacting any
DeKalb County School District                                               Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                    Project No. N/A
April 2, 2026                                                                             Page 13 of 21
                                       of the references provided to confirm information provided.

                               6.1.1.2 DCSD staff will provide input on a firm’s past work
                                       performance, this information includes but is not limited to the
                                       number of warranty requests and responsiveness, contract and
                                       process compliance, and information from the DCSD contractor
                                       evaluation process if available.

                       6.1.2   Overall Approach, Methodology and Knowledge of the Site (35 points):

                               6.1.2.1 The firm shall provide information regarding its knowledge of
                                       working on active school campuses, local codes and
                                       ordinances, local subcontractors, and suppliers as an
                                       indication of its ability to deliver quality workmanship in an
                                       effective and timely manner.

                               6.1.2.2 The firm shall demonstrate verbally and graphically its plan for
                                       performing the Project, documenting the services to be provided
                                       and showing the interrelationship of all parties. As part of its
                                       services, the firm shall indicate knowledge and experience in
                                       the evaluation of building systems, construction techniques
                                       and the recommendation of materials to create an optimum
                                       value in meeting the design and budget requirements.

                                      Note: The services to be provided on the Project will include, but
                                      they are not limited to, the Pre-construction, Construction, and
                                      Post Construction Phases.
                       6.1.3 Project Team (15 points):
                             The firm shall express the general and specific project related
                             experience and capability of in-house staff and subconsultants and
                             their functions as it relates to this project.

                               6.1.3.1 Organization Chart: Develop an organization chart as it
                                       relates to the Project indicating key personnel and their
                                       relationship. It shall be understood that it is the intent of the
                                       District to insist that those key personnel indicated as the
                                       project team in this RFQU response actually executes the
                                       Project.

                               6.1.3.2 If a joint venture, or prime subcontractor arrangement of two (or
                                       more) firms, indicate how the work shall be distributed between
                                       the associated firms. Describe how the organizational structure
                                       will ensure orderly communications, distribution of information,
                                       effective coordination of activities and accountability.
                       6.1.4   Cost Control (20 points):

                               6.1.4.1 Describe how you develop cost estimates, and how they are
                                       updated, providing specific examples of successful
                                       recommendations implemented and cost containment strategies
                                       utilized to maintain project budgets without sacrificing quality.
                                       Describe your preconstruction bidding process and explain the
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 14 of 21
                                       benefits to the Owner.

                               6.1.4.2 The firm shall provide a comparison of any representative
                                       current projects demonstrating their ability to hold to original
                                       budgets.

                               6.1.4.3 Provide a list of onsite staff that you propose for this project and
                                       the number of hours that each staff member will work on the
                                       project during the construction phase.

                       6.1.5   Project Scheduling (20 points):

                               6.1.5.1 As part of the project approach, the firm shall propose a
                                       process for scheduling multiple projects and effectively
                                       managing and executing the work in the optimum time.
                                       Provide a sample schedule and describe any major
                                       milestones for achieving the schedule and any other
                                       recommendations that may directly impact the schedule.

                               6.1.5.2 The firm shall describe any representative current projects and
                                       the projected versus the actual schedule for each.

               6.2     Interview

                       6.2.1   The short-listed firms shall be invited for interviews before the PEC. At the
                               time of its scheduled interview, each short-listed firm shall provide
                               additional information about its firm and operations as may be required by
                               DCSD. This additional information shall be identified in the RFQu.

                       6.2.2   The PEC shall schedule a separate interview for each short-listed firm.
                               As part of its interview, and at the Selection Process Facilitator’s
                               discretion, each firm shall make a short oral presentation.

                       6.2.3   After the PEC has interviewed all the short-listed firms, the PEC shall
                               reconvene for the PEC members to discuss the interviews and review
                               each presentation. At the end of this discussion, PEC members shall
                               use the Presentation Evaluation Forms to record their evaluation of
                               each short-listed firm, and then submit the Presentation Evaluation
                               Forms to the Selection Process Facilitator.

