3. Exhibit M - Brockett ES - DCSD SV G1

AID 1876211 · View on Simbli

Agenda Item

ii. E-SPLOST VI ~ Capital Improvement Project ~ Contract ~ Guaranteed Maximum Price (GMP) ~ RFQu 24-752-029 ~ Security Vestibules Group 1 ~ Lefko Development, Inc. dba Lefko Construction (Not to exceed $18,457,627.24)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve the Guaranteed Maximum Price (GMP) for the Capital Improvement Project - Security Vestibules Group 1 to Lefko Development, Inc. dba Lefko Construction for an amount not to exceed $18,457,627.24.
Why: Approval of the Guaranteed Maximum Price to Lefko Development, Inc. dba Lefko Construction will allow for the installation and upgrades at each of the 25 security vestibules included in “Security Vestibules Group 1."
Details: On August 12, 2024, the Board approved the award of a Construction Manager at Risk (“CMAR”) contract to Lefko Construction for the installation and upgrades at each of the 25 security vestibules included in “Security Vestibules Group 1."

Pursuant to that agreement, the Design Professional (SSOE), Construction Manager (Lefko), Program Manager (HPM), and DCSD Operations have collaborated to generate a design, a safe construction phasing plan, and a GMP in the best interest of the DeKalb County School District for each of the 25 security vestibules included in “Security Vestibules Group 1”:



Avondale ES - $473,949.35
DeKalb School of the Arts -$802,170.26
Brockett ES - $640,612.05
Browns Mill ES - $476,756.15
Canby Lane ES - $496,913.00
Cedar Grove HS - $807,333.86
Chamblee HS - $1,899,565.93
Chamblee MS - $735,044.05
Columbia HS - $671,582.20
Coralwood Education - $800,454.22
Dunaire ES - $430,797.62
Dunwoody HS - $685,163.49
Flat Shoals ES - $608,971.46
Hightower ES - $483,602.09
Jolly ES - $590,118.95
Kingsley ES - $962,660.30
Lithonia HS - $1,047,350.38
Margaret Harris Comp School - $676,169.00
McLendon ES - $532,752.90
Panola Way ES - $1,005,186.05
Robert Shaw Theme ES - $936,707.87
Salem MS - $618,788.00
Stone Mountain MS - $801,799.17
Tucker MS - $733,298.81
Woodward ES - $539,880.06


The requested action establishes the Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached “Exhibit M” for each school.
Financial impact: Each site is funded as a separate project through the E-SPLOST VI capital improvement fund. This approval increases the budget of the general contractor cost code in each project and funds the approved GMP out of the general contractor cost code in each project:



Avondale ES - Project 20436- $473,949.35
DeKalb School of the Arts - Project 40836 -$802,170.26
Brockett ES - Project 20936 $640,612.05
Browns Mill ES - Project 21036- $476,756.15
Canby Lane ES - Project 21136- $496,913.00
Cedar Grove HS - Project 40336- $807,333.86
Chamblee HS - Project 40436- $1,899,565.93
Chamblee MS - Project 30336- $735,044.05
Columbia HS - Project 40636- $671,582.20
Coralwood Education - Project 50136-$800,454.22
Dunaire ES - Project 21936 $430,797.62
Dunwoody HS - Project 41036- $685,163.49
Flat Shoals ES - Project 22736- $608,971.46
Hightower ES - Project 23136 - $483,602.09
Jolly ES - Project 23636- $590,118.95
Kingsley ES - Project 23836- $962,660.30
Lithonia HS - Project 41236- $1,047,350.38
Margaret Harris Comp School - Project 50836- $676,169.00
McLendon ES - Project 24336-$532,752.90
Panola Way ES - Project 25336- $1,005,186.05
Robert Shaw Theme ES - Project 26036-$936,707.87
Salem MS - Project 31636-$618,788.00
Stone Mountain MS - Project 31836- $801,799.17
Tucker MS - Project 31936- $733,298.81
Woodward ES - Project 27636- $539,880.06
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1470
Mr. Hans Williams, Director Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
Commercial Construction
& General Contractor




                          Georgia Perimeter
                               College
                                   Project Name
                                   RFQ Number

                           Construction Management
                                        Date        at Risk
                           DCSD Group 1 Security Vestibules
                                     BROCKETT ES

                                      EXHIBIT M
                          STATEMENT OF QUALIFICATION
                                   SEPTEMBER, 2025




                                                     1|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



September 16th, 2025

DeKalb County Board of Education
Mr. Donte Brown
Operations Division – Sam A. Moss Service Center
1780 Montreal Road Tucker, GA 30084

Re: Construction Management at Risk Group 1 Security Vestibules

Dear DeKalb County Board of Education, Mr. Donte Brown.

Lefko Development, Inc. (LEFKO) is pleased to submit Exhibit M for the Construction Management at
Risk – Group 1 Security Vestibules project. This submission is based on the contract documents dated
Oct. 8th, 2024, and the bid process plan shared via email on May 9th, 2025, and confirmed in OAC meetings.

Your Project            Defining project expectations early on gives us the ability to take responsibility
for the complete success of your project (cost, schedule, quality, and safety). Your project requires
detailed planning and communication with all stakeholders to deliver on our first-time quality dedication
and on-time delivery. Our team has thoroughly reviewed the project RFQ to fully understand the scope.
    Over the years, we’ve completed many such projects. This experience allows us to develop site specific
methodologies for first-time quality. Prime among these is our process to understand the Owner’s needs
and implement regular communication protocols to eliminate delays and meet project milestones.

Well Versed             We are well versed in working within educational facilities and understand the
nature of safety and security for students, professionals, and administrators. LEFKO has completed
numerous projects for the educational systems of Cherokee, Dekalb, and Forsyth County Schools; Georgia
State University, Georgia Tech, and Atlanta Technical College. In the past few years our team has
managed 18 projects for GSU, as well as three projects for Forsyth County Schools. We recently
completed your $2.5M project to renovate 10 security vestibules, and Cherokee County Schools Bus
Washer Additions of $3.6M. Our team is currently wrapping up some Cobb County Schools projects such
as Nicholson ES Renovation of $5.2M and Rose Garden HVAC Upgrades of $2.5M. Given our history of
working in educational facilities within Georgia counties, cities, universities and schools, we are
accustomed in working in areas populated by students. LEFKO places the highest of priorities on client
relationships and communication. Our teams operate in an open collaborative environment ensuring
constant communication. We are certain you will find our knowledge and experience to align with what
Dekalb County values in their contractor services. We look forward to working with you again to improve
the educational environment for your students and maintain excellence in Dekalb County schools.

Respectfully submitted,

________________________________
Giuseppe Ceccarelli, Operations Manager
Lefko Development, Inc./dba Lefko Construction
105 Mansell Circle, Roswell GA 30075 PH: 404-846-6372 FX: 404-365-8328 Lefkoconstruction.com

                                                                                               2|P A G E
LEFKO CONSTRUCTION
                                          EXHIBITM
      GMPAMENDMENTTO AGREEMENTBETWEEN OWNERAND
               CONSTRUCTION CONTRACTOR

          AMENDMENT NO. 1 TO AGREEMENT BETWEEN OWNER AND
        CONSTRUCTION CONTRACTOR FOR Brockett ES G1 SV
                      AGREEMENT NO.    N/A
                                                    - ------------
                                                   ------
        Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
                       10/08/2024
 ("Agreement"), dated_ _ _ _ _ _ _, between The School Board of DeKalb County, Georgia
 ("Owner") and LEFKO Development Inc, dba, LEFKO Construction
 ("Construction Contractor"), with respect to the construct10n of Owner's
 Brockett
 _  ___      _G1
            ES  __ SV_ _ _ _ _ _ _ _ _ _ __ ("Project"), Owner and Construction
 Contractor hereby agree to amend and modify the Agreement by this Amendment No. 1 and
 establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
 capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
 unless otherwise noted.

                                          ARTICLE 1

                                      SCOPE OF WORK
                                                         safe,
 The scope of the Work consists of the construction of a _ __  finished,
                                                                 _ _ _and _ _fully
                                                                                __ functioning
                                                                                     __ __
 security
 _  ___   vestibule
             _ _ _--_ _ _ _ _ _ _ _ _ _, in accordance with the Agreement, this
 Amendment and the other Contract Documents listed as Attachments 1 through__  6 below, which
 are hereby incorporated into and made a part of the Amendment by this reference:

Attachment No.       Description                          Pages

List of Drawings, Specifications and Addendums
l.                   Allowances                           11 _ through _
                                                          _            11 _            09/16/2025
2.                   Assumptions and Clarifications       12          18 _
                                                          _ _ through _                09/16/2025
3.                   Completion Schedule                  19 _ through 24
                                                          _            __              09/16/2025
4.                   Schedule of Values                   _25 _           25 _
                                                                  through _            09/16/2025
5.                                                                    26 _
                                                         26 _ through _
                     List of Itemized General Conditions _                             09/16/2025
6.                   List of Subcontractors and           _27 _           28 _
                                                                  through _            09/16/2025
                     Major Suppliers
7.                   Alternates                           -- _ through _--_
                                                          _                            N/A



                                                  M-1
                                            ARTICLE 2

                              GUARANTEED MAXIMUM PRICE


        2.1     Construction Contractor's Guaranteed Maximum Price ("GMP") for the Work,
including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
Construction Management Fee as defined in Section 4 of the Agreement, is Six
                                                                         __  hundred
                                                                               ___   forty
                                                                                       __thousand
                                                                                           _
six hundred twelve with 05/100--   ($_ 640,612.05
                                          ___      -- ).

       2.2    The Construction Management Fee for the entire Work anticipated on this Project
is hereby established as a lump sum amount of _Fifty_three
                                                       __  thousand
                                                              _ _three
                                                                    __         _ _four
                                                                         _ _eighty
                                                                       hundred     __  with_
                                                                                           34/100--
                                                                                             _ __
   53,384.34 ), said lump sum amount is included within the above noted GMP.
($_____

        2.3    The general condition expenses for the entire Work anticipated on this Project are
hereby established as a lump sum amount of _   One_  _ _twenty
                                                   hundred _ _thousand _hundred
                                                               _ _ _five ___    ninety
                                                                                   __  nine_  _00/100
                                                                                            with __
  120,599.00
($_   _ _ __, , said lump sum amount is included within the above noted GMP ("General
Conditions Expenses"). The items included as General Condition Expenses are listed in the List
of Itemized General Conditions attached hereto and incorporated herein as Attachment No. _       -5-
                                                                                                   _.
Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
Change Order or Construction Change Directive, Construction Contractor acknowledges and
agrees that Owner shall have no liability for any General Condition expenses beyond payment of
the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
to receive any additional compensation from Owner for the General Conditions beyond the above
lump sum amount. There shall be no additional General Conditions Expenses payable to
Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
Change Directive Work). Further, there shall be no mark-up for a subcontractor's General
Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
Change Order and Construction Change Directive Work to be performed by such subcontractor.

       2.4    Monthly installment payment of the Construction Management Fee and the General
Condition Expenses shall be based upon the percent completion of the designated portion of the
Work for each particular month.

        2.5     In order to efficiently and timely address any unknown or unanticipated conditions
that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
of the Work, but 1;;xclu ding all items that are to be reimbursed unde r the lump sum General
Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
                                                                            Twenty six thousand six
contingency within the GMP in an amount not-to-exceed amount of hundred ninety two                  and
17
_ / 100 Dollars ($ _  26,692.17--
                       _ _ _ _ _ __, ("Owner's Contingency"). Owner's Contingency
funds shall be used to cover costs that may result from incomplete design and unanticipated costs
that arise during construction that are not identified by the construction documents. Construction

                                                    M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner's Contingency without first obtaining Owner's express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner's Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor's Work compensated within the
GMP and not chargeable against Owner's Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner's Contingency expenditures. Further, the work that
is the subject of any Owner's Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner's Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner's Contingency.

                2.6     In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above, the parties have agreed to
                                                                           Twenty six thousand six
establish a contingency within the GMP in an amount not-to-exceed_            _ ninety
                                                                           hundred __     two _ and 17 /100

Dollars ($ 26,692.17
           ___) ("Contractor's Contingency"). Construction Contractor shall not proceed
with any portion of the Work which it intends to charge against the Contractor's Contingency
without first obtaining Owner's express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor's
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor's Work compensated within the GMP and not chargeable against
Contractor's Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor's Contingency expenditures. Further, the work that is the subject of any Owner's
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor's Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor's Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of_              10.00
                                                                                                     _% of
the Cost of the Work charged against the Contractor's Contingency.

         2.7    The parties have agreed to establish an allowance within the GMP for
Patching of existing finishes, and              Sixteen
unforeseen conditions         in the amount of thousand and 00/100 Dollars ($._        16,000.00--
                                                                                         _ ___ ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance ("Allowance Work") without first obtaining Owner's express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments___  1    through . Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor's costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenev er cost s are m o re
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.




                                                      M-3
       2.8    Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
payment is made to Construction Contractor the total Cost of the Work has been increased by
approved Change Orders in an amount causing the original GMP as set forth in this Amendment
to be exceeded by more than_______     zero       and 00 / 100 Dollars ($_0.00--
                                                                            _ _ _ _ _), then
Construction Contractor shall be entitled to an increase in the Construction Management Fee in
the amount of_and /100 Dollars'-_ _ _        7.50
                                               _ _ _ _%) of the amount exceeding the sum of
zero
_  _ _ _and 00/100 Dollars ($ _   0.00--
                                     _ _ _ _._,, plus that original GMP amount.

        2.9     Construction Contractor recognizes that the Contract includes work for trench
excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
set forth by all federal, state, and local requirements. Construction Contractor certifies that the
required trench safety standards will be in effect during the period of construction of the Project
and Construction Contractor agrees to comply with all such required trench safety standards.

               2.10.1 The amount of _ _ _ _N/A                 _ _ _ _ _and -- /100            Dollars
   N/A
($______          ) has been separately identified for the cost of compliance with the required trench
safety standards; said amount is included within the GMP.

        2.10 At the completion of the Work, should the actual amount of "General
Requirements" expenses be less than the amount included therefor in the Schedule of Values
approved by Owner, the resulting "savings" shall accrue to the benefit of Owner and a deductive
Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
separate guaranteed maximum price for such expenses and any overruns in General Requirements
expenses shall be borne by Construction Contractor without reimbursement from Owner.

        2. 11 By executing this Amendment and furnishing Owner with a GMP based on a
detailed Schedule of Values and a Master Project Schedule, Consh·uction Contractor represents
and warrants that the Contract Documents, including the Construction Documents, as well as other
materials, and infonnation furnished Construction Contractor as of the date of this Amendment
have described the scope, construction requirements, and design intent of the Work in detail
sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
Project Schedule. To the extent that the Construction Documents are anticipated to require further
development, Construction Conh·actor has provided in the GMP for such further development
consistent with the Contract Documents and reasonably inferable therefrom.

        2 .12   Savings will be computed as of the date of final completion of the Work and shall
consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
benefit of Owner.



                                                    M-4
                                          ARTICLE3

                                      CONTRACT TIME
        3 .1    The Construction Phase Commencement Date for the Work is_ _ _ _ _. The
total period of time beginning with the Construction Phase Commencement Date through the date
required for Substantial Completion of the Work is_ _ _ _ _ _ _ _ _ _ _ _ _(                )
days ("Contract Time"). THE SUBSTANTIAL COMPLETION DATE IS THEREFORE
ESTABLISHED AS _ _ _ _ _ _ _ _ __

        3.2     Pursuant to the Agreement, the parties have established liquidated damage rates for
reasons stated therein, which the parties acknowledge and agree apply to this Amendment and
Construction Contractor's responsibility to substantially complete the Work within the Contract
Time as stated herein and finally complete the Work within the time prescribed in the Contract.
Accordingly, the liquidated damage rates established in the Agreement shall be assessed against
Construction Contractor for each calendar day Construction Contractor fails to achieve Substantial
Completion of the Work within the Contract Time or final completion of the Work within the time
prescribed in the Contract.

                                          ARTICLE 4


                                      MISCELLANEOUS
4.1 Except as expressly modified herein, the terms and conditions of the Agreement remain
unchanged. All terms not specifically defined herein shall have the mec'lning ascribed to them in
the Agreement. In the event of a conflict between the terms of this Amendment and those of the
Agreement, Owner and Construction Contractor agree that the terms of this Amendment shall
prevail and control. This Amendment may be executed in counterparts, each of which shall be
deemed to be an original, but all of which shall constitute one and the same instrument.

Owner                                        Construction Contractor

By:_ __ _ _ __ _ _ _ _ _ __                          By:                           LEFKO Construction


Its:- - - - - - - - - - - - - - -                    Its: Operations Manager

Date:- - - - - -- - - -- - - -                       Date:-09/17/2025
                                                           -- - - - - - - - -- - -
Attest:_ _ _ _ __ _ _ _ _ _ _ __                            Jesus Martinez
                                                     Attest:- -------------




                                                  M-5
Commercial Construction
& General Contractor



                LIST OF DRAWINGS, SPECIFICATION, ADDENDUMS & RFIs

                          CMAR – DCSD Group 1 Security Vestibules
DRAWINGS (Created by LS3P)

       G-000, AD-101, AD-121, A-050, A-101, A-102, A-121, A-321, A-322, A-600, A-601, A-602,
        A-603, A-720, S-001, S-101, S-301, S-501, M-000, E-000, ED-101, E-101, E-121, LV-000,
        LVD-101, LV-101. (Dated: 04-30-2025 & Revised per Add#1 05/13/2025 & Add#2
        06/30/2025)

SPECIFICATIONS

       Project Manual packages provided on 04/30/2025 and revised per Add#1 05/13/2025 as
        follows:

        Avondale ES: 385 pages
        Avondale HS: 386 pages
        Brockett ES: 415 pages
        Browns Mill ES: 385 pages
        Canby Lane ES: 386 pages
        Cedar Grove HS: 386 pages
        Chamblee HS: 415 pages
        Chamblee MS: 416 pages
        Columbia HS: 383 pages
        Coralwood Education School: 388 pages
        Dunaire ES: 383 pages
        Dunwoody HS: 385 pages
        Flat Shoals ES: 385 pages
        Hightower ES: 385 pages
        Jolly ES: 385 pages
        Kingsley ES: 432 pages
        Lithonia HS: 418 pages
        Margaret Harris Comp School: 391 pages
        McLendon ES: 387 pages
        Panola Way ES: 416 pages
        Robert Shaw Theme ES: 389 pages
        Salem MS: 386 pages
        Stone Mountain MS: 385 pages
        Tucker MS: 416 pages
        Woodward ES: 384 pages
                                                                                   8|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor




ADDENDUMS

       Addendum #1: (Date issued June 13, 2025): The contract documents for the project are
        modified as set forth in this Addendum. The original contract documents dated
        04/30/2025 and any previously issued addenda remain in full force and effect, except for
        any clarifications, amendments, additions, deletions and/or modifications to the
        specifications and drawings modified by this Addendum, which is hereby part of the
        contract documents. Also, changes per RFI responses have been incorporated,
        specification section 087100 Door Hardware has been added in Kingsley ES, and
        specification section 088000 Glazing has been revised for all schools in this addendum
        along with the below listed drawings.

        Avondale HS: Supplemental drawing provided for supplemental frames.
        Chamblee HS: G-000, existing drawings provided (for reference only).
        Chamblee MS: G-000.
        Kingsley ES: A-050, A-321, M-000, Supplemental drawing provided for Rooftop curb and
        pipe penetration details.

       Addendum #2: (Date issued July 30th, 2025): The contract documents for the project are
        modified as set forth in this Addendum. The original contract documents dated
        04/30/2025 and any previously issued addenda remain in full force and effect, except for
        any clarifications, amendments, additions, deletions and/or modifications to the
        specifications and drawings modified by this Addendum, which is hereby part of the
        contract documents. Also, changes per RFI responses have been incorporated in this
        Addendum 2 dated 06/30/2025.

RFIs
        1. Permit Fees
        2. Special Inspections
        3. Removal of existing furniture and offices items
        4. Furnishings Responsibility
        5. Graphic Film
        6. Exterior Graphics
        7. Sprinkler scope of work
        8. Low Voltage scope of work
        9. Millwork and AWI certification
        10. HP-1 and HP-2 at Kingsley ES
        11. HVAC scope at Kingsley ES
        12. Custom color for storefronts
        13. Delegated design

                                                                                      9|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



        14. Metal stud gauge
        15. New storefronts at Hightower ES
        16. Fire Alarm Manufacturer & scope
        17. LV details at Hightower ES
        18. LV – Video surveillance system
        19. HVAC controls and BAS
        20. Steel lintels at CMU walls
        21. Metal header above storefronts
        22. Elevations at BES, CHS and CMS
        23. Elevations at Kingsley ES
        24. Elevations at LHS and PWES
        25. Elevations at Tucker MS
        26. Door thickness and stile for aluminum doors
        27. Exterior and interior thermal doors
        28. Supplemental interior frame details
        29. Hardware set for Kingsley ES
        30. Mid rail and Bottom rail for glazing doors
        31. Existing roofing system at Kingsley
        32. New exterior wall-mounted lights
        33. Light fixture schedule at Kingsley
        34. Door schedules (Aluminum doors)
        35. Door schedules (Wood doors)
        36. Door schedules (HM doors)
        37. Exterior graphics specs at Avondale HS
        38. Steel lintel thickness
        39. ACT type desired
        40. Flooring type desired
        41. Fiberglass panel on the vestibule side
        42. Kevlar panels
        43. Glass replacement at Chamblee HS
        44. Door06 composition at CES
        45. Film or glass replacement required at KES
        46. Structural reinforcement for new HVAC outdoor units
        47. Canopy fascia panels
        48. Laminated system specs
        49. Permit fees
        50. Electrical General Note
        51. Contingency for horn strobe units at Kingsley
        52. Door hardware replacement at Kingsley ES
        53. Stored Material billed


                                                                  10 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                      ATTACHMENT 1
                                        Allowances

                          CMAR – DCSD Group 1 Security Vestibules
ALLOWANCES (Included in base price)

       Allowance no. 1 – Patch and repair miscellaneous flooring materials to match existing
        Amount: $10,000.00

       Allowance no. 2 – Shoring
        Amount: N/A

       Allowance no. 3 – Furnish and install two (2) horn/strobe units and four (4) strobe-only
        units per RFI #51
        Amount: N/A

       Allowance no. 4 – Structural reinforcement angle at ductless outdoor unit per RFI #46
        Amount: N/A

       Allowance no. 5 – Brick patching to match existing
        Amount: $2,500.00

       Allowance no. 6 – Patching holes in concrete slab
        Amount: $1,000.00

       Allowance no. 7 – Unforeseen conditions: Sealants, and fire caulking for new wall
        penetrations
        Amount: $2,500.00

       Allowance no. 8 – Electrical: removing and reinstalling existing outlets and switches per
        site visit.
        Amount: N/A




                                                                                      11 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                    ATTACHMENT 2
                               Assumptions & Clarifications

                          CMAR – Group 1 Security Vestibules
DIV – 02 EXISTING CONDITIONS

       It is assumed that all demolition areas are clearly identified and accessible as shown on
        the drawings.
       The owner will provide a location for placing dumpsters
       Pollution liability and professional insurance are not included.
       Disconnection and reconnection of all technology items (computers, printers, etc.) is
        excluded from the General Contractor's scope.
       This scope excludes any core drilling or relocation and adjustment of utilities.
       Asbestos abatement or the handling of any hazardous materials is not included, if GC
        discovers/exposes any existing asbestos and/or lead contaminated produces or materials,
        GC will immediately notify the owner and architect.
       Demolition of any partitions, glazing, or items not explicitly identified on the drawings is
        excluded.
       Shoring and any shoring plans are excluded.
       DCSD shall provide secure and accessible temporary storage locations for all items
        removed.
       DCSD will be responsible for removal, storage, protection, and reinstallation of the
        existing furniture and offices items (boxes, desks, printer, clock etc.), of all personal
        belongings and school loose items at existing furniture, cabinets and desks affected by
        the renovation work. GC will coordinate with owner for moving large furniture items
        (including trophy cases, modular office furniture, bookcases etc.) per RFI #03
       Coordination will be required with the school principal or designated DCSD authorities to
        determine and maintain a temporary egress pathway in compliance with applicable safety
        standards during school operations.

DIV – 04 MASONRY

       No new CMU walls work, this GMP only includes patch, infill and repair existing CMU walls
        affected by the new scope of work.

DIV – 05 METAL

       Per RFI #13 this GMP does not include sealed engineer metal shop drawings
       Specialty coatings and galvanization are excluded
                                                                                        12 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       Shoring or temporary bracing is excluded

DIV – 06 MILLWORK

       Per RFI #9, AWI (Architectural Woodwork Institute) certification and/or labels will not be
        provided. However, all millwork will be constructed in compliance with AWI standards.
       GMP is based on custom fabricated woodworks per specs section 064116
       All prices are based on Wilsonart Laminate Selections. The GMP assumes standard, readily
        available colors from the specified manufacturer's palette.
       GMP is based on standard cabinet construction, including: MDF Carcass, White Melamine
        Interiors, Standard PLAM Colors/Finish, 4" Chrome Wire Pulls, European-Style Hinges, Peg
        hole Shelves, Square-Edge Tops. Standard Wall-Hung Shelves (Unless Specifically Noted
        Above): KV83 Metal Standards/Brackets
       4” plinth shown on details on drawing A-720 is assumed to be covered with 4” rubber wall
        base
       Current lead-times: 7-10 weeks.

DIV – 08 OPENING (DOORS)

       Excludes overhead, rolling, coiling, gate doors, and associated hardware.
       Excludes any modifications to existing doors and frames.
       Current lead-times: Bullet Resistant doors: 8-12 weeks / Standard Solid Core Wood Doors:
        7-8 weeks / Hollow Metal doors and frames: 4-8 weeks / Hardware: 4-13 weeks.

DIV – 08 OPENING (GLAZING)

       Break metal covers are made of aluminum to match framing.
       All exposed finishes shall be as specified per school, including clear anodized, bronze and
        custom color, complying with RFI #12.
       Spec section 084113 “Aluminum-Framed Entrances and Storefronts”, calls for a 20-year
        special finish warranty. However, this can only be achieved at schools that call for custom
        color finish. Clear anodized and bronze finish will carry a 10-year special finish warranty,
        which is the current warranty available by the approved manufacturer.
       Spec section 066400 “Plastic Paneling” and RFIs #41 and #42, call for UL 752 level 2 bullet
        resistant fiberglass panels by Fortified Estate. As an alternative, the contractor is
        providing TSS BB-2 panels, complying with spec section 066400 plastic paneling, including
        solid anodized aluminum panels on both sides.
       Spec section 087100 “Door Hardware” calls for Ives hinges. The contractor is including
        ABH hinges instead, as Ives no longer warranties hinges for doors thicker than 1.75” and
        the project requires 2” thick exterior doors.

                                                                                        13 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       This proposal includes glass replacement only at existing doors, sidelites or windows,
        labeled “GL/L2.” No glass replacement is included for doors, sidelites or windows labeled
        “L2” only.
       All new doors and framing in this proposal are 2” x 4 ½” thermal at exterior locations and
        1 ¾” x 4 ½” non-thermal at interior locations per RFIs #26.
       Perimeter sealants shall be a standard color at exterior and interior of the aluminum
        storefront systems only. 2-beads included.
       There’s no guarantee new exterior sealant will fully bond to the existing surfaces. Each
        area will need to be checked on-site. If the building’s exterior (brick or other materials)
        hasn’t been properly sealed or maintained to manage water, extra prep work might be
        needed, which could lead to additional costs (Unforeseen conditions).
       This proposal excludes PE calculations for new storefronts, delegated design or PE stamp
        on shop drawings per RFI #13
       Installation of permanent cores is excluded. The contractor will coordinate with the
        Owner and hardware supplier to ensure proper timing and delivery of cores.
       No fire rated or laminated glass included.
       This GMP assumes that existing glazing in doors and adjacent sidelites is ¼" per notes on
        drawings A-600 and A-601.
       The use of film on existing or new insulated glass units may void the typical 10-year
        warranty for hermetic seals.
       This GMP includes to provide a single-pane 3/8’’ tempered glass or 1’’ single pane
        insulated glass as substrate to receive new UL752 BR laminate system per glazing note #2
        on drawing A-601.
       This GMP is based on the assumption shown on drawings that existing glazing will be able
        to be removed from perimetral doors, sidelites and frames without causing any damage
        and that will accommodate new 3/8” glazing. New doors, sidelites and frames are not
        included, unless they are shown on drawings.
       This proposal includes quarterly maintenance starting at substantial completion of each
        school for 6 months. Maintenance to be during regular business hours. No overtime or
        after hours.
       Current lead-times: Storefronts: 4-6 weeks / Doors: 8 weeks / Door Hardware: 12 weeks
        / Glass: 2-4 weeks

DIV – 08 OPENING (FILM)

       As the film installation will be completed in an active environment, minor dust particles
        may appear after the installation of the laminate as a result of airborne dust. These
        particles should be few and not significantly detract from clarity or aesthetics when
        looking through the glass at a distance of 6 feet.


                                                                                       14 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       Ballistic Laminate installation includes the use of liquid sprayed from high pressure tanks.
        Any item which may sustain water damage and subsequently devalue such item, shall be
        relocated prior to installation.
       DCSD has already received, reviewed and approved samples and product demonstration
        for this level 2 BRLF. No additional samples or cut sheets will be provided.
       Per RFI #48 this GMP includes DCSD accepted Safe Haven Defense product “SW600BR” as
        basis of design instead of product listed on specs section 088000 Glazing.
       Current lead-times: 6-8 weeks

DIV – 09 FINISHES (DRYWALL / ACT)

       Per RFI #13 sealed engineer drawings for Specs Section 095113 Acoustical panel ceilings
        will not be required
       Per RFI #14 this GMP includes 16 GA at all metal stud framing
       Per RFI #39, The intent is to reutilize the existing installed ceiling tiles as much as practical
        at all locations. Where new ACT is required to repair ceilings basis of design ACT-1
        Armstrong; Fine Fissured™ High NRC; Product #1754 will be used
       Per RFI #41, Basis of Design product for Ballistic Fiberglass Panels Certified UL 752 Ballistic
        Level 2 by Fortified Estate
       All ceilings and partitions not explicitly identified within the scope of demolition or new
        construction are assumed to be in good, sound condition, structurally stable, and not
        requiring any adjustments, repairs, or finishes as part of this project.
       The Guaranteed Maximum Price (GMP) for ceiling patching is strictly limited to the areas
        explicitly indicated and quantified on drawing A-121
       All untagged partitions not specifically identified on drawings are assumed to be existing
        CMU (Concrete Masonry Unit)
       No mockups are included
       No spray or rigid insulation are included in this GMP
       No fire rated partitions are anticipated in this GMP, as none are referred to in project
        drawings
       New studs at walls receiving new UL 752 fiberglass bulletproof panels are not included
       Lead time for UL 752 fiberglass bulletproof panels is 6 weeks.

DIV – 09 FINISHES (FLOORING)

       Patching areas were estimated at approximately 2 feet wide at anticipated locations
       Floor patches will match existing materials as closely as possible. However, uniformity can
        only be guaranteed through full-room material replacement
       Any patching at areas out of scope are included in the GMP
       No polishing or waxing of existing floor surfaces are included
       No moisture testing or floor preparation are included
                                                                                             15 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       No mockups are expected to be performed
       Specs section 096519 Resilient tile flooring states LVT types 1-5, and basis of design
        manufacturer as Armstrong Flooring, however no flooring schedule was provided so GMP
        is based on an allowance to match existing per RFI #40
       Specs section 096813 Tile Carpeting states CPT types 1-4 and requires compliance with
        Basis of Design products indicated on Room Finish Legend, however no flooring schedule
        was provided so GMP is based on an allowance to match existing per RFI #40.

DIV – 09 FINISHES (PAINTING)

       Painting scope is limited to the areas explicitly listed on the drawings
       Access to all painting areas will be provided without obstruction or the need for special
        equipment
       No specialty coatings or high-performance systems are required unless specified
       Painting of any additional areas or surfaces not identified is not included
       Concealed or inaccessible surfaces are not part of the painting scope unless otherwise
        noted
       Painting of perimetral doors, frames or sidelights is not included
       Painting of murals or any other specific design on walls is not included.

DIV – 21 FIRE SUPPRESSION (SPRINKLERS)

       No sprinkler work is included in this GMP per RFI #7.

DIV – 21 FIRE SUPPRESSION (FIRE ALARM)

       No fire alarm work is included in this GMP per RFI #16

DIV – 22 PLUMBING

       No plumbing work is included in this GMP.

DIV – 23 HVAC

       Any duct cleaning or work on existing to remaining equipment or duct, not shown on
        drawings, are excluded
       Any new equipment not shown on mechanical drawings is excluded.




                                                                                      16 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



DIV – 26 ELECTRICAL

       No electrical trenching, compaction, backfill, directional boring and coring for electrical
        work is expected
       It is assumed that all new conduits will be surface mounted and exposed
       No occupancy sensors are anticipated for this project (electrical general note #37 drawing
        E-000) per RFI # 50
       No fall of potential method to measure ground resistance is included for this project
        (electrical general note #49 drawing E-000) per RFI #50
       Current lead times 4-6 weeks.

DIV – 27 LOW VOLTAGE

       Permits and associated fees are excluded
       Customer to provide static IP addresses and network connections at panel locations
       Customer to provide a secured staging & storage area for project-related materials
       It is assumed that electronic AutoCAD files are available from customer for LEFKO’s
        subcontractors’ usage in creating submittal drawings
       Any and all interfacing to other equipment unless specifically noted is excluded
       Servers and workstations hardware and Microsoft operating system are excluded
       This GMP is based on DCSD approved LV vendors’ quote. No information related to
        manufacturers, models, or brands was provided either on drawings or specs
       No new speakers are anticipated for this project. Pre and post testing is included.

GENERAL

       Due to the significant market volatility and the implementation of new tariffs that
        materially impact labor or material costs this GMP is valid until December 31st, 2025.
        LEFKO reserves the right to reevaluate this proposal and work with DCSD after the above
        mentioned date.
       This GMP and preliminary schedule is based on placed orders provided by the time of the
        proposal submission; accurate lead times and estimated delivery dates can only be
        provided once submittals are approved and orders placed. LEFKO will constantly follow
        up and provide updates regarding this matter
       All permit fees for this project will be waived by DeKalb County School District except for
        Avondale ES and Hightower ES per RFI #49
       All furniture will be Owner provided per RFI #4
       Any special inspections will be performed by Owner's contracted third-party Inspector
        per RFI #2
       P&P Bond will be provided per school basis

                                                                                       17 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       The warranty period will commence once the substantial completion has been achieved
        for this project/contract
       Per RFI #53 Contractor is allowed to bill for stored materials as long as photos are provided
        and proof is submitted showing the materials are kept in a bonded warehouse
       Construction contractor's fee associated to any portion of the Work which it intends to
        charge against the Owner's Contingency will be reviewed and included by the time the
        change order or PCO is submitted for review and approval
       The commencement date of the construction phase and the substantial completion date
        are contingent upon the approval of this GMP and the issuance of the Notice to Proceed.
        Therefore, Article No. 3 of Exhibit "M" remains blank at this time.




                                                                                         18 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                    ATTACHMENT 3
                                  Completion Schedule

                          CMAR – Group 1 Security Vestibules
Find schedule attached. The lead times used in this preliminary schedule are place holder based
on preliminary feedback received from our subcontractors that will be updated once orders are
placed. During the construction process, LEFKO will consider all time saving processes and/or
ideas to ensure completion on time and on budget. The compliance of this schedule will be
conditioned to current lead times and availability by the time of approval of this GMP.




