Agenda Item
b. Approval of Network Cabling, Fiber Infrastructure Installation Services, and Wireless with Integrated Communication Networks, Inc. (ICN) for New Sequoyah High School, New Sequoyah Middle School, and New Cross Keys High School (Not to Exceed $2,540,002.52)
Summary: Presented by: Dr. Kermit Belcher, Chief Information Officer, Division of Information and Instructional Technology
Request: It is requested that the DeKalb County Board of Education approve the purchase of network cabling and fiber infrastructure installation services from Integrated Communication Networks, Inc. (ICN) to support the opening of New Sequoyah High School, New Sequoyah Middle School, and New Cross Keys High School at a cost not to exceed $2,540,002.52.
Why: The opening of New Sequoyah High School, New Sequoyah Middle School, and New Cross Keys High School requires a reliable and scalable network infrastructure to support instructional, administrative, and operational systems across the new facility. The services provided by Integrated Communication Networks, Inc. (ICN) will establish the foundational connectivity needed for the school to operate, including structured cabling, wireless access point installation, fiber connectivity, and telecommunications room buildouts. This infrastructure ensures consistent network performance, supports district technology standards, and enables all instructional and operational systems to function effectively on the first day of school.
Details: The network infrastructure scope for New Sequoyah High School, New Sequoyah Middle School, and New Cross Keys High School was developed in coordination with district leadership, instructional technology staff, and construction partners to ensure both facilities meet district standards for connectivity, performance, and reliability.
Key Services Include:
Structured Cabling Systems, Interior Fiber Connectivity & Wireless= $2,121,925.44
Integrated Communication Networks, Inc. (ICN) will install district-standard Category 6A structured cabling systems and supporting fiber infrastructure to provide reliable network connectivity for instructional, administrative, safety, and operational systems across all campuses. At the Sequoyah High School and Middle School campus, ICN will install Cat 6A structured cabling throughout both facilities and complete the build-out of one Main Distribution Frame (MDF) and twelve Intermediate Distribution Frame (IDF) telecommunications rooms. Work includes installation of fiber backbone infrastructure between the MDF and IDFs, telecommunications cabinets, ladder rack systems, and the termination, testing, and certification of copper and fiber network connections.
At New Cross Keys High School, ICN will install Cat 6A structured cabling and support the buildout of one temporary MDF, seven new IDF telecommunications rooms, and upgrades to three existing IDF rooms. The project also includes the deployment of Aruba AP-615 wireless access points with mounting hardware and five-year Aruba Central licensing to support district-wide wireless connectivity at the Sequoyah High School and Middle School campus and New Cross Keys High School. Additional network connectivity will be installed to support portable classroom pods at the Cross Keys campus, including fiber connectivity and cabling to support data, wireless, and security systems within those instructional spaces.
Labor = $86,772.40
Labor services will include the installation and configuration of structured cabling and fiber infrastructure across both campuses, and the buildout and preparation of the Main Distribution Frame (MDF) and Intermediate Distribution Frame (IDF) telecommunications rooms. ICN will perform cabinet installation, ladder rack installation, fiber terminations, and the termination, testing, and certification of all copper and fiber network systems to ensure proper performance and reliability. Work will be coordinated with construction partners and district technology staff to ensure compliance with district standards and alignment with project timelines.
Contingency =$331,304.68
A contingency amount of 15% above quoted costs is included to manage unforeseen conditions associated with network installation in a new construction environment and to ensure timely project completion.
Financial impact: $2,540,002.52
SPLOST VI
306.2210.530000.80336.7600.9990.0308.070.0000
Contact: Dr. Kermit Belcher, Chief Information Officer, Division of Information and Instructional Technology, 678.676.1274
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
Chronology: Network Cabling, Interior Fiber Infrastructure and Wireless (ICN)
New Sequoyah HS/MS & Cross Keys High School
The Division of Information and Instructional Technology (DIIT) identified the need for
comprehensive network infrastructure and connectivity services to support the opening of New
Sequoyah High School, New Sequoyah Middle School, and New Cross Keys High School. These
needs were validated through planning activities associated with new school construction,
district network standards, and coordination with construction and instructional technology
teams.
