4. Exhibit M - Chapel Hill MS - DCSD SV G2

AID 1868345 · View on Simbli

Agenda Item

ii. E-SPLOST VI ~ Capital Improvement Project ~ Contract ~ RFQu 24-752-039 ~ Guaranteed Maximum Price (GMP) ~ Security Vestibules Group 2 ~ Lefko Development, Inc. dba Lefko Construction (Not to exceed $17,680,721.65)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve the Guaranteed Maximum Price (GMP) for Capital Improvement Project -Security Vestibules Group 2 in the not to exceed amount of $17,680,721.65.
Why: Approval of the Guaranteed Maximum Price to Lefko Development, Inc. dba Lefko Construction will allow for the installation and upgrades at each of the 25 security vestibules included in “Security Vestibules Group 2”.
Details: On October 7, 2024, the Board approved the award of a Construction Manager at Risk (“CMAR”) contract to Lefko Construction for the installation and upgrades at each of the 25 security vestibules that comprise the “Security Vestibules Group 2”.

Pursuant to that agreement, the Design Professional (SSOE), Construction Manager (Lefko), Program Manager (HPM), and DCSD Operations have collaborated to generate a design, a safe construction phasing plan, and a GMP in the best interest of the DeKalb County School District for each of the 25 security vestibules included in “Security Vestibules Group 2”:



DeKalb Arts Academy
Avondale MS - $626,164.25
Cedar Grove MS - $701,551.28
Chapel Hill ES - $888,365.56
Chapel Hill MS - $713,266.45
Columbia MS - $663,682.54
Eagle Woods Academy - $489,695.26
Evansdale ES - $459,603.56
Fairington ES - $648,491.40
Huntly Hills ES - $1,090,661.86
Mary Mcleod Bethune MS - $679,612.05
McNair MS - $487,776.76
Miller Grove MS - $843,398.91
Montclair ES - $902,832.20
Montgomery ES - $500,171.38
Oakcliff ES - $478,878.41
Peachtree MS - $876,583.22
Pine Ridge ES - $682,714.94
Redan ES - $641,913.08
Redan HS - $730,672.39
Redan MS - $707,443.01
Rowland ES - $483,243.35
Snapfinger ES - $1,016,937.17
Southwest DeKalb HS - $1,071,834.60
Stone Mountain ES - $597,098.07
Towers HS - $698,129.93
Financial impact: Each site is funded as a separate project in the E-SPLOST VI capital improvement fund. This approval increases the budget of the general contractor cost code in each project and funds the approved GMP out of the general contractor cost code in each project:



DeKalb Arts Academy
Avondale MS - Project 30136 - $626,164.25
Cedar Grove MS - Project 30236 - $701,551.28
Chapel Hill ES - Project 21436 - $888,365.56
Chapel Hill MS - Project 30536 - $713,266.45
Columbia MS - Project 30636 - $663,682.54
Eagle Woods Academy - Project 50336 - $489,695.26
Evansdale ES - Project 22336 - $459,603.56
Fairington ES - Project 22436 - $648,491.40
Huntly Hills ES - Project 23236 - $1,090,661.86
Mary Mcleod Bethune MS - Project 31136 - $679,612.05
McNair MS - Project 31536 - $487,776.76
Miller Grove MS - Project 31236 - $843,398.91
Montclair ES - Project 24536 - $902,832.20
Montgomery ES - Project 24636 - $500,171.38
Oakcliff ES - Project 25236 - $478,878.41
Peachtree MS - Project 31336 - $876,583.22
Pine Ridge ES - Project 25536 - $682,714.94
Redan ES - Project 25936 - $641,913.08
Redan HS - Project 41536 - $730,672.39
Redan MS - Project 31436 - $707,443.01
Rowland ES - Project 26436 - $483,243.35
Snapfinger ES - Project 26836 - $1,016,937.17
Southwest DeKalb HS - Project 41736 - $1,071,834.60
Stone Mountain ES - Project 27036 - $597,098.07
Towers HS - Project 42036 - $698,129.93
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1470
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
Commercial Construction
& General Contractor