                                                                                    19 | P A G E
LEFKO CONSTRUCTION
                                                                                   DeKalb County School District - CMAR for Group 1 Security Vestibules
                                                                                                                                   PRELIMINARY MASTER PROJECT SCHEDULE
ID        Task Name                                                     Duration   Start          Finish        Mar '25   Apr '25  May '25    Jun '25  Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25  Jan '26    Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26  Oct '26    Nov '26  Dec '26   Jan '27   Feb '27 Mar '27   Apr '27   May '27   Jun '27  Jul '27    Aug '27
                                                                                                                     172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10172431 7 142128 5 121926 2 9 162330
     1    DeKalb County School District - Security Vestibules Group 1   575 days   Fri 5/2/25     Fri 7/23/27                                                                                                                         DeKalb County School District - Security Vestibules Group 1
                                                                                                                             5/2                                                                                                                                                                                                                                                                        7/23


     2      Pre-Construction Phase                                      265 days   Fri 5/2/25     Thu 5/14/26                                                                     Pre-Construction Phase
                                                                                                                             5/2                                                                                                                               5/14


     3         100% Drawings & Specs                                    0 days     Fri 5/2/25     Fri 5/2/25         100% Drawings & Specs
                                                                                                                          5/2    5/2


     4         Guaranteed Maximum Price Prep and Submittal              96 days    Mon 5/5/25     Tue 9/16/25                 Guaranteed Maximum Price Prep and Submittal
                                                                                                                              5/5                                    9/16


     5         Guaranteed Maximum Price Approval                        0 days     Mon 11/10/25   Mon 11/10/25                                                             Guaranteed Maximum Price Approval
                                                                                                                                                                                     11/10  11/10


     6         POs, Contract Amendment, Notice to Proceed               20 days    Mon 11/10/25   Mon 12/8/25                                                             POs, Contract Amendment, Notice to Proceed
                                                                                                                                                                                     11/10          12/8
                                                                                                                                                                                                   0%

     7         Submittals & approvals                                   40 days    Tue 12/9/25    Thu 2/5/26                                                                                         Submittals & approvals
                                                                                                                                                                                                  12/9                   2/5


     11        Lead Times                                               70 days    Fri 2/6/26     Thu 5/14/26                                                                                                                           Lead Times
                                                                                                                                                                                                                      2/6                                      5/14


     12           Storefront materials lead time                        70 days    Fri 2/6/26     Thu 5/14/26                                                                                                                Storefront materials lead time
                                                                                                                                                                                                                       2/6                                    5/14
                                                                                                                                                                                                                                            0%

     13           Ballistic film lead time                              40 days    Fri 2/6/26     Thu 4/2/26                                                                                                            Ballistic film lead time
                                                                                                                                                                                                                       2/6                     4/2
                                                                                                                                                                                                                                      0%

     14     Construction Phase                                          360 days   Fri 3/6/26     Fri 7/23/27                                                                                                                                                                                             Construction Phase
                                                                                                                                                                                                                                3/6                                                                                                                                                                     7/23


     15        SUB-GROUP 1                                              85 days    Fri 3/6/26     Fri 7/3/26                                                                                                                                     SUB-GROUP 1
                                                                                                                                                                                                                                3/6                                           7/3


     16           Salem Middle School (Middle)                          75 days    Fri 3/6/26     Fri 6/19/26                                                                                                                          Salem Middle School (Middle)
                                                                                                                                                                                                                                3/6                                        6/19


     17               First Phase                                       15 days    Fri 3/6/26     Thu 3/26/26                                                                                                                      First Phase
                                                                                                                                                                                                                                3/6           3/26


     22               Second Phase                                      25 days    Thu 5/14/26    Fri 6/19/26                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                     5/14                  6/19


     30           Flat Shoals Elementary School                         75 days    Fri 3/6/26     Fri 6/19/26                                                                                                                          Flat Shoals Elementary School
                                                                                                                                                                                                                                3/6                                        6/19


     31               First Phase                                       15 days    Fri 3/6/26     Thu 3/26/26                                                                                                                      First Phase
                                                                                                                                                                                                                                3/6           3/26


     36               Second Phase                                      25 days    Thu 5/14/26    Fri 6/19/26                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                     5/14                  6/19


     44




                                                                                                                                                                                              Page 20
                                                                    DeKalb County School District - CMAR for Group 1 Security Vestibules
                                                                                                                   PRELIMINARY MASTER PROJECT SCHEDULE
ID        Task Name                                      Duration   Start         Finish        Mar '25   Apr '25  May '25    Jun '25  Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25  Jan '26    Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26  Oct '26    Nov '26  Dec '26   Jan '27   Feb '27 Mar '27   Apr '27   May '27   Jun '27  Jul '27    Aug '27
                                                                                                     172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10172431 7 142128 5 121926 2 9 162330
     45          Cedar Grove High School (Large)         85 days    Fri 3/6/26    Fri 7/3/26                                                                                                                           Cedar Grove High School (Large)
                                                                                                                                                                                                               3/6                                               7/3


     46               First Phase                        20 days    Fri 3/6/26    Thu 4/2/26                                                                                                                         First Phase
                                                                                                                                                                                                               3/6                 4/2


     51               Second Phase                       35 days    Thu 5/14/26   Fri 7/3/26                                                                                                                                                    Second Phase
                                                                                                                                                                                                                                         5/14                    7/3


     59          Browns Mill Elementary School (Small)   70 days    Fri 3/6/26    Fri 6/12/26                                                                                                                  Browns Mill Elementary School (Small)
                                                                                                                                                                                                               3/6                              6/12


     60               First Phase                        10 days    Fri 3/6/26    Thu 3/19/26                                                                                                                    First Phase
                                                                                                                                                                                                               3/6         3/19


     64               Second Phase                       20 days    Thu 5/14/26   Fri 6/12/26                                                                                                                                               Second Phase
                                                                                                                                                                                                                                         5/14          6/12


     72        SUB-GROUP 2                               100 days   Thu 4/2/26    Fri 8/21/26                                                                                                                                                   SUB-GROUP 2
                                                                                                                                                                                                                         4/2                                                       8/21


     73          Panola Way Elementary School            100 days   Thu 4/2/26    Fri 8/21/26                                                                                                                                        Panola Way Elementary School
                                                                                                                                                                                                                         4/2                                                       8/21


     74               First Phase                        20 days    Thu 4/2/26    Thu 4/30/26                                                                                                                                  First Phase
                                                                                                                                                                                                                         4/2                 4/30


     79               Second Phase                       35 days    Fri 7/3/26    Fri 8/21/26                                                                                                                                                                  Second Phase
                                                                                                                                                                                                                                                        7/3                        8/21


     87          Lithonia High School                    100 days   Thu 4/2/26    Fri 8/21/26                                                                                                                                                Lithonia High School
                                                                                                                                                                                                                         4/2                                                       8/21


     88               First Phase                        20 days    Thu 4/2/26    Thu 4/30/26                                                                                                                                  First Phase
                                                                                                                                                                                                                         4/2                 4/30


     93               Second Phase                       35 days    Fri 7/3/26    Fri 8/21/26                                                                                                                                                                  Second Phase
                                                                                                                                                                                                                                                        7/3                        8/21


 101             Columbia High School                    90 days    Thu 4/2/26    Fri 8/7/26                                                                                                                                              Columbia High School
                                                                                                                                                                                                                         4/2                                                 8/7


 102                  First Phase                        15 days    Thu 4/2/26    Thu 4/23/26                                                                                                                               First Phase
                                                                                                                                                                                                                         4/2           4/23


 107                  Second Phase                       25 days    Fri 7/3/26    Fri 8/7/26                                                                                                                                                                  Second Phase
                                                                                                                                                                                                                                                        7/3                  8/7


 115             Canby Lane Elementary School            85 days    Thu 4/2/26    Fri 7/31/26                                                                                                                                      Canby Lane Elementary School
                                                                                                                                                                                                                         4/2                                            7/31


 116                  First Phase                        10 days    Thu 4/2/26    Thu 4/16/26                                                                                                                              First Phase
                                                                                                                                                                                                                         4/2         4/16


 120                  Second Phase                       20 days    Fri 7/3/26    Fri 7/31/26                                                                                                                                                             Second Phase
                                                                                                                                                                                                                                                        7/3          7/31




                                                                                                                                                                              Page 21
                                                        DeKalb County School District - CMAR for Group 1 Security Vestibules
                                                                                                         PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                             Duration   Start          Finish         Mar '25   Apr '25  May '25    Jun '25  Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25  Jan '26    Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26  Oct '26    Nov '26  Dec '26   Jan '27   Feb '27 Mar '27   Apr '27   May '27   Jun '27  Jul '27    Aug '27
                                                                                           172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10172431 7 142128 5 121926 2 9 162330
 128        SUB-GROUP 3                      60 days    Fri 8/21/26    Fri 11/13/26                                                                                                                                                                                   SUB-GROUP 3
                                                                                                                                                                                                                                                         8/21                                 11/13


 129          Tucker Middle School           50 days    Fri 8/21/26    Fri 10/30/26                                                                                                                                                                             Tucker Middle School
                                                                                                                                                                                                                                                         8/21                             10/30


 130               First Phase               15 days    Fri 8/21/26    Fri 9/11/26                                                                                                                                                                           First Phase
                                                                                                                                                                                                                                                         8/21           9/11


 135               Second Phase              25 days    Fri 9/25/26    Fri 10/30/26                                                                                                                                                                                        Second Phase
                                                                                                                                                                                                                                                                    9/25                  10/30


 143          Stone Mountain Middle School   60 days    Fri 8/21/26    Fri 11/13/26                                                                                                                                                                        Stone Mountain Middle School
                                                                                                                                                                                                                                                         8/21                         11/13


 144               First Phase               20 days    Fri 8/21/26    Fri 9/18/26                                                                                                                                                                              First Phase
                                                                                                                                                                                                                                                         8/21                 9/18


 149               Second Phase              35 days    Fri 9/25/26    Fri 11/13/26                                                                                                                                                                                           Second Phase
                                                                                                                                                                                                                                                                    9/25                      11/13


 157          Jolly Elementary School        50 days    Fri 8/21/26    Fri 10/30/26                                                                                                                                                                          Jolly Elementary School
                                                                                                                                                                                                                                                         8/21                        10/30


 158               First Phase               15 days    Fri 8/21/26    Fri 9/11/26                                                                                                                                                                           First Phase
                                                                                                                                                                                                                                                         8/21           9/11


 163               Second Phase              25 days    Fri 9/25/26    Fri 10/30/26                                                                                                                                                                                        Second Phase
                                                                                                                                                                                                                                                                    9/25                  10/30


 171          Brockett Elementary School     50 days    Fri 8/21/26    Fri 10/30/26                                                                                                                                                                        Brockett Elementary School
                                                                                                                                                                                                                                                         8/21                      10/30


 172               First Phase               15 days    Fri 8/21/26    Fri 9/11/26                                                                                                                                                                           First Phase
                                                                                                                                                                                                                                                         8/21           9/11


 177               Second Phase              25 days    Fri 9/25/26    Fri 10/30/26                                                                                                                                                                                        Second Phase
                                                                                                                                                                                                                                                                    9/25                  10/30


 185        SUB-GROUP 4                      60 days    Fri 11/13/26   Fri 2/5/27                                                                                                                                                                                                                 SUB-GROUP 4
                                                                                                                                                                                                                                                                                     11/13                              2/5


 186          Woodward Elementary School     45 days    Fri 11/13/26   Fri 1/15/27                                                                                                                                                                                                    Woodward Elementary School
                                                                                                                                                                                                                                                                                     11/13                   1/15


 187               First Phase               10 days    Fri 11/13/26   Fri 11/27/26                                                                                                                                                                                                      First Phase
                                                                                                                                                                                                                                                                                     11/13         11/27


 191               Second Phase              20 days    Fri 12/18/26   Fri 1/15/27                                                                                                                                                                                                                Second Phase
                                                                                                                                                                                                                                                                                              12/18          1/15


 199          McLendon Elementary School     45 days    Fri 11/13/26   Fri 1/15/27                                                                                                                                                                                                    McLendon Elementary School
                                                                                                                                                                                                                                                                                     11/13                   1/15


 200               First Phase               10 days    Fri 11/13/26   Fri 11/27/26                                                                                                                                                                                                      First Phase
                                                                                                                                                                                                                                                                                     11/13         11/27




                                                                                                                                                                    Page 22
                                                                            DeKalb County School District - CMAR for Group 1 Security Vestibules
                                                                                                                             PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                                                 Duration   Start          Finish         Mar '25   Apr '25  May '25    Jun '25  Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25  Jan '26    Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26  Oct '26    Nov '26  Dec '26   Jan '27   Feb '27 Mar '27   Apr '27   May '27   Jun '27  Jul '27    Aug '27
                                                                                                               172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10172431 7 142128 5 121926 2 9 162330
 204               Second Phase                                  20 days    Fri 12/18/26   Fri 1/15/27                                                                                                                                                                                                                Second Phase
                                                                                                                                                                                                                                                                                                                  12/18          1/15


 212          Margaret Harris Comprehensive School               50 days    Fri 11/13/26   Fri 1/22/27                                                                                                                                                                                              Margaret Harris Comprehensive School
                                                                                                                                                                                                                                                                                                     11/13                       1/22


 213               First Phase                                   15 days    Fri 11/13/26   Fri 12/4/26                                                                                                                                                                                                      First Phase
                                                                                                                                                                                                                                                                                                       11/13           12/4


 218               Second Phase                                  25 days    Fri 12/18/26   Fri 1/22/27                                                                                                                                                                                                                    Second Phase
                                                                                                                                                                                                                                                                                                                  12/18                   1/22


 226          Coralwood Education School                         60 days    Fri 11/13/26   Fri 2/5/27                                                                                                                                                                                                      Coralwood Education School
                                                                                                                                                                                                                                                                                                       11/13                         2/5


 227               First Phase                                   20 days    Fri 11/13/26   Fri 12/11/26                                                                                                                                                                                                        First Phase
                                                                                                                                                                                                                                                                                                       11/13                 12/11


 232               Second Phase                                  35 days    Fri 12/18/26   Fri 2/5/27                                                                                                                                                                                                                        Second Phase
                                                                                                                                                                                                                                                                                                                  12/18                         2/5


 240        SUB-GROUP 5                                          60 days    Fri 2/5/27     Fri 4/30/27                                                                                                                                                                                                                                             SUB-GROUP 5
                                                                                                                                                                                                                                                                                                                                       2/5                                4/30


 241          Avondale Elementary School                         45 days    Fri 2/5/27     Fri 4/9/27                                                                                                                                                                                                                                  Avondale Elementary School
                                                                                                                                                                                                                                                                                                                                       2/5                    4/9


 242               First Phase                                   10 days    Fri 2/5/27     Fri 2/19/27                                                                                                                                                                                                                                   First Phase
                                                                                                                                                                                                                                                                                                                                       2/5         2/19


 246               Second Phase                                  20 days    Fri 3/12/27    Fri 4/9/27                                                                                                                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                                                                                                                 3/12          4/9


 254          Dunaire Elementary School                          45 days    Fri 2/5/27     Fri 4/9/27                                                                                                                                                                                                                                  Dunaire Elementary School
                                                                                                                                                                                                                                                                                                                                       2/5                    4/9


 255               First Phase                                   10 days    Fri 2/5/27     Fri 2/19/27                                                                                                                                                                                                                                   First Phase
                                                                                                                                                                                                                                                                                                                                       2/5         2/19


 259               Second Phase                                  20 days    Fri 3/12/27    Fri 4/9/27                                                                                                                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                                                                                                                 3/12          4/9


 267          Avondale High School - Dekalb School of the Arts   60 days    Fri 2/5/27     Fri 4/30/27                                                                                                                                                                                                                       Avondale High School - Dekalb School of the Arts
                                                                                                                                                                                                                                                                                                                                   2/5                            4/30


 268               First Phase                                   20 days    Fri 2/5/27     Fri 3/5/27                                                                                                                                                                                                                                        First Phase
                                                                                                                                                                                                                                                                                                                                       2/5                 3/5


 273               Second Phase                                  35 days    Fri 3/12/27    Fri 4/30/27                                                                                                                                                                                                                                                     Second Phase
                                                                                                                                                                                                                                                                                                                                                 3/12                     4/30


 281          Robert Shaw Theme Elementary School                60 days    Fri 2/5/27     Fri 4/30/27                                                                                                                                                                                                                               Robert Shaw Theme Elementary School
                                                                                                                                                                                                                                                                                                                                       2/5                         4/30


 282               First Phase                                   20 days    Fri 2/5/27     Fri 3/5/27                                                                                                                                                                                                                                        First Phase
                                                                                                                                                                                                                                                                                                                                       2/5                 3/5




                                                                                                                                                                                        Page 23
                                                       DeKalb County School District - CMAR for Group 1 Security Vestibules
                                                                                                      PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                            Duration   Start         Finish        Mar '25   Apr '25  May '25    Jun '25  Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25  Jan '26    Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26  Oct '26    Nov '26  Dec '26   Jan '27   Feb '27 Mar '27   Apr '27   May '27   Jun '27  Jul '27    Aug '27
                                                                                        172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10172431 7 142128 5 121926 2 9 162330
 287               Second Phase             35 days    Fri 3/12/27   Fri 4/30/27                                                                                                                                                                                                                                              Second Phase
                                                                                                                                                                                                                                                                                                                       3/12                     4/30


 295        SUB-GROUP 6                     60 days    Fri 4/30/27   Fri 7/23/27                                                                                                                                                                                                                                                                   SUB-GROUP 6
                                                                                                                                                                                                                                                                                                                                      4/30                                    7/23


 296          Kingsley Elementary School    60 days    Fri 4/30/27   Fri 7/23/27                                                                                                                                                                                                                                                             Kingsley Elementary School
                                                                                                                                                                                                                                                                                                                                      4/30                                    7/23


 297               First Phase              20 days    Fri 4/30/27   Fri 5/28/27                                                                                                                                                                                                                                                             First Phase
                                                                                                                                                                                                                                                                                                                                      4/30                 5/28


 302               Second Phase             35 days    Fri 6/4/27    Fri 7/23/27                                                                                                                                                                                                                                                                           Second Phase
                                                                                                                                                                                                                                                                                                                                                   6/4                        7/23


 310          Chamblee Middle School        50 days    Fri 4/30/27   Fri 7/9/27                                                                                                                                                                                                                                                           Chamblee Middle School
                                                                                                                                                                                                                                                                                                                                      4/30                     7/9


 311               First Phase              15 days    Fri 4/30/27   Fri 5/21/27                                                                                                                                                                                                                                                          First Phase
                                                                                                                                                                                                                                                                                                                                      4/30           5/21


 316               Second Phase             25 days    Fri 6/4/27    Fri 7/9/27                                                                                                                                                                                                                                                                          Second Phase
                                                                                                                                                                                                                                                                                                                                                   6/4                  7/9


 324          Hightower Elementary School   45 days    Fri 4/30/27   Fri 7/2/27                                                                                                                                                                                                                                                        Hightower Elementary School
                                                                                                                                                                                                                                                                                                                                      4/30                    7/2


 325               First Phase              10 days    Fri 4/30/27   Fri 5/14/27                                                                                                                                                                                                                                                         First Phase
                                                                                                                                                                                                                                                                                                                                      4/30         5/14


 329               Second Phase             20 days    Fri 6/4/27    Fri 7/2/27                                                                                                                                                                                                                                                                      Second Phase
                                                                                                                                                                                                                                                                                                                                                   6/4          7/2


 337          Chamblee High School          50 days    Fri 4/30/27   Fri 7/9/27                                                                                                                                                                                                                                                              Chamblee High School
                                                                                                                                                                                                                                                                                                                                      4/30                              7/9


 338               First Phase              15 days    Fri 4/30/27   Fri 5/21/27                                                                                                                                                                                                                                                          First Phase
                                                                                                                                                                                                                                                                                                                                      4/30           5/21


 343               Second Phase             25 days    Fri 6/4/27    Fri 7/9/27                                                                                                                                                                                                                                                                          Second Phase
                                                                                                                                                                                                                                                                                                                                                   6/4                  7/9


 351          Dunwoody High Facility        50 days    Fri 4/30/27   Fri 7/9/27                                                                                                                                                                                                                                                           Dunwoody High Facility
                                                                                                                                                                                                                                                                                                                                      4/30                      7/9


 352               First Phase              15 days    Fri 4/30/27   Fri 5/21/27                                                                                                                                                                                                                                                          First Phase
                                                                                                                                                                                                                                                                                                                                      4/30           5/21


 357               Second Phase             25 days    Fri 6/4/27    Fri 7/9/27                                                                                                                                                                                                                                                                          Second Phase
                                                                                                                                                                                                                                                                                                                                                   6/4                  7/9


 365        Project Completion              0 days     Fri 7/23/27   Fri 7/23/27                                                                                                                                                                                                                                                                              Project Completion
                                                                                                                                                                                                                                                                                                                                                                         7/23




                                                                                                                                                                 Page 24
Commercial Construction
& General Contractor



                                      ATTACHMENT 4
                                     Schedule of Values

                          CMAR – Group 1 Security Vestibules
BROCKETT ES


                                                                       GMP FOR DCSD -
      DIVISION                       ACTIVITY
                                                                        BROCKETT ES

         D01       GENERAL REQUIREMENTS                            $           120,599.00
         D02       EXISTING CONDITIONS (INTERIOR DEMO)             $            13,636.05
         D03       CONCRETE                                        $               855.75
         D04       MASONRY                                         $            19,800.00
         D05       METAL                                           $             8,703.50
         D06       WOOD, PLASTIC & COMPOSITES (MILLWORK)           $            11,066.16
         D08       OPENINGS (DOORS)                                $            23,035.92
         D08       OPENINGS (GLAZING)                              $           122,326.15
         D08       OPENINGS (SAFETY AND SECURITY FILM)             $           132,128.00
         D09       FINISHES (DRYWALL / ACT)                        $            24,516.00
         D09       FINISHES (FLOORING)                             $            10,000.00
         D09       FINISHES (PAINTING)                             $             5,644.00
         D23       HVAC                                            $             7,314.42
         D26       ELECTRICAL                                      $             9,152.00
         D27       LOW VOLTAGE                                     $            25,066.42
                                                  GMP SUB TOTAL    $           533,843.37
                                                   GMP FEE (10%)   $            53,384.34
                                       OWNER'S CONTINGENCY (5%)    $            26,692.17
                                 CONTRACTOR'S CONTINGENCY (5%)     $            26,692.17
                                                  TOTAL GMP $               640,612.05




                                                                                   25 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                        ATTACHMENT 5
                              Itemized General Conditions Expenses

                               CMAR – Group 1 Security Vestibules
                          ACTIVITY                             UNIT    QUANT.    UNIT PRICE        TOTAL
                                                               LUMP
Bond                                                                     1.00      7,705.00   $        7,705.00
                                                                SUM
                                                               LUMP
Builder's Risk Ins.                                                      1.00      1,474.00   $        1,474.00
                                                                SUM
                                                               LUMP
Tech Fee (Procore)                                                       1.00      1,239.50   $        1,239.50
                                                                SUM
                                                               LUMP
General Liability Insurance & Umbrella                                   1.00      3,484.00   $        3,484.00
                                                                SUM
Supervision: Pre construction / Project engineer
                                                               WEEKS     3.00      2,500.00   $        7,500.00
(Construction phase)
Supervision: Project Manager                                   WEEKS     3.00      3,500.00   $      10,500.00
Supervision: Assistant PM                                      WEEKS     4.00      2,800.00   $      11,200.00
Supervision: Superintendent                                    WEEKS     3.00      3,000.00   $       9,000.00
Supervision: Assistant Superintendent                          WEEKS    12.00      2,400.00   $      28,800.00
                                                               LUMP
Transportation & Vehicle Insurance                                       1.00      8,250.00   $        8,250.00
                                                                SUM
                                                               LUMP
Project scheduling                                                       1.00      4,000.00   $        4,000.00
                                                                SUM
Interior site preparation (Minor protection, plastic, layout   LUMP
                                                                         1.00      2,500.00   $        2,500.00
and others).                                                    SUM
                                                               LUMP
Exterior Site Preparation (Container / Storage)                          1.00      4,450.00   $        4,450.00
                                                                SUM
                                                               LUMP
Maintenance Period                                                       1.00      7,500.00   $        7,500.00
                                                                SUM
                                                               LUMP
Portable Potties & Mobile office                                         1.00      2,020.00   $        2,020.00
                                                                SUM
                                                               LUMP
Permit fees                                                              1.00      1,000.00   $        1,000.00
                                                                SUM
                                                               LUMP
Copies, documents and misc. during contract process                      1.00        756.50   $         756.50
                                                                SUM
                                                               LUMP
Dumpsters                                                                1.00      5,720.00   $        5,720.00
                                                                SUM
                                                               LUMP
Final cleaning & Misc.                                                   1.00      3,500.00   $        3,500.00
                                                                SUM
                                                               TOTAL GENERAL REQUIREMENTS     $     120,599.00




                                                                                                  26 | P A G E
LEFKO CONSTRUCTION
 Commercial Construction
 & General Contractor



                                              ATTACHMENT 6
                                           List of subcontractors

                                 CMAR – Group 1 Security Vestibules
           PORTION OF THE          SUBCONTRACTOR             CONTACT                          ADDRESS
DIV #
                 WORK                     NAME                PERSON                           PHONE
          Existing conditions         Atlanta Cargo                             P.O. Box 360218. Decatur, GA 30036
                                                           Yolanda Shields
        (Furniture relocation)     Transportation, co.                                 Phone: 404-329-4505
          Existing conditions     Integrated Scanning       Robert Price      11330 Vanstory Dr Ste 115. Huntersville,
D02      (Concrete Scanning)            Solutions                                             NC 28078
                                                                              1092 W Atlanta St., Bldg 200, Suite 200.
          Existing conditions      Interior Demolition
                                                            Ryan Shanik                 Marietta, GA, 30060
           (Interior Demo)            Services, Inc.
                                                                                       Phone: 770-792-0071
                                                                               220 Old Loganville Rd. Loganville, GA
                                   Paramount Cutting          Latasha
D03           Concrete                                                                         30052
                                    Contracting, LLC          Johnson
                                                                                       Phone: 404-777-1485
                                                                               7231 Capps Ferry Rd. Douglasville, GA
D04            Masonry            Figozz Masonry, LLC      Fidel Gonzalez                      30135
                                                                                       Phone: 678-598-1319
                                        Silver Oak                              811 Tucker Court. Winder, GA 30680
D05             Metal                                      Andrew Pierce
                                       Contracting                                     Phone: 470-429-5515
                                                               Elliot         5319 Dividend Drive. Decatur, GA 30035
D06            Millwork             DCourts Cabinets
                                                             Thompson                  Phone: 470-282-3870
                                                                             2915 Courtyards Drive, Suite A. Peachtree
D08       Openings (Doors)          Southern GF, co.        Shane Smith                  Corners, GA 30071
                                                                                       Phone: 404-609-9300
                                                                                1900 W Oak Cir Unit B. Marietta, GA
                                   ClearVue Glass and
D08      Openings (Glazing)                                   Eric Holt                        30062
                                       Mirror, co
                                                                                       Phone: 678-772-4770
        Openings (Safety and      Safe Haven Defense                             P.O. Box 218. Manning, SC 29102.
D08                                                         Frank Jones
           Security Film)              Southeast                                       Phone: 803-225-5194
                                                                                  183 Scott rd. Canton, GA 30115
D09     Finishes (ACT/Drywall)     Drake Interiors, Inc.    Daniel Drake
                                                                                       Phone: 678-201-9446
                                    Grateful Painting,                             PO Box 130. Rydal, GA 30171
D09       Finishes (Painting)                               Joshua Lewis
                                           LLC                                         Phone: 470-439-0305
                                                                             415 Gees Mill Business Court. Convers, GA
                                   Strictly Mechanical,
D23             HVAC                                       Kevin Beasley                       30013
                                            inc.
                                                                                       Phone: 770-880-0132
                                     Lost Mountain                                       1825 Corner Road
D26           Electrical               Electrical            Ted Scott               Powder Springs, GA 30127
                                    Contractors, Inc.                                  Phone: 404-867-3298
                                                                                1955 Evergreen Boulevard, Suite 50,
         Low Voltage (Safety                                    Brian
                                       Convergint                                         Duluth, GA 30096
            and Security)                                    Sturdevant
                                                                                       Phone: 678-977-0790
D27
                                       Integrated                                        5108 Minola Drive.
          Low Voltage (Data
                                     Communication           Otis Sams                   Lithonia, GA 30038
              Cabling)
                                     Networks (ICN)                                    Phone: 678-300-3861
                                                                                                       27 | P A G E
 LEFKO CONSTRUCTION
 Commercial Construction
 & General Contractor



              PORTION OF THE        SUBCONTRACTOR         CONTACT                      ADDRESS
DIV #
                  WORK                    NAME             PERSON                       PHONE
                                      South Western                       3630 Shallowford Rd NE. Doraville, GA
            Low Voltage (Intercom
                                    Communications of   Blake Schindler                  30340
                  Vendor)
                                      Atlanta (SWC)                              Phone: 404-787-5420
            Find Qualified subcontractor proposals attached.




                                                                                                  28 | P A G E
 LEFKO CONSTRUCTION
Commercial Construction
& General Contractor




                               INTERIOR DEMO
                     Selected price: Interior Demolition Services, Inc. (Interior demo)




LEFKO CONSTRUCTION
                                Interior Demolition Services, Inc.
                                1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                Phone (770) 792-0071       Fax (770) 792-0074
                                ryan@idsdemo.com


              B Automatic Door Opener                                Remove and Dispose

Brockett ES
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Wood Door & Transom System                  Remove and Dispose
                and Hollow Metal Frame                               Remove and Dispose
              C Interior Wood Door and Window System                 Remove and Dispose
              D Ceiling Modified Where Indicated                     Remove and Dispose
              E CCTV Camera                                          Remove and Salvage to Owner
              F Reception Desk                                       Remove and Dispose
                Any Floor Penetrating Electrical Conduit             Remove and Dispose
                Capping & Patch / Repair                             By Others

AD-121
              A Ceiling Modified Where Indicated                     Remove and Dispose
              B Exit Sign and Conduit                                Remove and Dispose

Browns Mill ES
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Hollow Metal Frame Door & Window System              Remove and Dispose
                CMU Curb                                             To Remain
              C Ceiling Modified Where Indicated                     Remove and Dispose
              D Millwork Below Counter to Provide Continuous         Remove and Dispose
                Knee Room                                            Remove and Dispose

AD-121
              A Ceiling Modified Where Indicated                     Remove and Dispose

Canby Lane ES
AD-101
            A Exterior Hollow Metal Door System                      Remove and Dispose
            B Interior Wood Door & Hollow Metal Frame                Remove and Dispose
            C Section of Existing Wall as Shown for New              Remove and Dispose
              Plaque on Wall                                         Remove and Salvage to Owner
              TV                                                     Remove and Salvage to Owner
            D Ceiling Including Lighting                             Remove and Dispose
            E Heater                                                 Remove and Dispose
            F Reception Desk                                         Remove and Dispose
              Any Floor Penetrating Electrical Conduit               Remove and Dispose
              Capping & Patch / Repair                               By Others



AD-121
              A Ceiling to be Modified                               Remove and Dispose
              B Intercom System                                      To Remain

                                                      Page 2 of 10
                                  Interior Demolition Services, Inc.
                                  1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                  Phone (770) 792-0071      Fax (770) 792-0074
                                  ryan@idsdemo.com



Cedar Grove HS
AD-101
             A Exterior Hollow Metal Door System                       Remove and Dispose
             B Interior Wood Door & Hollow Metal Frame                 Remove and Dispose
               and Section of CMU Wall Adjacent                        Remove and Dispose
             C Window System and Hollow Metal Frame                    Remove and Dispose
               and Section of CMU Wall Above & Below                   Remove and Dispose
             D Ceiling Including Lighting                              Remove and Dispose
             E Reception Desk                                          Remove and Dispose
               Any Floor Penetrating Electrical Conduit                Remove and Dispose
               Capping & Patch / Repair                                By Others
             F Door Panel Into Reception                               Remove and Dispose
               Hollow Metal Frame                                      Remove and Salvage to Owner
             G Interior Window and Section of CMU Wall                 Remove and Dispose
               Adjacent and Below                                      Remove and Dispose
             H Automatic Door Opener                                   Remove and Dispose

AD-121
              A Ceiling Including Lighting                             Remove and Dispose
              B Automatic Door Opener                                  Remove and Dispose

Chamblee HS
AD-101
              1 Ceiling to be Modified                                 Remove and Dispose
                Drywall Layer                                          Remove and Dispose

AD-121
              A Ceiling to be Modified                                 Remove and Dispose

Chamblee MS
AD-101
              A Exterior Hollow Metal Door System                      Remove and Dispose
              B Interior Hollow Metal Window System                    Remove and Dispose
              C Interior Door and Hollow Metal Frame                   Remove and Dispose
              D Portion of Wall to Extent Shown (3' x 3')              Remove and Dispose
              E Display Window, Shelving, Lighting and                 Remove and Dispose
                Metal Stud Wall Below                                  Remove and Dispose
              F Desk                                                   Retain and Relocate           R1
                Drywall Layer                                          Remove and Dispose



AD-121
                  Ceiling Areas                                        Remove and Dispose

Columbia HS
AD-101

                                                        Page 3 of 10
                              Interior Demolition Services, Inc.
                              1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                              Phone (770) 792-0071      Fax (770) 792-0074
                              ryan@idsdemo.com


             A Interior Wood Door, Window System and               Remove and Dispose
               Hollow Metal Frame                                  Remove and Dispose
             B Reception Desk                                      Retain and Relocate           R1
               Any Floor Penetrating Electrical Conduit            Remove and Dispose
               Capping & Patch / Repair                            By Others
             C Security Desk                                       Retain and Relocate           R1
               Any Floor Penetrating Electrical Conduit            Remove and Dispose
               Capping & Patch / Repair                            By Others
             D Relocate Sprinkler Head                             By Others
             E Television and Associated Electrics                 Remove and Salvage to Owner

               Brick to Attach Header to CFS Stud/CMU Wall         Remove and Dispose            R1
               (4 ea)
AD-121
             A Relocate Sprinkler Heads                            By Others
             B Television and Associated Electronics               Remove and Salvage to Owner

Coralwood
AD-101
             A Hollow Metal Door System                            Remove and Dispose
             B Interior Hollow Metal Door System                   Remove and Dispose
             C Interior Wood Door and Transom System               Remove and Dispose
                and Hollow Metal Frame                             Remove and Dispose
             D Interior Wood Door and Hollow Metal Frame           Remove and Dispose
             E Interior Wood Door and Glazed Sidelite and          Remove and Dispose
                Hollow Metal Frame                                 Remove and Dispose
             F Interior Window System                              Remove and Dispose
             G Section of CMU Wall                                 Remove and Dispose
             H Ceiling Including Lighting                          Remove and Dispose
              I Reception Desk                                     Remove and Dispose
                Any Floor Penetrating Electrical Conduit           Remove and Dispose
                Capping & Patch / Repair                           By Others
             J Low Height Wall and Gate                            Remove and Dispose
             K Automatic Door Opener                               Remove and Dispose
             K Equipment                                           Remove and Salvage to Owner
             L Furniture                                           Retain and Protect            R1
                GWB Layer on Vestibule Side

AD-121
             A Ceiling to be Modified                              Remove and Dispose
             B Exit Sign                                           Remove and Salvage to Owner
             C Automatic Door Opener                               Remove and Dispose

Dunaire ES
AD-101
             A Ceiling Lighting                                    Remove and Dispose
             B Interior Hollow Metal Frame Door and Window         Remove and Dispose
             C Portion of Wall to Extents Shown                    Remove and Dispose

                                                    Page 4 of 10
                                 Interior Demolition Services, Inc.
                                 1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                 Phone (770) 792-0071       Fax (770) 792-0074
                                 ryan@idsdemo.com


               D Back Desk                                            Remove and Dispose
                 Any Floor Penetrating Electrical Conduit             Remove and Dispose
                 Capping & Patch / Repair                             By Others
               E Portion of Newly Purchased Desk up to                Remove and Dispose
                 the Module Split of Desk 4'-0" VIF                   Remove and Dispose

AD-121
               A Ceiling to be Modified                               Remove and Dispose

Dunwoody HS
AD-101
               A Interior Wood Door and Hollow Metal Frame            Remove and Dispose
               B Section of CMU Wall                                  Remove and Dispose
               C Display Boards                                       Remove and Dispose
               D Ceiling to be Modified                               Remove and Dispose
               E Security Desk                                        Retain and Relocate           R1
                 Any Floor Penetrating Electrical Conduit             Remove and Dispose
                 Capping & Patch / Repair                             By Others
               F Reception Desk                                       Remove and Dispose
                 Any Floor Penetrating Electrical Conduit             Remove and Dispose
                 Capping & Patch / Repair                             By Others

AD-121
               A Ceiling to be Modified                               Remove and Dispose
               B Automatic Door Opener                                Remove and Dispose

Flat Shoals ES
AD-101
              A Exterior Hollow Metal Door System                     Remove and Dispose
              B Interior Wood Door & Hollow Metal Frame               Remove and Dispose
              C Section of CMU Wall                                   Remove and Dispose
              D Relocate Fire Alarm Panel                             By Others
              E Ceiling to be Modified                                Remove and Dispose
               F Reception Desk                                       Remove and Dispose
                  Any Floor Penetrating Electrical Conduit            Remove and Dispose
                  Capping & Patch / Repair                            By Others
              G Desk                                                  Retain and Relocate           R1
              H Desk                                                  Retain and Relocate           R1
                I Exit Sign                                           Remove and Salvage to Owner
               J Automatic Door Opener                                Remove and Dispose

AD-121
               A Ceiling to be Modified                               Remove and Dispose
               B Automatic Door Opener                                Remove and Dispose
               C Exit Sign                                            Remove and Salvage to Owner

Hightower ES
AD-101

                                                       Page 5 of 10
                                Interior Demolition Services, Inc.
                                1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                Phone (770) 792-0071      Fax (770) 792-0074
                                ryan@idsdemo.com


              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Hollow Metal Frame Window System            Remove and Dispose
                and Section of CMU Wall Below                        Remove and Dispose
              C Ceiling to be Modified                               Remove and Dispose
              D Exit Sign                                            Remove and Salvage to Owner

AD-121
              A Ceiling to be Modified                               Remove and Dispose
              B Exit Sign                                            Remove and Salvage to Owner

Jolly ES
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Hollow Metal Frame Door and Window System            Remove and Dispose
              C Ceiling to be Modified                               Remove and Dispose
              D Reception Desk                                       Remove and Dispose
                Any Floor Penetrating Electrical Conduit             Remove and Dispose
                Capping & Patch / Repair                             By Others
              E Pipe Rod                                             Remove and Dispose
                Any Floor Penetrating Electrical Conduit             Remove and Dispose
                Capping & Patch / Repair                             By Others
              F Exit Sign                                            Remove and Salvage to Owner
              G Automatic Door Opener                                Remove and Dispose

AD-121
              A Ceiling to be Modified                               Remove and Dispose
              B Exit Sign                                            Remove and Salvage to Owner

Kingsley ES
AD-101
              A Exterior Window System                               Remove and Dispose
              B Portion of Wall to Extents Shown                     Remove and Dispose
                Relocate Electrical Fixtures, Conduit & Outlets      By Others
              C Sink and Counter                                     Remove and Dispose
                Repair Wall and Cap Utilities                        By Others
              D Wood Cabinets                                        Remove and Dispose
                Patch and Repair Wall and Floor                      By Others
              E Marker Boards                                        Remove and Dispose
                Patch and Paint                                      By Others
              F Reception Desk                                       Remove and Dispose
                Floor Penetrating Utiliites                          By Others
                Patch and Repair                                     By Others
              G Brick Sill                                           Remove and Dispose
              H Hollow Metal Door                                    Remove and Dispose

AD-121
              A Ceiling and Light Fixtures                           Remove and Dispose


                                                      Page 6 of 10
                                Interior Demolition Services, Inc.
                                1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                Phone (770) 792-0071      Fax (770) 792-0074
                                ryan@idsdemo.com


S-101
                Foundation for New Canopy System                     Excavate and Dispose          R1



Lithonia HS
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Hollow Metal Frame Window                   Remove and Dispose
                and Section of CMU Below                             Remove and Dispose
              C Interior Wood Door, Transom System and               Remove and Dispose
                Hollow Metal Frame                                   Remove and Dispose
              D Ceiling to be Modified                               Remove and Dispose
              E Reception Desk                                       Remove and Dispose
                Floor Penetrating Utiliites                          By Others
                Patch and Repair                                     By Others
              F Equipment                                            Remove and Salvage to Owner

AD-121
              A Ceiling to be Modified                               Remove and Dispose
              B Exit Sign                                            Remove and Salvage to Owner

Margaret Harris
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Hollow Metal Window System                  Remove and Dispose
              C Interior Hollow Metal Door and Frame System          Remove and Dispose
              D Ceiling to be Modified                               Remove and Dispose
              E Reception Desk                                       Remove and Dispose
                Floor Penetrating Utiliites                          By Others
                Patch and Repair                                     By Others

AD-121
              A Ceiling Tiles and Grid as Needed for New             Remove and Dispose
              B Automatic Door Opener                                Remove and Dispose

McLendon ES
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Hollow Metal Door and Window System         Remove and Dispose
              C Portion of Wall to Extents Shown                     Remove and Dispose
              D Wall Mounted Cabinet                                 Remove and Salvage to Owner
              E ADO Button Pedestal                                  Remove and Dispose
                Patch and Repair Terrazzo                            By Others
              F Wall Mounted ADO Button                              Remove and Dispose
                Provide Sainless Steel Cover Plate                   By Others

AD-121

                                                      Page 7 of 10
                               Interior Demolition Services, Inc.
                               1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                               Phone (770) 792-0071      Fax (770) 792-0074
                               ryan@idsdemo.com


             A Modify Portion of Stud Header                        Remove and Dispose
             B Automatic Door Opener                                Remove and Dispose

Panola Way ES
AD-101
            A Ceiling to be Modified                                Remove and Dispose
            B Interior Hollow Metal Frame Door and                  Remove and Dispose
              Window Frame System                                   Remove and Dispose
            C Exterior Storefront                                   Remove and Dispose
            D Portition of Desk up to Module Split                  Remove and Dispose
              of Desk 5'-0" VIF                                     Remove and Dispose

AD-121
             A Ceiling to be Modified                               Remove and Dispose
             B Light                                                Remove and Salvage to Owner
             C Devices on Demolished Ceiling Tiles                  Remove and Salvage to Owner

Robert Shaw ES
AD-101
             A Exterior Hollow Metal Door System                    Remove and Dispose
             B Interior Hollow Metal Door &Hollow Metal Frame       Remove and Dispose
             C Wall to Extents Shown                                Remove and Dispose
             D Fire Alarm Strobes and Conduit                       Remove and Dispose
             E Video Doorbell                                       Remove and Salvage to Owner
             F Ceiling to be Modified                               Remove and Dispose
             G Moveable Furniture                                   Remove and Salvage to Owner

AD-121
             A Ceiling to be Modified                               Remove and Dispose

Salem MS
AD-101
             A Exterior Hollow Metal Door System                    Remove and Dispose
             B Interior Wood Door and Window System                 Remove and Dispose
               and Hollow Metal Frame                               Remove and Dispose
             C Ceiling to be Modified                               Remove and Dispose
             D Section of CMU Wall                                  Remove and Dispose
             E Reception Desk                                       Remove and Dispose
               Floor Penetrating Utiliites                          By Others
               Patch and Repair                                     By Others

AD-121
             A Ceiling to be Modified                               Remove and Dispose

Stone Mountain MS
AD-101
             A Exterior Hollow Metal Door System                    Remove and Dispose
             B Interior Door and Hollow Metal Frame                 Remove and Dispose

                                                     Page 8 of 10
                                Interior Demolition Services, Inc.
                                1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                Phone (770) 792-0071      Fax (770) 792-0074
                                ryan@idsdemo.com


              C Hollow Metal Window System and                       Remove and Dispose
                Portion of Wall                                      Remove and Dispose
              E Millwork Portion of Below Countertop to              Remove and Dispose
                Provide Knee Room                                    Remove and Dispose

AD-121
              A Ceiling to be Modified                               Remove and Dispose

Tucker MS
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Hollow Metal Frame Window System            Remove and Dispose
              C Interior Wood Door and Hollow Metal Frame,           Remove and Dispose
                Enlarge Opening to 7' x 3' Door                      Remove and Dispose
              D Section of Metal Stud Wall                           Remove and Dispose
              E Desk                                                 Retain and Relocate           R1

                GWB Layers as Illustrated                            Remove and Dispose            R1

AD-121
                Ceiling Areas Specified                              Remove and Dispose

Woodward ES
AD-101
              A Exterior Hollow Metal Door System                    Remove and Dispose
              B Interior Wood Door, Window System and                Remove and Dispose
                Hollow Metal Frame                                   Remove and Dispose
              C Interior Wood Door and Transom System                Remove and Dispose
                and Hollow Metal Frame                               Remove and Dispose
              D Ceiling to be Modified                               Remove and Dispose
              E Exit Sign                                            Remove and Salvage to Owner
              F Bench Seating                                        Retain and Relocate           R1
              G Cabinet                                              Retain and Relocate           R1

                Hauling and Disposal (Dumpsters)                     Included

                Base Bid:                                                 132,480                  R2

                MEP Made Safe / Cut / Capped By Others

Resources

                Days            25-35 (Most Schools Should be Completed in 1 Day)
                Crew            6-Man + Foreman
                Equipment       Dump Trailer, Scissor Lift

                                                                                                   R2
Note:           Electricians will handle the removal of all exit sign-related components.