                       6.2.4   The Selection Process Facilitator shall combine the evaluation scores
                               submitted by all PEC members and determine the PEC’s ranking of the
                               short-listed firms based upon the total scores assigned to each firm for
                               the presentation stage. If the ranking results in a tied score for the
                               number one or number two ranked firms, additional information shall be
                               requested from the tied firms and presented to the committee. The
                               committee will score the firms based on the responses to the additional
                               information.
               6.3     Submittal of recommended highest ranked firm. The Selection Process
                       Facilitator shall submit the highest ranked firm recommended by the PEC to the
                       COO for approval. The COO, in his or her sole discretion, shall either accept the
DeKalb County School District                                                 Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                      Project No. N/A
April 2, 2026                                                                               Page 15 of 21
                       results of the PEC’s ranking recommendation and forward it to the Board of
                       Education for approval or reject the results of the ranking recommendation. If the
                       COO accepts the ranking recommendation, the approval and negotiation
                       process continue as noted below. If the COO rejects the results of the ranking
                       recommendation, he or she, in his or her sole discretion, shall proceed with any
                       of the following methods: directing the PEC Selection Process Facilitator to
                       recommence the selection and ranking process at whatever stage the COO
                       deems appropriate (including the Individual Review stage, the Group Review
                       stage, or the Interview process); pursuing the project by any other alternative
                       method permitted under Georgia law; or abandoning the project all together. If the
                       COO elects to pursue the project through an alternative method or abandon the
                       project all together, DCSD shall provide public notice of that decision.

               .       Upon the COO’s approval of the PEC’s recommendation, an agenda item shall
                       be prepared and put on the next available agenda for the Board of Education review
                       and approval.

        7.0    SELECTION PROCESS:

               7.1     The Proposal Evaluation Committee (“PEC”) shall be established by the COO.
                       The COO, or his designee, shall approve the members of the PEC, to include the
                       following:

                       7.1.1   At least three (3) DCSD staff persons with expertise in facilities
                               design, construction, operation, and/or maintenance, property,
                               surveying and environmental, as recommended by the Chief Operations
                               Officer from their respective divisions, for the purpose of evaluating
                               and scoring only those elements of the responses that relate to facilities
                               design, construction, operation, and maintenance proposals, and on an
                               as needed basis, those that include property, surveying and
                               environmental.

                       7.1.2   At least one (1) member of the CIP staff with expertise in facilities design,
                               construction, operation, and/or maintenance, property, surveying and
                               environmental, as recommended by the Chief Operations Officer, for
                               the purpose of evaluating and scoring only those elements of the
                               responses that relate to facilities design, construction, operation, and
                               maintenance proposals.

                       7.1.3   Such other staff person(s) as deemed appropriate by the COO, or
                               his designee, in order to ensure that the PEC includes persons with
                               experience and knowledge in the contractual services being sought, for
                               the purpose of evaluating and scoring only those elements of the
                               responses that relate to the person(s)’ area of experience and
                               knowledge.


                       7.1.4   Membership of the PEC may include representation from other public
                               or private entities or others deemed appropriate as recommended by
                               the Chief Operations Officer. The recommendation may be based on
                               project complexity, project cost and staff capacity.
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 16 of 21

        7.2    All voting members of the PEC are required to comply with the provisions of Board
               Policy DJE and the provisions of the Code of Ethics for Public Officers and Employees.
               No member shall solicit or knowingly accept any gift, gratuity, loan, special discount,
               entertainment, transportation, lodging, meals, favor or promise of future employment,
               based upon any understanding that the vote, official action, or judgment of the member
               would be influenced thereby. The Chief Operations Officer, or his designee, shall select
               a Procurement representative who shall serve as the Selection Process Facilitator to
               monitor the selection process, ensure compliance with all applicable procedural
               requirements, limiting discussion which facilitates the procurement process, the facts of
               the procurement and documentation on file, and will maintain objectivity at all times.

        7.3    The Selection Process Facilitator shall be responsible for ensuring that each member is
               provided information on the project, directs discussion as necessary and determines when
               the committee may need to vote on any compliance related issues.

        7.4    The final rankings as approved by the Board of Education will rank all proposers from
               highest to lowest scores based on the selection criteria described in the RFQu.


 8.0    SCHEDULE

        8.1    Pre-submittal conference attendance (mandatory).
               A virtual mandatory pre-submittal conference will be held on Tuesday, April 21, 2026, 2:00
               p.m., EST, via TEAMS. Attendees must provide the following information by 5:00 p.m.,
               EST on Monday, April 20, 2026:

                  1.   Individual Name and Title
                  2.   Company Name
                  3.   Telephone Number
                  4.   Email Address

              This information must be sent to dcsd-op-solicitation@dekalbschoolsga.org. A meeting link
              will be sent to all registered attendees no later than 9:30 a.m., EST on Tuesday, April 21,
              2026. The RFQu will be reviewed, and questions will be addressed.