                           Georgia Perimeter
                                College
                                   Project Name
                                   RFQ Number

                           Construction Management
                                        Date        at Risk
                           DCSD Group 2 Security Vestibules
                                   CHAPEL HILL MS

                                      EXHIBIT M
                          STATEMENT OF QUALIFICATION
                                      JUNE, 2025




                                                    1|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



June 25th, 2025

DeKalb County Board of Education
Mr. Fritzgerald Joseph
Operations Division – Sam A. Moss Service Center
1780 Montreal Road Tucker, GA 30084

Re: Construction Management at Risk Group 2 Security Vestibules

Dear DeKalb County Board of Education, Mr. Fritzgerald Joseph.

Lefko Development, Inc. (LEFKO) is pleased to submit Exhibit M for the Construction Management at
Risk – Group 2 Security Vestibules project. This submission is based on the contract documents dated
Nov. 13th, 2024, and the bid process plan shared via email on May 7, 2025, and confirmed in OAC meetings.

Your Project            Defining project expectations early on gives us the ability to take responsibility
for the complete success of your project (cost, schedule, quality, and safety). Your project requires
detailed planning and communication with all stakeholders to deliver on our first-time quality dedication
and on-time delivery. Our team has thoroughly reviewed the project RFQ to fully understand the scope.
    Over the years, we’ve completed many such projects. This experience allows us to develop site specific
methodologies for first-time quality. Prime among these is our process to understand the Owner’s needs
and implement regular communication protocols to eliminate delays and meet project milestones.

Well Versed             We are well versed in working within educational facilities and understand the
nature of safety and security for students, professionals, and administrators. LEFKO has completed
numerous projects for the educational systems of Cherokee, Dekalb, and Forsyth County Schools; Georgia
State University, Georgia Tech, and Atlanta Technical College. In the past few years our team has
managed 18 projects for GSU, as well as three projects for Forsyth County Schools. We recently
completed your $2.5M project to renovate 10 security vestibules, and Cherokee County Schools Bus
Washer Additions of $3.6M. Our team is currently wrapping up some Cobb County Schools projects such
as Nicholson ES Renovation of $5.2M and Rose Garden HVAC Upgrades of $2.5M. Given our history of
working in educational facilities within Georgia counties, cities, universities and schools, we are
accustomed in working in areas populated by students. LEFKO places the highest of priorities on client
relationships and communication. Our teams operate in an open collaborative environment ensuring
constant communication. We are certain you will find our knowledge and experience to align with what
Dekalb County values in their contractor services. We look forward to working with you again to improve
the educational environment for your students and maintain excellence in Dekalb County schools.

Respectfully submitted,

________________________________
Giuseppe Ceccarelli, Operations Manager
Lefko Development, Inc./dba Lefko Construction
105 Mansell Circle, Roswell GA 30075 PH: 404-846-6372 FX: 404-365-8328 Lefkoconstruction.com

                                                                                               2|P A G E
LEFKO CONSTRUCTION
                                                     Chapel Hill MS G2 SV
                                                     N/A

                          11/13/2024
                        LEFKO Development Inc, dba, LEFKO Construction


Chapel Hill MS G2 SV




                                                          safe, finished, and fully functioning
security vestibule --
                                                                                   6




                                                            11               11              06/25/25
                                                            12               17              06/25/25
                                                             18              23              06/25/25
                                                             24              24              06/25/25
                                                             25              25              06/25/25
                                                             26              26               06/25/25

                                                              --              --              N/A
                                                                                               Seven hundred thirteen
thousand two hundred sixty six with 45/100   713,266.45--




                                                            Fifty nine thousand four hundred thirty eight with 87/100
  59,438.87--




                                                     One hundred thirteen thousand two hundred four with 50/100
     113,204.50--


                                                                                                                    -5-




                                                                                        Twenty nine thousand seven
                                                                                        hundred nineteen
44                       29,719.44--
                                                                  Twenty nine thousand seven
                                                                  hundred nineteen             44
             29,719.44




                                                                                           10.00




Patching of existing finishes, and   Eleven thousand seven
                                                                                  11,750.00--
unforeseen conditions                hundred fifty           00