                                                      Page 9 of 10
                                  Interior Demolition Services, Inc.
                                  1092 W Atlanta St., Bldg 200, Suite 200, Marietta, GA 30060

                                  Phone (770) 792-0071      Fax (770) 792-0074
                                  ryan@idsdemo.com


                 Fire alarm crew will remove strobes and conduits.
                 Plumbers will remove the sink at Kingsley ES to allow for proper capping.
                 Glazing subcontractors will address windows that do not require modifications to the openings.
                 Drywall subcontractors will modify ceilings as needed to accommodate new storefronts,
                 per the owner's request to preserve as many ceiling tiles as possible.

Exclusions:
                 Permits / Notifications                               MEP Disconnects and Capping
                 Pollution/Professional Insurance                      Temp Barricades / Temporary Entrance
                 Floor Grinding or Prep                                Items to Be Relocated / Salvaged
                 Sprinkler System                                      Hazardous or Regulated Materials
                 Shoring and Bracing                                   Surface Patching or Repairing
                 Replace with New                                      Clean & Repair
                 No Layouts of Any Kind                                Protection by Others
                 GPR Scanning




                                     TERMS AND CONDITIONS

IDS as subcontractor will not execute any contract for less than $20,000 that contains a provision for
the withholding of retainage.

For contracts of $20,000 or more, IDS will discount the contract amount by 2% of the bid amount
for contracts submitted without a retainage provision. 1% for payment of retainage within 120 days
of completion.

For worked performed by IDS under contract for which payment has not been received seventy days
after the last day on the jobsite, IDS may file a mechanics lien on said property. The filing of
mechnics liens is required to secure our financial interest under Georgia law.




                                                       Page 10 of 10
School            Price                Revised Price 6/26/25
Avondale ES           $     5,120.00   $                         5,920.00
Avondale HS           $     3,000.00   $                         3,800.00
Brockett ES           $     4,790.00   $                         5,590.00
Browns Mill ES        $     5,200.00   $                         6,000.00
Canby Lane ES         $     5,140.00   $                         5,940.00
Cedar Grove HS        $     5,320.00   $                         6,120.00
Chamblee HS           $     3,000.00   $                         4,300.00
Chamblee MS           $     5,200.00   $                         6,000.00
Columbia HS           $     4,580.00   $                         5,380.00
Coralwood             $     5,530.00   $                         6,330.00
Dunaire ES            $     4,220.00   $                         5,020.00
Dunwoody HS           $     5,010.00   $                         5,810.00
Flat Shoals ES        $     5,100.00   $                         5,900.00
Hightower ES          $     4,510.00   $                         5,310.00
Jolly ES              $     5,320.00   $                         6,120.00
Kingsley ES           $     5,270.00   $                        13,260.00
Lithonia HS           $     5,420.00   $                         6,220.00
Margaret Harris       $     4,000.00   $                         4,800.00
McLendon ES           $     4,230.00   $                         5,030.00
Panola Way ES         $     3,790.00   $                         4,590.00
Robert Shaw ES        $     5,150.00   $                         5,950.00
Salem MS              $     4,160.00   $                         4,960.00
Stone Mtn MS          $     4,570.00   $                         5,370.00
Tucker MS             $     3,900.00   $                         4,700.00
Woodward ES           $     3,260.00   $                         4,060.00

Total             $       114,790.00 $                         142,480.00
QUOTE
Date:        08/07/2025                               FIGOZZ MASONRY
Quote No.:   131                                      7231 Capps Ferry Rd Douglasville ,GA 30135
                                                      678-598-1319
                                                      figozzmasonryllc@yahoo.com



Bill To:                                                              Ship To:
LEFKO CONSTRUCTION                                                    Project: BROCKETT ES (3)
INC                                                                   ( GROUP 1 )
105 Mansell Circle Roswell                                            Address ;1855 BROCKETT
GA 30075                                                              ROAD TUCKER GA 30084
office 404-846-6372                                                   CONCRETE SOW

 Qty Item             Description                                         Unit Price               Total
   1   CONCRETE       Concrete scope including ( Setting                  $3,250.00            $3,250.00
                      /Installation of (2) 3/8 DIA HILTI KWIK-
                      HUS-EZ W/1-1/8'',(provided by metal
                      subcontractor ) embed at EA angle for
                      connection of ( 1 ) HSS post to existing
                      concrete above ,per detail 16 on drawing
                      S-101 )NOT INCLUDING CONCREETE
                      SCAN




                                                                                       Total   $3,250.00

                             Please contact me if you have any question

                                    Thank you for your business.
Commercial Construction
& General Contractor




                               INTERIOR DEMO
                 Selected price: Atlanta Cargo Transportation, co. (Furniture relocation)




LEFKO CONSTRUCTION
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                        Estimate
      Decatur, GA 30036                                                                               DATE      ESTIMATE #
      404-329-4505
                                                                                                    6/25/2025      2690



         NAME / ADDRESS

       Lefko Group




                                                  P.O. NO.               TERMS            PROJECT        RELOCATION SPEC.




                         DESCRIPTION                                          QTY            COST               TOTAL


Avondale ES - Secure vestibule, reception                                           4.5             165.50            744.75
Return items to original location                                                   6.5             165.50          1,075.75

Avondale HS - Secure vestibule, reception room                                      4.5             165.50            744.75
Return items to original location                                                   6.5             165.50          1,075.75

Brockett ES - Secure vestibule, reception room                                      4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Browns Mill ES - Secure vestibule and waiting/reception room                        4.5             165.50           744.75
Return items to original location                                                   5.5             165.50           910.25

Canby Lane ES - Secure vestibule, reception                                         4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Cedar Grove HS - Corridor, secure vestibule                                         4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Chamblee HS - Secure vestibule, corridor                                            4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Chamblee MS - Secure vestibule, corridor, reception                                 5.5             165.50            910.25
Return items to original location                                                   7.5             165.50          1,241.25

Columbia HS - reception, secure vestibule                                           5.5             165.50            910.25
Return items to original location                                                   7.5             165.50          1,241.25

Coralwood Education School - Secure vestibule, reception, corridor                  4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00
We appreciate your business. Have a blessed day.
                                                                                          TOTAL




                                                                     Page 1
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                    Estimate
      Decatur, GA 30036                                                                           DATE      ESTIMATE #
      404-329-4505
                                                                                                6/25/2025      2690



          NAME / ADDRESS

       Lefko Group




                                                      P.O. NO.          TERMS         PROJECT        RELOCATION SPEC.




                          DESCRIPTION                                     QTY            COST               TOTAL


Dunaire ES - Secure vestibule, reception lobby adm                              5.5             165.50            910.25
Return items to original location                                               7.5             165.50          1,241.25

Dunwoody HS - Secure vestibule , corridor                                       5.5             165.50           910.25
Return items to original location                                                 6             165.50           993.00

 lat Shoals ES - secured vestibule, reception                                   4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

Hightower ES - Secure vestibule, corridor                                       4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

 olly ES - Corridor, secure vestibule                                           4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

  ingsley ES - admin vestibule, secure vestibule, kindergarten                   7              165.50          1,158.50
classroom
Return items to original location                                                9              165.50          1,489.50

Lithonia HS - Secure vestibule, corridor, reception                             4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

Margaret Harris Comp School - Secure vestibule, corridor                        4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

McLendon ES - Secure vestibule, corridor                                        4.5             165.50           744.75
Return items to original location                                                 6             165.50           993.00

Panola Way ES - Security vestibule, corridor                                    5.5             165.50           910.25
We appreciate your business. Have a blessed day.
                                                                                      TOTAL




                                                                 Page
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                   Estimate
      Decatur, GA 30036                                                                         DATE       ESTIMATE #
      404-329-4505
                                                                                               6/25/2025      2690



          NAME / ADDRESS

       Lefko Group




                                                   P.O. NO.          TERMS         PROJECT          RELOCATION SPEC.




                          DESCRIPTION                                  QTY            COST                 TOTAL

Return items to original location                                             6               165.50            993.00

Robert Shaw heme ES - reception      secure vestibule                        4.5              165.50            744.75
Return items to original location                                              6              165.50            993.00

Salem MS - reception, secured vestibule                                      4.5              165.50            744.75
Return items to original location                                              6              165.50            993.00

Stone Mountain MS - Secure vestibule, lobby                                  5.5              165.50             910.25
Return items to original location                                            6.5              165.50           1,075.75

 ucker MS - Secure vestibule                                                 4.5              165.50            744.75
Return items to original location                                              6              165.50            993.00

Woodward ES - Secure vestibule, lobby                                        4.5              165.50            744.75
Return items to original location                                              6              165.50            993.00

Additional Supplies                                                           1              2,453.00          2,453.00
25 rolls of tape   45
8 rolls of Shrink Wrap    208
15 Speed packs      450
625 boxes      1750

15   Contingency                                                                             7,306.54          7,306.54




We appreciate your business. Have a blessed day.
                                                                                   TOTAL                      56,016.79




                                                              Page
Commercial Construction
& General Contractor




                               INTERIOR DEMO
                    Selected price: Integrated Scanning Solutions (Concrete Scanning)




LEFKO CONSTRUCTION
                                                                                                                   Estimate
                                                                         ESTIMATE#                           1070028394
           11330 Vanstory Dr Ste 115
                                                                             DATE                            07/01/2025
             Huntersville, NC 28078
                 (877) 337-2267                                               PO#
              invoice@intscan.com

                            CUSTOMER                                                        SERVICE LOCATION
                    LEFKO Construction                                                      LEFKO Construction
                        Julio Arellanes                                                        Julio Arellanes
             105 Mansell Circle, Roswell GA 30075                                             Brockett ES #3
                       (404) 365-8966                                                       1855 Brockett Road
                                                                                           Tucker , Georgia 30084
                                                                                              (404) 365-8966


                    Requested by: Andrea Torres
                    Scope: Performed slab-on-grade concrete scanning for the vestibule project using a high-frequency
                    GPR system. Additionally, inspected the designated area using a utility GPR to evaluate the presence
 DESCRIPTION        of subsurface utilities.

                    Note: Pricing listed below is per site visit. If the area is prepared and accessible upon arrival,
                    only one visit should be required.



                                               Standard Hours Rate

 Description                                                                                Qty       Rate               Total

 Concrete Scanning Slab on Grade
 Concrete Scanning using Ground Penetrating Radar. Scan slab on grade to a depth of
 up to 18". All located obstructions will be marked directly on the concrete surface. 6.00            250.00             1,500.00
 Price includes PDF with notated photos emailed.
 Minimum fee per mobilization $750.

 Out of Area Mobilization                                                                   4.00      125.00             500.00



                   CUSTOMER MESSAGE                                  Estimate Total:                                     $2,000.00
Ground Penetrating Radar & 3D Laser Scanning are
technologies designed to gather data for
interpretation. These technologies are limited in
their ability by the conditions of any given project. Any
information collected by these technologies should be
verified by other available means.
No liability is accepted by iSS.
For more information on -
Concrete scanning: https://goo.gl/XAsv4E
Utility Locating: https://goo.gl/QbEuWM


                   PRE-WORK SIGNATURE




Signed By:
                                 LEFKO CONSTRUCTION
PROPOSAL




GPRS is the nation’s premier company specializing in the detection of
underground utilities and underground storage tanks, video pipe inspection,
leak detection and the imaging of concrete structures. Our services enable
your projects to stay safe, on time and on budget.

SIM-CERTIFIED FIELD STAFF
Our SIM-Certified Project Managers are equipped with the latest technology, industry
leading training and a methodology that has produced over 99.8% accuracy on over
300,000 projects. Visit SIMSPEC.ORG today for details.

NATIONWIDE FOOTPRINT
GPRS is the largest company of our kind. With highly trained Project Managers
across America we can provide rapid response to your job site — wherever it
may be located.

CONSULTATIVE APPROACH
GPRS Project Managers are trained to help you remove barriers that could impact
your project being safe, on time and on budget. They provide industry-leading
deliverables such as CAD, 3D drawings, NASSCO reports, and a .KMZ and .PDF
map is included with every utility locating project which accelerates planning,
organizes operations and increases communication.




                           VISUALIZING
                           THE BUILT
                                                        TM



                               ABOVE
                                      WORLD
                                        AND
                                     BELOW GROUND



                                                                                       GPRSINC.COM
 June 24, 2025                                                                                                                                   Submitted By:
 Client: LEFKO CONSTRUCTION                                                                                                                      Chayse Maunz
 Project Address: 1855 Brockett Road Tucker, GA 30084                                                                                To schedule, please email:
 Quote Number: GPRSQUOTE­212836                                                                                                       georgiainfo@gprsinc.com
 GPRS Opportunity Name/Number: 1855 Brockett Road, Tucker, GA, 30084



GPRS appreciates the opportunity to provide this proposal. We encourage you to visit our website (www.gprsinc.com) and contact any of
the numerous references listed. Our insurance certificate and W­9 can also be downloaded here. Please feel free to contact us if you have
any questions or need additional information. Visit for an overview of our industry­leading best practices.

SCOPE OF WORK
Concrete Anchors: We understand the scope of work on this project is to scan for reinforcing or conduits in a slab near 1 proposed anchor
locations (overhead). Client will need to provide a ladder or lift to access the spot, as stated, 10' high. To avoid additional charges, the
anchor locations should be laid out, marked, and cleared of obstructions before our arrival. We will scan an area of approximately 12”x12”
around each proposed location, and our findings will be marked directly onto the surface using a marker, chalk, or other methods depending
on the site conditions. We will label known conduits or cables as such by detecting changes in patterns, depths, etc. However, these items
can look identical to reinforcing, so all markings should be avoided. GPR cannot determine the diameters of reinforcing or conduits, so avoid
all markings by at least 1” or more. Please visit www.simspec.org for an overview of our industry­leading best practices that will be applied
to this project.

• GPRS is not responsible for housekeeping. Any debris, equipment, or other obstructions in the area at the time of scanning could potentially block out needed data.
• All of our technicians have OSHA­10 safety training or greater. Site­specific safety training is not included in this quote. Please notify us if this project requires
  additional safety training.

EQUIPMENT
• Concrete Scanning GPR Antenna. This GPR Antenna is handheld and rolls over the surface. The device displays scan data on a screen, and
  the operator marks detected objects on the surface in real­time. The antenna needs a reasonably smooth, unobstructed surface for
  scanning and cannot scan within 2”­4” of obstructions such as walls and metal tracks. Ideally, the client removes obstacles such as these
  before our work begins. The total effective scan depth can be as much as 18” or more with this antenna but can vary depending on the
  concrete conditions, composition, and other factors such as the spacing of the reinforcing. Depth accuracy depends on obtaining a precise
  depth calibration for the concrete. This device does not emit harmful radiation and can be safely operated while people are in close
  proximity. For more information, please visit Link
• Electromagnetic Pipe Locator. This receiver can passively detect the signals from live AC power or radio signals traveling along some
  conductive utilities. Operators can connect a transmitter directly to accessible metallic pipes, risers, or tracer wires to generate a current
  at a specific frequency. The receiver can then detect the resulting signal along the pipe or tracer wire. Various factors may impact this
  device's effectiveness, including (but not limited to) access to the utility, conductivity, grounding, and interference from other utilities.
  The depths provided should always be treated as estimates as their accuracy can be affected by multiple factors. For more information,
  please visit: Link




 GPRSQUOTE-212836 v.1                                                                                                                                    Page 2 of 3
PROJECT COSTS
                    SERVICE                                                                          DESCRIPTION
 FIELD SERVICES                                    Described on Page 2
 JOB SUMMARY REPORT                                PDF including a brief description of equipment used, findings, limitations, and site photos sent at
                                                   the conclusion of every job.
 TOTAL                                                                                                                                                       $700.00

GENERAL TERMS & CONDITIONS
This proposal is subject to the General Terms and Conditions for Services of Ground Penetrating Radar Systems, LLC posted at Link (the
“Terms and Conditions”) and is hereby incorporated by reference into and made a part of this proposal. Customer acknowledges it has
read and agrees to be bound by such Terms and Conditions. In the event of any conflict between the terms of this proposal and the Terms
and Conditions, the Terms and Conditions will prevail. Customer also acknowledges that Ground Penetrating Radar Systems, LLC may,
from time to time and at its discretion, modify the Terms and Conditions and Customer agrees to be bound by such Terms and Conditions
as modified.

1.    Customer agrees to meet and perform all requirements described in this document and has fully read and understands all items listed within this document.
2.    It is the customer’s responsibility to prepare the site for scanning, including clearly identifying areas to be scanned, securing access to all areas required for
      scanning, removing and keeping these areas clear and free of obstructions. Delays caused by customer’s failure to do so may result in an increased price.
3.    GPRS does not conduct an investigation, analysis, or interpretation of soil composition, soil/concrete conditions, or geophysical, geological, engineering, or land
      surveying information. The customer acknowledges understanding that we are merely reporting retrieved data and that we do NOT provide geophysical,
      geological, engineering, or land surveying services. Customer should contact a professional in those fields if such services are needed. Data collected during may
      only be suitable for use within the scope of this proposal.
4.    If any work to be performed is within a road or street, unless specifically included by GPRS within this proposal, it is the customer’s responsibility to provide
      adequate traffic control to allow GPRS’ personnel to safely and efficiently work in the road/street.
5.    Time­on­site in excess of 8­hours will be billed at overtime rates.
6.    This price assumes that we will be given access to perform the work during normal, weekday business hours. Work performed outside of 6am­5pm Monday­
      Friday will be billed at overtime rates.
7.    These rates assume that there are no certified payroll or prevailing wage requirements for this work. If GPRS receives notice that any of these conditions exist,
      there will be additional costs.
8.    If this proposal is not accepted within 90 days of June 24, 2025, then the pricing may be subject to review.
9.    If for some reason the technician arrives on site and the work is cancelled there will be a charge of $500 per requested technician.
10.   If your project is in WV, SD, NM, or HI: State sales tax is not included in the total on this proposal, but will be included on the invoice.
11.   Payment Terms are Net 30; or as specified if a current Master Service Agreement is in place.

ACCEPTED AND AGREED
Print Name:_____________________ Signature:_____________________ Date:________________

Company Phone/Email:___________________________ PO #:___________ Job #:______________




 GPRSQUOTE-212836 v.1                                                                                                                                      Page 3 of 3
Commercial Construction
& General Contractor




                                     CONCRETE
                          Selected price: Paramount Cutting Contracting, LLC




LEFKO CONSTRUCTION
                             PARAMOUNT CUTTING CONTRACTING LLC (DBE | MBE | SBO | AABE Certified)
                                 Phone: 404-777-1485 ext 2 | Fax: 470-200-3241 | services@paramountcutting.org | www.paramountcuttingorg.org




                 CONCRETE POUR-BACK PROPOSAL                                                 7/3/2025

               PROJECT ID:
               DCSD - Brockett Elementary School Security Vestibule
               ADDRESS:
               1855 Brockett Road, Tucker, GA, 30084


    ITEM #                                          ITEM                                              DESCRIPTION          UNIT         QUANTITY     PRICE


               Core for 3/8" DIA HILTI KWIK- HUS-EZ



      1        3/8" Dia W/ 1-1/8" Embed                                                                  V.I.F.            EA                2       $520



               Note: All quantities shall be based on site measurement / consumption                                                                  Subtotal    $520


               Mobilization, labor, equipment and final cleaning                                                                                                 $295.00

               OVERHEAD & CONTINGENCY                                                                                                                            $40.75


                TOTAL BASE BID                                                                                                                                   $855.75

We are pleased to submit our bid proposal for concrete cutting works based on plans provided.


Scope of Work:



1. Core for 3/8" DIA HILTI KWIK- HUS-EZ



General Notes:
- This proposal is valid for next 180 days only.
- Work to be completed during normal daylight hours with no noise restrictions
- Contractor assumes no extraordinary delays, especially caused by other subcontractors
- Estimate considers all concrete to be 6 '', any excess depth will be added on at $.5 per inch foot of cut
- Projected timeframe for work is 1 days. Mobilization includes all travel, equipment, and breakdown
- This proposal is based off slab sawing only, if conditions require Hand Sawing there will be a change
 order process as hand sawing prices differ from slab sawing prices.
- This proposal and price is only for the scope of work explicitly outlined. Please refer us to any
 other saw cutting and/or demolition work in the project.

                                    We look forward to working with you on this project. If you have any questions, please do not hesitate to call

                                                            © This document shouldn’t be copied, edited or reproduced.
QUOTE
Date:        08/07/2025                               FIGOZZ MASONRY
Quote No.:   131                                      7231 Capps Ferry Rd Douglasville ,GA 30135
                                                      678-598-1319
                                                      figozzmasonryllc@yahoo.com



Bill To:                                                              Ship To:
LEFKO CONSTRUCTION                                                    Project: BROCKETT ES (3)
INC                                                                   ( GROUP 1 )
105 Mansell Circle Roswell                                            Address ;1855 BROCKETT
GA 30075                                                              ROAD TUCKER GA 30084
office 404-846-6372                                                   CONCRETE SOW

 Qty Item             Description                                         Unit Price               Total
   1   CONCRETE       Concrete scope including ( Setting                  $3,250.00            $3,250.00
                      /Installation of (2) 3/8 DIA HILTI KWIK-
                      HUS-EZ W/1-1/8'',(provided by metal
                      subcontractor ) embed at EA angle for
                      connection of ( 1 ) HSS post to existing
                      concrete above ,per detail 16 on drawing
                      S-101 )NOT INCLUDING CONCREETE
                      SCAN




                                                                                       Total   $3,250.00

                             Please contact me if you have any question

                                    Thank you for your business.
Commercial Construction
& General Contractor




                              MASONRY
                          Selected price: Figozz Masonry, LLC




LEFKO CONSTRUCTION
QUOTE
Date:        07/31/2025                                 FIGOZZ MASONRY
Quote No.:   131                                        7231 Capps Ferry Rd Douglasville ,GA 30135
                                                        678-598-1319
                                                        figozzmasonryllc@yahoo.com



Bill To:                                                                 Ship To:
LEFKO CONSTRUCTION                                                       Project: BROCKETT ES 3
INC                                                                      Address ;1855 BROCKETT
105 Mansell Circle Roswell                                               ROAD TUCKER GA 30084.
GA 30075                                                                 MASONRY SCOPE
office 404-846-6372

 Qty Item             Description                                           Unit Price                Total
   1   MASONRY        Masonry including ( -Patch to match existing         $13,800.00            $13,800.00
                      CMU partition after demolition of (1) exisiting
                      exterior hollow metal door system at detail A1
                      on drawing AD-101 ,Demolition Note A .
                      -Patch to match existing CMU partition after
                      demolition of (1) existing interior wood door
                      and window system at detail A5 on drawing
                      AD-101,Demolition Note C. -Patch ,prepare
                      and install (1) HM door frame with transom (
                      supplied by door subcontractor )after
                      demolition of (1) existing interior hollow metal
                      frame wood door with transom system at
                      detail A5 on drawing AD -101 ,Demolition
                      note B ,per door schedule on drawing A-600
                      .*Grout solid and apply continous joint sealant
                      ,on all sides ,at head of HM door frame ,per
                      detail B3 on drawing A-600 . *Grout solid and
                      install frame anchors (supplied by door
                      subcontractor ) at jamb of HM door frame ,per
                      detail B4 on drawing A-600 . -Grout cells
                      with 2500 PSI grout at header ( supplied and
                      installed by drywall subcontractor ) to (
                      E)CMU wall connections on one end ,from
                      floor to ceiling ,for (1) new interior aluminum
                      storefront system marked as !SF-1 in detail
                      1on drawing A-101 and detail A2 on drawing
                      A-600 ,also shown in detail 1 on drawing
                      S-101 ,grout shall conform to ASTM C476.
                      -Grout cells with 2500 PSI grout at header
                      (supplied and installed by drywall
                      subcontractor )to (E) CMU wall connections
                      on one end ,from floor to ceiling ,for (1) new
                      interior aluminum storefront system with (1)
                      new transaction window shown in detail 1 on
                      drawing A-101,floor Plan note #4,also shown
                      in detail 1 on drawings S-101 .Grout shall
                      conform to ASTM C476.)



                                                                                         Total   $13,800.00

                             Please contact me if you have any question

                                    Thank you for your business.
Commercial Construction
& General Contractor




                                   METAL
                          Selected price: Silver Oak Contracting




LEFKO CONSTRUCTION
                                                                Formerly DBA Builder’s Steel Supply
Date: 07/28/2025

From: Andrew Pierce / andrew@silveroakinc.com                                         Project: CMAR – DCSD – Group 1 Security Vestibules – REV 1

We offer to detail, furnish, fabricate, prime, deliver and install the structural steel as per our inclusions.

Bid set drawings as provided by GC dated: Architectural & Structural drawings dated 04/30/25.
Addendums applied: Addendum #1 acknowledged and incorporated. RFI #46 & #38 acknowledged & incorporated – REV 1.

Sheets referenced:
*Structural and Misc. Steel indicated and/or detailed on the following sheets were used when generating this quote.
**Note - When discrepancies exist between the structural design drawings and the architectural design drawings; structural sheets shall govern.
***Architectural sheets are used as reference only for Miscellaneous Steel as it applies to this project.

Project Specific Inclusions/Breakdown:
     1) Columns with associated steel elements (Baseplates, anchor rods, etc…).
     2) Miscellaneous angles for kickers and/or connections to existing beams (where shown on applicable details).
     3) Galvanized RTU Frames on Kingsley ES #16 – REV 1.
     4) Lintels per specified details and locations – Install included.
     5) Base plates, miscellaneous plates, steel angles (Where shown on applicable details).
     6) PE Stamp of connection details.
     7) Equipment to erect scope of work on each project.
     8) Details as they apply per their specifications.
     9) Detailing, Fabrication, Delivery, Erection, Sales Tax.

Breakdown:
   •  3. Brockett ES Security Vestibule:
           o     Pages/Details included – S-001, S-101/1, 16, 17.
           o Base Price: $7,500
           o Background Check Add Alt – (+$200)
           o (1) Mobilization included – (1) full work day to complete scope of work.

     •    5. Canby Lane ES Security Vestibule:
               o    Pages/Details included – A-321/A4, AD-101/A5, A-600/B3, RFI#38 Response – REV 1.
                       ▪    (1) additional New channel lintel ((2) total) – REV 1.
                       ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
               o Base Price: $8,000
               o Background Check Add Alt – (+$200)
               o (1) Mobilization included – (2) full work days to complete scope of work.
               o REV 1 Price: $11,400
                       ▪    This price assumes no equipment remobilization - work to be completed in (2) back to back days.
                                 •     Additional costs will be incurred if equipment remobilization is required.

     •    6. Cedar Grove HS Security Vestibule:
               o    Pages/Details included – A-322/B1, AD-101/A4 & B4.
                       ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
               o Base Price: $12,800
               o Background Check Add Alt – (+$200)
               o (1) Mobilizations included – (2) full work days to complete scope of work.

     •    7. ADD #1 Chamblee HS Security Vestibule:
               o   Pages/Details included – S-001, S-101/1, 4, 8, 17.
               o Base Price: $7,750
               o Background Check Add Alt – (+$200)
               o (1) Mobilization included – (1) full work day to complete scope of work.




                                            811 Tucker Court, Winder, GA 30680
                                      Tel 770.921.1550 Fax 770.564.0938 GC__ SOC__
•   8. ADD #1 Chamblee MS Security Vestibule:
         o   Pages/Details included – S-001, S-101/1, 2, 5, 9, 17, 18.
         o Base Price: $13,750
         o Add Alt for joist connection per detail S-101/2: (+$100).
         o Background Check Add Alt – (+$200)
         o (1) Mobilizations included – (2) full work days to complete scope of work.

•   11. Dunaire ES Security Vestibule:
         o    Pages/Details included – A-321/A2 & A4, AD-101/A5.
                  ▪   (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
         o Base Price: $8,000
         o Background Check Add Alt – (+$200)
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   12. Dunwoody HS Security Vestibule:
         o   Pages/Details included – A-321/B4, AD-101/B4.
                 ▪   (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
         o Base Price: $5,000
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   13. Flat Shoals ES Security Vestibule:
         o     Pages/Details included – A-321/A3 & A2, AD-101/A5.
                   ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
         o Base Price: $8,000
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   15. Jolly ES Security Vestibule:
         o     Pages/Details included – A-101/A1, A-321/A4 & A2.
                   ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
         o Base Price: $8,000
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   16. ADD #1 Kingsley ES Security Vestibule:
         o   Pages/Details included – S-001, S-101/1 & 2, S-301/3, S-501/6, 3, 7, A-121/A1, A-321/A3, AD-101/A5, M-000.
                 ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
                 ▪    (2) Roof Frames for the HP-1 & HP-2 units – Framed with Galvanized L4x4x1/4 angles – REV 1.
                 ▪    See below for our assumption on framing:




                  ▪
        o    Base Price: $14,000
        o    Background Check Add Alt – (+$200).
        o    (1) Mobilizations included – (2) full work days to complete scope of work.
        o    REV 1 Price: $15,361

•   17. Lithonia HS Security Vestibule:
         o     Pages/Details included – S-001, S-101/1, 15, 17.
         o Base Price: $8,500
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   19. McLendon ES Security Vestibule:
         o   Pages/Details included – A-321/A3 & C5, AD-101/A5.
                 ▪   (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
         o Base Price: $5,000
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

•   20. Panola Way ES Security Vestibule:
         o    Pages/Details included – S-001, S-101/1, 15, 17.
         o Base Price: $8,500
         o Background Check Add Alt – (+$200).
         o (1) Mobilization included – (1) full work day to complete scope of work.

                                    811 Tucker Court, Winder, GA 30680
                              Tel 770.921.1550 Fax 770.564.0938 GC__ SOC__
    •    21. Robert Shaw Theme ES Security Vestibule:
              o    Pages/Details included – A-321/A3 & D5, AD-101/A5.
                       ▪   (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
              o Base Price: $5,000
              o Background Check Add Alt – (+$200).
              o (1) Mobilization included – (1) full work day to complete scope of work.

    •    22. Salem MS Security Vestibule:
              o    Pages/Details included – A-321/A3 & A2, AD-101/A5.
                      ▪    (Lintel detail only applicable where existing CMU wall openings are expanded horizontally or vertically upward).
              o Base Price: $8,000
              o Background Check Add Alt – (+$200).
              o (1) Mobilization included – (1) full work day to complete scope of work.

    •    24. Tucker MS Security Vestibule:
              o    Pages/Details included – S-001, S-101/1, 16, 17, 18.
              o Base Price: $8,500
              o Background Check Add Alt – (+$200).
              o (1) Mobilization included – (1) full work day to complete scope of work.

Project Specific Exclusions:
    •    Grouting to be done by others.
    •    Where no steel lintel detail is shown on drawings, but a new opening is shown on demo plan, Silver Oak assumes light gauge steel header to
         be used.
              o Add alt for steel lintel can be provided.
    •    Where openings in existing CMU walls are made vertically downwards, below an existing opening, Silver Oak assumes no steel lintel to be
         needed.
    •    Stainless steel and aluminum in any and all instances.
    •    Pre-engineered structures are excluded.
    •    Any details not specifically called out on plans are excluded.
    •    Gauge steel is excluded.


Project Specific Qualifications:
Our Quote is based off of the items as described above in Project Specific Inclusions/Breakdown.
Please contact me should you have any questions regarding items not indicated in this area.
This / That / The Other


Base Price (excluding alternates)………..…………..$ 136,300.00

Price (including alternates)………..………………...$ 139,600.00

REV 1 Price (including alternates)……….………...$ 141,061.00
Pricing is valid for 30 days from date sent 07/28/25.
*Due to the volatility of the current market, pricing will be verified upon notice of award.

    A.   Our price is based on a 40 hour work week and includes all detailing, fabrication, delivery, erection, hoisting, and taxes.
    B.   Our price assumes safe, free & clear access into & out of the project work areas, including accessing areas directly involved with erecting
         steel safely, and providing safe accessible staging areas according to OSHA guidelines.
    C.   Re-mobilizations due to circumstances beyond our control will result in additional costs, minimum $ 600.00 per each occasion.
               a. The above applies to a crew re-mobilization only. Additional costs will be applied if equipment re-mobilization is required.

NOTE: APPROVED CHANGE ORDERS require signed execution of Change Order documents by all parties PRIOR to ordering,
      fabrication, delivery, or installation of materials.



Structural steel shall conform to the following standards:
•   AISC Manual for Steel Construction, 13 th Edition
•   AISC 360-05 Specifications for Structural Steel Buildings
•   AISC 303-05 Code of Standard Practices for Structural Steel Buildings and Bridges
•   AISC 326-02 Detailing for Steel Construction, 2 nd Edition
•   Standard shop practice for painting is SSPC-SP2 hand tool cleaning and one coat of shop primer.



                                            811 Tucker Court, Winder, GA 30680
                                      Tel 770.921.1550 Fax 770.564.0938 GC__ SOC__
                                         Silver Oak Contracting Standard Contract Qualifications
     A.    Subcontract “Master Agreements” will not be signed or executed unless project specific “Attachment A” documents, including scope,
           specific exclusions, and contract price are submitted for execution with the Master Agreement.
     B.    Any changes to detailed plans as a result of Addendums, Adds, Revisions, Changes, etc. once approved BFA (Back From Approval) plans
           are scrubbed and issued as approved Field Use plans by detailers will result in added detailing and Admin costs as required to comply.

                                                   Silver Oak Contracting Standard Exclusions
Labor Exclusions:
     1. Excludes night or weekend work UNO
     2. Quote based on standard M-F 8 hour days
     3. Excludes Davis Bacon UNO
     4. Excludes AISC certified fabrication or erection.
         A. Although not AISC certified Silver Oak Contracting adheres to the standards and protocols put forth in the latest AISC manual.
     5. Bonding or CTP insurance UNO.
     6. Cutting of roof deck for RTU’s and other openings (To be done by others)
     7. Penetrations through Beams and/or Columns for HVAC and other trades.
Drawing & Engineering Exclusions:
     1. Excludes P.E. stamp on drawings and connections UNO
     2. Excludes engineering of any type. UNO
     3. Excludes any steel not transferred from “Architectural” drawings to “Structural drawings.” UNO
     4. Approved drawings returned and stamped by the EOR will be basis of design, any variation may result in price change.
Material Exclusions:
     1. Simpson materials
     2. Any materials for any other trades
     3. Attachment to or for non-ferrous metals, gauge metal, CFM studs/trusses, stainless, aluminum, wood, light gauged metals or any effice.
     4. Any aluminum or stainless steel UNO
Finishing Exclusions:
     1. All material will be prime coat only UNO
     2. Excludes galvanization UNO
     3. Excludes specialty coatings
     4. Excludes cleaning of steel due to contamination in staging areas.
     5. Excludes any AESS finish UNO.
Testing Exclusions:
     1. Fees for tests and inspections
     2. Any ultrasound testing of existing floors, walls & ceilings for exposing undetectable obstructions or PT cabling.
Work Site Exclusions:
     1. Furnish, install, or maintenance to perimeter edge protection, floor opening protection and temp rail at stairs.
     2. Grout and grouting. Excludes setting plates or templates. We provide ananchor bolt setting plan for your use.
     3. Excludes shoring or temp bracing.
     4. Excludes layout of anchor bolts.
     5. Excludes protection of existing.
     6. Excludes any wood materials.
     7. Excludes fire protection.
     8. Excludes safety cables.
     9. Excludes demolition.
     10. Excludes ventilation.
     11. Extensive layout or verification of design dimensions.
     12. Excludes jobsite security for materials, once delivered to the jobsite.
     13. In existing spaces we exclude the following; removal of existing ceiling tile and grid, pipe, conduit, wiring, fiber optic cabling, sprinkler pipe,
         ductwork, manual smoke removal, de-activation of fire detection and suppression, finished floors, walls, ceilings, and room contents. These
         factors are to be completed by others prior our to mobilization/erection of steel associated with this project.