        8.2    Site visit attendance (mandatory).
               A mandatory project site visit is scheduled for Thursday, April 23, 2026. Details will be
               provided during the pre-submittal conference.

        8.3    Statements of Qualifications will be received electronically on the DeKalb County School
               District website at https://dekalbschoolsga.ionwave.net for CONSTRUCTION
               MANAGEMENT AT RISK SERVICES FOR DUNWOODY HIGH SCHOOL STADIUM
               IMPROVEMENTS, until 2:00 p.m. EST, Thursday, May 14, 2026. Qualifications received
               after the specified time will not be considered. All potential respondents must register as
               a vendor at http://dekalbschoolsga.ionwave.net. Based on evaluations of Statements of
               Qualifications, a maximum of five firms may be interviewed, at times and location to be
               determined at a later time. The order of presentation will be determined at DCSD’s
               sole discretion, and the firms so notified.
        8.4    The dates and times identified in this RFQu are subject to change. All changes will
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 17 of 21
               be posted to the DeKalb County School District solicitation website via addendum as it
               becomes available for all phases of this project.
 9.0    GENERAL INSTRUCTIONS

        9.1        Submit electronically in accordance with the requirements contained in the Request for
                   Qualifications (RFQu).
        9.2        The response shall contain manual signature of an authorized representative of the
                   responding firm.
        9.3        Submittals received after the specified date and time will not be considered.
        9.4        Firms responding to the RFQu shall be available for presentations and interviews
                   to the DCSD PEC Selection Committee.
        9.5        The contents of the proposal of a successful firm may become part of its
                   contractual obligations.
        9.6        Excluding items 5.1.5 and 5.2, Proposals shall respond to each item noted in sections
                   4.0 and 5.0 in the order noted. Identify responses with the same paragraph notation
                   as contained in this RFQu.
        9.7        Proposals shall be typed. All corrections made by the proposer prior to the opening
                   shall be initialed and dated by the proposer. No changes or corrections will be allowed
                   after proposals have been opened.
        9.8        Questions: Any questions concerning the RFQu should be submitted electronically via
                   email to the Procurement Manager at dcsd-op-bidquestion@dekalbschoolsga.org.
                   Questions submitted to any other email address will not be considered. The
                   deadline for receipt of vendor questions is Wednesday, April 29, 2026, at 2:00 p.m.
                   EST. Questions received after the deadline time will not be considered. Questions
                   received by the deadline time will be answered in writing and posted to the DCSD
                   solicitation website http://dekalbschoolsga.ionwave.net no later than Thursday, May
                   7, 2026, by 2:00 p.m. EST. No response other than written by the Procurement
                   Manager, will be binding upon DCSD. All supplemental instructions will be in the form
                   of written Addenda to the RFQu.

        9.9        Selection committee members, school board members and school board
                   personnel are not to be contacted prior to the Board of Education’s decision to
                   approve or reject the final recommendation presented to it by the Chief Operations
                   Officer. At the discretion of DCSD, failure to comply with this requirement
                   will be grounds for disqualification.

        9.10       Specifically, this NO-CONTACT PERIOD shall commence on the initial date of the
                   advertisement for Request for Qualifications and continue through and include the
                   date the DeKalb County Board of Education makes its determination to approve or
                   reject the final recommendations.

        9.11       The assigned contact person for this RFQu is Fred Christopher Procurement Manager
                   III. Mr. Christopher can be reached at (678) 676-0217 or by email at dcsd-op-
                   bidquestion@dekalbschoolsga.org. Prospective Respondents must limit their contact
                   regarding this RFQu to the assigned contact persons.

        9.12       Failure to meet any of these requirements may disqualify your firm from
                   consideration.
DeKalb County School District                                                   Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                        Project No. N/A
April 2, 2026                                                                                 Page 18 of 21

 10.0   TERMS AND CONDITIONS:
        10.1.       DCSD reserves the right to accept or reject any or all proposals in the best interest
                    of DCSD. DeKalb County School District reserves the right to waive any formalities
                    in the selection process.
        10.2        It is mutually understood and agreed that the nature, amount, and frequency of the
                    Services shall be determined solely by Owner and that Owner does not represent or
                    guarantee unto firm that any specific amount of services will be requested or required
                    of firm pursuant to this RFQu.

        10.3       Proposals which do not comply with these instructions or that do not include the
                   requested data may not be considered.