                   -1-
                zero        00    0.00--

                     7.50
zero   00   0.00--




                            N/A      --
 N/A
                     LEFKO Construction

Operations Manager


  06/25/2025


 Jesus Martinez
Commercial Construction
& General Contractor



             LIST OF DRAWINGS, SPECIFICATION, ADDENDUMS & RFIs

                          CMAR – DCSD Group 2 Security Vestibules
DRAWINGS (Created by SSOE)

       G1.00, G1.10, AD1.00, A0.50, A1.00, A1.10, A2.50, A3.10, A3.30, A5.10, FP0.01, M0.01,
        M1.01, E0.01, ED1.01, E1.01, E2.01. (Dated: 03-28-2025 & Revised per Add#1 04/25/2025
        & Add#2 05/02/2025)

SPECIFICATIONS

       Project Manual package (610 pages, dated 03/28/2025 and revised per Add#1
        04/25/2025)

ADDENDUMS

       Addendum #1: (Date issued April 25, 2025): The contract documents for the project are
        modified as set forth in this Addendum. The original contract documents dated
        03/28/2025 and any previously issued addenda remain in full force and effect, except for
        any clarifications, amendments, additions, deletions and/or modifications to the
        specifications and drawings modified by this Addendum, which is hereby part of the
        contract documents. Specification section 087100 Door Hardware has been revised in this
        addendum along with the below listed drawings.

        Chapel Hill ES: AD1.00, A1.00, A3.10, A5.10, A0.51, P1.01, M1.00
        Eagles Wood Academy: E1.01, E2.01
        Evansdale ES: E1.01, E2.01
        Fairington ES: E1.01, E2.01
        Huntley Hills ES: AD1.00, A1.00, A3.10, A5.10, A0.51, PD1.01, P1.01, P5.01, M1.01, E4.10
        Montclair ES: AD1.00, A1.00, A3.10, A5.10, A0.51, M1.01, E1.01, E2.01
        Montgomery ES: E1.01, E2.01
        Oakcliff ES: E1.01, E2.01
        Pine Ridge ES: E1.01, E2.01
        Redan ES: M1.01, E1.01, E2.01
        Rowland ES: E1.01, E2.01
        Snapfinger ES: AD1.00, A1.00, A3.10, A5.10, A0.51, PD1.01, P1.01, P5.01.
        Stone Mountain ES: AD1.00, A1.10, M1.01, E1.01, E2.01
        Cedar Grove MS: AD1.00, A1.00, A3.10, FP0.01, M1.01, E1.01, E2.01
        Chapel Hill MS: AD1.00, A1.00, A3.10, FP0.01, M1.01, E1.01, E2.01
        Columbia MS: M1.01, E1.01, E2.01
                                                                                      8|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



        Avondale MS: G.100, G1.10, G3.10, AD1.00, A1.00, A1.10, A2.50, A2.10, A3.30, A5.10,
        FP0.01, M0.01, M1.01, E0.01, E1.01, E2.01
        Mary Mcleod Bethune MS: AD1.00, FP0.01, M1.01, E1.01, E2.01
        Miller Grove MS: M0.01, M1.01, E1.01, E2.01
        Peachtree Charter MS: AD1.00, A1.00, A3.10, A5.10, FP0.01, M0.01, M1.01, ED1.01,
        E1.01, E2.01
        Redan MS: E1.01, E2.01
        Ronald E. Mcnair: AD1.00, A1.00, A1.10, A3.10, E1.01, E2.01
        Redan HS: AD1.00, A1.00, A3.10, A5.10, FP0.01, M1.01, ED1.01, E1.01, E1.02, E2.01
        Southwest Dekalb: AD1.00, FP0.01, ED1.01, E1.01, E2.01
        Towers HS: M1.01, E1.01, E2.01.

       Addendum #2: (Date issued May 2nd, 2025): The contract documents for the project are
        modified as set forth in this Addendum. The original contract documents dated
        03/28/2025 and any previously issued addenda remain in full force and effect, except for
        any clarifications, amendments, additions, deletions and/or modifications to the
        specifications and drawings modified by this Addendum, which is hereby part of the
        contract documents. Also, changes per RFI responses have been incorporated in this
        Addendum 2 dated 05/02/2025. The following drawings have been revised in this
        addendum.