Additional Notes:

Silver oak Contracting (SOC) must receive a signed contract or purchase order before materials will be ordered and fabrication will begin. SOC must have approved
and stamped shop drawings returned and scrubbed before fabrication will begin. Any variance in design or plans made after app roval drawings have been returned will
be the direct financial responsibility of the GC. Payment for shop drawings is due upon delivery of drawings to G.C. No reta inage to be held on shop drawings or
fabricated steel. All material invoices are due upon delivery of steel to jobsite. All other invoices are net 30 from date of invoicing. Amounts past due beyond these terms
are subject to a 3% late fee per month service charge. Payment to SOC is the sole obligation of the GC and is not a condition of receiving payment from owner or other
parties. Fabricated materials that cannot be delivered to the jobsite due to construction delays, weather or any other reasons will be billed as stored materials. GC
agrees to pay for materials stored at SOC within 30 days of invoicing. If material remains on SOC site over 30 days after invoice date a storage fee of 3% of material
cost may be assessed. No extra work will be performed until a signed approved change order has been issued and received by SOC. By accepting this proposal it becomes
a legal and binding document which will be an amendment to any other contracts associated with the above referenced project. This document will be used as the
defining scope of work., issuing of contract by G.C. for this project is acceptance of all terms listed above.

Acceptance Signature___________________ Print____________________ Date__________




                                               811 Tucker Court, Winder, GA 30680
                                         Tel 770.921.1550 Fax 770.564.0938 GC__ SOC__
                                                        E S T I M A T E

 Rays Stairs Inc         Sales Representative
 3546 Kenton Place SE    Bryan Ramirez
 Atlanta , GA 30316      (770) 609-0219
 (678) 993-4033          bramirez@raysstairsinc.com




 LEFKO Construction
                                                                                     Estimate #     4462
 105 Mansell Circle
 RoswellGA30075                                                                      Date           7/31/2025
 Job #3670 - CMAR-DCSD
 105 Mansell Circle
 Roswell, GA 30075



               Item                                Description                              Qty         Price     Amount

  Post                         Material, fabrication, and installation cost for             1.00   $50,000.00   $50,000.00
                               HSS6x6 and HSS6x4 posts for vestibule header
                               supports. Brace to the top joist or anchor to
                               concrete joist. Anchor and epoxy to the slab,
                               primed.

                               * $4,166 each column *

                               #3 Brocket ES - HSS6x6x1/4 - 1pc
                               #7 Chamblee HS - HSSS6x6x1/4 - 1pc
                               #8 Chamblee MS - HSS6x6x1/4 - 3pc
                               #16 Kingsley ES - HSS6x4x1/4 - 1pc
                               #17 Lithonia HS - HSS6x4x1/4 - 2pc
                               #20 Panola Way ES - HSS6x6x1/4 - 1pc ,
                               HSS6x4x1/4
                               #24 Tucker MS - HSS6x6x1/4 - 2pc



  Channel Supports             Material, fabrication, and installation for C8x11.5          1.00   $63,000.00   $63,000.00
                               channel lintel support for new CMU openings.
                               Thru bolt and weld 1/2" thick closure plate after
                               demo. Shoring, saw cutting and demo work by
                               others

                               * $7,000 each lintel *

                               #5 Canby Lane ES - 2 lintels
                               #6 Cedar Grove ES - 2 lintels
                               #11 Dunaire ES - 1 lintel
                               #13 Flat Shoals - 1 lintel
                               #15 Jolly ES - 1 lintel
                               #16 Kingsley ES - 1 lintel
                               #22 Salem MS - 1 lintel

  Angle Supports               Material, fabrication, and installation for                  1.00   $15,000.00   $15,000.00
                               L6x4x5/16 angle lintels for new CMU wall
                               openings. Weld 1/4" thick closure plate after
                               demo. Shoring, saw cutting and demo work by
                               others

                               * $5,000 per lintel *

                               #12 Dunwoody HS - 1 lintel
                               #19 McLendon ES - 1 lintel
                               #21 Robert Shaw Theme ES - 1 lintel



Document ID: D2DFD97F-D5C8-4892-A01A-E711CF036139                                                                Page 1 of 2
                 Item                                       Description                                  Qty          Price          Amount

  Angle Supports                        Material, fabrication, and installation cost for                 1.00    $5,000.00          $5,000.00
                                        L6x4x5/16 angle supports @ 6' O.C for new
                                        header support.

                                        #7 Chamblee H.S

  Canopy Braces                         Material, fabrication and installation cost for 2" dia           1.00   $15,000.00        $15,000.00
                                        pipe kickers at canopy connections to CMU wall.
                                        Thru bolt, pre-fab canopy by others Qty 4

                                        #16 Kingsley ES

  Lintels                               Allowance cost for steel support at roof for (2)                 1.00    $8,000.00          $8,000.00
                                        new HP units at #16 Kinglsey ES

  Equipment Rental                      Scissor lift rental cost $1,175 each.                            1.00   $18,800.00        $18,800.00

  Shop Drawings                         Stamp and sign $1,763 each                                       1.00   $28,200.00        $28,200.00




                                                                                                 Sub Total                       $203,000.00

                                                                                                 Total                           $203,000.00




 Sign To accept Estimate
                                               S P E C I A L        I N S T R U C T I O N S

 EXCLUSIONS: Exclude setting of anchor bolts and leveling nuts, Lines, grates and elevations. Field paint, finish paint and touch up paint.
 Grout and grouting. Ridge andf valley zinc plates
 Brass products. Julius Blum products. Aluminium canopies/fences, shoring, split rail systems, products from specific manufacturers,
 backstop
 posts/netting systems, standing seam metal deckings, gutters, PEMB steel, walking suspended ceiling and parts.
 Shop drawings with engineer's seal. Block ties and welding of ties. Insulated metal panels and attachments.
 Liquidated damages bonding and bonds. Demolition work. AISC certification.
 MATERIAL TO BE SHOP PRIME ONLY UNLESS OTHERWISE NOTED
 Note: During storage, loading, transport, unloading, and erection, blemishes and abrasions caused by slings, chains, blocking, tie-downs,
 etc. occur in varying degrees and should be expected.
 Responsibility for field touch-up should be assigned in the contract documents. Traditionally, this work has been delegated to the painting
 contractor.
 Note: No. Shop-painted steel that is stored in the field pending erection should be kept free of the ground and so positioned as to minimize
 water-holding pockets, dust, mud, and other contamination of the paint film. However, because site conditions are frequently muddy, sandy,
 dusty, or a combination of all three, it may be impossible to store and handle the steel in such a way as to completely avoid accumulation of
 mud, dirt, or sand on the surface of the steel. When required, provision should be made in the contract documents for an appropriate
 cleaning program.
 * THIS QUOTE IS VALID FOR 30 DAYS *




Document ID: D2DFD97F-D5C8-4892-A01A-E711CF036139                                                                                   Page 2 of 2
7/17/2025

GCs BIDDING

RE: CMAR - DCSD - Group 1 Security Vestibules @ Various locations
    Advantage Quote #25-07-64A


We are pleased to submit our proposal on the above referenced project. We propose to perform the work
shown on our attached scope letter.

This proposal must be accepted, in writing, within ten (10) days.

Our prices are FURNISHED AND INSTALLED: SEE ITEMIZED SCOPE LETTER


We are excluding: See attached scope letter.

We have reviewed the following plans in preparing our proposal: civil, structural and architectural

We have received the following addenda: one

Any materials or work shown on any other plans or specified in any other specification sections are excluded
from our bid. Any unusual terms and general conditions of the general contract also are excluded.
American Institute of Architects documents are considered to have “usual terms”.

Our proposal is contingent upon you tendering to us the current edition of AIA Document 401. We reserve
the right to withdraw this proposal if you do not provide us with adequate assurance, in the form of verified
financial information, which the owner has the ability to pay for the project.

Should we be awarded a contract or purchase order, this proposal will be considered a rider to that
document.

Delivery is subject to the availability of material and manpower.

We appreciate the opportunity to quote this project to you. If you have any questions, please do not hesitate
to give me a call. Thank you.

Sincerely,


Matt VonDielingen
Advantage Steel LLC
888-232-0474 x 700
matt@advantagesteelllc.com




web: www.advantagesteelllc.com
p: 888-232-0474
                         ***** SCOPE OF WORK *****
                                         7/17/25
                 CMAR - DCSD - Group 1 Security Vestibules @ Various locations
                               Advantage Quote #25-07-64A

ITEMS INCLUDED:

DCSD Brockett ES: $11,042.00

•   (1) Steel post per A-600
•   Shop Drawings

DCSD Canby Lane ES: $24,416.00

•   (2) Pair of Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Cedar Grove HS: $24,416.00

•   (2) pair Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Chamblee HS: $14,165.00

•   Structural Steel per S-101
•   Shop Drawings

DCSD Chamblee MS: $19,866.00

•   Structural Steel per S-101
•   Shop Drawings

DCSD Dunaire ES: $12,208.00

•   (1) pair Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Dunwoody HS: $8,406.00

•   Steel angle lintel per A-321
•   Shop Drawings



                                           Page 1 of 4 of “Scope”




web: www.advantagesteelllc.com
p: 888-232-0474
                                   ***** SCOPE OF WORK *****
                                         7/17/25
                 CMAR - DCSD - Group 1 Security Vestibules @ Various locations
                               Advantage Quote #25-07-64A

DCSD Flat Shoals ES: $12,208.00

•   (1) pair Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Jolly ES: $12,208.00

•   (1) Pair Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Kingsley ES: $22,846.00

•   (1) Steel post per S-101
•   (1) pair Steel channel lintel (S-501)
•   Pre-engineered canopy connection (7/S501) ($2,653.00 incl above)
•   Allowance for structural reinforcement angle at ductless outdoor unit ($4,500.00 incl above)
•   Shop Drawings

DCSD Lithonia HS: $15,085.00

•   Structural Steel per S-101
•   Shop Drawings

DCSD McLendon ES: $8,406.00

•   Steel angle lintel per A-321
•   Shop Drawings

DCSD Panola Way ES: $17,173.00

•   Structural Steel per S-101
•   Shop Drawings

DCSD Robert Shaw Theme ES: $8,406.00

•   Steel angle lintel per A-321
•   Shop Drawings

DCSD Salem MS: $12,208.00

•   (1) pair Steel channel lintel (Ref: A-321)
•   Shop Drawings

DCSD Tucker MS: $14,819.00

•   Structural Steel per S-101
•   Shop Drawings
                                           Page 2 of 4 of “Scope”

web: www.advantagesteelllc.com
p: 888-232-0474
                        ***** SCOPE OF WORK *****
                                         7/14/25
                 CMAR - DCSD - Group 1 Security Vestibules @ Various locations
                               Advantage Quote #25-07-64A


JOB SPECIFIC QUALIFICATIONS:
•   With the recent announcement of tariffs on steel, the raw material market volatility has increased
    exponentially, due to this we cannot guarantee our material pricing beyond 10 days. Further, once an
    order is placed for the job, material will be immediately ordered as per the contract documents. Any
    changes to material sizes or lengths will result in a change order for extra cost. Also, the General
    Contractor shall allow Advantage Steel, LLC to bill for stored raw materials stored at Subcontractors
    shop or at the warehouse where the steel is purchased.
•   After 10 days our bid becomes null and void and material pricing will have to be reviewed and re-priced.
•   Assumes forklift access within and around the perimeter of the building or additional pricing will be
    applicable


JOB SPECIFIC EXCLUSIONS:
•   Canopy columns noted to be by others.
•   AVONDALE HS
•   BROWNS MILL ES
•   COLUMBIA HS
•   HIGHTOWER ES
•   MARGARET HARRIS COMP SHOOL
•   SEC VEST CORALWOOD EDUCATION SCHOOL
•   STONE MOUNTAIN MS
•   WOODWARD ES
•   DCSD Avondale ES
•   Chipping of concrete slab




                                         Page 3 of 4 of “Scope”




web: www.advantagesteelllc.com
p: 888-232-0474
                           ***** SCOPE OF WORK *****
                                           7/17/25
                   CMAR - DCSD - Group 1 Security Vestibules @ Various locations
                                 Advantage Quote #25-07-64A

STANDARD EXCLUSIONS & QUALIFICATIONS:

•   AISC CERTIFICATIONS
•   INSTALLATION OF EMBEDS OR LINTELS (regardless of the size or type of the lintel unless it attaches to a
    steel column or beam. Ie a lintel sitting on bearing plates is to be installed by others, a lintel attached to
    column on one end installed by Advantage Steel LLC)
•   ALLOWANCES
•   Material quoted as SP-2 Cleaned with 1 coat of Sherwin Williams Standard Shop Primer UNO
•   Trench drain and frame
•   Liquidated damages
•   Masonry ties, channels, slots, straps or anchors
•   Ladder fall arrest systems, ladder up telescoping post
•   Slotted Channel Framing
•   Unistrut
•   Light gauge metal
•   Abrasive Nosings
•   Unsized material
•   Tar or bituminous coatings
•   Holes for other trades
•   Survey (Advantage will require an as built survey of the ABs be provided to us prior to setting of any steel on ABs)
•   Grout
•   Testing and inspection
•   Shoring
•   Demolition
•   Touch up painting
•   Cutting and patching
•   Cutting of holes in decking for other trades
•   Cleaning of steel after installation
•   Any item on mechanical, electrical or plumbing drawings
•   Any aluminum, bronze, cast iron or stainless-steel items not noted as specifically included
•   Anchors to attach wood or other materials to steel or masonry
•   Any items not specifically listed as “ITEMS INCLUDED”
•   Must have adequate access to the work area for manpower, equipment, and materials
•   Assumes Crane/Forklift access within and around the perimeter of the building
•   Quote based on OSHA 29 CFR Subpart R&X
•   Additional $2,000 charge if Advantage Steel is unable to Erect at time of delivery
•   Field work will be completed with non-union labor, no prevailing wage, no davis bacon
•   Temporary safety cable supply, installation or maintenance
•   Structural steel is bid as per the structural drawings any discrepancies between the structural and other trade
    drawings have not been accounted for
•   Dewatering
•   GENERAL CONTRACTOR TO PROVIDE CLEAR AND ADEQUATE CRANE PATH, SOIL CONDITIONS TO
    ACCOMMODATE MACHINERY NEEDED TO ERECT, HOIST, AND STAGE BUILDING MATERIALS.
•   BOND, PERMITS, SURVEYING, TESTING, OVER TIME, WEATHER PROTECTION, JOB CLEAN UP
•   PRICE AND SCHEDULE ARE SUBJECT TO MATERIAL AND MANPOWER AVAILABILITY AT THE TIME OF
    ORDER


                                              Page 4 of 4 of “Scope”




web: www.advantagesteelllc.com
p: 888-232-0474
Commercial Construction
& General Contractor




                           MILLWORK
                          Selected price: DCourts Cabinets




LEFKO CONSTRUCTION
                                                      5319 DIVIDEND DRIVE                                         ESTIMATE
                                                       DECATUR, GA 30035
                                              OFFICE:470-282-3870, FAX: 678-585-4883                            DATE             ESTIMATE #
                                                  estimate@dcourtscabinets.com
                                                      www.dcourtscabinets.com                                  6/18/2025            1435

  NAME/ADDRESS:                                                                SHIP TO:
  ESTIMATE DEPARTMENT                                                          DCSD-BROCKETT ELEMENTARY SCHOOL
                                                                               SECURITY VESTIBULE
                                                                               1855 BROCKETT ROAD
                                                                               TUCKER, GA 30084

                                                                                      DWG. DATE                      EST. REV DATE

                                                                                                                           6/17/2025

ELEV/NOT...                                             DESCRIPTION                                                U/M QTY          TOTAL
                MANUFACTORY & INSTALL:
                MAIN FLOOR

  A1/A-101  ADMIN
C3,C5&D3/A- 8.92LF Plastic Laminate "L" Shaped Transaction Ledge x 10" Deep On 10LF Plastic Laminate                         1      6,158.25
    720     Low Wall. 18.75LF Plastic Laminate "L" Shaped Countertop On 1.5LF Plastic Laminate
            Drawerstacks w/ Melamine Interior & Bracket Supports.


                SHOP DRAWINGS:                                                                                                         750.00

                FREIGHT & INSTALLATION:                                                                                             2,000.00

                EXCLUSIONS: Demo, Fixtures, Gyp Bd Low Wall, Rubber Base, Signage, Standing & Running
                Trim, In-Wall Brackets & In-Wall Blocking are not Included in Bid Proposal.

                NOTES:

                Prices Based On Wilsonart Laminate Selections.

                Pricing Includes After-Hours/Weekend Work w/ Multiple Mobilizations (if Needed).




 In order to expedite your order, we ask that you approve by signing below and return to us via
                                           e-mail or fax                                            TOTAL                   $8,908.25

STANDARD CABINET CONSTRUCTION (Unless Specifically Noted Above): MDF Carcass, White Melamine Interiors, Standard PLAM
Colors/Finish, 4" Chrome Wire Pulls, European-Style Hinges, Peg hole Shelves, Square-Edge Tops. Standard Wall-Hung Shelves (Unless
Specifically Noted Above): KV83 Metal Standards/Brackets.
DCourts Cabinets terms are 30 Days Net from date of Invoice. All work is guarnateed to be specified. All work to be completed in workman like
 manner in accordance with standard practices. Any alteration or deviation from the above specifications invloving extra costs will be executed
                          only upon written change order and will become extra charge over and above the estimate.
ACCEPTANCE OF PROPOSAL: THE ABOVE PRICES, SPECIFICATIONS AND CONDITIONS ARE SATISFACTORY AND HERBY ACCEPTED.

Sign_____________________________ Print __________________________________________________ Date _____________________
                                                                                                                                                                                                                                                                                        DCSD - GROUP 1 PROJECTS
                                                                                                                                                                                                                                                                                                    BID PROPOSAL

                                                                                                                                                                                                                                                                                                                       6/20/2025
Andrea Torres
andrea@lefkogroup.com
Georgia                                                                                                                                                                                                                                                                                                              DCSD - GROUP 1
(404) 400-2907

                                                                                                                                                                                                                                                                                          Cabinets Quote

                                                   Avondale - ES        Avondale - HS        Brocket - ES         Brownmill - ES        Canby Lane ES    Cedar Grove - HS       Chamblee -HS     Chamblee - HS(A,S)       Chamblee - MS          COLUMBIA - HS         Coralwood - ES          Dunaire - ES          Dunwoody - HS          Flat Shoals - ES       Hightower - ES        Jolly - ES           Kingsley - ES        Lithonia - HS    Margaret Harris comp        MC Lendon - ES       Panola Way - ES   Robert shaw - ES   Salem - MS        Stone Mountain - MS    Tucker - MS     Woodward - ES

                        Particulars                  Amount               Amount              Amount                 Amount               Amount             Amount               Amount              Amount                 Amount                 Amount                Amount                 Amount                 Amount                 Amount                 Amount             Amount                 Amount               Amount               Amount                   Amount               Amount             Amount             Amount             Amount                Amount          Amount
                   Cabinet Materials           $          924.00
                                                                    $         2,002.00   $           924.00   $          1,848.00   $           924.00   $         924.00   $         1,232.00   $        51,898.00   $           770.00     $           616.00    $            616.00     $            616.00   $          1,386.00    $           1,386.00   $           770.00    $          616.00    $           770.00   $           924.00   $              924.00   $           462.00   $            770.00   $        770.00    $ 1,078.00    $               1,232.00   $     308.00    $       462.00
            Cabinets Assembly & Installation   $          264.00
                                                                    $           572.00   $           264.00   $            528.00   $           264.00   $         264.00   $          352.00    $        14,828.00   $           220.00     $           176.00    $            176.00     $            176.00   $            396.00    $            396.00    $           220.00    $          176.00    $           220.00   $           264.00   $              264.00   $           132.00   $            220.00   $        220.00    $    308.00   $                 352.00   $      88.00    $       132.00
                        Hardware               $           39.60                         $            39.60
                                                                    $            85.80                        $             79.20   $            39.60   $          39.60   $           52.80    $         2,224.20   $            33.00     $            26.40    $             26.40     $             26.40   $             59.40    $              59.40   $             33.00   $           26.40    $            33.00   $            39.60   $               39.60   $            19.80   $             33.00   $          33.00   $     46.20   $                  52.80   $      13.20    $        19.80
              Shipping and Crew Expenses       $           92.40
                                                                    $           200.20   $            92.40   $            184.80   $            92.40   $          92.40   $          123.20    $         5,189.80   $            77.00     $            61.60    $             61.60     $             61.60   $            138.60    $            138.60    $             77.00   $           61.60    $            77.00   $            92.40   $               92.40   $            46.20   $             77.00   $          77.00   $    107.80   $                 123.20   $      30.80    $        46.20
                    Total cabinets             $        1,320.00
                                                                    $         2,860.00   $         1,320.00   $          2,640.00   $         1,320.00   $       1,320.00   $         1,760.00   $        74,140.00   $         1,100.00     $          880.00     $           880.00      $         880.00      $          1,980.00    $          1,980.00    $          1,100.00   $          880.00    $         1,100.00   $         1,320.00   $           1,320.00    $           660.00   $          1,100.00   $       1,100.00   $ 1,540.00    $               1,760.00   $     440.00    $       660.00
                                                                                                                                                                                                                                                                                         Countertops Quote

                        Particulars                  Amount               Amount              Amount                 Amount               Amount             Amount               Amount              Amount                 Amount                 Amount                Amount                 Amount                 Amount                 Amount                 Amount             Amount                 Amount               Amount               Amount                   Amount               Amount             Amount             Amount             Amount                Amount          Amount
                 Countertops Material          $         1,154.40
                                                                    $         1,154.40   $           951.60   $          1,762.80   $         1,029.60   $         936.00   $          904.80    $        33,212.40   $           826.80     $           639.60    $            686.40     $            655.20   $          1,450.80    $            858.00    $           702.00    $          951.60    $         1,404.00   $           967.20   $              982.80   $           592.80   $            748.80   $        858.00    $ 1,076.40    $               1,326.00   $     514.80    $       390.00
                Countertops Installation       $          577.20
                                                                    $           577.20   $           475.80   $            881.40   $           514.80   $         468.00   $          452.40    $        16,606.20   $           413.40     $           319.80    $            343.20     $            327.60   $            725.40    $            429.00    $           351.00    $          475.80    $           702.00   $           483.60   $              491.40   $           296.40   $            374.40   $        429.00    $    538.20   $                 663.00   $     257.40    $       195.00
              Shipping and Crew Expenses       $          192.40
                                                                    $           192.40   $           158.60   $            293.80   $           171.60   $         156.00   $          150.80    $         5,535.40   $           137.80     $           106.60    $            114.40     $            109.20   $            241.80    $            143.00    $           117.00    $          158.60    $           234.00   $           161.20   $              163.80   $            98.80   $            124.80   $        143.00    $    179.40   $                 221.00   $      85.80    $        65.00
                          Sinks                $              -
                                                                    $              -     $              -     $               -     $              -     $            -     $              -     $         8,000.00   $               -      $               -     $               -       $               -     $                  -   $                -     $               -     $                -   $               -    $               -    $                 -     $               -    $               -     $            -     $       -     $                    -     $         -     $            -
                  Total Countertops            $        1,924.00
                                                                    $         1,924.00   $         1,586.00   $          2,938.00   $         1,716.00   $       1,560.00   $         1,508.00   $        63,354.00   $         1,378.00     $         1,066.00    $          1,144.00     $        1,092.00     $          2,418.00    $          1,430.00    $          1,170.00   $        1,586.00    $         2,340.00   $         1,612.00   $           1,638.00    $           988.00   $          1,248.00   $       1,430.00   $ 1,794.00    $               2,210.00   $     858.00    $       650.00


                     Total Amount              $        3,244.00
                                                                    $         4,784.00   $         2,906.00   $          5,578.00   $         3,036.00   $       2,880.00   $         3,268.00   $       137,494.00   $         2,478.00     $         1,946.00    $          2,024.00     $        1,972.00     $          4,398.00    $          3,410.00    $          2,270.00   $        2,466.00    $         3,440.00   $         2,932.00   $           2,958.00    $         1,648.00   $          2,348.00   $       2,530.00   $ 3,334.00    $               3,970.00   $    1,298.00   $     1,310.00
                                                                                                                                                                                                                                                                                                Notes

                                                                                                                                                                                                                                                                                All pricing is valid for 90 days

                                                                                                                                                                                                                                                                                   Sink Cutouts are included

                                                                                                                                                                                                                                                                  Above Quote Includes of Shipping and Crew Expenses

                                                                                                                                                                                                                                                             Lead times are 120 days from the Date of approved Shop Drawings

                 Name                                                                                                                                                                                                                                                                                                   Signature




                                                                                                                                                                                                                                                                             7800 the bluffs, Austell, GA 30168
                                                                                                                                                                                                                                          Phone:-3472827608        Email:-rama@kcabinetry.net       www.kcabinetry.net
Andrea Torres

From:                            Daniel Drake <Daniel@drake-interiors.com>
Sent:                            Thursday, July 24, 2025 9:50 AM
To:                              Andrea Torres
Cc:                              Julio Arellanes; Jesus Martinez
Subject:                         RE: Dekalb County - Security Vestibules GROUP 1

Follow Up Flag:                  Follow up
Flag Status:                     Completed



In red below

Daniel Drake
183 Scott RD
Canton, GA 30115
Office: 470-863-5939
Cell 678-201-9446

Drake Interiors

From: Andrea Torres <andrea@lefkogroup.com>
Sent: Wednesday, July 23, 2025 11:26 AM
To: Daniel Drake <Daniel@drake-interiors.com>
Cc: Julio Arellanes <julio@lefkogroup.com>; Jesus Martinez <jesus@lefkogroup.com>
Subject: Dekalb County - Security Vestibules GROUP 1

Good morning, Daniel

Per our conversation, please see below the list of small millwork items that I'd appreciate you pricing out for us.

Avondale ES
   1. Covering the new metal stud wall it with plastic laminate on top and ½” reveal painted black as called for
      on Dwg A321/A5. $950
   2. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
      1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
Avondale HS
   1. High-pressure laminated mdf sheet with finish to match adjacent desk surface finish at the new metal
      stud wall as shown on Dwg A321/ A2 and A3. $1,200
Brockett ES
   1. High-pressure laminated mdf sheet with finish to match adjacent desk surface finish at the new metal
      stud wall as called for on Dwg A101/10 and Dwg A321/A3. $1,450
Browns Mill ES
   1. Providing a finished edge at exposed millwork on the existing reception desk as called for on Dwg
      A101/10. $750
   2. New millwork infill section, plastic laminate finish and blocking, H: 2’-8” (to be verified in field) as called
      for on Dwg A321/ A2. $1,250

                                                          1
Canby Lane ES
    1. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
Cedar Grove HS
    1. ¼” vinyl face bulletin board (both sides of stud infill wall) as shown on elevation B4 (Dwg
        A101/9). $1,500
    2. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
Chamblee HS
    1. ½” high-pressure laminated mdf sheet to finish the new metal stud wall as called for on A321/ A1 and
        A600/B3. $1,150
Columbia HS
    1. Demolish upper section of existing desk to provide access to new transaction window, as required on
        dwg A101, keynote 7 $500
    2. New wood side piece to provide a finished edge at exposed millwork (finish to match existing desk) after
        demolishing the upper section of the existing desk as called for on Dwg A321/A3. $1,350
Coralwood Education School
    3. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-601/E3. $750
Dunaire ES
    1. Demolish portion of newly purchased desk up to the module split of desk per dwg AD101, keynote E
        $500
    2. Providing a finished edge at exposed millwork as called for on Dwg A101/8. $950
    3. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
Dunwoody HS
    1. High-pressure laminated mdf sheet at the new metal stud wall as detailed on Dwg A321/A3. $1,250
Flat Shoals ES
    1. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-321/B5. $750
Hightower ES
    1. Providing a finished edge at exposed millwork as detailed on DwgA321/A2. $1,200
    2. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking as required) as called for on Dwg A-321/B5. $750
Jolly ES
    1. High-pressure laminated mdf sheet at the new metal stud wall as detailed on Dwg A321/A2. $1,250
Kingsley ES
    1. High-pressure laminated mdf sheet at the new metal stud wall as called for on Dwg A321/A3. $1,250
Lithonia HS
    1. High-pressure laminated mdf sheet at the new metal stud wall as called for on Dwg A321/A3. $1,250
McLendon ES
    1. New solid surface countertop as called for on Dwg A321/A3 and A5. $1,450
Panola Way ES
    1. Demolish portion of desk up to the module split of desk per AD101/D $1,100
    2. Finished edge at exposed millwork as called for on Dwg A101/10. $1,200
    3. High-pressure laminated mdf sheet at the new metal stud wall as called for on Dwg A321/A3. $1,250
    4. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
        1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
                                                       2
Robert Shaw ES
   1. Backsplash (1/2" high-pressure laminated mdf to match desk surface, mitered at corners and set back
       1/2" from transaction window and fixed to blocking) as called for on Dwg A-600/A5. $750
Salem MS
   1. High-pressure laminated mdf sheet at the new metal stud wall as called for on Dwg A321/A2. $1,250
Stone Mountain MS
   1. New solid surface material to be flush with existing glazed brick, as shown on DwgA321/ A3, A5 and D5.
       $1,250
Woodward ES
   1. New reception counter as called for on keynote 8 and detailed on A-720, and detailed on Dwg A321/A2.
       $1,500
   2. High-pressure laminated mdf sheet at the new metal stud wall, detailed on A600/B5. $1,250

Per specs section 064116, Basis of Design for High-Pressure Decorative Laminate: NEMA LD 3, Product by
Wilsonart, PLM-1 on vertical surfaces and PLM-2 on horizontal surfaces. Submittal package including samples
should be considered.

Please let me know if you need any additional information from our team

Once again thank you for all your help,

Andrea Torres
C: 404-400-2907
O: 404-846-6372
LEFKO Construction
www | in | fb




                                                      3
Commercial Construction
& General Contractor




                                DOORS
                          Selected price: Southern GF, co.




LEFKO CONSTRUCTION
                                                                                                                    Quote
                                                   2915 Courtyards Drive                   Quote #         : 406969
                                                   Suite A
                                                   Peachtree Corners, GA 30071             Quote Date      : Jul 16, 2025
                                                   Tel: 404-609-9300
                                                                                           Expiration Date : Aug 15, 2025

    Customer:                                                                          Ship To:
    OTC                                                                                Brockett Elementary School
    2915 Courtyards Drive , Suite A                                                    1855 Brockett Rd
    Peachtree Corners, GA 30071                                                        Tucker, GA 30084
                                                                                       Attn: Shane Smith

Account Code          : 10158
Terms                 : COD                                             Purchase Order # :
Customer Job #        :                                                 Shipped Via      : Customer Pickup
Salesperson           : Shane Smith
Order Name            : Brockett ES

*** Keying Not Included***
*** Wiring Diagrams Not Included in this proposal. Wiring Diagrams to come in later proposal.***
*** Transom Glass By Others ***

  Qty Product Description
    1 3070 1 3/4 WD 5502 QK RCNB N PC CH18
         - Ceco Hinge Locations
         - ND80EU Lock Prep
         - Concealed Overhead Stop: Glynn Johnson 100S
         - 6" x 36" Narrow Lite Bullet Resistant UL 725 Level 2 Glass
         - Bullet Resistant UL 725 Level 2
     1 SGL 3070 M 16 534 WFT A40 4 4
         - Bullet Resistant UL 725 Level 2
         - Ceco Hinge Locations
         - EPT Prep
         - Door Position Switch in Head
         - Concealed Overhead Closer Reinforcement
         - ASA Strike
         - RA/PA Closer Reinforcement
         - Punch & Dimple W/ Anchors
     3   Hinges 5BB1 HW BSC 4 1/2 652
     1   Electric Power Transfer EPT 10 CON SP28
     1   Electrified Lockset ND80 EU B SPA CON 626
     1   Core 1CX-7X3Y1 626
     1   Overhead Stop 104S SP28
     1   Closer 4040XP REGARM AL
     3   Metal Frame Silencer 307D GREY
     1   Wire Harness CON-192
     1   Power Supply Extension CON-6W
     1   Wall Mount Reader MTB15-C1 BLACK
     1   Switch 679-05WD

                                                                        Pre-Tax Total                        :          19,592.21
     Add for wiring diagrams: $1,000.00                                 40178 - GA - Dekalb (In ATL)         :           1,743.71
                                                                        Quote Total                          :        21,335.92


                                                                                                        Printed Aug 7, 2025 9:11 AM
                                                                                                                     Page 1 of 2
***** Customer Pick Up Hours: 8:00 A.M. - 3:30 P.M. Monday - Friday *****
      Closed for Lunch 12:00 - 1:00
      3.5 % Fee for all Credit/Debit Card Payments


ACCEPTED____________________________

BY___________________________________

DATE_________________________________




                                                                            Printed Aug 7, 2025 9:11 AM
                                                                                         Page 2 of 2
                                                    Proposal
                                                                                      Date: September 15, 2025
                                                                                      To:      Lefko Construction
25 Liberty Drive, Suite 3832
Cartersville GA, 30120                                                                Attn: Ana Cegarra
Phone: 706 – 996 – 3866                                                               Project: Brockett ES
Prepared by: Miguel Merida
Email: miguelm@aoinc.us


                           We are pleased to quote the following items for the noted project.


            Qty                                            Description                                     Price



                                         Hollow Metal Doors and Frames – 081110
             1             Hollow Metal Frame- 16 Ga- Welded- Primed- BR- 3 sided-Transom
                                                        Glazing excluded


                                                     Wood Doors – 081416
             1                    AA Grade- 5 Ply-BR- Plain Sliced White Birch Book & Run
                               Machined for hardware- Factory pre-finished standard color
                                              Vision kits included- Glass Included


             1                                     Finish Hardware – 087100
                                                     Set of Finish Hardware


             1                            Installation of Door and Hardware Above



                                                                         Base Bid Total excluding tax    $16,280.00




    Clarifications:
    1. All Materials have been included with Manufacturers standard lead-times.
    2. Cores have been priced along with BR door, frame, hardware.
    3. Frames must be installed plumb/level/square.
    4. No retention allowed on material only proposals.
    5. Payment Terms- Net 30 Days. No discount terms allowed.
    6. Proposal subject to mutually and agreeable contract terms.
    7. Curries is HM Manufacture.
    8. Glass sizes may vary from drawings and specs due to tolerances for UL 752.
           Exclusions:
           1. Aluminum Doors and Frames, Overhead, Rolling, Coiling, Gate Doors, and associated hardware.
           2. Installation of permanent cores.
           3. Set up and installation of key cabinet.
           4. Knox Box
           5. Offsite parking.
           6. Special inspections or testing.
           7. P&P Bond. If required add 2.5%
           8. Glass and Glazing, unless noted above.
           9. Mock up materials
           10. Groat, bituminous coating, or any backfilling of frames.
           11. Undercutting of doors due to floor conditions.
           12. Use of stairs to move doors and hardware up building. The contractor must provide a working elevator or lift.
           13. Allowances and Alternates.
           14. AHC on staff.
           15. Unloading, Staging, Receiving and installation of all materials is by others.
           16. Modifications to existing doors and frames.
           17. Wires, conduit, and terminations are by others.
           18. Site inventory and secure lockup.


THIS PROPOSAL IS SUBMITTED SUBJECT TO THE FOLLOWING CONDITIONS AND NEEDS YOUR SIGNATURE TO RELEASE.
Prices quoted are for acceptance within thirty days from the date of this sheet, after which they will be subject to change without notice. Orders are not subject to
cancellation unless authorized by the Company and unless cancellation charges are assumed by the Purchaser. Invoices will be rendered either for complete or partial
shipment as shipments are made. No Federal, State, or other taxes, except as noted, have been included in the above prices. Any such taxes which are or become
applicable to the equipment quoted herein will be added to the invoice. All previous agreements, guarantees and proposals covering equipment or service for this subject
are hereby nullified. The purchaser agrees to pay all costs of collection, including but not limited to the actual amount of attorney's fees incurred, if this contract is
collected by or through an attorney at law." All property purchased from seller under this, previous, and subsequent contracts shall be kept at address entered on
shipping bill of lading, shall not be sold, transferred, delivered or moved there from (except upon seller’s written consent) and title thereto shall remain in seller until all
amounts due thereon are fully paid and until full payment has been received for all liabilities and indebtedness of any and every kind and nature now or hereafter owing,
arising due or payable from purchaser to seller, howsoever evidenced, created or incurred including any future advances or renewals made to purchaser by seller. Any
special conditions applying will be discussed on a sheet attached to this agreement. TERMS: Net 30 days from date of shipment to Purchasers with established credit with
Company by having a previous purchase. Where credit is not established and unless satisfactory references are given, terms are NET DUE C.O.D or if approved by
management a 50% deposit at the placement of order and balance due prior to shipping/receipt of material. Any balance not paid in full within 30 days of the due date
stated herein shall accrue interest at the rate of 1.5% per month (18% per annum) on any outstanding balance until the remaining balance is paid in full. A 2.5% fee will be
applied on credit card payments.
ACCEPTANCE: This proposal is accepted subject to the conditions contained therein.