Following the planning phase, DIIT worked with Integrated Communication Networks, Inc. (ICN)
to develop a scope of services focused on establishing the core network foundation required for
instructional, administrative, safety, and operational systems across both campuses. The
proposed work includes structured cabling systems, telecommunications room buildouts, fiber
backbone connectivity, and associated labor services, all coordinated with construction
milestones to ensure network readiness prior to school opening.
Key Services Include:
Structured Cabling Systems, Interior Fiber Connectivity & Wireless = $2,121,925.44
ICN will provide Category 6A structured cabling and fiber backbone infrastructure to support all
instructional, administrative, safety, and operational spaces across both facilities, including:
● Installation of district-standard Category 6A cabling to support classroom technology,
wireless access points, VoIP telephony, security cameras, and administrative systems
across both campuses
● Buildout and full outfitting of two Main Distribution Frame (MDF) telecommunications
rooms and nineteen Intermediate Distribution Frame (IDF) telecommunications rooms,
including equipment cabinets, environmental support components, ladder rack systems,
runway supports, and pathway infrastructure
● Deployment of high-capacity fiber backbone infrastructure between MDF and IDF
locations to ensure scalable, high-speed connectivity throughout both campuses and to
support portable classroom connectivity at the Cross Keys campus
● Installation of wireless infrastructure across both campuses, including 281 Aruba
wireless access points with mounting hardware and centralized wireless management
licensing, to provide comprehensive wireless coverage for instructional and operational
use
● Installation of patch panels, fiber shelves, modules, connectors, and structured cable
management systems to ensure organized, secure, and maintainable network pathways
● Comprehensive termination, labeling, testing, certification, and documentation of all
copper and fiber systems to meet district performance standards and industry
compliance requirements
These services establish the resilient wired and wireless network backbone required to support
instructional technology, administrative operations, security systems, and digital learning
environments across the new school facilities.
Labor = $86,772.40
Labor services associated with this installation include:
● Installation, configuration, and physical deployment of structured cabling and fiber
infrastructure across both campuses
● Buildout, preparation, and equipment staging within MDF and IDF telecommunications
rooms
● Termination, performance testing, system validation, and certification of copper and fiber
network systems
● Coordination with general contractors, construction teams, and district technology staff to
ensure adherence to district standards, safety requirements, and construction timelines
Installation and configuration of structured cabling and fiber infrastructure across both
campuses
● Buildout and preparation of MDF and IDF telecommunications rooms
● Termination, testing, and certification of copper and fiber network systems
● Coordination with construction partners to ensure compliance with district standards and
project timelines
Contingency = $331,304.68
A contingency amount of 15% above quoted costs is included to manage unforeseen conditions
associated with network installation in a new construction environment and to ensure timely
project completion.
Procurement:
In accordance with Board of Education Purchasing Policy DJE III.C.3., Purchases or contracts
with a total estimated cost of $100,000.00 or more shall be awarded through a written
competitive sealed bid process to the lowest responsible, responsive bidder, or through a
competitive request for proposal process where the offer deemed to be the most advantageous
to the District may be selected. The competitive solicitation for RFP 26-703 was conducted in
accordance with DeKalb County School District procurement policies.
Financial Impact:
Category Description Cost
Structured Cabling Systems, Category 6A structured cabling, $2,121,925.44
Fiber Connectivity & Wireless MDF/IDF buildouts, fiber backbone
deployment, termination, testing, and
certification
Labor Installation, configuration, $86,772.40
telecommunications room preparation,
system testing, and project
coordination
Contingency Additional 15% above quoted amount $331,304.68
for unforeseen conditions
TOTAL $2,540,002.52