        Montclair ES: E0.01, ED1.01, E2.01, E3.01, E4.10
        Ronald E. Mcnair: AD1.00, A1.00, A1.10, A2.50, A3.10.

RFIs
        1. HVAC control and BAS
        2. Removal of existing furniture and offices items
        3. Safe Haven structural requirement
        4. Shop drawings for Safety and Security Film
        5. Millwork modifications
        6. Mechanical drawings scope vrs Demolition Drawing Scope
        7. Electrical Panels - Huntley Hills ES
        8. IG-1T vs. 3/8'' tempered glazing - max thickness
        9. Film scope for R. McNair MS
        10. Avondale MS Door Schedule Aluminum infills or Glazing Infills
        11. Miller Grove MS Roofing Scope
        12. Southeast Dekalb HS - Film Scope for Large Window
        13. Concrete specs
        14. Flooring scope
        15. DCSD Principals' additional comments / changes
        16. AWI certification

                                                                                      9|P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



        17. Missing details (11/A3.30 & 12/A3.30) for Peachtree MS
        18. Hardware for Door 1101A in R. McNair MS
        19. EMERGENCY LOAD/GENERATOR TRANSFER DEVICE detail at Monclair ES
        20. Intercom approved vendor for DCSD Schools
        21. Electrical Panel "B" for Montclair ES




                                                                             10 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                       ATTACHMENT 1
                                         Allowances

                          CMAR – DCSD Group 2 Security Vestibules
ALLOWANCES (Included in base price)

       Allowance no. 1 – Unforeseen conditions: CMU walls patching
        Amount: $2,500.00

       Allowance no. 2 – Temporarily close of new openings
        Amount: $250.00

       Allowance no. 3 – Sound attenuation batts and Compressed Mineral Wool
        Amount: $500.00

       Allowance no. 4 – Hollow metal frame installation
        Amount: N/A

       Allowance no. 5 – Patch and repair floors not labeled on drawings as affected by
        Demolition
        Amount: $3,500.00

       Allowance no. 6 – Furnishing and Installation of toilet accessories
        Amount: N/A

       Allowance no. 7 – Patch existing Stucco at entrances after storefront removal (if
        required)
        Amount: N/A

       Allowance no. 8 – Chair railing and paneling to match existing below transaction
        window
        Amount: N/A

       Allowance no. 9 – Unforeseen conditions: Sealants, and fire caulking for new wall
        penetrations
        Amount: $5,000.00




                                                                                      11 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                    ATTACHMENT 4
                               Assumptions & Clarifications

                          CMAR – Group 2 Security Vestibules
DIV – 02 EXISTING CONDITIONS

       It is assumed that all demolition areas are clearly identified and accessible as shown on
        the drawings.
       The owner will provide a location for placing dumpsters.
       This scope excludes any core drilling or relocation and adjustment of utilities.
       Asbestos abatement or the handling of any hazardous materials is not included, in the
        event that GC discovers/exposes any existing asbestos and/or lead contaminated
        produces or materials, GC will immediately notify the owner and architect.
       Demolition of any partitions, glazing, or items not explicitly identified on the drawings is
        excluded.
       Shoring and any shoring plans are excluded.
       DCSD shall provide secure and accessible temporary storage locations for all items
        removed.
       Disconnection and reconnection of all technology items (computers, printers, etc.) is
        excluded from the General Contractor's scope.
       Any roof work is excluded from this GMP.

DIV – 03 CONCRETE

       The design criteria, cast-in-place-concrete specs, and slab and foundation notes shown
        on drawing S1.00 at school Miller Grove MS apply to all schools with Concrete SOW per
        RFI #13.

DIV – 04 MASONRY

       Detail #8 “Typical Opening in Existing CMU Wall” and “Lintel Schedule for New Opening
        in Existing Wall” on drawing A0.50 is excluded from the scope of work, as it is not
        referenced in any floor plan or elevation throughout the architectural drawings.
       The concrete masonry specs shown on drawing S1.00 at school Miller Grove MS apply to
        all schools per RFI #13.