        10.4       The successful firm shall not discriminate against any person in accordance with
                   Federal, State or Local law.

        10.5       It is the sole responsibility of the submitting firm to ensure proposals are received
                   at the proper place on or before the time and date required, and in the format stated.
        10.6       By responding to this RFQu, the offeror certifies that the proposing company and/or
                   its principals have not been suspended, excluded, disqualified, debarred, proposed
                   for debarment, declared ineligible or voluntarily excluded from participation in any
                   transaction by any Federal or State department or agency and that the bidder
                   complies with all applicable orders, rules and regulations related thereto. Further, by
                   responding to this RFQu, the offeror certifies that all lower tier participating individuals
                   and/or company(s) and all respective principals of lower tier participants have not
                   been suspended, excluded, disqualified, debarred, proposed for debarment, declared
                   ineligible or voluntarily excluded from participation in any transaction by any Federal
                   or State department or agency and that the bidder complies with all applicable orders,
                   rules and regulations related thereto.
        10.7       DeKalb County School District, Georgia, does not discriminate in admission or
                   access to, or treatment or employment in its programs and activities, on the basis
                   of race, color, religion, age, sex, national origin, marital status, disability, genetic
                   information, sexual orientation, gender identity or expression, or any other reason
                   prohibited by law.
        10.8       Any person who is adversely affected by a decision of the DeKalb County School
                   District concerning this procurement, shall adhere to the following Protest
                   Procedures:

                   10.8.1      Protests. A bidder may file a written protest challenging DCSD’s
                               compliance with applicable procurement procedures subject to the
                               bidder’s compliance with the provisions outlined below. Any such written
                               protest will be resolved in accordance with these provisions.

                   10.8.2      Types of Challenges. Any bidder interested in and capable of responding
                               to a competitive solicitation may file a protest with respect to the competitive
                               solicitation process including, but not limited to, a challenge to
                               specifications or any events or facts arising during the solicitation process.
                               Any bidder submitting a timely bid/proposal in response to a competitive
                               solicitation may file a protest with respect to DCSD’s intended or actual
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 19 of 21
                             contract award including, but not limited to, events or facts arising during
                             the evaluation and/or negotiation process.

                   10.8.3    Form of Protest. At a minimum, the written protest must include the
                             following:
                             a.       the name and address of the protestor;
                             b.       appropriate identification of the solicitation;
                             c.       a statement of reasons for the protest;
                             d.       supporting exhibits, evidence, or documents to substantiate any
                                      claims unless not available within the filing time (in which case
                                      the offeror must proceed to file the protest during the filing period
                                      identified below but state the expected availability of the
                                      material); and
                             e.       the desired remedy.
                             DCSD, at its discretion, may deem issues not raised in the initial
                             protest as waived with prejudice by the protesting offeror.

                   10.8.4    Filing Protests. A protest is considered to be properly filed when it is in
                             writing, signed by a company officer authorized to sign contracts on behalf
                             of the offeror, and is received by the Design and Construction Department.
                             The protest may be sent by any of the following means:
                             MAIL: Attention: Mr. Erick Hofstetter
                                              Chief Operating Officer
                                              DeKalb County School District
                                              Sam A. Moss Service Center
                                              1780 Montreal Road
                                              Tucker, Georgia 30084
                             EMAIL:           erick_hofstetter@dekalbschoolsga.org

                   10.8.5    Type of Protests. A challenge to the competitive solicitation process
                             must be filed within two (2) business days prior to the closing date and
                             time of the solicitation as identified on the RFQu.
                             A challenge to an intended or actual contract award must be filed within
                             ten (10) calendar days of the date the Notice of Intent to Award (NOIA) is
                             posted by DCSD. In the event DCSD does not post a NOIA, the protest
                             must be filed within ten (10 calendar days of the date the Notice of Award
                             (NOA) is posted.

                             If a protest is not filed by the applicable deadline, such failure shall
                             be deemed as a waiver with prejudice of any grounds the bidder may
                             have for protest.