Buyer (Print Name):


Date of Acceptance: ___________________________________



Signature:


Title:____________________________________
                      Owner       Partner Officer
EntryFab Doors LLC
6085 Mountain Trail Ct.
Gainesville , Ga 30506
Please note address change

(404)449-4793



LEFKO Construction

                                                                                                          QUOTE

                                                                                             Quote #     dekalbCOSCHool

                                                                                          Quote Date          07/30/2025



  Item            Description                                                Unit Price      Quantity         Amount

                  Install door / hardware +Trip charge Avondale ES               930.00           1.00          930.00
                  8 Lakeshore Dr., Avondale Estates, GA, 30002:

                  Install Door Hardware + Trip charge Avondale HS                680.00           1.00          680.00
                  1192 Clarendon Rd, Decatur, GA, 30032:

                  Install Door Hardware + Trip charge Brockett ES                780.00           1.00          780.00
                  1855 Brockett Road, Tucker, GA, 30084

                  Install Door Hardware + Trip charge                           1750.00           1.00        1,750.00
                  Cedar Grove HS
                  2360 River Road, Ellenwood, GA, 30294

                  Install Door Hardware + Trip charge Chamblee MS                840.00           1.00          840.00
                  3601 Sexton Woods
                  Drive, Chamblee, GA, 30341

                  Install Door Hardware + Trip charge Coralwood Education        610.00           1.00          610.00
                  School (a 24/1
                  Coralwood Drive, Decatur, GA, 30033

                  Install Door Hardware + Trip charge Dunwoody HS                580.00           1.00          580.00
                  5035 Vermack Road,
                  Dunwoody, GA, 30338

                  Install Door Hardware + Trip charge / Kingsley ES              610.00           1.00          610.00
                  2051 Brendon Drive,
                  Dunwoody, GA, 30338

                  Install Door Hardware + Trip charge Margaret Harris Comp       610.00           3.00        1,830.00
                  School
                  1634 Knob Hill Drive NE Atlanta, GA 303329

                  Install Door Hardware l+ Trip charge                           650.00           2.00        1,300.00
                  Robert Shaw Theme ES
                  @ 385 Glendale
                  Road, Scottdale, GA, 30079
              Install Door Hardware + Trip charge / Stone Mountain MS       650.00     2.00    1,300.00
              4293 Sarr Parkway, Stone Mountain, GA, 30083

              Install Door Hardware + Trip charge                           650.00     1.00      650.00
              Tucker MS
              2160 Idlewood Road, Tucker, GA, 30084

              Install Door Hardware + Trip charge Woodward ES               650.00     1.00      650.00
              3034 Curtis Dr. NE, Atlanta, GA, 30319

              Trip charge                                                   300.00    19.00    5,700.00




NOTES: Dekalb County School System


                                                                        Subtotal               18,210.00

                                                                        Total                  18,210.00

                                                                        Amount Paid                 0.00

                                                                        Quote                 $18,210.00
 L & P Openings LLC                                Estimate 1276
 52 Fayetteville Rd.
 Fairburn, GA 30213 US
 +16786225696
 landpopenings@gmail.com

ADDRESS               SHIP TO

LEFKO CONSTRUCTION LEFKO CONSTRUCTION                         TOTAL
                                             DATE
LEFKO CONSTRUCTION LEFKO CONSTRUCTION      07/28/2025       $18,200.00


JOB NAME
DCSD-GROUP1 SECURITY VESTIBULES

DATE                            ACTIVITY   DESCRIPTION        QTY        RATE     AMOUNT

                                LABOR      Avondale ES          1 1,500.00      1,500.00
                                            (1) exterior
                                           HM
                                            (panel to be
                                           BR)
                                           hardware
                                           group #4
                                LABOR      Avondale HS          1 1,200.00      1,200.00
                                           (1) wood door
                                           P1 (panels to
                                           be BR),
                                           hardware
                                           group #4
                                LABOR      Brockett ES          1 1,250.00      1,250.00
                                            (1) wood door
                                           P4 (panels to
                                           be BR)
                                           hardware
                                           group #3
                                LABOR      Cedar Grove          1 1,000.00      1,000.00
                                           HS
                                           (1) wood door
                                            (not BR)
                                            hardware
                                           group #5
                                LABOR      Chamblee MS          1 1,250.00      1,250.00
                                           (1) wood door
                                           P6 (panels to
                                           be BR)
                                           hardware
                                           group #03
DATE   ACTIVITY   DESCRIPTION       QTY    RATE     AMOUNT

       LABOR      Coralwood          1 2,000.00   2,000.00
                  Education
                  (1) wood door
                  pair (P7, full
                  glass w/
                  center
                  mullion)
                   (1) wood
                  doors
                  (P1) All BR,
                  hardware
                  group #03
       LABOR      Dunwoody HS        1 1,250.00   1,250.00
                  (1) wood door
                  P7 (panels to
                  be BR)
                  hardware
                  group #03
       LABOR      Kingsley ES        1 1,500.00   1,500.00
                  (1) wood door
                  P5 (panel to
                  be BR)
                  (1) wood door
                  P1
                   (not BR)
                  hardware
                  group #03
                  (qty: 2)
       LABOR      Margaret           1 1,750.00   1,750.00
                  Harris Comp
                  School
                   (2) wood
                  doors P2 and
                  (1) wood door
                  P1 (full glass,
                  full panel).
                  All BR,
                  hardware
                  groups #s 03,
                  04, 05
       LABOR      Robert Shaw        1 1,500.00   1,500.00
                  Theme ES (1)
                  wood door P4
                  (1) wood door
                  P5 with full
                  glass.
                  All BR,
                  hardware
                  groups #s 03
                  & 03.1
DATE   ACTIVITY     DESCRIPTION       QTY    RATE     AMOUNT

       LABOR      Stone                1 1,500.00   1,500.00
                  Mountain MS
                  (1) wood door
                  P4
                  (1) HM door
                  P7 with full
                  glass.
                  All BR
                  hardware
                  group #s 02 &
                  02.1
       LABOR      Tucker MS            1 1,250.00   1,250.00
                  (1) wood door
                  P6 with half
                  glass.
                  All BR
                  hardware
                  group #03
       LABOR      Woodward ES          1 1,250.00   1,250.00
                  (1) wood door
                  P4.
                  All BR
                  hardware
                  group #03
       SCOPE OF   Install wood &       1     0.00       0.00
       WORK       hollow metal
                  doors and
                  hardware.
       EXCLUSIONS EXCLUDES             1     0.00       0.00

                    All Alum
                    Storefront
                    doors and
                    hardware.

                    Low Voltage
                    Wiring past
                    the hinge.
                    *(Raceways
                    factory
                    prepped)

                    Glazing

                    Modifications
                    to doors or
                    frames

                    Installation of
                    door frames .
              SUBTOTAL           18,200.00
              TAX                     0.00


              TOTAL           $18,200.00
                                 THANK YOU.




Accepted By   Accepted Date
Commercial Construction
& General Contractor




                                    GLAZING
                          Selected price: ClearVue Glass and Mirror, co




LEFKO CONSTRUCTION
                                                                                              August 25, 2025

                                                                                              Lefko Construction

                                                                                              Proposal: $3,787,810.00

Clearvue Glass & Mirror Co. proposes to furnish and install the following scope of work for this project. Our
proposal shall include all inclusions and exceptions as shown herewith. Our quotation is valid for (30) days*
from the date of this quotation. After that, Clearvue Glass & Mirror Co. has the right to review and revise its
pricing. This bid is conditioned on the use of the AIA A401 contract document or otherwise mutually agreeable
subcontract. Please send LOI’s or Contracts to the Estimator and contracts@cvgco.com.
Please contact Eric Holt at 678-772-4770 or CJ Smith (Senior Estimator) at (253) 393-0071 if you have any
questions. Thank You!

Project:     DCSD Security Vestibules
Architect:   LS3P
Plans Dated: 04/30/2025

                  Interior & Exterior Glazing
                      • The exterior storefront glass shall be 1” insulated SNX 51/23 LowE/ Clear tempered.
                      • All interior glass shall be 3/8” clear tempered.
                      • All transaction windows shall be 1 3/8” BR level 2 glass.
                      • All BR@ panels shall be TSS BB-2. (Submittal will be sent with revised proposal).

                  Interior & Exterior Aluminum Framed Entrances & Storefronts
                      • Price includes 2” x 4 ½” thermal storefront framing for exterior.
                      • Price includes 1 ¾” x 4 ½” non-thermal storefront framing for interior.
                      • Price includes 6’0” x 7’0” pair wide stile entrance doors with cross rails.
                      • Price includes 3’0” x 7’0” single wide stile entrance doors with cross rails.
                      • The door hardware shall be as specified per door per school.
                              o Changed hinges to ABH as Ives will no longer warranty the specified
                                  hinges for doors that are over 1.75”T.
                      • All exposed finishes shall be as specified per school.
                      • Price includes CRL bullet resistant level 2 transaction windows with 12” D, 2”H stainless
                          steel level 2 shelf with integral deal tray & Speak hole cover.
                      • Price does not include any film or graphics in pricing.
                      • All elevations per school are based off information provided on A-600 per set.
                      • Price includes the removal of all ¼” glass to be replaced with 3/8” clear tempered as
                          stated and shown on A-600 of each set of drawings per school.
                              o Add/Alt3, per school, shall be listed in the proposal as an increase to
                                  change existing glass described above from 3/8” to 1” IGs.

 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                       •   Price includes the demo of all hollow metal, aluminum, or wood framing that directly
                           affects our work scope area.
                               o No demo is included for any framing that does not affect our scope.

                       •   All replacement from ¼” to 3/8” as designated on A-601 is included in pricing.
                                o Add/Alt1, per school, shall be listed in the proposal as an increase to
                                   change existing glass described above from 3/8” to 1” IGs.
                       •   All new wood and hollow metal doors in the security vestibule have been included for
                           door inserts in doors by others.
                                o Add/Alt2 shall be the replacement of 3/8” door inserts to UL752 level 2
                                   bullet resistant glass.
                                o Add/Alt2 is for glass only. Stops or door insert kits by others.

                       •   Add/Alt4: $325.00 per core
                             o Price includes the installation and 1-year maintenance of all permanent cores to
                                 be installed by ClearVue Hardware supplier. ClearVue Counted 288 cores that
                                 are associated with our doors. All other doors, door hardware and cores by
                                 others.

                  Perimeter Joint Sealers
                     • Perimeter sealants shall be a standard color at exterior and interior of the aluminum
                        storefront systems only. 2-beads included.




 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Avondale ES: $98,800.00
                     • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-2 frame with (1) pair of
                       doors, (1) iSF-1 with (1) single door & transaction window.
                     • Price includes (1) wood door insert in wood door by others & (12) pieces of replacement
                       glass as shown on D3 on A-600.
                     • Add/Alt1: $2,770.00
                     • Add/Alt2: $1,310.00
                     • Add/Alt3: $480.00
                     • Add/Alt4: $2,925.00

                  Avondale HS: $236,030.00
                     • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 with (1) single door, (1)
                       iSF-2 frame with (1) pair of doors, (1) iSF-3 frame with transaction window, & (1) iSF-4
                       frame.
                     • Price includes (30) pieces of replacement glass shown on A6 on -600.
                     • Price includes the furnish and install of (16) 42 ½” x 98” Riot Glass AP2-SF-HD framing
                       with AP100-BR2 1” bullet resistant Level 2 framing and glazing.
                           o Please note that there are no horizontals in the specified system. This will be a
                               full-height system sitting in front of the existing system. You will see the
                               horizontals through this system from the original system, but there will be no true
                               divided lites. 1 Unit.
                     • ADD/ALT3: $1,020.00
                     • ADD/ALT4: $2,925.00

                  Brockett ES: $113,940.00
                     • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with (1) pair of
                        doors, & (1) iSF-2 with (1) single door & transaction window.
                     • Price includes (1) wood door insert in wood door by others & (30) pieces of replacement
                        glass as shown on A4 on A-600.
                     • Add/Alt1: $5,530.00
                     • Add/Alt2: $1,310.00
                     • Add/Alt3: $4,250.00
                     • Add/Alt4: $2,925.00

                  Browns Mill ES: $130,280.00
                     • Price includes (3) single doors with transom, (1) iSF-1 frame, (1) iSf-2 frame with (3)
                       single doors, & (1) iSF-3 frame with (2) single doors.
                     • Price includes (5) pieces of replacement glass shown on A5 on A-600.
                     • ADD/ALT1: $1,120.00
                     • ADD/ALT3: $1,100.00
                     • ADD/ALT4: $3,250.00

 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Canby Lane ES: $120,490.00
                     • Price includes (1) SF-1 frame with (1) pair of doors & (1) single door, (1) iSF-2 frame
                        with (1) pair of doors & (1) single door, & (1) iSF-2 with (1) single door & transaction
                        window.
                     • Price includes (12) pieces of replacement glass shown on D2 on A-600.
                     • ADD/ALT1: $7,900.00
                     • ADD/ALT3: $600.00
                     • ADD/ALT4: $3,575.00

                  Cedar Grove HS: $154,920.00
                     • Price includes (1) SF-1 frame with (1) pair of doors & (1) single door, (1) iSF-1 frame
                        with (1) pair of doors & (1) single door, & (1) iSF-2 with (1) single door & transaction
                        window.
                     • Price includes (12) pieces of replacement glass shown on D3 on A-600.
                     • Price includes the furnish and install of (4) 3/8” Level 2 Ballistic fiberglass panels in
                        existing frames as shown on D3 on A-600.
                     • Add/Alt1: $1,320.00
                     • Add/Alt3: $ 1,040.00
                     • Add/Alt4: $3,900.00

                  Chamblee HS: $150,600.00
                     • Price includes (1) iSF-1 frame with (2) pair of doors, (1) iSF-2 frame with (1) pair of
                       doors & (1) single door, (1) iSF-3 frame with (2) single doors and (2) transaction
                       windows, & (1) iSF-3 frame with glass only.
                     • Add/Alt4: $4,550.00

                  Chamblee MS: $171,240.00
                     • Price includes (1) SF-1 frame with (2) pair of doors, (1) iSF-01 frame with (1) transaction
                       window, (1) iSF-2, (1) iSF-3, & (1) iSF-4 frame with glass only, (1) iSF-5 frame with (2)
                       pair of doors, (1) transaction window with framing as seen on A6 on A-600.
                     • Price includes (1) P6 door insert in wood door by others.
                     • Add/Alt1: $4,200.00
                     • Add/Alt2: $1,940.00
                     • Add/Alt4: $4,875.00




 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Columbia HS: $111,070.00
                     • Price includes the furnish and install of (1) iSF-1 frame with (1) single door and
                       transaction window & (1) iSF-2 frame with (3) single interior doors.
                     • Price includes the furnish and install of (9) pieces of 3/8” replacement glass and removal
                       of existing ¼” glass as shown on C1 on A-600.
                     • Price includes the furnish and install of (3) 3/8” level 2 ballistic fiberglass panels in new
                       storefront iSF-1.
                     • Add/Alt1: $4,200.00
                     • Add/Alt3: $450.00
                     • Add/Alt: $1,625.00

                  Coralwood Education School: $147,410.00
                     • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with (1) pair of
                        doors, (1) iSF-2 frame with (1) pair of doors, & (2) new standalone transaction windows.
                     • Price includes (2) pieces of glass for (1) PNL-FG-WD2 door by others.
                     • Price includes the furnish and install of (4) pieces of 3/8” replacement glass and removal
                        of existing ¼” glass as shown on C1 on A-600.
                     • Add/Alt1: $5,430.00
                     • Add/Alt2: $3,870.00
                     • Add/Alt3: $220.00
                     • Add/Alt4: $4,875.00

                  Dunaire ES: $ 68,720.00
                    • Price includes the furnish and install of (1) iSF-1 frame with (1) pair of doors & (1) iSF-2
                        frame with (1) single door and transaction window.
                    • Price includes the furnish and install of (6) pieces of 3/8” replacement glass and removal
                        of existing ¼” glass as shown on C3 on A-600.
                    • Add/Alt1: $2,100.00
                    • Add/Alt3: $690.00
                    • Add/Alt4: $1,625.00

                  Dunwoody HS: $89,650.00
                    • Price includes (1) iSF-1 frame with (2) pair of doors & (1) iSF-2 frame with transaction
                       window only.
                    • Price includes (2) pieces of glass for (1) PNL-FG-WD2 door by others.
                    • Price includes the furnish and install of (16) pieces of 3/8” replacement glass and
                       removal of existing ¼” glass as shown on D3 & D4 on A-600.
                    • Add/Alt1: $5,230.00
                    • Add/Alt2: $3,870.00
                    • ADD/ALT3: $1,800.00
                    • ADD/ALT4: $2,275.00
 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Flat Shoals ES: $145,640.00
                      • Price includes (1) SF-1 frame with (3) single doors, (1) iSF-1 frame with (3) single doors,
                         & (1) iSF-2 with (1) single door and (1) transaction window.
                      • Price includes the furnish and install of (15) pieces of 3/8” replacement glass and
                         removal of existing ¼” glass as shown on C5 on A-600.
                      • Add/Alt1: $2,760.00
                      • Add/Alt3: $ 1,000.00
                      • Add/Alt: $2,925.00


                  Hightower ES: $132,990.00
                     • Price includes (1) SF-1 frame with (2) pair of doors, (1) iSF-1 frame with (2) pair of
                        doors, & (1) iSF-2 frame with transaction window.
                           o Transom glass to be spandrel on SF-1.
                     • Price includes the furnish and install of (14) pieces of 3/8” replacement glass and
                        removal of existing ¼” glass as shown on C4 on A-600.
                     • Add/Alt1: $2,200.00
                     • Add/Alt3: $1,380.00
                     • Add/Alt4: $4,550.00

                  Jolly ES: $119,390.00
                      • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with (1) pair of
                         doors, & (1) iSF-2 frame with (1) single door & (1) transaction window.
                      • Price includes the furnish and install of (12) pieces of 3/8” replacement glass and
                         removal of existing ¼” glass as shown on C5 on A-600.
                      • Add/Alt1: $2,590.00
                      • Add/Alt3: $1,500.00
                      • Add/Alt: $2,925.00
                  Kingsley ES: $71,430.00
                     • Price includes (1) SF-1 frame with (1) single door & (1) iSF-1 frame with (1) single door
                        and transaction window.
                     • Price includes the furnish and install of (1) PNL-FG-WD door insert in door by others.
                     • Price includes the furnish and install of (2) 3/8” level 2 ballistic fiberglass panels in
                        existing windows as shown on A3 on a-600.
                     • Add/Alt2: $6,040.00
                     • Add/Alt4: $975.00
                     • Add/Alt for New Glass: $840.00
                            o Price includes thew removal of existing glass and AC panel to be replace with 1”
                                IGs to match the rest of the school.
                     • Add/Alt for New Pair Doors: $32,940.00
                                 o Price includes the removal of existing door, furnish and install (1) pair of doors and
                                   hardware. The door is to be painted blue to match existing area to best possible match

 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Lithonia HS: $290,170.00
                      • Price includes (1) SF-1 set of frames with (3) single door & (3) pair of doors, (1) iSF-1
                         set of frames with (3) single door & (3) pair of doors, (1) iSF-2 frame with (1) single door,
                         and (1) transaction window with frame and transom.
                      • Price includes the furnish and install of (24) pieces of 3/8” replacement glass and
                         removal of existing ¼” glass as shown on C3, C4, & C5 on A-600.
                      • Add/Alt1: $11,690.00
                      • Add/Alt3: $1,920.00
                      • Add/Alt: $8,775.00

                  Margaret Harris Comp School: $162,420.00
                     • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with (1) pair of
                        doors, & (1) iSF-1 frame with transaction window.
                     • Price includes the furnish and install of (8) pieces of 3/8” replacement glass and removal
                        of existing ¼” glass as shown on A4 on A-600.
                     • Price includes the furnish and install of (9) 3/8” ballistic fiberglass panels. (1) in
                        transaction window framing & (8) in existing windows as shown on A3 & A4 on A-600.
                     • Add/Alt1: $2,210.00
                     • Add/Alt2: $8,480.00
                     • Add/Alt3: $1,920.00
                     • Add/Alt: $4,225.00

                  McLendon ES: $152,000.00
                    • Price includes (2) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with transaction
                       window, (1) iSF-2 frame with (1) single door, & (1) iSF-3 frame with (2) pair of doors.
                    • Price includes the furnish and install of (12) pieces of 3/8” replacement glass and
                       removal of existing ¼” glass as shown on A5 on A-600.
                    • Add/Alt1: $1,128.00
                    • Add/Alt3: $780.00
                    • Add/Alt4: $4,875.00

                  Panola Way ES: $186,790.00
                     • Price includes (1) SF-1 frame with (2) pair of doors, (1) iSF-2 frame with (2) pair of
                        doors, (1) iSF-1 frame with transaction window, & (1) iSF-1 frame with (1) single door.
                     • Add/Alt1: $13,740.00
                     • Add/Alt4: $4,875.00




 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Robert Shaw Theme ES: $384,280.00
                    • Price includes (1) SF-1 frame with (2) single doors & (1) pair of doors, (1) single
                        transaction window, & (1) iSF-2 frame with (2) single doors & (1) pair of doors
                    • Price includes (1) pieces of glass for (1) PNL-FG-WD & (1) PNL-N-WD in door by others.
                    • Add/Alt1: $1,760.00
                    • Add/Alt2: $7,270.00
                    • Add/Alt4: $4,550.00

                  Salem MS: $149,420.00
                     • Price includes (1) SF-1 frame with (2) pair of doors, (1) iSF-1 frame with (1) single door
                        & (1) transaction window, & (1) iSF-2 frame with (2) pair of doors.
                     • Price includes the furnish and install of (8) pieces of 3/8” replacement glass and removal
                        of existing ¼” glass as shown on C4 on A-600.
                     • Add/Alt1: $3,730.00
                     • Add/Alt3: $1,520.00
                     • Add/Alt4: $4,875.00

                  Stone Mountain MS: $137,770.00
                     • Price includes (1) SF-1 set of frames with (2) pair of doors, (1) iSF-1 frame with (1)
                        transaction window, (1) iSF-2 frame with transaction window, & (1) iSF-3 frame with (1)
                        pair of doors.
                     • Price includes (1) piece of glass for (1) PNL-FG-HM & (1) PNL-N-WD in doors by others.
                     • Add/Alt1: $1,620.00
                     • Add/Alt2: $7,270.00
                     • Add/Alt: $3,575.00

                  Tucker MS: $161,250.00
                     • Price includes (2) SF-1 frame with (1) pair of doors each, (1) iSF-1 with (2) pair of doors
                        and (1) SF-1 frame with no doors, (1) iSF-2 frame, (1) transaction window with frame, (1)
                        iSF-3 frame with (1) transaction window & (1) iSF-4 frame.
                     • Price includes (1) pieces of glass for (1) PNL-G-WD in door by others.
                     • Add/Alt1: $1,760.00
                     • Add/Alt2: $1,940.00
                     • Add/Alt: $4,550.00




 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Woodward ES: $101,110.00
                    • Price includes (1) SF-1 frame with (1) pair of doors, (1) iSF-1 frame with (1) pair of
                       doors, & (1) iSF-2 frame with transaction window.
                    • Price includes the furnish and install of (9) pieces of 3/8” replacement glass and removal
                       of existing ¼” glass as shown on D3 on A-600
                    • Add/Alt1: $4,820.00
                    • Add/Alt2: $1,310.00
                    • Add/Alt3: $1,790.00
                    • Add/Alt4: $2,600.00




 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  Qualifications:
                    • ClearVue recommends that GC or School handle final coring. ClearVue to supply
                         construction cores.
                    • No Dumpsters
                    • Quarterly maintenance starting at substantial completion of each school for 6
                         months included. Maintenance to be during regular business hours. No overtime
                         or after hours. We may be able to do the maintenance on school holidays that
                         ClearVue does not take.
                    • Sales tax is included.
                    • Price includes Clearvue Glass prepared shop drawings.
                    • No PE calcs
                    • Escalation included through 2025, ClearVue reserves the right to reevaluate our
                         number January 2, 2026. If no price increases ClearVue number will stay the same.
                    • No Bond (if required add 1%)
                    • Warranties included
                             o 1-year Clearvue Glass labor warranty
                             o 1-year BR fiberglass panels
                             o 10-year glass seal warranty
                             o 3-year BR laminated glass warranty
                             o 10-year metal finish warranty
                             o 2-year installer’s warranty on sealants
                             o 10-year manufacturer's warranty on sealants
                    • No mirrors
                    • No access controls
                    • Power supply, Card Reader, Intercom System, Push Button and balance of access
                         control is BY OTHERS.
                    • No card readers
                    • No electrical hook ups
                    • No Film or Graphics
                    • No ACM panels
                    • No thru-wall flashing
                    • No wood blocking
                    • No attic stock
                    • No heat soaking
                    • No safing
                    • No insulation
                    • No testing
                    • No final cleaning or protection of work after installation
                    • Daily clean up & protection of surrounding work is included
                    • ClearVue reserves the right to bill for stored materials.

 * Due to rapidly escalating and unpredictable pricing and uncertain availability and late delivery of construction materials, the price set
forth in this proposal/contract and the date(s) of delivery are subject to change based on price increases and changes in delivery dates
communicated to Clearvue Glass between the date of this proposal and when the materials are delivered. Major construction materials
manufacturers have stated that the price of materials will be the price in effect at the time of delivery and that delivery dates are subject
                                                                 to change.
                  ATLANTA STOREFRONTS, LLC



July 30 2025

Andrea Torres
LEFKO Construction
1056 Mansell Circle
Roswell, Ga. 30075

RE: Brockett ES Security Vestibule
    084113 Aluminum Framed Entrances And Storefronts
    085693 Transaction Windows
    087100 Door Hardware
    088000 Glazing

Andrea,
As per your request, the following Bid Proposal outlines Atlanta Storefronts Scope Of
Work at the above referenced facility in accordance with Plans and Speci cations
dated April 30 2025 and Addendum #1. Revised with alternate

                                 SCOPE OF WORK
1. Supply and Install Oldcatle Series 3000 Thermal MultiPlane, 2” x 4-1/2” Front Plane
   Glazed Exterior Aluminum Storefront System nished in Class 1 Dark Bronze
   anodized in Exterior opening marked :
   A1 SFI A600 = 13’-8” x 10’-0” including 1 Pair of doors #001 6’-0” x 7’-0” with
   transom frame. The doors leafs are Thermal Clad, 2-1/4” thick, with 5” Wide Stiles,
   10” bottom rails, 6-1/2” mid rails and 8” top rails. We include hardware for our
   door per speci cations. #001 = Group No. 01.
   The frames and doors are glazed with 1” Insulated Clear Tempered with Guardian
   SNX51/23 Low E Coated glass.

2. Supply and Install Oldcastle Series 3000 Non thermal 2 x 4-1/2”, center glazed
   Aluminum Storefront system nished in Class 1Dark Bronze anodized in Interior
   openings marked :
   A3 ISF2 = 14’-7 1/4” x 7’-2”, including 1 Single Door #004 = 3’-0” x 7’-0”, no transom
   The doors leafs are 1-3/4” thick, with 5” Wide Stiles, 10” bottom
   rails, 6-1/2” mid rails and 8” top rails.
   A2 ISF1 = 14’-4” x 7’-2” including 1 Pair of Doors #003 = 6’-0” x 7’-0” no transom
   and made like door listed above.
   Includes BM D3 on Page A600.
       fi
                      fi
                                      fi
                                                               fi
                   ATLANTA STOREFRONTS, LLC



     We include SF Door Hardware for #003 = Group No. 02 and #004 = Group No. 04.
     The interior frames and doors are glazed with 3/8” clear tempered glass.

3. Supply and Install 1- 60”x 56” Level 3 BR Transaction Security Ticket Window by
   QuikServ with 1-1/4” Acrylic Glazing, natural Speak-Around clear anodized framing
   and SS 60” x 12” x 2” Base with Integrated Deal Tray.

4. Supply and Install “Glass Only” in Door #002 A5 and transom = 3/8” clear Tempered.

5. Per page A600 remove existing glazing in A4 and replace with 1” insulated with SNX
   51/23 Low E clear Tempered glass in 5 windows Marked A4, 30 lites.

6. Per page A601 remove existing glazing and replace with 1” Insulated with SNX 51/23
   Low E clear Tempered glass in openings Marked #1, #2, and #3.

7. Demolish and put in GC dumpster. Per Page AD101, 1 Pair, 2 Singles and 6 side lites.

8.   Supply and Install sealant to the Exterior and Interior perimeters of all the
     new aluminum frames, The caulk color will match the frames.

9.   We Include a daily clean up of our debris and one final clean of our installed
     materials.

10. We include the protection of our installed materials by wrapping them with brown
    paper held on with non residue tape.

11. Included are Shop Drawings, Submittal Data, Samples, and Existing test reports.

12. The aluminum finish warranty is 10 years, Workmanship warranty is 2 Years, and the
    Transaction windows are 3 Years.

Items Not Included in this Proposal :
1.   Bond, if needed ADD 3850
2.   Pre construction Mockup that is Not part of the permanent work.
4.   Hiring of a Testing Agency or supplying supervision or equipment for testing.
5.   Designing of Field Quality-Control Inspection reports or programs.
6.   Free glass replacement if “ broken” or “scratched” by others after installed.
7.   Delegated Design
                 ATLANTA STOREFRONTS, LLC



8. In the areas where we do demolition we do not include any repair or patching of
   surfaces, or demo of Partitions and walls.
9. Purchasing of Safe Haven Film lm.

Lead Times and Installation
1)   Shop drawings and submittals are a 4 week lead time
2)   The Custom Aluminum Doors and Hardware have a 10 week lead time.
3)   Fab of aluminum is 2 weeks
4)   Installation duration is 4 weeks.


BASE BID         $128,950


Alternate
1. To use 3/8” glass in door #3 ( 2 lites) on A601 will deduct $160


Note : This Quote will remain valid as long as we receive a written commitment
       within 90 days.

If there is any other information you require, please do not hesitate to call me. We
look forward to the opportunity of working with you,

Thank You

Respectfully submitted,
Chuck Morris
Senior PM
Atlanta Storefronts LLC
                       fi
                                                     BDL
                                               Glass and Glazing LLC
                                                255 E Plantation Dr
                                               Sharpsburg GA 30277
Date: 8 July 2025

Job: DCDS Security Vestibules

Base bid: $2,175,000.00 – Quote valid for 30 days
       ***Storefront doors/frames/glazing quoted are not ballistic rated – ballistic laminate by others***
       ***Add Alternate – Add $1,060,050.00 to provide and install door hardware
Addendum 2 received

Included in base:

EFCO Series D502 Thermastile and D518 Storefront Doors w/ Series 401 and 403 Framing
Frame Finish/Color: See next page for door quantity and finish breakdown by school
1” Insulated/Tempered Glazing for exterior storefront framing
3/8” Clear Tempered glazing for interior framing and 3/8” replacement glazing as scheduled for existing perimeter
doors shown in drawing A601/A602 for each school
CRL Level 2 Bullet Resistant Transaction Windows (30 total)
Installation of material
Interior and exterior caulking for storefront frames (2 beads)
Shop Drawings
Dumpsters


Excluded: Demolition not noted above, tornado/blast/impact/ballistic rated assemblies not noted above, existing
window repairs/painting, door hardware not listed above, wiring/connection of electrified hardware, any fire rated
materials not listed above, asbestos abatement, mirrors, louvers, temporary opening closures, skylights, glazed
railings, display cases, water testing fees, traffic doors and glazing thereof, overhead roll-up/coiling doors, final
cleaning, and bond.
Thank you
Matt Davidson
BDL Glass and Glazing LLC
Matt.BDLGlass@gmail.com
205-667-3845
Avondale ES – 1 single, 2 pairs of doors – Clear anodized
Avondale HS – 1 single, 2 pairs – Dark bronze anodized – Add $3,000 for custom paint finish
Brockett ES – 1 single, 2 pairs – Dark bronze anodized – Add $3,000 for painted finish
Browns Mill ES – 8 singles – Clear anodized
Candy Lane ES – 3 singles, 2 pairs – Clear anodized
Cedar Grove ES – 3 singles, 2 pairs – Clear anodized
Chamblee HS – 3 singles, 3 pairs – Clear anodized – Add $4,500 for custom paint finish
Chamblee MS – 4 pairs – Dark bronze anodized
Columbia HS – 4 singles – Clear anodized
Dunaire ES – 1 single, 1 pair – Clear anodized
Dunwoody HS – 2 pairs – Clear anodized
Flat Shoals ES – 7 singles – Clear anodized
Hightower ES – 4 pairs - Clear anodized
Jolly ES – 1 single, 2 pair - Clear anodized
Kingsley ES – 2 singles – Clear anodized
Lithonia HS – 7 singles, 6 pairs – Clear anodized
Margaret Harris Comp School – 2 pair – Clear anodized
McLendon ES – 1 single, 4 pairs – Clear anodized
Panola Way ES – 1 single, 4 pairs – Dark bronze anodized – Add $4,500 for custom paint finish
Robert Shaw ES – 4 singles, 2 pairs – Clear anodized
Salem MS – 1 single, 4 pairs – Dark bronze anodized – Add $3,600 for custom paint finish
Stone Mtn MS – 3 pairs – Custom paint finish
Tucker MS – 4 pairs – Dark bronze anodized
Woodward ES – 2 pairs – Clear anodized
                            ADD FOR      ADD FOR       ADD FOR 1"
School       BASE BID                                                    TOTAL
                           HARDWARE MAINTENANCE          GLASS
  1      $     70,000.00   $ 33,000.00 $    2,500.00   $ 1,199.00    $     106,699.00
  2      $     77,000.00   $ 45,000.00 $    2,500.00   $ 8,175.00    $     132,675.00
  3      $     87,000.00   $ 30,750.00 $    2,500.00   $ 3,488.00    $     123,738.00
  4      $     82,000.00   $ 33,450.00 $    2,500.00   $ 3,409.00    $     121,359.00
  5      $     76,000.00   $ 36,000.00 $    2,500.00   $ 4,982.00    $     119,482.00
  6      $     85,000.00   $ 48,000.00 $    2,500.00   $ 5,668.00    $     141,168.00
  7      $    103,000.00   $ 49,800.00 $    2,500.00   $         -   $     155,300.00
  8      $    114,000.00   $ 52,500.00 $    2,500.00   $ 4,142.00    $     173,142.00
  9      $     59,000.00   $ 22,000.00 $    2,500.00   $ 7,022.00    $      90,522.00
 10      $     84,000.00   $ 57,000.00 $    2,500.00   $ 18,379.00   $     161,879.00
 11      $     62,000.00   $ 16,000.00 $    2,500.00   $ 4,321.00    $      84,821.00
 12      $     81,000.00   $ 37,000.00 $    2,500.00   $ 11,076.00   $     131,576.00
 13      $     78,000.00   $ 43,500.00 $    2,500.00   $ 6,379.00    $     130,379.00
 14      $     86,000.00   $ 42,750.00 $    2,500.00   $ 5,102.00    $     136,352.00
 15      $     57,000.00   $ 39,000.00 $    2,500.00   $ 5,316.00    $     103,816.00
 16      $     65,000.00   $ 16,500.00 $    2,500.00   $ 4,634.00    $      88,634.00
 17      $    199,000.00   $ 93,750.00 $    2,500.00   $ 24,857.00   $     320,107.00
 18      $     93,000.00   $ 54,000.00 $    2,500.00   $ 9,052.00    $     158,552.00
 19      $     82,000.00   $ 57,000.00 $    2,500.00   $ 7,194.00    $     148,694.00
 20      $    110,000.00   $ 46,500.00 $    2,500.00   $ 33,383.00   $     192,383.00
 21      $     97,000.00   $ 46,500.00 $    2,500.00   $ 2,507.00    $     148,507.00
 22      $    110,000.00   $ 46,500.00 $    2,500.00   $ 9,007.00    $     168,007.00
 23      $    123,000.00   $ 44,000.00 $    2,500.00   $ 1,635.00    $     171,135.00
 24      $    113,000.00   $ 45,000.00 $    2,500.00   $ 9,507.00    $     170,007.00
 25      $    100,000.00   $ 28,000.00 $    2,500.00   $ 10,015.00   $     140,515.00
                              TOTAL BID                              $   3,619,449.00
        8105 Odessa Place, Building A   Douglasville, Georgia 30134    Tel: (770) 838-3966

6-27-25
To: Ana Cegarra
Company: LefKo
Email: ana@lefkogroup.com
Phone: 678-682-9813

PROJECT: Brockett ES

                                     SCOPE OF WORK
Exterior Storefront
Furnish and install:
   • YKK YES 45 TU – Thermal 2” x 4 ½” storefront system
            o Tags: SF-1
   • YKK YES 50T Wide stile - 2” thk thermal storefront doors
            o Dr 001
   • Finish: Bronze Anodized
   • Glazing: 1” SNX 51/23 HT tempered
   • Two perimeter joints
   • Door hardware included per specs dated 4/30/25

Interior Storefront
Furnish and install:
    • YKK YES 45 FS – non thermal 1 ¾” x 4 ½” storefront system
            o Tags: ISF-1; ISF-2
    • YKK YES 50D Wide stile - non thermal 1 ¾” storefront doors
            o Dr 003, 004
    • Finish: Bronze Anodized
    • Glazing: 3/8” clear tempered glazing
    • GL/L2 – Replacing existing door glass with new 3/8” tempered glass
   •   CRL –transaction window with level 2 laminated polycarbonate bullet resistant glazing,
       CRL 834a speak-thru & deal tray@ iSF-1
  •    Two perimeter joints
  • Door hardware included per specs dated 4/30/25
  •
Demolition

   •   Removal of existing glazing systems at areas noted on the bid drawings dated 4/30/25.

                                                                           Base Price $120,440.00
ALT 1 DEDUCT
Furnish and install:
   • Defenselite -Bullet shield - fixed transaction window with UL 752 Level 2 protection,
       CRL 834a speak-thru and a deal tray

                                                                                          Deduct $4,107.00



CLARIFICATIONS
Spandrel glass is not meant to be visible from the inside. Inconsistencies not visible from the exterior
view can be visible from the interior view. This does not mean that it is faulty. Our scope of demolition is
limited exclusively to the removal of existing glazing systems. This includes the selective demolition of
glazing infill at designated openings, including the removal and disposal of existing glass, aluminum
storefront/window framing systems, associated perimeter sealants, setting blocks, and glazing gaskets as
required. No adjacent building components such as surrounding substrates, drywall, framing,
waterproofing, or structural elements are to be disturbed or removed.
All demo will be performed in accordance with industry standards and project safety requirements.
Protection of adjacent finishes and coordination with other trades is by others.


EXCLUSIONS
 Hollow metal doors. Access control and wiring of any electrical devices; payment and performance
bonds; Liability for material price escalations due to global events; unrestricted site access is assumed,
with any delays due to site conditions or other trades requiring schedule extensions and additional costs;
Weather, natural disasters, and unforeseen delays are excluded, with remobilization or extended general
conditions billed separately. Door hardware. Removal or remediation of existing conditions, concealed
hazards, or deteriorated substrates; Temporary protection and final cleaning beyond a broom-swept
condition are excluded; Damage by others; Testing, mockups, and samples beyond standard submittals;
On-site storage and material handling; Overtime, night shifts, or schedule acceleration; Specialty
hardware, decorative metals, custom finishes, and non-standard components unless listed in our scope;
blocking and junction box at mirrors
TERMS AND CONDITIONS
Any alterations of deviations from above specifications may result in additional charges. In the event
customer cancels order after confirmation, deposit will not be returned.
Standard payment terms: 2% 10 net 30 days. Late fees of 10% per week will be charged for every week
past the due date.
Material payment terms: Net 30 upon receipt of material. Purchase documentation can be provided upon
request.
This proposal is valid for 30 days and is subject to change if material price increases occur after 30 days.
ACCEPTANCE OF PROPOSAL
____________________________
Date

Respectfully Submitted By:
 Vik Malut
vmalut@clearviewinstallations.com

C: 561.568.3340



ADDITIONAL SERVICES - CLEANING/INSPECTIONS/MAINTENANCE
We now offer cleaning/inspection/maintenance programs to follow completion of our projects. Pricing is
separate from this proposal and can be provided upon request. Please let us know if would like additional
information.
520 Wes Walker Memorial Drive                                                                                      July 8, 2025
Ball Ground, Ga 30107
(404) 351-8724 Phone
ashley@tuxedoglass.com

Ana Cegarra
Lefko Construction
105 Mansell Circle
Roswell, GA 30075
                                                        PROPOSAL
Project: DCSD Group 1: #1- #9
Drawings & Specifications Dated: 4/30/2025

Dear Ana,

Tuxedo Glass & Mirror is pleased to provide a proposal with the following scope of work:

Framing:         Kawneer 451T & 451 Center Set (2” x 4 1/2”)
                 Clear Anodized Finish **Unless noted otherwise within individual school notes
                 Exterior & Interior Vestibules

Glass:           1” IG – Energy Select28 @ Exterior Vestibule
                 3/8” Clear Tempered @ Replacement Glass
                 3/8” Clear Tempered Glass @ Interior Vestibule

Caulking:        2 lines of silicone caulk at perimeter of all aluminum framing

Doors:           Kawneer Wide Stile Exterior Doors
                            o Thermal
                            o Hardware as specified
                 Kawneer Wide Stile Interior Doors
                            o Non Thermal
                            o Hardware as specified

Security:        QuikServ Ticket Window
                              o 36” x 36”
                              o Speak Around
                              o BR Deal Tray
                              o Level 3 acrylic BR glazing
                              o Clear Anodized

Demolition:      Demolition included at the following
                              o Refer to notes in cover letter referencing waterproofing at openings and glass replacement.