DIV – 08 OPENING (GLAZING)

       Break metal covers are made of aluminum to match framing.
                                                                                        12 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       All new storefront frames to be clear anodized/aluminum finish. No special colors
        included.
       Spec section 085653 “Security window” calls for a 10-year special warranty against failure
        and deterioration of security windows. However, the current warranty available by the
        approved manufacturer is for 5 years. This is the maximum warranty period that can be
        provided under the current proposal according to the accepted manufacturer.
       Spec section 088000 “Glazing” calls for AGC Glass Energy Select 28 Clear. This product is
        no longer in production. The proposal includes Guardian SunGuard SNX 62/27 as a
        substitute, which is considered an equivalent.
       The use of 3/8” clear tempered glass on exterior openings does not meet the SHGC code
        for Georgia.
       Putty glaze is not a conventionally captured system, this GMP is based on using glazing
        tape and silicone for providing the exterior glazing bead at the perimeter of the glass
        units.
       There’s no guarantee new exterior sealant will fully bond to the existing surfaces. Each
        area will need to be checked on-site. If the building’s exterior (brick or other materials)
        hasn’t been properly sealed or maintained to manage water, extra prep work might be
        needed, which could lead to additional costs (Unforeseen conditions).
       This proposal only includes PE calculations for new storefronts and excludes delegated
        design or PE stamp on shop drawings.
       Installation of permanent cores is excluded. The contractor will coordinate with the
        Owner and hardware supplier to ensure proper timing and delivery of cores.
       Per the design assumptions noted on the drawings, existing glazing in doors and adjacent
        sidelites is indicated as ¼". However, during site visits to multiple schools, contractors
        observed that the existing glazing appears to be 1”.
       The use of film on existing or new insulated glass units may void the typical 10-year
        warranty for hermetic seals.
       Mock-ups are excluded from this GMP.
       Per RFI #3, no repairs or modifications to wood windows are needed.
       This GMP is based on the assumption shown on drawings that existing glazing will be able
        to be removed from perimetral doors, sidelites and frames without causing any damage
        and that will accommodate new 3/8” glazing. New doors, sidelites and frames are not
        included, unless they are shown on drawings.
       Current lead-times: 14-16 weeks.

DIV – 08 OPENING (FILM)

       As the film installation will be completed in an active environment, minor dust particles
        may appear after the installation of the laminate as a result of airborne dust. These
        particles should be few and not significantly detract from clarity or aesthetics when
        looking through the glass at a distance of 6 feet.
                                                                                       13 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       Ballistic Laminate installation includes the use of liquid sprayed from high pressure tanks.
        Any item which may sustain water damage and subsequently devalue such item, shall be
        relocated prior to installation.
       DCSD has already received, reviewed and approved samples and product demonstration
        for this level 2 BRLF. No additional samples or cut sheets will be provided.
       This GMP assumes, per RFI #3, that all existing windows, doors and sidelites receiving new
        level 2 BRLF, are structurally sound.
       Current lead-times: 6-8 weeks.

DIV – 09 FINISHES (DRYWALL / ACT)

        All ceilings and partitions not explicitly identified within the scope of demolition or new
        construction are assumed to be in good, sound condition, structurally stable, and not
        requiring any adjustments, repairs, or finishes as part of this project.
       The Guaranteed Maximum Price (GMP) for ceiling patching is strictly limited to the areas
        explicitly indicated and quantified on drawing AD1.00.
       All untagged partitions not specifically identified on drawings are assumed to be CMU
        (Concrete Masonry Unit) construction
       No temporary barrier installation such as dust partitions, construction barricades for
        separation of occupied areas is included in this GMP since not specifically detailed in
        drawings for specific areas.
       The GMP excludes the installation of Type B partitions for this school, based solely on the
        locations and configurations explicitly detailed on drawing A1.00.
       No specs section for ACT-1 and grid was provided. Therefore, GMP assumes 5/8 in x 2 ft
        x 2 ft Armstrong Dune 15/16 in Square Lay-In Panel / White.
       The steel angle kickers connected to existing steel structure requested at detail 5 on
        drawing A3.30 for the interior storefront were assumed to be 10’-0” length.
       The separation of steel angle kickers connected to existing steel structure requested at
        detail 5 on drawing A3.30 for the interior storefront was assumed to be 4’-0” on center.
       The placing of the reference tag to detail 5/A3.30 on elevation 3/A3.10 was assumed to
        be incorrect since it was the only school in which that discrepancy was observed.
        Therefore, the steel angles were assumed to be running along the length, only
        horizontally, of the interior storefront.
       Existing structural steel to which the steel angle kickers are connected to was assumed to
        be accessible for welded connections. Welded connections were assumed to be
        acceptable.
       PE Stamps are excluded.
       GMP excludes shoring or temporary bracing.