                   10.8.6    Stay of Procurement During Protest Review. When a protest
                             challenging the competitive solicitation process has been timely filed at
                             least two (2) business days prior to the closing date and time, the
                             solicitation shall not close until a final decision resolving the protest has
                             been issued, unless the Design and Construction Department makes a
                             written determination that the closing of the solicitation without delay is
                             necessary to protect the interests of DCSD.
DeKalb County School District                                                Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                     Project No. N/A
April 2, 2026                                                                              Page 20 of 21

                              When a protest challenging an intended contract award has been timely
                              filed, DCSD shall not proceed to actual contract award unless the Design
                              and Construction Department makes a written determination that the
                              issuance of a contract or performance of the contract without delay is
                              necessary to protect the interests of DCSD. If it is determined that it is
                              necessary to proceed with contract performance without delay, the
                              bidder/offeror with this contingent contract may proceed with performance
                              and receive payment for work performed in strict accordance with the
                              terms of the contract. The provisions of this paragraph are not applicable
                              to a protest pertaining to events or facts arising during the solicitation
                              process.

                   10.8.7     Protest Resolution. The Design and Construction Department shall
                              review and issue a written decision on the protest within seven (7)
                              business days. This decision shall be deemed final. Available remedies for
                              sustained protests are as follows:

                              10.8.7.1 If a protest is sustained prior to the closing date and time of the
                                       solicitation, available remedies may include, but are not limited to,
                                       the following: modification of the solicitation document including,
                                       but not limited to, specifications and terms and conditions;
                                       extension of the solicitation closing date and time (as appropriate);
                                       and cancellation of the solicitation.

                              10.8.7.2 If a protest of the intended/actual contract award is sustained,
                                         available remedies may include but are not limited to, the
                                         following: revision or cancellation of the NOIA/NOA, re-evaluation
                                         and re-award, or re-solicitation with appropriate changes to the
                                         new solicitation.
                   10.8.8     Costs. In no event shall a bidder be entitled to recover any costs incurred
                              in connection with the solicitation or protest process, including, but not
                              limited to, the costs of preparing a bid/proposal, the costs of participating
                              in the protest process, or any attorney fees.


       10.9        By making a submission, it is understood and agreed that the submitting entity
                   consents to DCSD contacting any parties referenced in the entities response
                   including, but not limited to, all project owners and references herein.

        10.10      Submitters acknowledge and agree that the contracting entity will be the CM name
                   identified in the response to 4.3.1.1

        10.11      Attachment H is the most current version of DCSD’ standard contract form for
                   Construction Management Services. By submitting a response to this RFQu,
                   submitters acknowledge and agree that they have reviewed this standard form and
                   have no objection to it. Further, if selected by DCSD, Submitters acknowledge and
                   agree that they will execute this standard form contract, subject to DCSD right to
                   make revisions and modifications thereto prior to execution, where DCSD has
                   determined, in its sole discretion that such revisions or modifications are in DCSD best
                   interest.
DeKalb County School District                                                    Revised RFQu No. 26-752-005
CM at Risk Dunwoody High School Stadium Improvements                                         Project No. N/A
April 2, 2026                                                                                  Page 21 of 21

                                           NOTICE
                              CONSTRUCTION MANAGEMENT AT RISK
                    FOR DUNWOODY HIGH SCHOOL STADIUM IMPROVEMENTS PROJECT

DeKalb County School District announces that Construction Management at Risk Services are required for the
project listed below.

PROJECT AND NUMBER:                                Construction Management at Risk Services for
                                                   Dunwoody High School Stadium Improvements Project
                                                   RFQu No. 26-752-005

SERVICES TO BE PROVIDED:                           Construction Management at Risk Services for
                                                   Dunwoody High School Stadium Improvements Project

PRE-SUBMITTAL MEETING:                             A virtual mandatory pre-submittal conference will be held
                                                   on Tuesday, April 21, 2026, 2:00 p.m., EST, via
                                                   TEAMS.

DCSD CONTACT:                                      Weyman Christopher, Procurement Manager III

SUBMISSION REQUIREMENTS:                           Qualifications will be received electronically on the
                                                   DeKalb County School district website at
                                                   https://dekalbschoolsga.ionwave.net
.
    PROPOSAL DUE DATE AND TIME:                    May 14, 2026, 2:00 p.m. EST


    Requirements: Interested firms are required to comply with all requirements of the Request for Qualification
    (RFQu). A copy of the RFQu and any and all clarifications issued shall be obtained from the DeKalb County
    School District web site http://dekalbschoolsga.ionwave.net. Furthermore, all Notices concerning this
    solicitation and award shall be posted to the aforementioned web site. These Notices shall include but are
    not limited to short list meeting dates and times, presentation meeting dates and times, intended decision
    and decision information.



                              End of RFQu Document Consisting of 21 Pages