Superintendent's Report - (PAC) Parklake Administrative Center

AID 2008470 · View on Simbli

Agenda Item

b. Update on the Park Lake Administrative Facility

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
PARKLAKE ADMINISTRATIVE CENTER
         APRIL 20, 2026
        2 1 7 5 PA R K L A K E D R I V E N E
          ADMINISTRATION & INSTRUCTION CENTER (AIC)
AIC
• Main Central Office - Currently Houses:
    • Superintendent’s Office
    • Board of Education Office
    • Board Room
    • Community Engagement & Innovative Partnerships
    • Human Resources
    • Finance
    • Accountability and Research
    • Legal Services
    • Schools & Leadership
    • Teaching & Learning
    • DeKalb Early College Academy (DECA)
    • Elizabeth Andrews High School

•   Parking area for two Bus regions



    4/20/2026                                          2
EAST DEKALB CAMPUS
• Houses:
   • DeKalb Alternative Program
   • Division of Public Safety
   • Selective Departments:
       • Wrap Around Services
       • Student Services
• Transportation Administrative
  Services (Blue Parcel)
   • Limited Bus Parking


•     Approximately 34 acres
•     Building in need of renovation
•     On Bus Line
•     Unsecure space


    4/20/2026                          3
.                                        FINANCING

    Board approved $6,500,000 transfer from Fund Balance in
    November 2024

    The district also sold a surplus property to DeKalb County for
    $1,067,000 in Fall of 2024
      • Proceeds to be used to operationalize the Parklake Building
        • Initial furniture package estimated at $450,000 workstations for ≈ 275 staff
          members, lobby furniture, training furniture, etc.




    4/20/2026                                                                            4
                                                        PROPOSED USAGE PLAN

                      Phase I                                              Phase II                                        Phase III

    Completion target November, 2026                      Completion target - July, 2027, Relocation TBD   Completion Target: TBD (after completion of
    1.Restore ParkLake Administrative Center facility     1.Move remaining Student Services staff and      Phase II)
     to operational use (in progress)                      Wrap Around Services staff from East DeKalb     1.Demolish East DeKalb Campus and build
     A.Move HR, Finance, Communications Staff              Campus to AIC                                    parking area
      from AIC to ParkLake Administrative Center          2.Move Remaining Student Services staff from     2.Move bus parking areas from AIC to East
     B.Move School Nutrition Services from Sam             Shadow Rock Center to AIC                        DeKalb Campus
      Moss Service Center to ParkLake                      A.Relocate DeKalb Alternative Program (TBD)      A.Fleet Maintenance will stay at AIC for the
      Administrative Center                                 for 2027-2028 school year via the Student        time being
     C.Move Public Safety from East DeKalb Campus           Assignment Project Process
      to Parklake Administrative Center


   Renovation updates anticipated not to exceed $700,000
   Estimated costs for furniture needs: not to exceed $450,000.
   • This would cover the cost for basic workstations (approximately 275 staff members), meeting/training room
      furniture, copy machines and other furniture's, fixtures, and equipment.
   • Note: Some of the existing office furniture for these Divisions/Departments may not survive a move due to
      age and condition. Additional costs for office furniture may be needed but will be addressed as need arises.


4/20/2026                                                                                                                                                  5
                                 PHASE I MOVEMENT
P R I M A R Y S I T E L O C AT I O N F O R :

1. Human Resources Division (≈90)
2. Finance Division (≈100)
3. Communications Department (≈25)
4. School Nutrition Services (≈35)
5. Public Safety Department (≈25)


Total Site Staff ≈ 275 Employees
                                                 Phase I = Blue Arrows – Phased movement coordinated during off
Total Capacity ≈ 400 (includes training rooms)   demand times to ensure continuity of operation
                                                 Phase II = Orange Arrow – Coordinated to ensure continuity of
                                                 operation after completion of Step 1
                                                 Phase III = Yellow Arrow – relocated as parking becomes available


4/20/2026                                                                                                            6
THANK YOU
D I V I S I O N O F O P E R AT I O N S




                                         7