Capital Improvement and Facilities Update

AID 1964379 · View on Simbli

Agenda Item

2. Capital Improvement & Facilities Update ~ Added 3.6.2026

Summary: Provided by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
CAPITAL IMPROVEMENT & FACILITIES
         MARCH 9, 2026
         B O A R D U P D AT E
GEORGIA STATE CAPITAL OUTLAY
 G A D O E L O C A L FA C I L I T Y P L A N ( L F P )
   GEORGIA DOE CAPITAL OUTLAY PROGRAM
• Partial reimbursement for some facility renovations
  and new construction
• Applications made annually
• Several Board touch points associated with
  reimbursement process:
     o Local Facility Plan
     o Capital Outlay Project Application
     o Project Closeout (Certificate of the Board)


  Reimbursement Requirements:
• Application must be made before work begins
• 5 years to complete work
• Work applied for must be in District's Local Facility
  Plan


3/6/2026                                                  3
  LOCAL FACILITIES PLAN (LFP)​ FOR GADOE​
• Statement from local school district to GaDOE of
  facility needs and planned facility changes
• Major LFP update every 5 years with annual
  adjustment
• Major LFP update requires Board approval
   o April 2026

 Plan Includes:
• List of all facility renovation and modification needs
  for all District instructional facilities
• List of planned facility additions, closures, and new
  builds
• Calculation of earned reimbursement for new
  construction (based on existing inventory and
  forecasted enrollment)


 3/6/2026                                                  4
              LOCAL FACILITIES PLAN AND SAP
The next major Local Facility Plan update will need to be
approved before May 2026

This GADOE Local Facility Plan is not the DCSD Long Range
Capital Facility Plan. The DCSD Long Range Capital Facility Plan
is being developed in alignment with SAP.

The current 5-year Local Facility Plan update will not include
any changes being discussed as part of the ongoing SAP
process, as nothing is yet approved
     Lessons learned from previous LFP updates

The Local Facility Plan will be updated after the Board votes on
proposed changes

While annual LFP updates do not require Board approval, the
extent of expected changes to the District's school facility
inventory will require a full Local Facility Plan update next year.



 3/6/2026                                                             5
CAPITAL IMPROVEMENT PROJECTS
C A P I TA L I M P R O V E M E N T S
           CAPITAL IMPROVEMENT PROJECTS

                                                                           The Operations and
                          The Planning Team
                                                                           Procurement teams are
The project team has      continues to meet                                advancing several
finalized and submitted   regularly with DCSD                              significant procurements     The project team
                                                  Major capital projects
the recommended list      staff and is                                     scheduled for                continues to work
                                                  — New Sequoyah MS
of 40 Summer 2026         incorporating SAP-                               advertisement in March       collaboratively across
                                                  & HS, Cross Keys HS,     and April, including
projects. Security        related and strategic                                                         Planning, Operations,
                                                  Dresden ES, and          Elevator Revitalization &
vestibule planning and    planning                                                                      Procurement, and
                                                  Ashford Park ES —        Upgrades, Fernbank
scheduling remain on      recommendations in                                                            District leadership to
                                                  remain on schedule       Science Center
track. The planning       coordination with                                Planetarium                  ensure strong fiscal
                                                  and within approved
efforts are including     District leadership.                             HVAC/Screen/Roof             stewardship, schedule
                                                  budgets, with
reviewing scope with      Public information                               improvements, Sagamore       discipline, stakeholder
                                                  continued monitoring
principals to ensure      sessions remain                                  Hills Roof Replacement,      alignment, and
                                                  of cost, schedule, and   Druid Hills CMAR and Roof
proper coordination,      ongoing with SAP                                                              successful program
                                                  quality controls.        Replacement, District-wide
scope, and construction   representatives and                                                           execution.
                                                                           Fire Alarm Upgrades, and
sequencing.               community
                                                                           Miller Grove HS Exterior
                          stakeholders.                                    Façade Renovation.




 3/6/2026                                                                                                                         7
    CAPITAL PROGRAMS REPORT
F I N A N C I A L S TAT E M E N T S
           REPORTING TERMINOLOGY

  Glossary of Meanings:

     ▪Revenue = Total money collected over a designated time
     ▪Commitment = Total Encumbrance(s) plus Total Expense(s)
      ▪Encumbrance = Unpaid amount remaining on contract(s)
      ▪Expenses = Actual funds paid against contract(s)




3/6/2026                                                        9
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         10
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         11
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         12
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         13
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         14
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         15
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         16
           CAPITAL PROGRAM FINANCIAL STATEMENT
                     JANUARY 31, 2026




3/6/2026                                         17
   SUMMER 2026 PREPARATION
FA C I L I T I E S M A I N T E N A N C E &
C A P I TA L I M P R O V E M E N T
3/6/2026   19 19
3/6/2026   20 20
    THANK YOU
QUESTIONS & COMMENTS