BR Frame/Glass: INFO HERE



                                                                                                                  1|Page
1.   Avondale Elementary School                                                         $139,382 tax included
         •   Approx. 64 sq/ft of new storefront framing
         •   1-thus Exterior Pair of Doors – Door #001
         •   1-thus Interior Pair & 1-thus Single Door #002 & #003
         •   1-thus Security Window
         •   4-thus replacement of glass @ Existing Windows
         •   16-thus replacement of glass @ Existing Doors
         •   Demo of 4 existing doors & sidelite framing



2.   Avondale High School                                                               $280,686 tax included
         •   Standard Bronze Finish Included at aluminum framing & doors
         •   Approx. 184 sq/ft of new storefront framing
         •   1-thus Exterior Pair of Doors with custom graphic at transom – Door #001
         •   1-thus Interior Pair & 1-thus Single Door #002 & #003
         •   1-thus Security Window
         •   4-thus Level 2 BR Supplemental Frames (Note 6)
         •   7-thus replacement of glass @ Existing Windows (Note 5)
         •   53-thus replacement of glass @ Existing Doors
         •   4-thus replacement of glass @ Existing Sidelites
         •   Demo of 4 existing doors & sidelite framing


3.   Brockett Elementary School                                                         $178,747 tax included
         •   Standard Bronze Finish Included at aluminum framing & doors
         •   Approx. 205 sq/ft of new storefront framing
         •   1-thus Exterior Pair of Doors #001
         •   1-thus Interior Pair & 1-thus Single Doors #003 & #004
         •   1-thus Security Window
         •   5-thus replacement of glass @ Existing Windows (Note 5)
         •   4-thus replacement of glass @ Existing Doors
         •   12-thus replacement of glass @ Existing Sidelites
         •   Demo of 3 existing doors & sidelite framing


4.   Browns Mill Elementary School                                                      $166,301 tax included
         •   Approx. 140 sq/ft of new storefront framing
         •   3-thus Exterior Single of Doors #001,#002 & #003
         •   5-thus Interior Single Doors #004, #005, #006, #007 & #008
         •   1-thus Security Window
         •   5-thus replacement of glass @ Existing Windows (Note 4)
         •   2-thus replacement of glass @ Existing Doors
         •   Demo of 5 existing doors & sidelite framing


5.   Canby Lane Elementary School                                                       $157,543 tax included
         •   Approx. 70 sq/ft of new storefront framing
         •   1-thus Exterior Single & 1-thus Pair Door #001 & #002
         •   2-thus Interior Single & 1-thus Pair Door #003, #004 & #005
         •   1-thus Security Window
         •   7-thus replacement of glass @ Existing Windows (Note 4)


                                                                                                        2|Page
         •   14-thus replacement of glass @ Existing Doors
         •   Demo of 4 existing doors & sidelite framing (Note A&B)


6.   Cedar Grove High School                                                                             $254,036 tax included
         •   Approx. 80 sq/ft of new storefront framing
         •   1-thus Exterior Single & 1-thus Pair Door #001 & #002 with custom graphic at transom
         •   2-thus Interior Single & 1-thus Pair Door #003, #004 & #006
         •   1-thus Security Window
         •   2-thus replacement of glass @ Existing Windows (Note 5)
         •   19-thus replacement of glass @ Existing Doors & approx. 585 sq/ft replacement glass at Existing
         •   Demo of 5 existing doors & sidelite framing (Note A, B, C &D)


7.   Chamblee Highschool                                                                                 $339,347 tax included
         •   Approx. 230sq/ft of new storefront framing
         •   3-thus Interior Single & 3-thus Pair Door #003, #004, #005, #006, #007 & #008
         •   2-thus Security Window
         •   48-thus replacement of glass @ Existing Doors
         •   Approx 3,000 sq/ft replacement glass as shown on A-602
         •   No demolition


8.   Chamblee Middle School                                                                              $256,603 tax included
         •   Standard Bronze Finish Included at aluminum framing & doors
         •   Approx. 245 sq/ft of new storefront framing
         •   2-thus Exterior Pair of Doors #001 & #002
         •   4-thus Interior Pair of Doors #004, #005, #006 & #007
         •   2-thus Security Window
         •   13-thus replacement of glass @ Existing Windows (Note 6)
         •   30-thus replacement of glass @ Existing Doors
         •   4-thus replacement of glass @ Existing Sidelites
         •   Demo of 5 existing doors & sidelite framing


9.   Columbia High School                                                                                $137,092 tax included
         •   Approx. 150 sq/ft of new storefront framing
         •   4-thus Interior Single Doors #004, #005, #006 & #007
         •   1-thus Security Window
         •   3-thus replacement of glass @ Doors #001, 002 & 003
         •   39-thus replacement of glass @ Existing Doors
         •   Demo of 1 pair existing doors & sidelite framing




EXCLUSIONS

     •   ACM Panel inserts (084113 1.2 A3)                                   •   Laminated Glass (088000 1.35B,1.10 B)
     •   Delegated Design (084113 1.4E) outside of PE Calcs for              •   PE Stamp on shop drawings (only PE Calcs are
         new storefront by TGM                                                   stamped)
     •   Safety & Security Window Laminates (088723)                         •   Testing of any kind in field or laboratory (084113 2.2)
     •   Mock Up (088000 1.7A & 08413 1.8)                                   •   Front set framing – drawings show center set (084113
     •   10 year water penetration warranty (084113 1.9 A D)                     2.3B)
     •   Washing glass (088000 3.5)                                          •   Non removeable glazing stops at doors (084113 2.4B3)

                                                                                                                         3|Page
     •       Three way adjustable anchors (084113 2.8B)                   •   Final Cleaning
     •       Maintenance agreement on new or existing doors &             •   Fire rated caulking, framing or glass
             hardware                                                     •   Concealed, Galvanized, and/or Stainless-Steel flashing
     •       Field Measuring prior to demolition                              or any counterflashing (by others)
     •       Protection                                                   •   Graphics/signage
     •       Concealed Flashing                                           •   Hollow metal framing and lite kits or glass stops at
     •       3-coat, XL, or SunStorm Paint                                    same
     •       Attic Stock                                                  •   Manuf. Certs. Or Approval
     •       Auto operators                                               •   NFRC- energy performance certificates
     •       Brake Metal Coping and Column Wraps or its                   •   Permanent Keying/Cores (see add)
             coordination (only included at storefront scope of           •   Protection from damage by Other Trades
             work)                                                        •   Replacement Warranties
     •       Casework/Millwork specialty glass/glazing, shelving,         •   Self-adhered flashing peel & stick
             etc.                                                         •   Structural support or wood blocking at perimeter of
     •       Electrical card reader & intercom systems                        windows
     •       Electrical (Hi or Lo) Voltage wiring or its coordination


QUALIFICATIONS

    •    Reference “Qualifications & Exclusions” Cover letter dated 5/21/2025 for additional qualifications & exclusions that may
         not be listed in this proposal.
    •    All performance, closeout, warranty is qualified as manufacturer’s standard paperwork & durations.
    •    TGM is not responsible for supply chain interruptions which affect the schedule.
    •    Price valid until September 2025
    •    Shop drawings will not have a PE stamp, PE calculations will be stamped.
    •    TGM does not include Mullion touch up due to damage by others.
    •    We have no testing Included. We will assist in any onsite testing provided by others.
    •    The glass (10) year warranty is for the hermetic seal of the IG unit & Coating. Breakage is not included.
    •    TGM is not responsible for landscape or sidewalk protection for any reason.
    •    If water testing is to be performed on this project, we require it to be done on the mockup and/or within the first 10% of
         the skin installation. All products used at the first water test need to be consistent throughout the building process and all
         sealant lines must be in place. We do not support one line of caulking defense only.




Thank you for the opportunity to provide pricing for this project and we look forward to working with you on this project.

Sincerely,
Ashley G Bramlett
Senior Project Manager




                                                                                                                           4|Page
Client Proposal – Brockett Elementary Security Vestibule

Client: DeKalb County School District
Prepared for: Ana Cegarra
Company: LEFKCO Construction
Project: DCSD – Brockett Elementary Security Vestibule
Location: 1855 Brockett Road, Tucker, GA 30084
Date: August 11, 2025

Scope of Work
- Furnish and install (6) aluminum storefront door leaves:
  • (2) Exterior door leaves – 3'-0" x 7'-0"
  • (4) Interior door leaves – 3'-0" x 7'-0"
- Provide glazing system:
  • Exterior Glass: 1" insulated tempered Low-E (non-ballistic)
  • Interior Glass: 3/8" tempered clear (non-ballistic)
- Provide and install (1) transaction window with integrated deal tray (non-ballistic)
- All aluminum framing and components in clear anodized finish
- All perimeter sealants and anchorage systems included
- Labor for installation: 4 men × 24 hours

Hardware Schedule (Per Door Leaf, or Equal)
- (1) Surface-mounted door closer (LCN 4040XP or equal)
- (1) Rim panic device (Von Duprin 99 series or equal)
- (1) Electric strike (HES 9600 or equal)
- (1) Card reader (HID iCLASS SE or equal)
- (1) Push-to-exit button
- (1) Cylindrical lock
- (1) Wiring and accessories
- All necessary fasteners, shims, and mounting accessories

Warranty and Installation
- All hardware and components furnished with manufacturer warranties per spec section 087100
- Installation duration estimated to be three (3) days

Sales Price
Total Price for Scope Above: $59,490.00

Proposal is valid for 90 days from the date of issue.
All aluminum and glazing systems per specification section 084113.
No glazing on this project is ballistic-rated; all glazing is standard non-ballistic.

Prepared by: Larry Love | Glass Inc. | 404-873-6991 | sales@Glassinc.net
Commercial Construction
& General Contractor




                SAFETY AND SECURITY FILM
                          Selected price: Safe Haven Defense Southeast




LEFKO CONSTRUCTION
                                                                                            PROPOSAL
Prepared for:                                      July 22, 2025                                          No. 2298
Lefko Construction (Group 1)
Attn: Andrea Torres                                Safe Haven Defense
105 Mansell Pl                                     16441 N 90th Street, Suite 100, Scottsdale, AZ 85260
Roswell, GA 30076                                  P: (803) 225-5194 | frank@shdsoutheast.com
andrea@lefkogroup.com                              www.shdsoutheast.com

Brocket ES - 1855 Brockett Rd, Tucker

Scope of Work                                                                                                Total
Supply & Install (643SF) Bullet Resistant Protection - Per LS3P                                     $128,280.00
Drawings (68 total panes)
 PRODUCT DESCRIPTION
 Safe Haven Defense SW440BR/SW600BR laminate offers protection for small arms bullet resistance as well as
 glass breakage due to burglaries, hurricanes, and blast. SW440BR/SW600BR provides ONE-WAY bullet resistance
 allowing bullets to pass through from the interior but stopping bullets from the exterior.
 CERTIFICATIONS
 NIJ 0108.01 - Bullet Resistance (3rd Party Lab Certified)
 UL752 - Bullet Resistance (3rd Party Lab Certified)
 USES/APPLICATION
 Safe Haven Defense SW440BR/SW600BR laminate is applied onsite, to the interior and exterior of existing
 windows/glass. Unlike traditional bullet resistant glass, no special modifications or retrofitting to the existing
 structure is required. SW440BR/SW600BR laminate can be applied over existing glass as thin as ¼ inch and will
 stop a 9mm on dual pane ¼” or 3/8” single pane.
 *Existing window must be inspected to be structurally sound.

Bond - 3%                                                                                              $3,848.00

Please advise of any special PPE, badges, identification, or additional
requirements for contractors/vendors. This project is expected to take     Grand Total:            $132,128.00
5 working days. Lead time will be 6-8 weeks. SHD will need access
after typical work hours and weekends with minimal traffic in the
work areas. SHD will need a clean/dust free working environment. This
price is valid until December 31, 2025.




  [sig|req|signer1||||240|35]                                     [sig|req|signer2||||240|35]

X                                                               X
Andrea Torres (Lefko Construction (Group 1))                    Company Authorized Signature
                                          SCOPE OF WORK

Safe Haven Defense Georgia, LLC will work with associated stakeholders adding security laminate to
existing windows at the address stated on the proposal. The following details the responsibilities and
performance objectives of Safe Haven Defense Georgia, LLC:
1. Responsibilities and Objectives
   1.1. Visually inspect windows for pre-existing damage/deformities.
   1.2. Care will be taken not to damage any areas around the windows.
   1.3. Employees will act in a professional manner when working and interacting with
        staff/employees.
   1.4. Clean & Install Safe Haven Defense Laminate on the windows as described in the proposal.
   1.5. Secure aforementioned laminate utilizing approved and standardized anchoring method.
   1.6. Conduct quality assurance inspections daily throughout the installation process.
   1.7. Maintain an orderly workspace during installation.
2. Glass Clarity:
   2.1. Installation crews will take every necessary action possible to clean all windows prior to the
        installation of the laminate.
       2.1.1. As this installation will be completed in an active environment; minor dust particles may
              appear after the installation of the laminate as a result of airborne dust.
       2.1.2. These particles should be few and not significantly detract from clarity or aesthetics when
              looking through the glass at a distance of 6 feet.
   2.2. Laminates and films are applied with a water-based solution; therefore, it is normal for minor
        bubbling and hazing to occur during installation process before curing.
       2.2.1. This curing period is between 30-120 days depending on the level of exposure to direct
              sunlight, temperature, and thickness of laminate.
3. Safe Haven Defense Georgia, LLC is not responsible for the following actions:
   3.1. Clearing of space (inside or outside) to provide clean and unobstructed access to the target
        windows. Minor items may be an exception.
       3.1.1. Issues such as tree trimming, desk moving, and computer/electronic relocation will be
              completed prior to installation.
   3.2. Permanent structures, piping, support beams etc. which may be an obstruction to the
        installation process, and cannot be relocated, will be evaluated on a case-by-case scenario.
   3.3. Ballistic Laminate installation includes the use of liquid sprayed from high pressure tanks.
        Any item which may sustain water damage and subsequently devalue such item, shall be
        relocated prior to installation.

Safe Haven Defense Georgia, LLC is actively following CDC guidelines to the best of our abilities. Our
COVID-19 response plan includes such measures as self-reporting of illness or feeling of illness and self-
reporting of possible or confirmed exposures. If your facility requires additional precautions, please
inform our team.
                                            SW600BR – PRODUCT SPECIFICATION SHEET
                                            *Proprietary information and not for public distribution.



    PRODUCT DESCRIPTION
    Safe Haven Defense SW600BR laminate offers
    protection for small arms bullet resistance as
    well as glass breakage due to burglaries,
    hurricanes, and blast. SW600BR provides ONE-
    WAY bullet resistance allowing bullets to pass
    through from the interior but stopping bullets
    from the exterior.


   TECHNICAL DATA
     PROTECTION LEVEL             Bullet                          CERTIFICATIONS & STANDARDS
                                  Resistance
     BREAK STRENGTH               Starting at           ANSI Z97.1 – Bldg Glaze Materials               NIJ 0108.01
                                  1200 psi                                                               Bullet Resistance
                                  34,000psi
                                                        CPSC 16 CFR 1201 – Impact Test
     TENSILE STRENGTH                                                                                        3rd Party
     PEEL STRENGTH                6psi                  ASTM E-1886 – Hurricane Wind                       Lab Certified
     TOTAL SOLAR ENERGY           20%
                                                        GSA EXPLOSIVE TEST: GSA TS01-2003
     REJECTION                                                                                              UL752
     IR REJECTION                 59%                   BMAG Level 1- Blast Mitigation                   Bullet Resistance
     UV REJECTION                 99%                                                                        3rd Party
                                                        UL972 / ULC – 332 – Burglary Protection            Lab Certified




                                         USES/APPLICATION
                                         Safe Haven Defense SW600BR laminate is applied onsite, to the interior and
                                         exterior of existing windows/glass. Unlike traditional bullet resistant glass, no
                                         special modifications or retrofitting to the existing structure is required.
                                         SW600BR laminate can be applied over existing glass as thin as ¼ inch and will
                                         stop a 9mm on dual pane ¼” or 3/8” single pane.
                                         *Existing window must be inspected to be structurally sound.




Safe Haven Defense Southeast
803-309-4765 | delmar@SHDsoutheast.com | 15 W. Rigby Street, Manning, SC 29102
*Proprietary information not for public distribution
                                        SECURITY LAMINATE LIMITED WARRANTY
                                        Thank you for purchasing Safe Haven Defense Security Laminate
What is Covered and how long Coverage Lasts. Safe Haven Defense warrants professionally sold and installed Safe Haven Defense Brand Security Laminates
(The “Product”) against the defects in manufacture or materials set forth below and for the time period set forth below. This warranty is valid only if the Product
installation was performed by a Safe Haven Defense installer in accordance with manufacturer’s installation procedures and applicable law.

                 ❏     Security Laminate (Lifetime Limited Warranty) Covers Forced Entry (22 Mil) and Smash Resistance (15 Mil) Films.
                       Safe Haven Defense warrants against fading, peeling, cracking, adhesive failure, and delamination.
                 ❏     Riot Control Security Laminate (10 Year Limited Warranty)
                       Safe Haven Defense warrants against fading, peeling, cracking, adhesive failure, and delamination.
                 ❏     Solar Control Bullet Resistant Laminate (7 Year Limited Warranty – May be extended to 10 Years after Inspection by Safe Haven
                       Defense Representative)
                       Safe Haven Defense warrants against fading, peeling, cracking, adhesive failure, and delamination.
Who is Covered? This limited warranty coverage is applied only to the owner of the structure/vehicle at the time of the Product’s installation and is not transferable.

How Safe Haven Defense Will Manage. If the product does not conform to the warranty described above, Safe Haven Defense will appoint an installer to remove the original
laminate and apply new Safe Haven Defense Laminate and will cover the reasonable labor charges of the removal of the original laminate and installation of new laminate. The
obligation of Safe Haven Defense under this warranty is limited solely to removal and replacement of any Product not conforming to the warranty.
How to Make a Claim. To submit a warranty claim, you must SUBMIT THIS ORIGINAL WARRANTY CARD AND ORIGINAL RECEIPT for the product,
along with a detailed description of the defect to the Safe Haven Defense distributor from whom the Product was purchased or to Safe Haven Defense at the address
below. Safe Haven Defense must approve all warranty claims prior to commencement of any warranty service. Safe Haven Defense US, LLC / 22849 N 19th Avenue,
Suite 100/ Phoenix AZ 85027 / 480-689-7871
Window Laminate Care. To extend the life and looks of your Safe Haven Defense Security Laminate and to maintain your warranty coverage, certain care and
maintenance should be followed. Do not wash the film with abrasive cleaners (e.g., Ammonia) or course cloths. Use a mild soap and a clean, soft cloth or
synthetic sponge.
Warranty Limitation. THE EXPRESS WARRANTIES CONTAINED IN THIS AGREEMENT ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS
OR IMPLIED. SAFE HAVEN DEFENSE HEREBY DISCLAIMS ALL OTHER EXPRESS AND IMPLIED WARRANTIES, INCLUDING THE IMPLIED
WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE.
Limitation of Liability. IN NO WAY SHALL SAFE HAVEN DEFENSE OR ANY INSTALLER BE LIABLE FOR ANY INDIRECT, SPECIAL,
INCIDENTAL, EXEMPLARY, OR CONSEQUENTIAL DAMAGES OF ANY KIND ARISING OUT OF OR RELATED TO (1) THE USE OF OR
INABILITY TO USE THE PRODUCT, (2) THE BREACH OF ANY WARRANTY OR OF THIS AGREEMENT, (3) ANY ACT OR FAILURE TO ACT
RELATING TO THIS AGREEMENT, OR OTHERWISE, INCLUDING WITHOUT LIMITATION DAMAGES FOR LOSS OF USE, LOST PROFITS,
INTERRUPTION OF BUSINESS, OR ANY OTHER MONETARY OR OTHER LOSS, REGARDLESS OF THE FORM OF ACTION WHETHER IN
CONTRACT, TORT (INCLUDING NEGLIGENCE), STRICT PRODUCT LIABILITY, OR OTHERWISE, EVEN IF SAFE HAVEN DEFENSE HAS
BEEN ADVISED OF OR IS OTHERWISE AWARE OF THE POSSIBILITY OF SUCH DAMAGES. CERTAIN JURISDICTIONS DO NOT ALLOW
THE EXCLUSION OR LIMITATION OF INCIDENTAL OR CONSEQUENTIAL DAMAGES, SO THE ABOVE LIMITATION OR EXCLUSION
MAY NOT APPLY TO YOU.
How State/Provincial Law Applies. This warranty provides you with specific legal rights, and you may also have other rights that vary between jurisdictions.

Exclusions and Miscellaneous Terms and Conditions. (1) This warranty does not cover or apply to losses, costs, damages or defects arising from or caused by
Improper Product Care, cleaning or abuse, misuse (including use not complying with applicable law), natural causes, accident, ordinary wear, damage caused
vandalism, the physical impact of rocks or other objects, abrasion or scratching or any other acts, occurrences or defects, faults, or damages not related to defects in
materials or manufacture of the Product. Except as otherwise provided by applicable law, Illegal use of the Product will render all warranties, whether express or
implied, invalid and of no effect and Safe Haven Defense shall have no liability therefor. (2) The Safe Haven Defense installer is trained and certified as an
independent contractor for Safe Haven Defense and Safe Haven Defense is not responsible for representations made by the installer. No Contractor, including the
Safe Haven Defense Installer has any authority or power to modify or extend this limited warranty. The benefits under this warranty shall be the sole and exclusive
remedy against Safe Haven Defense for any loss arising out of the sale, and/or use of the Product. (3) If any provision of this warranty is unenforceable or ineffective,
the rest of this warranty shall remain in effect and be construed as if such provision had not been contained in this warranty. (4) This warranty shall be governed by
Arizona law. Regardless of what venue would otherwise be permissive or required, Safe Haven Defense and the customer stipulate that all actions arising under or
related to this warranty shall be brought in the federal or state courts located in the City of Phoenix, Arizona. Safe Haven Defense and the customer agree that such
forum is mutually convenient and bears a reasonable relationship to this Agreement and waive objection to any venue laid therein.



                 PLEASE TURN OVER AND COMPLETELY FILL OUT AND RETAIN THIS WARRANTY
             CARD AND PRESENT IT TOGETHER WITH PROOF OF PURCHASE TO VALIDATE YOUR
                                                                            WARRANTY.



                                                                                    1
                                               Licensee Information



__________________________________________________________________________________________________________
                                                      Name

___________________________________________________________________________________________________________
                                                     Address

___________________________________________________________________________________________________________
              Phone                                 Email                                 Website

___________________________________________________________________________________________________________
                                Install Date                          Install Price

___________________________________________________________________________________________________________
                    Signature                                                           Date




                                               Customer Information




__________________________________________________________________________________________________________
                                                 Customer Name

___________________________________________________________________________________________________________
                                                Customer Address

___________________________________________________________________________________________________________
              Phone                                 Email                                 Website

___________________________________________________________________________________________________________
                    Signature                                                           Date




        PLEASE TURN OVER AND COMPLETELY FILL OUT AND RETAIN THIS WARRANTY CARD AND
           PRESENT IT TOGETHER WITH PROOF OF PURCHASE TO VALIDATE YOUR WARRANTY.

                                                       2
Commercial Construction
& General Contractor




                          DRYWALL / ACT
                          Selected price: Drake Interiors, Inc.




LEFKO CONSTRUCTION
July 2, 2025

Lefko Construction
105 Mansell Circle
Roswell GA 30075

Re: Brockett ES

 We are pleased to provide pricing for the above refenced project. Plans prepared by LS3P, dated 4-30-25. Our pricing is listed
below.

Included:

     1.   Soffit assembly per C/A321. 16ga (54mil).
     2.   Wall assembly per A3/A321.
     3.   Bullet proof fiberglass panels.
     4.   Patch and repair ceiling where demoed.
     5.   All supervision, equipment, material, labor, insurance, and taxes required to complete this scope of work.

Excluded:

     1.   All wood and metal blocking.
     2.   All wood items.
     3.   Caulking of penetration.
     4.   Over time premium.
     5.   Trash dumpster, GC to provide.

                                                  Total: $23,616


Quote valid for 30 days. Please call if you have any questions.


Daniel Drake




183 Scott RD
Canton Ga 30115
Office: 470-863-5939
                                        1750 Veterans Memorial Hwy
                                             Austell GA, 30168
                                            Office: 770-739-9671


                                         PROPOSAL
     To:           LEFKO Construction                                    Date:                      07/03/2025
     Attention:    Andrea Torres                                         Office:                 678-902-7270
     Address:      105 Mansell Cir, Roswell, GA 30075


           JOB NAME                       JOB NUMBER                             JOB ADDRESS
  CMAR - DCSD - Group 1 Security
                                             20250113                            Georgia Counties
           Vestibules.


                  PROPOSAL SUMMARY                                                 AMOUNT
    Alamo Drywall, Inc is pleased to present the following bid for CMAR - DCSD - Group 1 Security
    Vestibules, based on plans and specifications dated 04/30/2025 and subject to the following inclusions,
    exclusions and qualifications.

    Drawings Addendums #1

    Scope of work description – (1 - Avondale ES)

    Interior Package:                                                                               $2,548.00
         Wall type – A-321/A5 - height 4’-0”– 11 LF
         Wall type – A-321/D5 - height 6’-0”– 9 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                               $2.000.00
        ACT-1: 38 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF


Base Bid Amount                                                                                          4,548.00
    Bid Bond. 3.1%.                                                                                   $140.99

    Scope of work description – (2 - Avondale HS)

    Interior Package:                                                                            $17,675.00
         Wall type – 9 - height 12’-0”– 3 LF
         Wall type – A-321/A2 - height 3’-0”– 3 LF
         Wall type – A-321/A3 - height 4’-0”– 7 LF
         Wall type – A-321/D2 - height 4’-0”– 3 LF
         Wall type – A-321/D3 - height 12’-0”– 5 LF
         Wall type – A-600/D5 - height 6’-0”– 21 LF
         Included:
         Metal Stup per plan
         Installation of HM frames – 1 Pc.
         Insulation per plan
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU

    Acoustic ceiling:                                                                             $2,312.00
        ACT-1: 79 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF


Base Bid Amount                                                                                       19,987.00
    Bid Bond. 3.1%.                                                                                 $619.60

    Scope of work description – (3 - Brockett ES)

    Interior Package:                                                                            $36,604.00
         Wall type – A-321/A3 - height 10’-0”– 15 LF
         Wall type – A-321/A5 - height 4’-0”– 13 LF
         Wall type – A-321/C5 - height 6’-0”– 15 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $3,022.00
        ACT-1: 149 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       39,454.00
    Bid Bond. 3.1%.                                                                               $1,228.41

    Scope of work description – (4 - Browns Mill ES)

    Interior Package:                                                                             $8,413.00
         Wall type – A-321/A5 - height 4’-0”– 22 LF
         Wall type – A-321/C6 - height 10’-0”– 12 LF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $1,000.00
        ACT-1: 46 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671


Base Bid Amount                                                                                        9,413.00
    Bid Bond. 3.1%.                                                                                 $291,80

    Scope of work description – (5 - Canby Lane ES)

    Interior Package:                                                                             $4,865.00
         Wall type – A-321/A5 - height 4’-0”– 19 LF
         Wall type – A-321/A6 - height 6’-0”– 14 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $2,295.00
        ACT-1: 77 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                        7,160.00
    Bid Bond. 3.1%.                                                                                 $221,96

    Scope of work description – (6 - Cedar Grove HS)

    Interior Package:                                                                             $7,701.00
         Wall type – A-321/A3 - height 1’-0”– 3 LF
         Wall type – A-321/A5 - height 4’-0”– 17 LF
         Wall type – A-321/D3 - height 6’-0”– 15 LF
         Hard Ceiling – 10 SF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Kevlar wall panels level 2
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                              $874.00
        ACT-1: 85 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                        8,575.00
    Bid Bond. 3.1%.                                                                                 $265.83

    Scope of work description – (7 - Chamblee HS)

    Interior Package:                                                                            $33,059.00
         Wall type – A-321/A1 - height 3’-0”– 20 LF
         Wall type – A-321/A3 - height 1’-0”– 7 LF
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
         Wall type – A-321/A5 - height 4’-0”– 23 LF
         Wall type – A-321/D5 - height 12’-0”– 23 LF
         Hard Ceiling – 10 SF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $2,782.00
        ACT-1: 124 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       35,841.00
    Bid Bond. 3.1%.                                                                               $1,111.07

    Scope of work description – (8 - Chamblee MS)

    Interior Package:                                                                            $53,694.00
         Wall type – A-321/A3 - height 10’-0”– 47 LF
         Wall type – A-321/A5 - height 4’-0”– 52 LF
         Hard Ceiling – 4 SF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Installation of HM frames – 1 Pc.
         Insulation per plan
         5/8” Drywall
         Kevlar wall panels level 2
         Blocking
         Excluded:
         CMU

    Acoustic ceiling:                                                                             $1,425.00
        ACT-1: 137 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                       55,119.00
    Bid Bond. 3.1%.                                                                               $1,708.69

    Scope of work description – (9 - Columbia HS)

    Interior Package:                                                                             $6,788.00
         Wall type – A-321/A1 - height 2’-0”– 12 LF
         Wall type – A-321/A5 - height 4’-0”– 27 LF
         Hard Ceiling – 10 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         Excluded:
         CMU
         Installation of HM frames.
         Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                         6,788.00
    Bid Bond. 3.1%.                                                                                  $210.43

    Scope of work description – (10 - Coralwood Education School)

    Interior Package:                                                                             $48,817.00
         Wall type – A-321/A5 - height 3’-0”– 18 LF
         Wall type – A-321/D3 - height 12’-0”– 37LF
         Wall type – A-600/A4 - height 1’-6”– 24 LF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         Installation of HM frames. - 1 Pc.
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU

    Acoustic ceiling:                                                                              $1,739.00
        ACT-1: 175 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                        50,556.00
    Bid Bond. 3.1%.                                                                                $1,567.24

    Scope of work description – (11 - Dunaire ES)

    Interior Package:                                                                              $8,343.00
         Wall type – A-321/A5 - height 4’-0”– 11 LF
         Wall type – A-321/A6 - height 6’-0”– 12 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                               $900.00
        ACT-1: 65 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                         9,243.00
    Bid Bond. 3.1%.                                                                                  $286.53
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
    Scope of work description – (12 - Dunwoody HS)

    Interior Package:                                                                            $6,108.00
         Wall type – A-321/A3 - height 2’-4”– 4 LF
         Wall type – A-321/A4 - height 1’-0”– 18 LF
         Wall type – A-321/A5 - height 4’-0”– 38 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                            $1,821.00
        ACT-1: 182 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                       7,929.00
    Bid Bond. 3.1%.                                                                                $245.80

    Scope of work description – (13 - Flat Shoals ES)

    Interior Package:                                                                            $4,748.00
         Wall type – A-321/A5 - height 4’-0”– 16 LF
         Wall type – A-321/D3 - height 6’-0”– 15 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                            $2,795.00
        ACT-1: 126 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       7,543.00
    Bid Bond. 3.1%.                                                                                $233.83

    Scope of work description – (14 - Hightower ES)

    Interior Package:                                                                            $4,217.00
         Wall type – A-321/D5 - height 6’-0”– 16 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
    Acoustic ceiling:                                                                             $3,232.00
        ACT-1: 174 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                        7,449.00
    Bid Bond. 3.1%.                                                                                 $230.92

    Scope of work description – (15 - Jolly ES)

    Interior Package:                                                                             $5,086.00
         Wall type – A-321/A5 - height 4’-0”– 17 LF
         Wall type – A-321/A6 - height 6’-0”– 12 LF
         Hard Ceiling – 52 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $2,191.00
        ACT-1: 79 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                        7,277.00
    Bid Bond. 3.1%.                                                                                 $225.59

    Scope of work description – (16 - Kingsley ES)

    Interior Package:                                                                            $43,645.00
         Wall type – 16 - height 12’-0”– 33 LF
         Wall type – 6 - height 12’-0”– 13 LF
         Wall type – 7 - height 12’-0”– 3 LF
         Wall type – A-321/A3 - height 10’-0”– 19 LF
         Included:
         Metal Stup per plan
         Installation of HM frames.
         Insulation per plan
         5/8” Drywall
         Kevlar wall panels level 2
         Blocking
         Excluded:
         CMU

    Acoustic ceiling:                                                                          $11,071.00
        ACT-1: 1,025 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       54,716.00
    Bid Bond. 3.1%.                                                                               $1,696.20
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671

    Scope of work description – (17 - Lithonia HS)

    Interior Package:                                                                            $10,403.00
         Wall type – A-321/A3 - height 2’-6”– 3 LF
         Wall type – A-321/A4 - height 6’-0”– 35 LF
         Wall type – A-321/A5 - height 4’-0”– 20 LF
         Included:
         Metal Stup per plan
         Kevlar wall panels level 2
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $4,772.00
        ACT-1: 326 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       15,175.00
    Bid Bond. 3.1%.                                                                                 $470.43

    Scope of work description – (18 - Margaret Harris Comp School)

    Interior Package:                                                                             $6,313.00
         Wall type – A-321/A3 - height 6’-0”– 10 LF
         Wall type – A-321/A5 - height 4’-0”– 17 LF
         Wall type – A-321/D3 - height 4’-0”– 14 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $1,249.00
        ACT-1: 119 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                        7,562.00
    Bid Bond. 3.1%.                                                                                 $234.42

    Scope of work description – (19 - McLendon ES)

    Interior Package:                                                                             $4,779.00

         Wall type – A-321/A3 - height 1’-0”– 3 LF
         Wall type – A-321/C5 - height 6’-0”– 19 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                            $2,708.00
        ACT-1: 79 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       7,487.00
    Bid Bond. 3.1%.                                                                                $232.10

    Scope of work description – (20 - Panola Way ES)

    Interior Package:                                                                            $7,127.00
         Wall type – A-321/A3 - height 2’-6”– 5 LF
         Wall type – A-321/A5 - height 4’-0”– 8 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                            $2,462.00
        ACT-1: 236 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                       9,589.00
    Bid Bond. 3.1%.                                                                                $297.26

    Scope of work description – (21 - Robert Shaw Theme ES)

    Interior Package:                                                                            $4,882.00

         Wall type – A-321/A5 - height 4’-0”– 12 LF
         Wall type – A-321/E4 - height 6’-0”– 16 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                            $2,409.00
        ACT-1: 89 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                       7,291.00
    Bid Bond. 3.1%.                                                                                $226.02
                                       1750 Veterans Memorial Hwy
                                            Austell GA, 30168
                                           Office: 770-739-9671
    Scope of work description – (22 - Salem MS)

    Interior Package:                                                                             $11,843.00
         Wall type – A-321/A2 - height 2’-8”– 10 LF
         Wall type – A-321/A5 - height 6’-0”– 38 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                              $1,000.00
        ACT-1: 94 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                        12,843.00
    Bid Bond. 3.1%.                                                                                  $398.13

    Scope of work description – (23 - Stone Mountain MS)

    Interior Package:                                                                              $6,972.00
         Wall type – 9 - height 12’-0”– 1 LF
         Wall type – A-321/A2 - height 6’-0”– 8 LF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded:
         CMU
         Installation of HM frames.
         Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                         6,972.00
    Bid Bond. 3.1%.                                                                                  $216.13

    Scope of work description – (24 - Tucker MS)

    Interior Package:                                                                             $63,900.00
         Wall type – A-321/A3 - height 12’-0”– 53 LF
         Wall type – A-321/A4 - height 6’-0”– 35 LF
         Included:
         Patch and repair hard ceiling
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU
         Installation of HM frames.
                                          1750 Veterans Memorial Hwy
                                               Austell GA, 30168
                                              Office: 770-739-9671
    Acoustic ceiling:                                                                             $1.550.00
        ACT-1:151 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.

Base Bid Amount                                                                                        65,450.00
    Bid Bond. 3.1%.                                                                               $2,028.95

    Scope of work description – (25 - Woodward ES)

    Interior Package:                                                                             $5,289.00
         Wall type – A-321/A2 - height 2’-6”– 7 LF
         Wall type – A-321/D5 - height 6’-0”– 10 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Kevlar wall panels level 2
         Excluded:
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                                             $2,767.00
        ACT-1: 119 SF – 7/8 in x 2 ft x 2 ft Armstrong Fine Fissured High NRC
        15/16 in Square Lay-In Panel / White - 1754.
        Included removing, salvaging, and reinstalling of ACT (Exclude Store) – up to 1,000 SF

Base Bid Amount                                                                                          8,056.00
    Bid Bond. 3.1%.                                                                                  $249.74

    EXCLUSIONS
    Engineered Shop Drawings
    Installation of doors and frames
    Millwork
    Demo
    Dumpster
    Laminated MDF
    Wallcovering
    Spray insulation
    Rigid insulation
    CMU
    Concrete
    Structural steel
    Fire caulking at existing fire rated walls
    Access panels
    Level 5 finish unless where specified
    Night work

    QUALIFICATIONS
    All jobs are quoted for the current month due to material increase. Please provide 15 days’ notice to
    proceed.
    We look forward to working with you on this project. If you have any questions, please do not hesitate to
    call our Estimating Department at the number provided above.

                                       Roderic Guillen– Estimator 770-739-9671
1750 Veterans Memorial Hwy
     Austell GA, 30168
    Office: 770-739-9671
1



                 LC Contractors & Services LLC
                 644 Gilles Ln Cumming ga 30041
                 LC Contractors & Services LLC
                 lcservicesus@gmail.com
                 770-568-0222

           Insured:    3-Brockett ES
          Property:    1855 Brockett Road
                       Tucker, GA 30084


        Estimator:     Carlos Osorio                                             Business:   (470) 495-6004
                                                                                  E-mail:    lcservicesus@gmail.com


    Claim Number:                            Policy Number:                          Type of Loss:

     Date of Loss:                                       Date Received:
    Date Inspected:                                       Date Entered:   7/2/2025 7:35 PM

         Price List:   GAAT8X_JUL25
                       Restoration/Service/Remodel
         Estimate:     3_BROCKETT_ES
2



                             LC Contractors & Services LLC
                             644 Gilles Ln Cumming ga 30041
                             LC Contractors & Services LLC
                             lcservicesus@gmail.com
                             770-568-0222

                                                                    3_BROCKETT_ES
                                                                         Main Level


                   14' 11"
                    14' 3"
                                              Vestibule                                                                                        Height: 8'
                                                             612.00 SF Walls                                       342.00 SF Ceiling
                                                             954.00 SF Walls & Ceiling                             342.00 SF Floor
                                     24' 8"
                               24'




                   Vestibule
                                                              38.00 SY Flooring                                     76.50 LF Floor Perimeter
                                                              76.50 LF Ceil. Perimeter


     DESCRIPTION                                           QTY       REMOVE            REPLACE                   TAX               O&P           TOTAL

     ---Ceiling Tile---
     1. Suspended ceiling tile - 2' x 2'            550.00 SF               0.29               2.78             73.48             352.40         2,114.38
     (partial demo and repair – approx. 400 SF per plan)
     2. Suspended ceiling grid - 2' x 2'            550.00 SF               0.27               2.50             36.52             312.00         1,872.02
     (partial demo and repair – approx. 400 SF per plan)
     ---Walls---
     3. 5/8" drywall - hung, taped, floated,        500.00 SF               0.00               3.42             34.40             348.88         2,093.28
     ready for paint
     Only one face of drywall is included where metal studs are directly anchored to brick walls.
     Where freestanding walls are framed, both faces of drywall are accounted for.
     Door and glazing openings are deducted from total SF to avoid overestimation.
     4. Tape joint for new to existing               40.00 LF               0.00              11.48              1.22              92.08           552.50
     drywall - per LF
     5. Drywall patch / small repair, ready          15.00 EA               0.00            104.60               5.58             314.92         1,889.50
     for paint
     6. Seal/prime (1 coat) then paint (2           500.00 SF               0.00               3.08             22.00             312.40         1,874.40
     coats) the surface area
     ---Cleaning & Debris---
     7. Dust control barrier per square foot        800.00 SF               0.92               0.00             10.88             149.38           896.26
     Dust barriers, and surface protection. Includes temporary containment, dust mitigation, and floor protection during all phases of work.
     8. Final cleaning - construction -             350.00 SF               0.00               0.31              0.00              21.70           130.20
     Commercial
     Includes post-construction cleaning, removal of all debris.
     9. Haul debris - per pickup truck load -         2.00 EA             191.15               0.00              0.00              76.46           458.76
     including dump fees
     Includes rental, pickup, and debris management
     ---Misc---
     10. Delivery charge (Bid Item)                   1.00 EA               0.00            250.00               0.00               0.00           250.00
     After-hours delivery, offloading, and secured staging


    3_BROCKETT_ES                                                                                                            8/7/2025               Page: 2
3



                         LC Contractors & Services LLC
                         644 Gilles Ln Cumming ga 30041
                         LC Contractors & Services LLC
                         lcservicesus@gmail.com
                         770-568-0222

                                                               CONTINUED - Vestibule

     DESCRIPTION                                       QTY          REMOVE           REPLACE                  TAX               O&P            TOTAL

     11. Commercial Supervision / Project        16.00 HR                   0.00            84.45              0.00            270.24          1,621.44
     Management - per hour
     Work is anticipated to be performed during off-hours (nights/weekends), and the estimate includes a labor factor adjustment and commercial project
     supervision fee accordingly.
     12. Labor (Agreed Price)                     1.00 EA                   0.00         2,000.00              0.00              0.00          2,000.00
     Night Shift Labor    25% markup on direct labor for night scheduling

     Totals: Vestibule                                                                                      184.08           2,250.46         15,752.74

     Total: Main Level                                                                                      184.08           2,250.46         15,752.74

     Line Item Totals: 3_BROCKETT_ES                                                                        184.08           2,250.46         15,752.74



     Grand Total Areas:
            612.00 SF Walls                                 342.00 SF Ceiling                            954.00 SF Walls and Ceiling
            342.00 SF Floor                                  38.00 SY Flooring                            76.50 LF Floor Perimeter
              0.00 SF Long Wall                               0.00 SF Short Wall                          76.50 LF Ceil. Perimeter

            342.00 Floor Area                               367.94 Total Area                            612.00 Interior Wall Area
            712.50 Exterior Wall Area                        79.17 Exterior Perimeter of
                                                                   Walls

               0.00 Surface Area                              0.00 Number of Squares                        0.00 Total Perimeter Length
               0.00 Total Ridge Length                        0.00 Total Hip Length




    3_BROCKETT_ES                                                                                                          8/7/2025               Page: 3
4



                     LC Contractors & Services LLC
                     644 Gilles Ln Cumming ga 30041
                     LC Contractors & Services LLC
                     lcservicesus@gmail.com
                     770-568-0222




                                                        Summary for Dwelling
     Line Item Total                                                                       13,318.20
     Material Sales Tax                                                                       184.08

     Subtotal                                                                              13,502.28
     Overhead                                                                               1,125.23
     Profit                                                                                 1,125.23

     Replacement Cost Value                                                               $15,752.74
     Net Claim                                                                            $15,752.74




                                             Carlos Osorio




    3_BROCKETT_ES                                                              8/7/2025        Page: 4
5



                  LC Contractors & Services LLC
                  644 Gilles Ln Cumming ga 30041
                  LC Contractors & Services LLC
                  lcservicesus@gmail.com
                  770-568-0222



                                           Recap of Taxes, Overhead and Profit




                                Overhead (10%)       Profit (10%)   Material Sales Tax   Storage Rental Tax Local Food Tax (4%)
                                                                                 (8%)                 (8%)

     Line Items                        1,125.23          1,125.23              184.08                 0.00                0.00

     Total                             1,125.23          1,125.23              184.08                 0.00                0.00




    3_BROCKETT_ES                                                                                    8/7/2025             Page: 5
6



                    LC Contractors & Services LLC
                    644 Gilles Ln Cumming ga 30041
                    LC Contractors & Services LLC
                    lcservicesus@gmail.com
                    770-568-0222

                                                     Recap by Room

    Estimate: 3_BROCKETT_ES

    Area: Main Level
           Vestibule                                                 13,318.20    100.00%

            Area Subtotal: Main Level                                13,318.20    100.00%

    Subtotal of Areas                                                13,318.20    100.00%


    Total                                                            13,318.20    100.00%




    3_BROCKETT_ES                                                      8/7/2025       Page: 6
7



                  LC Contractors & Services LLC
                  644 Gilles Ln Cumming ga 30041
                  LC Contractors & Services LLC
                  lcservicesus@gmail.com
                  770-568-0222

                                                   Recap by Category

     O&P Items                                                           Total          %
     ACOUSTICAL TREATMENTS                                              2,904.00   18.43%
     CLEANING                                                             108.50    0.69%
     GENERAL DEMOLITION                                                 1,426.30    9.05%
     DRYWALL                                                            3,738.20   23.73%
     LABOR ONLY                                                         1,351.20    8.58%
     PAINTING                                                           1,540.00    9.78%
     O&P Items Subtotal                                                11,068.20   70.26%

     Non-O&P Items                                                       Total          %
     PERMITS AND FEES                                                     250.00    1.59%
     LABOR ONLY                                                         2,000.00   12.70%
     Non-O&P Items Subtotal                                             2,250.00   14.28%
     O&P Items Subtotal                                                11,068.20   70.26%
     Material Sales Tax                                                   184.08    1.17%
     Overhead                                                           1,125.23    7.14%
     Profit                                                             1,125.23    7.14%

     Total                                                             15,752.74   100.00%




    3_BROCKETT_ES                                                      8/7/2025       Page: 7
Commercial Construction
& General Contractor




                               PAINTING
                          Selected price: Grateful Painting, LLC




LEFKO CONSTRUCTION
                                                         Proposal #1842623
Guiseppe Ceccarelli
Lefko Construction                                                                                                  Proposal #                  1842623
giuseppe@lefkogroup.com                                                                                             Proposal Date              7/10/2025
(404) 846-6372                                                                                                      Proposal Amount        $108,845.00
105 Mansell Cir                                                                                                     Job Address          105 Mansell Pl
Roswell, GA 30075                                                                                                                     Roswell, GA 30076

Grateful Painting LLC
PO Box 130
Rydal, Ga 30171
Phone: (470) 439-0305
  Product / Service                                                                                      Quantity     Price       Subtotal        Total

  Avondale ES                                                                                            1.00         $3,340.00   $3,340.00   $3,340.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.


  Avondale HS                                                                                            1.00         $7,105.00   $7,105.00   $7,105.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.

  Includes:

         painting the wall after TV relocation, as required at Avondale HS – keynote C on drawing AD-
         101
         painting the wall after the removal of existing security devices, as required by keynote 1 on
         drawing LVD-101
         painting the double-walled exposed ductwork, as indicated in the mechanical floor plan on
         drawing M-000


  Brockett ES                                                                                            1.00         $3,340.00   $3,340.00   $3,340.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.

         painting the wall after TV relocation – keynote C on drawing AD-101


  Browns Mill ES                                                                                         1.00         $5,775.00   $5,775.00   $5,775.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.


  Canby Lane ES                                                                                          1.00         $3,540.00   $3,540.00   $3,540.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.

         painting the wall after TV relocation
         painting the wall after heater removal – keynote E on drawing AD-101


  Cedar Grove HS                                                                                         1.00         $3,340.00   $3,340.00   $3,340.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.


  Chamblee HS                                                                                            1.00         $3,440.00   $3,440.00   $3,440.00
  Perform all work in accordance with the project scope and specifications outlined in drawings A-
  101, A-121, A-321, and A-600, as applicable to the painting scope of work.

         Painting fiberglass wall lining to match adjacent finishes – detail D5 on drawing A-321


  Chamblee MS                                                                                            1.00         $3,340.00   $3,340.00   $3,340.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.


Columbia HS                                                                                               1.00   $3,540.00   $3,540.00   $3,540.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after TV relocation – keynote E on drawing AD-101

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Coralwood Education School                                                                                1.00   $6,575.00   $6,575.00   $6,575.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101
       Painting fiberglass wall lining to match adjacent finishes – detail D3 on A-321, details D1, D2,
       D3 on A-601




Dunaire ES                                                                                                1.00   $6,575.00   $6,575.00   $6,575.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after TV relocation – keynote 1 on drawing ED-101

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Dunwoody HS                                                                                               1.00   $3,840.00   $3,840.00   $3,840.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after TV relocation – keynote 1 on drawing ED-101

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101

       Painting wall after trophy cabinet removal – keynote 13 on drawing A-101


Flat Shoals ES                                                                                            1.00   $3,840.00   $3,840.00   $3,840.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after TV relocation – keynote 4 on drawing ED-101

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101

       Painting wall after fire alarm panel removal – keynote 1 on drawing ED-101

       Painting wall after removal of electrical devices – keynote 3 on drawing ED-101


Hightower ES                                                                                              1.00   $3,440.00   $3,440.00   $3,440.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Jolly ES                                                                                                  1.00   $3,540.00   $3,540.00   $3,540.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Kingsley ES                                                                                               1.00   $6,575.00   $6,575.00   $6,575.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101

       Painting fiberglass wall lining to match adjacent finishes – keynotes 6 & 7 on drawing A-101



Lithonia HS                                                                                             1.00   $3,440.00   $3,440.00   $3,440.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-121, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Margaret Harris Comp School                                                                             1.00   $3,440.00   $3,440.00   $3,440.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


McLendon ES                                                                                             1.00   $3,440.00   $3,440.00   $3,440.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101


Panola Way ES                                                                                           1.00   $6,575.00   $6,575.00   $6,575.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101

       Painting wall after removal of electrical devices – keynote 1 on drawing ED-101


Robert Shaw Theme ES                                                                                    1.00   $3,340.00   $3,340.00   $3,340.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.


Salem MS                                                                                                1.00   $3,340.00   $3,340.00   $3,340.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.


Stone Mountain MS                                                                                       1.00   $3,740.00   $3,740.00   $3,740.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101

       Painting wall after removal of electrical devices – keynote 1 on drawing ED-101


Tucker MS                                                                                               1.00   $6,575.00   $6,575.00   $6,575.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       ? Painting wall after fire alarm panel removal – keynote 2 on drawing ED-121

       ? Painting fiberglass wall lining to match adjacent finishes – details A2 and A3 on drawing A-
       321


Woodward ES                                                                                             1.00   $3,540.00   $3,540.00   $3,540.00
Perform all work in accordance with the project scope and specifications outlined in drawings A-
101, A-321, and A-600, as applicable to the painting scope of work.

       Painting wall after removal of existing security devices – keynote 1 on drawing LVD-101
  Background Check                                                                                       6.00         $45.00        $270.00          $270.00
  Background check fees for 6 personnel.


  Option - Afterhours Labor                                                                              1.00         $16.00        $16.00                 ---
  After-Hours Work Provision
  This proposal includes standard weekday working hours (7:00 AM to 5:00 PM). Work required outside
  of these hours—including evenings, weekends, and school holidays—will incur an additional labor
  charge of $16.00 per hour per crew member, billed as a change order and approved in writing prior
  to commencement of after-hours work. This provision accounts for premium pay, adjusted logistics,
  and staffing availability required for off-hour mobilization.


  Subtotal                                                                                                                                      $108,845.00

  Total                                                                                                                                          $108,845.00



Terms and Conditions

We propose hereby to furnish material and labor - complete in accordance with above specifications.

All material is guaranteed to be as specified. All work to be completed in a substantial workmanlike manner according to the specifications submitted, per
standard practices. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become
an extra charge over and above the estimate. If either party commences legal action to enforce its rights pursuant to this agreement, the prevailing party in
said legal action shall be entitled to recover its reasonable attorney’s fees and costs of litigation relating to said legal action, as determined by a court of
competent jurisdiction. Client has a (3) day right to cancel without loss of deposit.

Sign And Date To Accept Proposal:

  Customer Signature:                                                                                                                Date:
Commercial Construction
& General Contractor




                                      HVAC
                          Selected price: Strictly Mechanical, inc.




LEFKO CONSTRUCTION
                                                                    PROPOSAL
                                                    STRICTLY MECHANICAL, INC.
                                                       415 GEES MILL BUSINESS CT., NE
                                                             CONYERS, GA 30013
                                                             Phone (770) 981-2325
                                                                                                                  Page ___1   of ___1__
PROPOSAL SUBMITTED TO                                                                                                     DATE
                                                                                                                          6/23/25
STREET                                                                        JOB NAME
                                                                              CMAR – DCSD – GROUP 1
CITY, STATE AND ZIP CODE                                                      JOB LOCATION

ATTN:




Furnish & install HVAC systems as shown on LS3P M drawings . Plus written specifications aside
from those on prints.
                                            See Next Page for Bldg breakdown & Pricing
All Bldgs:
   • Includes selective demo as shown on M drawings only.
   • Includes ductwork/air distribution as shown.
   • Includes condensate/refrigerant piping for MC equipment only as shown.
   • Includes rigging, startup, permit & warranty. Any dry wells by others.
Clarifications:
Any duct cleaning or work on existing to remain equip or duct -        included       not included
Test & balance -       included       not included
Any louvers or fire dampers not shown on mechanical drawings -           included      not included
Concrete equipment pads/any concrete work -          included     not included
Any gas pipe, gas regulators/med gas piping -        included     not included
Any grading, underground or earthmoving -          included     not included
Any shop drawings -       included       not included
Any service agreement not stated aside from standard one year warranty -          included       not included
Building/roof/wall/floor coring or patches or wall/ceiling access doors -       included      not included
P&P bond -      included       not included – Please add 1% to prices below if needed.
Any ceiling/grid work -      included       not included
Any Davis Bacon wages or federal certified wage scale increases -         included      not included
Any exterior caulking or waterproofing -        included     not included
Any electrical wiring, temporary power, line voltage or disconnects -        included       not included
Any structural steel/structural framing/roof flashing -     included      not included
Any plumbing/floor drains/ or piping that are normally by plumber -         included       not included
Any painting -     included     not included
Payment to be made as follows:
                                                      PROGRESS DRAWS MONTHLY

All material is guaranteed to be as specified. All work to be completed in a workmanlike
manner according to standard practices. Any alteration or deviation from above
specifications involving extra costs will be executed only upon written orders, and will   Authorized Signature    Kevin Beasley
become an extra charge over and above the estimate. All agreements contingent upon
strikes, accidents or delays beyond our control. Owner to carry fire, tornado and other
necessary insurance. Our workers are fully covered by Workman’s Compensation               Note: This proposal may be withdrawn by us if
Insurance.                                                                                 not accepted within 30 days.
Avondale ES – Incl install of added air distribution- $5,400. – No controls work quoted.
Avondale HS – Incl install of added air distribution- $10,200. – No controls work quoted.
Brockett ES – Incl demo & install of added air distribution- $7,100. – No controls work quoted.
Browns Mill ES – No mechanical scope quoted.
Canby Lane ES – Incl install of added air distribution- $6,600. – No controls work quoted.
Cedar Grove HS – No mechanical scope quoted.
Chamblee HS – Incl install of added air distribution- $7,900. – No controls work quoted.
Chamblee MS – No mechanical scope quoted.
Columbia HS – Incl install of added air distribution- $5,800. – No controls work quoted.
Coralwood – No mechanical scope quoted.
Dunaire ES – No mechanical scope quoted.
Dunwoody HS – No mechanical scope quoted.
Flat Shoals ES – Incl install of added air distribution- $5,600. – No controls work quoted.
Hightower ES – Incl install of added air distribution- $5,500. – No controls work quoted.
Jolly ES – Incl install of added air distribution- $5,100. – No controls work quoted.
Kingsley ES – Incl equip/install of 2 DSS, CCI controls & 1 EF - $55,500.
Lithonia HS – Incl install of added air distribution- $9,600. – No controls work quoted.
Margaret Harris – No mechanical scope quoted.
McLendon ES – Incl install of added air distribution- $6,100. – No controls work quoted.
Panola Way ES – No mechanical scope quoted.
Robert Shaw ES – Incl install of added air distribution- $5,200. – No controls work quoted.
Salem MS – No mechanical scope quoted.
Stone Mountain MS – Incl install of added air distribution- $6,200. – No controls work quoted.
Tucker MS – No mechanical scope quoted.
Woodward ES – Incl install of added air distribution- $6,400. – No controls work quoted.
ASL Mechanical
1000 Hurricane Shoals Rd NE, Ste C300
Lawrenceville GA 30043
C: 404-914-1612 | mo@aslmechanical.com



========================================================================

Proposal Date: 07/25/2025 | Project Name: DCSD - Group 1 Security Vestibules
Drawings Date: 04/30/2025         | Engineer of Records: Hammond Engineering

Mechanical Price: $97,716.72

Price breakdown per School:


                          School                               Proposed Price

                       Avondale ES                                                  $7,233.83

                       Avondale HS                                                  $7,235.93

                       Brockett ES                                                  $6,722.43

                     Canby Lane ES                                                  $7,768.76

                      Chamblee HS                                                   $4,296.93

                       Columbia HS                                                  $5,904.53

                      Flat Shoals ES                                                $6,756.08

                      Hightower ES                                                  $6,595.50

                          Jolly ES                                                  $5,954.93

                        Kingsley ES                                                $15,862.23

                        Lithonia HS                                                 $4,697.03

                      McLendon ES                                                   $4,210.93

                Robert Shaw Theme ES                                                $4,853.68

                   Stone Mountain MS                                                $4,920.13

                      Woodward ES                                                   $4,703.05




1000 Hurricane Shoals Rd NE, Ste C300 Lawrenceville GA 30043 | T: 404-914-1612 | E: mo@aslmechanical.com
Scope of Work:
            -​   Furnish and Install Air distribution systems for all schools except Kingsley per
                 project schedule and specifications
            -​   Furnish and Install (2) Heat Pumps located exclusively at Kingsley E.S per
                 specifications.
            -​   Furnish and install (1) exhaust fan exclusively at Kingsley E.S per schedule and
                 specifications
            -​   Conduct all necessary demolition work per specifications
            -​   Furnish and install condensate drain and refrigerant piping for Kingsley per
                 specifications.
            -​   Install transfer grill exclusively to per schedule and specifications.
            -​   Furnish and install sheet metal for all schools ductwork except Chamblee HS and
                 Lithonia HS per specifications..
            -​   Furnish and Install Low Voltage wiring for KIngsley per specifications
            -​   Furnish and Install all Mechanical Insulation for all required schools per
                 Specification
            -​   Provide Mechanical Permit and all associated Inspections
            -​   Provide NEBB certified test and balance service




We Exclude from our scope of work: ELECTRICAL - PLUMBING - STRUCTURAL - DOOR CUTTING - PAINTING -
MAIN GAS METER REPLACEMENT - EXISTING EQUIPMENT OPERATIONS - ROOF WORK - CORING - DDC CONTROLS - EMS - PROPOSAL
                                           IS ONLY VALID FOR 15 DAYS
Commercial Construction
& General Contractor




                                       ELECTRICAL
                          Selected price: Lost Mountain Electrical Contractors, inc.




LEFKO CONSTRUCTION
    ESTIM ATE
    Lost Mountain Electrical         tedscott@lmecinc.com
    Contractors, Inc                 +1 (404) 867-3298
    1825 Corner Road
    POWDER SPRINGS, GA
    301274917




    LEFKO:CMAR - DCSD - Group 1 Security Vestibules @ Various locations
    Bill to                                                                                     Ship to
    CMAR - DCSD - Group 1 Security                                                              CMAR - DCSD - Group 1 Security
    Vestibules @ Various locations                                                              Vestibules @ Various locations




    Estimate details
    Estimate no.: 5598
    Estimate date: 06/18/2025




#       Product or service                   Description                                              Qty          Rate          Amount


1.      z                                    Avondale ES                                                  1    $8,000.00     $8,000.00
                                             Demo, 3 outlets, 2 quads, 15 low voltage
                                             boxes, new circuits, refeed fire alarm panel
                                             with 120 volt, reinstall lights, 2 door conduits
                                             and power


2.      z                                    Avondale HS                                                  1    $7,000.00     $7,000.00
                                             Demo, 2 outlets, 16 low voltage boxes, new
                                             circuits, 2 exit lights, 2 door conduits and
                                             power


3.      z                                    Brocket ES                                                   1    $8,000.00     $8,000.00
                                             Demo, 2 outlets, 2 quads, 2 exit lights,12
                                             low voltage boxes, new circuits, 2 door
                                             conduits and power


4.      z                                    Browns Mill ES                                               1    $6,200.00     $6,200.00
                                             Demo, 1 outlet, 3 exit lights, 6 low voltage
                                             boxes, new circuits, 2 door conduits and
                                             power


5.      z                                    Canby Lane ES                                                1    $9,000.00     $9,000.00
                                             Demo, 3 outlets, 5 quads, 4 exit lights,14
                                             low voltage boxes, new circuits, 2 door
                                             conduits and power


6.      z                                    Cedar Grove HS                                               1    $8,500.00     $8,500.00
                                             Demo, 3 outlets, 3 quads, 1 exit lights,18
                                             low voltage boxes, new circuits, 2 door
                                             conduits and power
7.    Services   Chamblee HS                                     1    $8,000.00    $8,000.00
                 Demo, 1 quad, 3 exit lights,17 low voltage
                 boxes, new circuits, 3 door conduits and
                 power


8.    z          Chamblee MS                                     1    $7,300.00    $7,300.00
                 Demo, 1 outlet, 1 quad, 1 exit light,14 low
                 voltage boxes, new circuits, 2 door
                 conduits and power


9.    z          Columbia HS                                     1    $8,000.00    $8,000.00
                 Demo, 3 outlets, 2 quads, 1 exit light,15 low
                 voltage boxes, new circuits, 2 door
                 conduits and power


10. z            Coralwood Education School                      1   $10,800.00   $10,800.00
                 Demo, 4 outlets, 3 quads, 2 exit lights, 22
                 low voltage boxes, new circuits, relocate 1-
                 2x4 light, 3 door conduits and power


11. z            Dunaire ES                                      1    $8,000.00    $8,000.00
                 Demo, 4 outlets, 2 quads, 14 low voltage
                 boxes, new circuits, 2 door conduits and
                 power


12. z            Dunwoody HS                                     1   $14,500.00   $14,500.00
                 Demo, 10 outlets, 6 quads, 2 exit lights,26
                 low voltage boxes, new circuits, 2 door
                 conduits and power


13. z            Flat Shoals ES                                  1   $11,500.00   $11,500.00
                 Demo, 5 outlets, 4 quads, 25 low voltage
                 boxes, 1 exit sign, new circuits, 2 door
                 conduits and power


14. z            Hightower ES                                    1    $4,500.00    $4,500.00
                 Demo, 1 exit sign, 9 low voltage boxes, 1
                 outlet, 2 door conduits and power


15. Services     Jolly ES                                        1    $9,800.00    $9,800.00
                 Demo, 6 outlets, 3 quads, 23 low voltage
                 boxes, 1 exit sign, new circuits, 2 door
                 conduits and power


16. z            Kingsley ES                                     1   $37,250.00   $37,250.00
                 Demo, 11 outlets, 3 quads, 14 low voltage
                 boxes, 1 exit sign, refeeding high mounted
                 lights, man lift, new circuits, supply and
                 install 15 2x4 lights and 2 wall lights, 3
                 switches, 2 door conduits and power
                 mechanical equipment AC-1, AC-2, HP-1,
                 HP-2 and EF-1


17. z            Lithonia HS                                     1    $9,000.00    $9,000.00
                 Demo, 3 outlets, 3 quads, 3 exit signs, 16
                 low voltage boxes, new circuits, 2 door
                 conduits and power


18.
      z                                            Margaret Harris Comp School                              1   $8,000.00   $8,000.00
                                                   Demo, 3 outlets, 2 quads, 20 low voltage
                                                   boxes, new circuits, 2 door conduits and
                                                   power


19. z                                              Mclendon ES                                              1   $4,500.00   $4,500.00
                                                   Demo, 1 outlet, 10 low voltage boxes, new
                                                   circuits, 2 door conduits and power


20. z                                              Panola Way ES                                            1   $7,000.00   $7,000.00
                                                   Demo, 3 outlets, relocate 4-2x4 lights, 2 exit
                                                   signs, 12 low voltage boxes, new circuits, 1
                                                   door conduits and power


21. z                                              Robert Shaw Theme ES                                     1   $8,500.00   $8,500.00
                                                   Demo, 4 outlets, 2 quads, 13 low voltage
                                                   boxes, 2 exit signs, new circuits, 2 door
                                                   conduits and power


22. z                                              Salem MS                                                 1   $7,500.00   $7,500.00
                                                   Demo, 3 outlets, 3 quads, 16 low voltage
                                                   boxes, 2 exit signs, new circuits


23. z                                              Stone Mountain MS                                        1   $4,000.00   $4,000.00
                                                   Demo, 1 outlet, 11 low voltage boxes, 1 exit
                                                   sign, new circuits, 2 door conduits and
                                                   power


24. z                                              Tucker MS                                                1   $7,800.00   $7,800.00
                                                   Demo, 2 outlets, 1 quad outlet, 2 exit signs,
                                                   10 low voltage boxes, new circuits, new
                                                   keyed switch, 1 door conduits and power


25. z                                              Woodward ES                                              1   $5,500.00   $5,500.00
                                                   Demo, 2 outlets, 1 quad outlet, 2 exit signs,
                                                   13 low voltage boxes


26.                                                FIRE ALARM WIRING NOT INCLUDED
                                                   (Boxes and conduits are included per
                                                   drawings)
                                                   DATA WIRING NOT INCLUDED
                                                   SECURITY AND ACCESS CONTROL
                                                   WIRING NOT INCLUDED


                                                                                                    Total              $228,150.00

      Note to customer
      Let me know if you have any questions,

      Thank you,

      Ted Scott
      Lost Mountain Electrical Contractors, Inc.
      404-867-3298




      Accepted date                                        Accepted by
                                                                                    Estimate
                                                                                     Estimate no.:           430

                                                                                     Estimate date: Jun 30, 2025




From                                                                                                      Bill to

Velectric                                                                                               LEFKO
velectricllc@gmail.com                                                                                 Dekalb ga
404-543-6692
Www.velectricllc.com
6663 south sweetwater lithia spring ga 30122


DESCRIPTION                                                     RATE, USD    QTY                     AMOUNT, USD


Avondale vestibule                                               11,000.00   1.00                        11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Browns mill                                                     10,000.00    1.00                       10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Chamblee hs                                                     10,000.00    1.00                       10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Columbia                                                         11,000.00   1.00                        11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Coralwood                                                       10,000.00    1.00                       10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Dunwoody c.c                                                    12,000.00    1.00                       12,000.00



Dunwoody hs                                                     10,000.00    1.00                       10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC
DESCRIPTION                                                     RATE, USD    QTY    AMOUNT, USD


Hightower                                                        11,000.00   1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Lithonia                                                         9,000.00    1.00       9,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Panola                                                          10,000.00    1.00      10,000.00



Salem                                                            9,000.00    1.00       9,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Stone mountain                                                  10,000.00    1.00      10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Tucker                                                          10,000.00    1.00      10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Avondale hs vestibule                                            11,000.00   1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Brockett                                                        10,000.00    1.00      10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Candy lane                                                      10,000.00    1.00      10,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Cedar grove                                                     12,000.00    1.00      12,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Dunaire                                                          11,000.00   1.00       11,000.00
DESCRIPTION                                                     RATE, USD           QTY    AMOUNT, USD


Flat Shoals                                                     12,000.00           1.00      12,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Jolly                                                           12,000.00           1.00      12,000.00



Kingsley                                                         11,000.00          1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Margaret harris                                                  11,000.00          1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Mclendon                                                        12,500.00           1.00      12,500.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Robert shaw                                                     12,000.00           1.00      12,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Woodward                                                         11,000.00          1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC


Chamblee ms                                                      11,000.00          1.00       11,000.00

Install all electrical low by plans and changes order will be
change order. All world done will be up to code according
to the NEC



Payment Instruction                                                  Subtotal:             $279,500.00

Make checks payable to                                               Tax (7.00%):            $12,355.00
Velectric
                                                                     T otal:               $291,855.00

Bank transfer
"N/A"

"Cash wallet\nN/A\n\n"
                           284 Lakestone Pkwy Woodstock, GA 30188

July 11, 2025
                                         Brockett ES
                             1855 Brockett Road, Tucker GA 30084

This Proposal is to furnish the labor and materials necessary for Bass Electric Inc. to install a
complete electrical system per the Plans and Specifications.
Bass Electric Inc. will install a complete electrical system, as mentioned above, for the price of
($33,200.00) Thirty-three thousand two hundred dollars and zero cents.

This Proposal includes:
   ●​ Remove all power from the demolition area and relocate any remaining devices to a
       nearby suitable location.
   ●​ Provide a new fire alarm pull station box (wiring by others).
   ●​ Provide power for a new receptacle.
   ●​ Connect the new exit sign circuit to a nearby existing exit sign circuit.
   ●​ Provide new power and a box for the card access door.
   ●​ Provide a new data outlet box (wiring by others).
   ●​ Connect the new power for the ID scanner to a nearby existing receptacle circuit.

Exclusions:
   ●​ Patching, finishing , and painting of drywall
   ●​ Low voltage (Fire alarm, HVAC controls, Security access control, Voice/Data, Sound
      system, CATV, Camera, Intercom system)
   ●​ Cut-saw and patch pavement and concrete for new conduit

If you have any questions or concerns, please feel free to contact me. Thank you for your
consideration.

                                                                                  Taeed Noparast
                                                                     hossein@basselectricinc.com
                                                                            Office: 678-994-9949
Commercial Construction
& General Contractor




                                 LOW VOLTAGE
                    Selected price: Convergint Technologies, LLC (Safety and Security)




LEFKO CONSTRUCTION
                                                         1955 Evergreen Blvd, Duluth, Georgia 30096
                                                                              Mobile (404) 643-9113
                                                                       paul.franco@convergint.com

 July 22, 2025

Dekalb County School District (“Customer” or “You”)             Quotation:     PF00829045P

Reference: DCSD Group 1 Vestibules
           Rev2.0

 On behalf of Convergint’s global network of colleagues, I would like to personally thank
 you for providing Convergint with the opportunity to present this proposal addressing your
 electronic security needs.

 The following security proposal is specifically designed to meet your needs. As your single
 point of contact, please feel free to contact me with any additional questions you may
 have. Thank you again for trusting Convergint as your partner.

Scope of Work
   •   Provide and install security equipment for the expansion of access control system
       (ACS), IP video surveillance, and intrusion detection system (IDS) at the following
       locations:
       1. Avondale Elementary School                   14. Hightower Elementary School
       2. Avondale High School                         15. Jolly Elementary School
       3. Brockett Elementary School                   16. Kingsley Elementary School
       4. Browns Mill Elementary School                17. Lithonia High School
       5. Canby Lane Elementary                        18. Maragaret Harris Comp School
           School                                      19. McLendon Elementary School
       6. Cedar Grove High School                      20. Panola Way Elementary
       7. Chamblee High School                             School
       8. Chamblee Middle School                       21. Robert Shaw Theme
       9. Columbia High School                             Elementary School
       10. Coralwood Education School                  22. Salem Middle School
       11. Dunaire Elementary School                   23. Stone Mountain Middle School
       12. Dunwoody High School                        24. Tucker Middle School
       13. Flat Shoals Elementary School               25. Woodward Elementary School
•   Convergint to provide and install card readers, access control cabling, as required
    per location.
       o Electrical Contractor to provide one (1) single-gang box for card reader (42”
            A.F.F.) and conduit stub-up to accessible ceiling.
       o Others to provide one (1) exit device with electric latch retraction hardware
            set on the active leaf closest to the card reader with lock power supply.
                 Electrical contractor to mount and connect 120VAC to lock power
                   supply above accessible ceiling near new vestibule card reader
                   door.
                 Electrical contractor to provide pathway with string within new door
                   frame for electric door hardware.
                 Convergint to provide low-voltage cabling and connect the electrified
                   exit device to the associated lock power supply and ACS.
       o One (1) door contact per leaf
       o Cabling to ACS enclosure (existing or new depending on availability).
                 Convergint to provide and install low-voltage cabling and connect
                   the electric lock power supply to the electric latch retraction
                   hardware.
                 Convergint to provide a two-door controller to connect the door to
                   the LenelS2 OnGuard ACS.
•   Convergint to provide and install one (1) ACS enclosure, as required.
       o If dedicated 120VAC circuit is desired, the Electrical contractor shall
            connect 120VAC to new enclosures. Otherwise Convergint shall use
            existing available local circuits.
•   Convergint to provide and install two (2) remote release buttons to unlock
    vestibule interior card reader door.
       o One (1) located to the right of the transaction window.
                 Electrical Contractor to provide one (1) single-gang box for release
                   button (42” A.F.F. and/or 8-10” above desk) and conduit stub-up to
                   accessible ceiling.
       o One (1) located by front staff desk(s).
                 Exact location to be determined in coordination with the principal.
                 Electrical Contractor to provide one (1) single-gang box for release
                   button (42” A.F.F. or 0-10” above desk and conduit stub-up to
                   accessible ceiling.
•   Convergint to provide and additional remote release buttons to unlock interior
    admin-area card reader doors located by front staff desk(s).
                 Exact location to be determined in coordination with the principal.
                 Electrical Contractor to provide one (1) single-gang box for release
                   button (42” A.F.F. or 0-10” above desk and conduit stub-up to
                   accessible ceiling.
•   For all cameras added:
       o Convergint to provide, device harden, and install IP Video camera.
       o Convergint to surface mount on the drop ceiling interior cameras and
            surface mount exterior cameras.
       o Others to provide and install CAT6 network cabling.
    •   Existing equipment to remain as-is where applicable, relocating existing
        equipment is included, as required.
    •   All required licensing is included.
    •   Automatic door openers provided and installed with cabling and low voltage
        connections is included, as required. 120VAC connections done by others.

Device Hardening (reduce cyber risk)
 Convergint may provide Device Hardening services for certain qualifying and scoped
 equipment. Services may include disabling unused & non-essential device features,
 disabling unused network comms (e.g., services, ports), changing default passwords,
 and updating firmware. The hardening services provided will depend on the equipment
 being installed, equipment capabilities, and manufacturer-provided permissions and
 recommendations. Not all equipment may receive hardening. Ask your Convergint
 contact for details on qualifying equipment and the hardening services being provided.

 These are one-time services — ask your Convergint contact for information on how
 Convergint can provide ongoing support.

 Convergint cannot guarantee the security of the devices it installs or of Customer’s
 IT environment, no networked system is completely secure, and Customer remains
 ultimately responsible for its IT environment.
Materials

  Line       Part                        Description                          Manufacturer
          J7-
 1                    4DR E4M 75W 4 LOCK 8 AUX A Wired: 1502/M                    LifeSafety Power
         75BCP4TA
                       Input Control Module (Series three) 12/24 VDC, 16
          LNL-1100-   zone input monitor module, (32) 1K resistors (with 2
 2                                                                                           lenel
         S3           programmable output relays) , RoHigh School, CE,
                      C-Tick and UL294 certified
                       12V 7AH Rechargeable SLA Battery with F1
 3       738415                                                                       Power-Sonic
                      Terminal
          NC-
 4                    VANDAL RESISTANT READER HID                                       Honeywell
         OP90HON
          LNL-
 5       R11320-      BlueDiamond Mobile Enabled: US Single Gang                             lenel
         05TB
 6        AC-RP26      PANIC BUTTON SS PLT - N/O MOM                                Alarm Controls
                       PIR REQUEST TO EXIT SENSOR WITH                          Bosch Security and
 7       DS160
                      SOUNDER GRAY                                                 Safety Systems
          0E-
 8       SRFMTMG3     3-Wire Surface-Mount Magnetic - SPDT                                ADI Pro
         W
          CM-
 9                    ALL IN ONE STRIKE                                      Camden Door Controls
         CXED1689L
                       12/24 VDC OUTPUT 120 VAC2 RELAYS, POWER
 10      PS902-2RS                                                                      von duprin
                      SUPPLY
                                                                                Bosch Security and
 11      B920         2 LINE ALPHA NUMERIC KEYPAD (SD12)
                                                                                   Safety Systems
                                                                                Bosch Security and
 12      D9127U       POPIT WITH NO TAMPER SWITCH
                                                                                   Safety Systems
                                                                                Bosch Security and
 13      DS936        LOW PROFILE CEILING MOUNT PIR
                                                                                   Safety Systems
 14       444340    22-04 Overall-Shielded Stranded Plenum Wht Jkt                 Windy City Wire
 15       002380    18-04 Unshielded Stranded Plenum Wht Jkt                       Windy City Wire
 16       4461030   4 Element Composite Cable Plenum Ylw Jkt                       Windy City Wire
          SQ-
 17                 12MP Fisheye Camera; AI                                               Hanwha
         XNF9013RV
          SQ-       4K Outdoor Vandal Dome Camera; 3-10mm; AI; IR;
 18                                                                                       Hanwha
         QNVC9083R IP66
          HAN-      2MP INTERCOM, WDR,1.6MM FIXED LEN,
 19                                                                                       Hanwha
         TID600R   TOUCHLESSCALL BUILT-IN MIC
 20       4642-689  Auto Equalizer Power Operator – Push Side                               LCN
 21       10PBS451  4.5” Square Blue ADA Puch Button                                 BEA Security
   Pricing Structure

                                  Description                                      Price
PROJECT BASE (Select A or B)
A. New Interior Vestibule Wall and Door: includes 2 release buttons, door access
                                                                                      $13,380.00
  hardware and cabling
B. New Exterior Vestibule Wall and Door: includes 2 release buttons, door access
  hardware cabling, intercom (network cabling excluded), and intrusion device         $15,130.00
  relocation

PROJECT ADD-ONS
C1. New Access Control Enclosure                                                      +$3,800.00
C2. Additional Interior Card Access Door                                              +$4,525.00
C3. Additional Exterior Card Access Door                                              +$5,625.00
C4. Intercom (network cabling excluded)                                               +$1,350.00
C5. Camera (network cabling excluded; *270° Cameras are shown as quantity 2)          +$1,350.00
C7. Electronic Panic Lock Power Supply                                                 +$840.00
C7. ADA Automatic Door Opener (120VAC connection excluded)                           +$11,080.00
     School Breakdown

 #               School               A       B       C1   C2    C3    C4    C5      C6      C7        Price
1     Avondale Elementary School          1                 1                   1        1         $    20,095.00
2     Avondale High School                1                 2                   2        2         $    26,810.00
3     Brockett Elementary School          1                 1            1               1         $    20,095.00
4     Browns Mill Elementary School       1                              1      1        1         $    16,920.00
5     Canby Lane Elementary School        1                 1                   1        1         $    20,095.00
6     Cedar Grove High School             1                 1                   1        1         $    20,095.00
7     Chamblee High School                        1    1    4      1     1      1        3         $    47,875.00
8     Chamblee Middle School              1                 1            1      2        1         $    22,795.00
9     Columbia High School                1                              1               1         $    15,570.00
10    Coralwood Education School                  1    1    3            1       3       2    2    $    61,745.00
11    Dunaire Elementary School           1                 1            1      4*       1         $    25,495.00
12    Dunwoody High School                1                 1            1       3       1         $    24,145.00
13    Flat Shoals Elementary School       1                 1            1       1       1    2    $    43,605.00
14    Hightower Elementary School         1                              1       1       1         $    16,920.00
15    Jolly Elementary School             1                 1            1      3*       1    2    $    46,305.00
16    Kingsley Elementary School          1                 1            1       1       1         $    21,445.00
17    Lithonia High School                1                 1                    2       1         $    21,445.00
18    Maragaret Harris Comp School        1                 3            1       1       2         $    31,335.00
19    McLendon Elementary School          1                 1            1       1       1         $    21,445.00
20    Panola Way Elementary School        1                 1                    1       1         $    20,095.00
      Robert Shaw Theme Elementary
21   School                               1                 2                   1        2         $    25,460.00
22    Salem Middle School                 1                 1                   1        1         $    20,095.00
23    Stone Mountain Middle School        1                 2                   3        2         $    28,160.00
24    Tucker Middle School                1                                     1        1         $    15,570.00
25    Woodward Elementary School          1                 1                   1        1         $    20,095.00



                                                                Total Project        $            653,710.00
                                                                Price
Clarifications and Exclusion


1.  All work proposed herein, shall be performed during normal business hours Monday
    through Friday 8:00 am - 5:00 pm.
2. Low voltage wiring shall be installed via open air code approved methods.
3. Provision or installation of conduit, wire, boxes, fittings or other electrical installation
    materials unless specifically listed under Inclusions or Bill of Materials.
4. Permits or associated fees are not included.
5. Customer to provide static IP addresses and network connections at panel locations.
6. Customer to provide a secured staging & storage area for project related materials.
7. Pricing assumes that electronic Auto CAD files are available from customer for our
    use in creating submittal drawings.
8. Fifty percent (50%) of the proposed sell price shall be payable to Convergint for
    project mobilization. Mobilization shall be invoiced and due upon customer
    acceptance of this proposal.
9. Proposal does not include sales tax unless otherwise noted.
10. Anything in the Contract Documents notwithstanding, in no event shall either
    Contractor or Subcontractor be liable for special, indirect, incidental or consequential
    damages, including commercial loss, loss of use, or lost profits, even if either party
    has been advised of the possibility of such damages.
11. Convergint reserves the right to negotiate mutually acceptable contract terms and
    conditions with customer by making mutually agreeable changes to the formal
    contract included in the Bid Documents.
12. Supply Chain Delays & Price Adjustments: Customer acknowledges that supply
    chain disruptions and shipping delays may occur for reasons beyond Convergint’s
    reasonable control and agrees to grant reasonable extensions for such delays.
    Pricing is based on current market conditions and excludes increases due to tariffs,
    duties, manufacturer-imposed surcharges, or other cost increases arising from trade
    policy, regulatory actions, or external factors beyond Convergint’s control. If such
    cost increases arise, Convergint will submit a formal change order, and Customer
    agrees to approve reasonable adjustments. Convergint will use commercially
    reasonable efforts to minimize such increases.

 REVIEW IMPORTANT PRODUCT SAFETY AND SERVICE INFORMATION PRIOR
 TO USING A CONVERGINT-INSTALLED SYSTEM: See the “IMPORTANT
 PRODUCT SAFETY AND SERVICE INFORMATION” documentation, available at
 convergint.com/terms.
                                          IMPORTANT NOTICE
You requested that Convergint provide you with certain security and safety products and services.
By using these products and services, you acknowledge that:
•   Under no circumstances should Convergint-provided products and services be your sole
    method of security or safety. Effective security and safety require a multi-layered approach involving
    people, processes, and technologies. Convergint-provided products and services do not guarantee
    security or safety, will not detect or prevent all threats or risks all the time (including threats they are
    designed to detect), and will not ensure overall safety and security. You are ultimately responsible for
    your people, premises, and property, including for maintaining an effective response plan and promptly
    implementing your response plan in response to alarms or threats.
•   All security products and services have limitations. No product or service can guarantee safety or
    security. It is your responsibility to ensure you are informed about product or service limitations and
    that you regularly test and validate the products and safety plans. Reach out to your Convergint
    account executive to learn how our support services can help. And if you have a service plan, you are
    responsible for promptly notifying Convergint in the event of any defect, malfunction, or performance
    issue with the products and services.
•   Various factors can impact product performance. Selecting products and settings may involve
    tradeoffs between the level of security and safety on the one hand and speed, convenience, and cost
    on the other hand. Convergint can give you guidance, but you are ultimately responsible for selecting
    products and settings based on your organization’s risk profile and tolerance.
•   The products are made by third-party manufacturers, not Convergint. You are bound by and must
    use, test, and maintain the products in accordance with the manufacturer’s terms and instructions.
    Convergint does not independently validate the accuracy of claims or statements made by
    manufacturers, and makes no assurances regarding their accuracy. You are responsible for using the
    products and services in compliance with laws and regulations applicable to you or as permitted in your
    jurisdiction.
•   All products and services are governed exclusively by a final agreement. No advertisement,
    literature, brochure, website, or statements made during the sale process or otherwise (whether orally or
    in writing) should be interpreted as a promise, warranty, or other assurance.
•   You have reviewed the “IMPORTANT PRODUCT SAFETY AND SERVICE INFORMATION”
    documentation, available at convergint.com/terms.
Total Project Investment:                                       $ 653,710.00


Thank you for considering Convergint for your Security needs. If you have any questions
or would like additional information, please don't hesitate to contact me immediately. If you
would like to proceed with the scope of work as outlined in this proposal, please sign below
and return to my attention.


Sincerely,

Paul Franco
Convergint
Paul Franco

By signing below or accepting the services described in this proposal, Customer accepts
and agrees to this proposal, including the enclosed Terms and Conditions, along with any
addendums or exhibits that may be attached or referenced therein. Any additional or
contrary terms, including on a Customer PO, are expressly rejected. By signing, you
represent and warrant that you have authority to accept this proposal on behalf of Customer.


                                                                      July 22, 2025
             Customer Name (Printed)                                       Date




               Authorized Signature                                        Title
Commercial Construction
& General Contractor




                                 LOW VOLTAGE
                 Selected price: Integrated Communication Networks, inc. (Data Cabling)




LEFKO CONSTRUCTION
 Integrated Communication Networks, Inc.

                                                                                      Quote
                                                                                       21-Jun-25
                                                           PO NUMBER:
                                                           WO NUMBER:
                                                           DCSD Ticket Number

CUSTOMER:                                                  BILL TO:
Lefko Group
Brockett ES


POC:
START DATE:

JOB DESCRIPTION
Install 1 data drop for new Cameras in Vestibule
Install 2 Duplex data drop for new Location.
Quoted from Drawings LV-101
No Data LV Demo Needed.
After hours and weekend rates included

See Attached for location and list all Hrs and work done
LABOR
 HOURS     SERVICE PERSON               DESCRIPTION               RATE                 QUANTITY             TOTAL
                                      Service              $             100.00           1             $       100.00

          0                                                                                SUB TOTAL $          100.00

PARTS                                                                                          TOTAL    $       100.00
  ITEM        PART NUMBER             DESCRIPTION               QUANTITY               UNIT COST
    1            Yellow            Yellow Cat 6a Cam               1              $            365.00   $        365.00
                  Blue             Blue Cat 6a Data                4              $            365.00   $      1,460.00
                                   Wiremold                        0              $            120.00   $           -
                   Orange          Orange Cat 6 Intercom           0              $            265.00   $           -
                                   Misc.                           1              $            100.00   $        100.00
                                                                                                        $           -

                                                                                  LABOR                 $        100.00
DATE                                                                              MATERIAL              $      1,925.00
                                                                                  TAX/HANDLING
TIME IN                                                                           TOTAL                 $      2,025.00

TIME OUT

CUSTOMER SIGNATURE
                                   Signature                                   Print Name
                                            5108 Minola Dr. Lithonia GA. 30038
                                      Phone: (470) 545-5425       Fax: (470) 545-5464
                                                Website: www.icnpros.com
Commercial Construction
& General Contractor




                                LOW VOLTAGE
                  Selected price: South Western Communications of Atlanta (Intercom)




LEFKO CONSTRUCTION
                DeKalb County School District - Group 1
                                    Security Vestibules
                                       3630 Shallowford Rd NE
                                           Doraville, GA 30340




Proposal for
DEKALB CO SCHOOL DISTRICT
(GA)




                                            SWC of Atlanta
                                70 Crestridge Dr., Suite 100
                                       Suwanee, GA 30024


                    blake.schindler@swc.net | 404.787.5420
                                          sales@swc.net |
                                               June 26, 2025
                                        Proposal valid for 30 days.
                                          www.swc.net | 2


TABLE OF CONTENTS

Content                                            Page
Scope of Work                                            3
Cost of Proposal                                         5
Terms and Conditions                                     7




                                                               SWC of Atlanta
                       blake.schindler@swc.net | 404.787.5420
                                             sales@swc.net |
                        Confidential. Not to be shared without express written permission by SWC.
                                                                                                www.swc.net | 3




                                             Scope
SWC is pleased to offer this quote for the following systems based on bid documents:
- Rauland Legacy Intercom Systems with Rauland TCU Overlay
- Rauland TCU Hybrid Systems

Architect/Engineer: LS3P Project/reference number: Multiple

Specification(s) dated:
- No specification sections applicable to SWC’s Scope of Work

Addenda, clarification(s), Add/Alternates, etc included:
- Addendum 1 6/13/2025
Unsolicited additions/alternates included:
- Included pre and post construction tests for the Rauland Intercom System at each site. This is
needed to insure the existing systems in the front office are functioning properly before and after
the renovations in these area are made.
-
Notable deviations from the drawings:
- Drawings provided do not depict the speakers currently installed as well as locations of
equipment needed to keep the existing Rauland intercom systems functional. See breakdown of
proposed scope at each site below.
-
Additional notes or scope:
- Price does not include any conduit, back cans, coring, boring, or 110v power.
- All work is to be performed outside of normal business hours.
- Unless defined as such under per site scope below, all existing cable, speakers, call buttons, and
Rauland Intercom components will be reused as part of this project.
- All CAT6 data cable by others.
- See breakdown of proposed scope at each site below.


***Many of these modifications are to systems that have been discontinued, and replacement parts
are no longer available. These systems will be referred to as Rauland “legacy” Intercom systems.
SWC will not be responsible for replacing, repairing or providing any warranty on these Rauland
legacy Intercom systems. ***




                                                                                                                     SWC of Atlanta
                                                                             blake.schindler@swc.net | 404.787.5420
                                                                                                   sales@swc.net |
                                                                              Confidential. Not to be shared without express written permission by SWC.
                                                                                              www.swc.net | 4




                                 Scope (cont)
SWC Scope of work per site:
 1. Avondale ES-Pre and Post testing of the intercom system.
 2. Avondale HS-Pre and Post testing of the intercom system and the removal and reinstallation of
 one speaker in corridor.
 3. Brockett ES-Pre and Post testing of the intercom system.
 4. Browns Mill ES-Pre and Post testing of the intercom system.
 5. Canby Lane ES-Pre and Post testing of the intercom system.
 6. Cedar Grove HS-Pre and Post testing of the intercom system and the removal and reinstallation
 of one speaker in corridor.
 7. Chamblee HS-Pre and Post testing of the intercom system and the removal and reinstallation of a
 double sided clock.
 8. Chamblee MS-Pre and Post testing of the intercom system.
 9. Columbia HS-Pre and Post testing of the intercom system.
10. Coralwood Education School-Pre and Post testing of the intercom system.
11. Dunaire ES-Pre and Post testing of the intercom system.
12. Dunwoody HS-Pre and Post testing of the intercom system and the removal and reinstallation of
 one speaker in corridor.
13. Flat Shoals ES-Pre and Post testing of the intercom system.
14. Hightower ES-Pre and Post testing of the intercom system and the removal and reinstallation of
 one speaker in corridor.
15. Jolly ES-Pre and Post testing of the intercom system.
16. Kingsley ES-Pre and Post testing of the intercom system. Remove speaker in room 106 and
 reinstall after renovation.
17. Lithonia HS-Pre and Post testing of the intercom system and the removal and reinstallation of one
 speaker in corridor.
18. Margaret Harris Comp School-Pre and Post testing of the intercom system.
19. McLendon ES-Pre and Post testing of the intercom system.
20. Panola Way ES-Pre and Post testing of the intercom system.
21. Robert Shaw Theme ES-Pre and Post testing of the intercom system and the removal and
 reinstallation of one speaker in corridor.
22. Salem MS-Pre and Post testing of the intercom system.
23. Stone Mountain MS-Pre and Post testing of the intercom system.
24. Tucker MS-Pre and Post testing of the intercom system.
25. Woodward ES-Pre and Post testing of the intercom system.




                                                                                                                   SWC of Atlanta
                                                                          blake.schindler@swc.net | 404.787.5420
                                                                                                sales@swc.net |
                                                                            Confidential. Not to be shared without express written permission by SWC.
                                                                                             www.swc.net | 5




                        Pricing Summary
OFFER: In accordance with the Scope of Work and Terms and Conditions attached hereto,
SWC is pleased to offer this pricing, valid through 7/26/2025, for the following project:



DeKalb County School District - Group 1
Security Vestibules                                   REF #: 64399_EST_1

 ESTIMATE GROUP                                           TOTAL PRICE
Avondale HS                                                                                  $4,255.29

Chamblee MS                                                                                  $3,714.73

Jolly ES                                                                                     $2,555.11

Panola Way ES                                                                                $2,555.11

Robert Shaw Theme ES                                                                         $3,095.67

Avondale ES                                                                                  $2,555.11

Brockett ES                                                                                  $2,555.11

Browns Mill ES                                                                               $2,555.11

Canby Lane ES                                                                                $2,555.11

Cedar Grove HS                                                                               $4,255.29

Chamblee HS                                                                                  $4,255.29

Columbia HS                                                                                  $3,714.73

Coralwood Education School                                                                   $2,555.11

Dunaire ES                                                                                   $2,555.11
                                                          Pricing Summary continues next page...




                                                                                                                  SWC of Atlanta
                                                                         blake.schindler@swc.net | 404.787.5420
                                                                                               sales@swc.net |
                                                                           Confidential. Not to be shared without express written permission by SWC.
                                                                                                                                       www.swc.net | 6




                 Pricing Summary (cont.)



 ESTIMATE GROUP                                                                             TOTAL PRICE
Dunwoody HS                                                                                                                            $4,255.29

Flat Shoals ES                                                                                                                         $2,555.11

Hightower ES                                                                                                                           $3,095.67

Kingsley ES                                                                                                                            $2,555.11

Lithonia HS                                                                                                                            $4,255.29

Margaret Harris Comp School                                                                                                            $3,714.73

McLendon ES                                                                                                                            $2,555.11

Salem MS                                                                                                                               $2,555.11

Stone Mountain MS                                                                                                                      $3,714.73

Tucker MS                                                                                                                              $3,714.73

Woodward ES                                                                                                                            $2,555.11




                                                         SUB-TOTAL:                                                                  $79,257.87
                                                         TAX:                                                                          $285.75


                                                         TOTAL:                                                                      $79,543.62
       Per my authority as an executing agent, please accept this as an intent to award and enter into a contractual agreement with SWC.




                                                                                                                                                            SWC of Atlanta
                                                                                                                   blake.schindler@swc.net | 404.787.5420
                                                                                                                                         sales@swc.net |
                                                                                                                     Confidential. Not to be shared without express written permission by SWC.
                                                                                                                         www.swc.net | 7




                        Terms & Conditions
Article A. Scope Includes:

Scope includes the following unless specifically modified by the written, project specific scope of work contained in this proposal.

1.    Submittals for review and approval, if required.
2.    SWC Construction documents from approved Submittals for strict use by others for providing a complete conduit/raceway
      system and all conjunctive efforts.
3.    Furnishing ONLY; special housings and special back boxes for installation by others.
4.    Furnishing and installing wire and cable for systems listed.
5.    5 Furnishing, installing and termination of field devices.
6.    Furnishing, installing and termination of head-end equipment in Equipment Rooms and Control areas.
7.    Functional testing of systems per SWC standards. Testing documents available upon request.
8.    Operation and maintenance documents in electronic format ONLY, per the standards of SWC.
9.    Project Management services in coordination with SWC scope of work.
10.   Site Supervision during the installation of SWC scope of work ONLY.
11.   As required; site conditions verification for SWC Scope of work ONLY.
12.   Consideration of prevailing wage requirements if and as applicable.
13.   Removal of only those existing system/devices and cable rendered obsolete by this project.
14.   Training and Go-Live support as defined in the bid documents, and will be on consecutive days Mon-Fri 8am-4pm. Customer
      conducted end-user training must be completed prior to Go-Live




Article B. Scope Excludes:

Scope excludes the following unless specifically modified by the written, project specific scope of work contained in this proposal.

1.    Service and circuit power requirements including final connections to any and all of our electronic equipment.
2.    A complete and independent conduit/raceway for system per the NEC and installed in the most direct and efficient manner
      and method including all necessary conduit, back boxes, pull/junction boxes, wire ways, ‘J’ hooks, racks, pull strings etc. all
      being properly identified and color coded.
3.    Any and all standard electrical boxes and conduit stubs to above accessible ceiling.
4.    Any and all demolition work.
5.    Any and all site work including trenching if and as applicable.
6.    Lead lined or similar back boxes unless specifically noted.
7.    Control work and/or annunciation except as noted in this scope of work.
8.    Finish Painting (except for those products furnished from the factory by SWC with finish paint).
9.    Patching of concrete, tile, drywall or masonry.
10.   Final Cleaning or composite cleanup crew.
11.   Core drilling and sleeves including any X-ray services needed.
12.   Furnishing and installing hardware for doors.
13.   Caulking and sealants.
14.   Any and all fire safing materials for penetrations, etc. This includes but is not limited to, sealants, caulking, fabric materials,
      etc.
15.   Trash debris container and its removal.
16.   Proper and sufficient temporary power and lighting for our installation efforts including power for final testing of equipment.
17.   Any and all interfacing to other equipment unless specifically noted. This includes lighting control relays.
18.   Server(s) and workstation(s) hardware and Microsoft operating system.
19.   This proposal excludes any and all unforeseen conditions.




                                                                                                                                              SWC of Atlanta
                                                                                                     blake.schindler@swc.net | 404.787.5420
                                                                                                                           sales@swc.net |
                                                                                                       Confidential. Not to be shared without express written permission by SWC.
                                                                                                                           www.swc.net | 8


ARTICLE C. TERMS & CONDITIONS:
      Term and Conditions are as follows unless specifically modified by the written, project specific scope of work contained in
this proposal.
1. These Standard Terms and Conditions are a part of the Proposal made by and between SWC and the Customer identified
      in the Proposal. Upon acceptance of the Proposal by the Customer by signature, the total Proposal contents and any
      other documents included or referenced in the Proposal create a legal and binding Contract/Subcontract between SWC
      and the Customer. The Agreement must be executed by the Parties, the Customer and SWC, prior to any action or work
      being performed by SWC.
2. Customer’s Contract and Bond. The Customer shall furnish to SWC a copy of its Contract; values may be removed, along
      with a copy of the Customer’s Performance and Payment Bond.
3. Builders Risk. The Customer shall also secure and furnish to the SWC a copy of the Builders Risk Insurance policy covering
      the entire project inclusive of the SWC’s on-site work and delivered equipment.
4. CAD Files. The Customer will furnish to SWC required and appropriate CAD files immediately after execution of this
      Agreement. Delays in furnishing CAD files will delay the project. Lack of appropriate CAD files will be cause for a change
      order at $250 per sheet.
5. Project Schedule & Site Requirements. The Project Schedule will be a mutually agreed upon document between the
      Customer and SWC inclusive of the original issue and all revisions. SWC will issue to the Customer its schedule to state
      and clarify SWC’s activities, durations and order of activities. The Customer shall issue any proposed revisions to the
      Schedule in a timely manner in order that SWC may respond with agreement and or changes.
          Schedule Acceleration by the Customer, for reasons not caused by SWC (i.e. other trades not meeting the schedule,
      weather, site conditions and other delays), may result in additional manpower or manhours to be required of SWC. These
      may result in additional compensation and or time extensions to SWC’s Work.
          Work Hours. SWC’s Proposal is based on normal work hours Monday through Friday. SWC may request of the
      Customer to self-schedule at SWC’s own expense. Any other requirement by the Customer of SWC will be cause for
      additional compensation.
          Schedule items of commencement and performance of possible SWC activities require completion of work by other
      trades. The possible key activities are as noted following:
           o Wire and cable installation – Completion of conduit and raceway with pull-strings in place, conduit color-coded per
                SWC system color designations (including conduit terminations and pull boxes) and all conduit and pull boxes
                being properly labeled.
           o Device installation – Walls and ceilings completed and finish paint applied with all areas dust and moisture free
                and building (Work area) secured.
           o Headend equipment installation – Equipment Rooms 100% complete, lockable and environmentally controlled.
           o Control equipment installation – Rooms 100% complete, lockable and environmentally controlled.
           o Release of a certain quantity of (minimum of 4) rooms or areas per consecutive day/week; failure to release or
                delay in release may be cause for additional compensation.
          Submittals (Shop Drawings). Normal timeframe is 8-12 weeks from receipt of execution by both parties of this proposal.
      Timeframe is dependent of the Project size, scope and requirements.
          Within the first 30-40 days of the execution of the Proposal, SWC will require the following, if applicable, in order to
      make the project a success and in order to proceed with final design, programming, manufacturing and installation: (1)
      necessary IP addresses and server access, (2) needs assessment session and sign-off and (3) final review and sign-off of
      project scope, submittals and schedule.
          Manning the Site (Installation Start). Allow a minimum of 2-8 weeks from receipt of approved Submittals for SWC to
      commence work on site.
          Unloading and distribution of our equipment will be directly into the areas of our work.
          SWC Site Supervision and Site Meetings. SWC will assign a designated Project Manager and or Site Superintendent to
      the Project. SWC shall have on-site supervision only when we have on going site work being performed by the SWC’s
      personnel. SWC shall attend all site meetings when we have on-going work on-site or any meetings requiring our
      attendance when proper notice has been received from the Customer.
          Customer/Owner Site Supervision. The Customer will assign a designated Project Manager and or Site Superintendent
      to the Project as the point of contact. For Health Care projects, the facility will appoint a Clinical Administrator, a Systems
      Resource Administrator and IT Administrator for coordination and working directly with SWC throughout the project.
          Protection of Work. SWC takes full responsible for protection of its work as it applies to the normal project conditions,
      however SWC’s responsibility does not cover damage to our equipment and work by other trades whether it by accident,
      negligence or a deliberate action.
          Temporary Site Facilities. Unless specifically identified in SWC’s scope of work, the Customer shall furnish all proper
      and sufficient temporary site facilities, including but not limited to site access, lockable storage space, hoisting facilities,
      guard rails, covers for floor, roof and wall openings, security, parking, toilets, potable water, electrical service, lighting, heat,
      ventilation, weather protection, fire protection, dewatering (pumping) and trash and recycling services.




                                                                                                                                                SWC of Atlanta
                                                                                                       blake.schindler@swc.net | 404.787.5420
                                                                                                                             sales@swc.net |
                                                                                                         Confidential. Not to be shared without express written permission by SWC.
                                                                                                                     www.swc.net | 9


          Safety Barriers and Fines. SWC shall not be liable for erecting or maintaining project safety barriers except those
     specifically needed for the work of SWC.
          Safety Policy. Safety First is mandated by SWC and as such all SWCs employees or subcontractors will operate under its
     written Safety Policy. The Customer may request a copy for its records.
          Drug Policy. Drug Free is mandated by SWC and as such all SWC’s employees or subcontractors will operate under its
     written Drug Free and Substance Policy. The Customer may request a copy for its records.
6.   Conduit As-Built Drawings. Quote is based on SWC being furnished an accurate set of conduit as-built drawings four (4)
     weeks prior to start of wire and cable pulling and or installation. If project is existing utilizing existing conduit-raceways
     and or cabling, then this requirement will be at receipt of contract or acceptable notice to proceed.
7.   Payment Terms, Stored Material & Changes to Work.
          Payment Terms. SWC shall issue its Schedule of Values for determining its progress payments, which will include the
     required downpayment, Engineering, Manufacturing, Project Management, off-site stored materials and any other
     disciplines of the Work. Progress payment invoices will be issued on the 25th of each month for work performed through
     that current month’s end. Payments are due within thirty (30) days of invoice date. All sums not paid when due shall bear
     interest at the rate of 1 ½% per month from the due date or the maximum rate permitted by law. Failure to pay any invoice
     when due shall constitute a breach of contract and will result in work stoppage until payments are brought up to date,
     remobilization fees shall apply. Additionally if SWC is forced to engage an outside source, legal or otherwise, to collect on
     any past due amount, then such costs and fees to do so will be born by SWC’s Customer.
          SWC’s standard payment application and invoice forms will be accepted and used for issuing the monthly request. No
     other additional documentation or forms will be required for payment. Any request for additional forms or documentation
     will be upon written request and, if approved by SWC, will be processed at an additional administrative fee to be invoiced
     separately. Certain requested information, if approved, will be redated for all confidential information and or pricing.
          SWC does not accept any contingent payment terms and or clauses of any type. SWC requires prompt payment by our
     Customer to meet our obligations to our labor and vendors alike and therefore will not accept the risk of our Customer’s
     receipt of payments from their customer or from any source for payment to SWC.
          Payment for Stored Materials. Payment for materials stored at SWC’s facilities will be allowed. Materials and
     components must be ordered in advance to assure Schedule requirements and along with the sensitivity of the equipment
     to the conditions of a construction site dictates storage offsite in a controlled environment until the facility is
     environmentally controlled and secured.” SWC’s facilities and warehouse are secured and monitored for fire and theft plus
     being environmentally controlled.
          Lien Waivers. SWC will only issue and sign final waivers of lien or bond rights that exclude any waiver of lien or bond
     rights securing payment, unbilled changes, and claims which have been asserted in writing or which have not yet become
     known to SWC, and any such waivers shall either apply only through the date of work covered by SWC’s last payment
     application that has been paid in full, or shall be conditional upon receipt of funds to SWC’s account. Releases of Lien for
     partial or final payment will be contingent on the receipt of the funds covered by the Release of Lien.
          Changes and Claims. SWC shall be entitled to equitable adjustments of its schedule and price for delays, acceleration,
     out-of-sequence work and schedule changes beyond its reasonable control, including but not limited to (a) those cause by
     labor unrest, fires, acts of nature, wars, or suspensions or delays caused by the Customer or others; (b) extra work it
     performs in accordance with the proposal; and (c) extra work it performs pursuant to written or verbal instructions of the
     Customer, provided that SWC gives the Customer notice in writing (except in an emergency threatening bodily injury or loss
     of property), prior to starting such extra work, identifying the date and source of the instructions considered as requesting
     extra work. All extra work will only be performed by the SWC only after issuance by the Customer of a signed and executed
     change order, time & material work order and or other SWC approved directive.
          Retainage. No retainage will be withheld on labor or materials.
          Payment Forms. Acceptable payment forms shall be submitted and approved by SWC. Payments forms that will be
     considered are Customer Company check, bank draft and credit card. Note, for credit card payments, SWC will charge a
     processing fee current to SWC at the time.
          Performance and Payment Bond. Proposal pricing does not include the cost of a performance and payment bond. The
     P&P Bond is available upon written request at a minimum cost of one (1%) percent of the final executed Proposal value. The
     P&P Bond, if required, will be invoiced separately.
          Project Startup and Mobilization Fee. A fee in the amount of thirty (30) percent of the final Proposal price will be
     required to be received by SWC prior to commencement of any work of the executed Proposal.
          Taxes are not included in the Proposal price unless specially noted.
          Ownership and Title of Equipment. Title and ownership to any Equipment and Software remains with SWC until receipt
     of full payment or invoiced portion thereof. Any Equipment or Software used to operate the system(s) is subject to the
     license or software license granted by the applicable manufacturer or SWC. All designs for the system(s) and software are
     proprietary to SWC and remain the sole and exclusive property of SWC and or SWC’s manufacturer. Such designs may not be
     modified by the Customer or any third party without prior written authorization.
8.   Permits, local license, inspections and all related cost will be furnished and paid by others. SWC is licensed to perform
     work in the state and has license as such.




                                                                                                                                          SWC of Atlanta
                                                                                                 blake.schindler@swc.net | 404.787.5420
                                                                                                                       sales@swc.net |
                                                                                                   Confidential. Not to be shared without express written permission by SWC.
                                                                                                                        www.swc.net | 10


9.    In the case of termination for our Customer’s or the Owner’s convenience, SWC shall be entitled to receive payment for
      work executed, materials purchased and costs incurred by reason of such termination along with reasonable overhead
      and profit on the work not executed.
10.   Regarding wire and cable footages, the Proposal is based on a raceway/conduit system being installed by code and in the
      most direct and efficient manner with the number of turns being kept at a minimum, but not to exceed the NEC code.
      Any deviation, thus requiring additional wire and cable, may be cause for a Change Order to SWC for additional material
      and labor costs.
11.   Customer/Owner Insurance. The Customer/Owner shall maintain a Builders Risk and other policies of public liability,
      property damage, burglary and theft insurance under which SWC and the Customer are named as insured, and under
      which the insurer agrees to indemnify and hold SWC harmless from and against all costs, expenses, including attorney
      fees, and liability arising out of or based upon any and all claims, injuries and damages arising under this agreement,
      including, but not limited to, those claims, injuries or damages contributed to by SWC’s negligent performance to any
      degree or its failure to perform any obligation.
           The minimum limits of liability of such insurance shall be $1,000,000.00 for any injury or death and property damage,
      burglary or theft coverage in an amount necessary to indemnify Customer for property on its premises. SWC shall not be
      responsible for any portion of any loss or damage which is covered or recoverable by the Customer from insurance covering
      such loss or damage against which the Customer is indemnified or insured.
           SWC’s Insurance. SWC’s insurance will name its Customer only as additional insured. SWC’s standard insurance policy
      and the limits therein, which will meet the minimum requirements, shall be acceptable.
           SWC shall maintain insurance with coverage until the end of the warranty period with the limits only as provided by
      SWC’s existing insurance program as shown by its certificate of insurance issued at the time of Proposal execution. SWC’s
      insurance is not and will not become at any time the primary coverage for the Customer or any other party and does not
      accept any contribution provisions for the Customer or any other party for any associated defenses or losses. Any “No
      Subrogation” clauses placed on the SWC are deemed null and void.
           Wrap-Up Projects (OCIPs and CCIPs). SWC will not participate in a consolidated insurance program (“CIP”). SWC’s
      Insurance Carrier does not allow SWC’s participation in any secondary insurance programs provided by the Customer,
      Owner, Construction Manager and or Contractor (OPIC, CCIC, etc.) due to most programs of such having limited coverage to
      the site and in coverage amounts.
12.   Warranty. SWC’s warranty, if applicable, will begin at SWC’s substantial completion (phased if applicable) and the
      issuance of the Certificate of Warranty by the SWC. Warranty will be one (1) year from substantial completion of our
      scope of work and or beneficial occupancy or use by the Owner and or the Owner’s agents / employees and as noted will
      be as defined by our Certification of Warranty issued at the time of substantial completion of our scope of work and or
      beneficial occupancy or use by the Owner and or the Owner’s agents / employees. Certain hardware may be covered by
      an additional manufacturer's warranty (shipping/freight, and labor excluded)
           Additional pricing is specially excluded in the Proposal for extended warranty services. Extended warranty services
      require a separate executed agreement. If such an agreement is executed and paid at the stated time, it will begin one year
      from issuance of SWC’s Certificate of Warranty. Failure to execute and issue payment will result in loss of service and
      support under warranty terms and conditions. However, if an extended warranty agreement is not executed then SWC’s
      normal billable service will remain available on a will-call basis.
13.   Force Majeure. SWC shall not be liable or responsible to any party, nor be deemed to have defaulted under or breached
      this Agreement, for any failure or delay in fulfilling or performing any term of this Agreement when and to the extent,
      directly or indirectly, such failure or delay is caused by or results from acts beyond SWC’s reasonable control, including,
      without limitation, the following force majeure events (a) acts of God; (b) flood, fire, earthquake or explosion; (c) war,
      invasion, hostilities (whether war is declared or not), terrorist threats or acts, riot or other civil unrest; (d) government
      order or law; (e) actions, embargoes or blockades in effect on or after the date of this Agreement; (f) action by any
      governmental authority; (g) national or regional emergency; (h) strikes, labor stoppages or slowdowns or other industrial
      disturbances; (i) epidemic, pandemic or similar influenza or bacterial infection (which is defined by the United States
      Center for Disease Control as virulent human influenza or infection that may cause global outbreak, or pandemic, or
      serious illness); (j) emergency state; (k) shortage of adequate medical supplies and equipment; (l) shortage of power or
      transportation facilities; (m) delayed at any time in the commencement or progress of its Work due to a delay in delivery
      of or unavailability of materials (transportation and or supply chain issues) beyond the control and fault of SWC, (n)
      unexpected skilled labor shortage, (o) access to the project that prevents performance to the agreed upon schedules and
      (n) other similar events beyond the reasonable control of SWC. For the avoidance of doubt, Force Majeure shall not
      include financial distress, the ability to make a profit, to avoid a financial loss or SWC’s inability to perform its obligation
      for reasons other than those stated.
14.   Special Site Conditions. Owner/Contractor will provide a safe, clean work environment free from any infectious and or
      hazardous conditions.




                                                                                                                                             SWC of Atlanta
                                                                                                    blake.schindler@swc.net | 404.787.5420
                                                                                                                          sales@swc.net |
                                                                                                      Confidential. Not to be shared without express written permission by SWC.
                                                                                                                      www.swc.net | 11


15. Anti-bid shopping clause. It is understood and agreed that this Quote is a confidential document between the parties and
    any use thereof to conduct business with any party other than SWC constitutes a breach of contract. The sharing of
    commercially sensitive business information with competitors (such as information relating to prices and costs) can
    amount to illegal conduct and must be avoided.
16. Hold Harmless and Indemnification Restriction. SWC’s indemnification is strictly limited to damages caused by and only
    caused by SWC’s own negligence. Any indemnification or hold harmless obligation of SWC extends only to claims relating
    to bodily injury, sickness, disease or death and property damage (other than to SWC’s work), and then only to that part or
    proportion of any claim caused by the negligence or intentional act of SWC, its sub-subcontractors and its employees.
    SWC shall not have a duty to defend any other party.
17. Lien and Bond Rights Preserved. This is a preliminary information pursuant to applicable State laws and does not
    constitute a current lien on the said property nor does it reflect adversely on the Customer and if applicable the Owner. It
    is a notice to protect the rights of SWC and is not a lien, cloud, nor encumbrance to the said property, nor is it a matter of
    public record. Certain State and local laws require the issuance of this notice as a prerequisite afforded by the lien and or
    bonding laws in most instances to protect the rights in the future. Accordingly, this provision, notice, is made a part of
    this agreement as a matter of protection to SWC as a standard practice. Notwithstanding any provision to the contrary,
    SWC may take all steps reasonably necessary to preserve and enforce its lien and bond rights.
18. Prevailing and or union wages are not included in our proposal unless specially noted.
19. Governing Law. This Agreement shall be governed by and construed in accordance with the laws of the State of the
    location of the facility for which product is installed or services are performed.
20. Severability. In the event any one or more of the clauses or provisions of this Agreement or any exhibit is held to be
    invalid or inapplicable to said Agreement or otherwise unenforceable, the enforceability of the remaining clauses and
    provisions shall remain enforceable.
21. Additional Provisions. Contract provisions and clauses not stated that strictly apply to this Agreement but may become
    applicable or necessary in the course of the Project (i.e., Dispute Remedies, Severability, Termination, Assignments,
    Conflicts, etc.) shall be in accordance with the standards of the American Subcontractors Association Contract Articles and
    Clauses.
22. Time validity of this Quote is 30 days.



PROPOSAL ACCEPTANCE
By signing this Proposal, the Customer accepts this Proposal, enters into a Subcontract Agreement with SWC in the amount of
$79,543.62 and authorizes SWC (South Western Communications, Inc.) to commence with the noted Work of Proposal
64399_EST_1. The authorization is inclusive of approval to commence Equipment procurement, Engineering, Programming,
Manufacturing and Installation with applicable progress invoicing of same.

Execution of this Agreement by the Parties. SWC reserves the right to delay the commencement of any required activities of this
Agreement until which time SWC has received the required Project Start-up and Mobilization fee and other applicable
requirements such as Customer Credit/Risk Application, Insurance Certificates (Customer and Builders Risk), Bond (Customer and
Owner, CAD Files, etc.,

Note: This proposal will expire if not accepted within thirty (30) days of the date of the Proposal. SWC reserves the right to
modify this Proposal at any time prior to acceptance.

Proposal Acceptance and Subcontract Execution:

By:
       ______________________________________                          ______________________________________
       Customer Authorized Signature                                   SWC Authorized Signature

       ______________________________________                          ______________________________________
       Printed Name                                                    Printed Name

       ______________________________________                          ______________________________________
       Title                                                           Title

       ______________________________________                          ______________________________________
       Acceptance Date                                                 Acceptance Date




                                                                                                                                           SWC of Atlanta
                                                                                                   blake.schindler@swc.net | 404.787.5420
                                                                                                                         sales@swc.net |
                                                                                                    Confidential. Not to be shared without express written permission by SWC.