                                                                                        14 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



DIV – 09 FINISHES (FLOORING)

       Specs section 096519 “Resilient Tile Flooring” states that BOD product for VCT is by
        Congoleum Corporation, Johnsonite or Mannington Mills, 12x12. However, drawings call
        for Armstrong products. GMP is based on Armstrong 12x12 VCT as shown on drawings.
       Specs section 096813 “Tile Carpeting” states that BOD product for carpet is by Bentley
        Mills, Interface, Mannington Commercial, Mohawk Carpet, or Tarkett USA, 24x24”.
        However, drawings call for Shaw products. GMP is based on Shaw 24x24” carpet tile as
        shown on drawings.
       No floor tag was provided for the existing conditions of this school. Therefore, patches
        were quoted based on allowance no. 5 to match existing.
       No moisture testing is included.

DIV – 09 FINISHES (PAINTING)

       Painting scope is limited to the areas explicitly listed on the drawings.
       Access to all painting areas will be provided without obstruction or the need for special
        equipment.
       No specialty coatings or high-performance systems are required unless specified.
       Painting of any additional areas or surfaces not identified is not included.
       Concealed or inaccessible surfaces are not part of the painting scope unless otherwise
        noted.
       Painting of perimetral doors, frames or sidelites is not included.

DIV – 21 FIRE SURPRESSION (SPRINKLERS)

       It is assumed that the existing sprinkler system is in good working condition and
        compatible with proposed modifications.
       Water supply will be available, with shut-off coordination managed by others.
       Final testing and inspection will be scheduled with adequate notice and cooperation from
        all parties.
       Modifications to existing sprinkler systems, not shown on the drawings, are excluded.
       Fire watch services or temporary fire protection measures required during system
        shutdowns are excluded.

DIV – 21 FIRE SURPRESSION (FIRE ALARM)

       No fire alarm scope is included in this GMP.




                                                                                      15 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



DIV – 23 HVAC

       Any duct cleaning or work on existing to remaining equipment or duct, not shown on
        drawings, are excluded.
       Any new equipment not shown on mechanical drawings is excluded.
       DDC system included by DCSD approved vendor Control Concepts.

DIV – 26 ELECTRICAL

       No electrical trenching, compaction, backfill, directional boring and coring for electrical
        work is expected.
       It is assumed that all new conduits will be surface mounted.

DIV – 27 LOW VOLTAGE

       Permits and associated fees are excluded.
       Customer to provide static IP addresses and network connections at panel locations.
       Customer to provide a secured staging & storage area for project-related materials.
       It is assumed that electronic AutoCAD files are available from customer for LEFKO’s
        subcontractors usage in creating submittal drawings.
       Any and all interfacing to other equipment unless specifically noted is excluded.
       Servers and workstations hardware and Microsoft operating system are excluded.
       This GMP is based on DCSD approved LV vendors’ quote. No information related to
        manufacturers, models, or brands was provided either on drawings or specs.

GENERAL

       GMP may be subject to adjustment in the event of significant market volatility or the
        implementation of new tariffs that materially impact labor or material costs that cannot
        be covered by the Contractor’s Contingency.
       This GMP and preliminary schedule is based on placed orders provided by the time of the
        proposal submission; accurate lead times and estimated delivery dates can only be
        provided once submittals are approved and orders placed. LEFKO will constantly follow
        up and provide updates regarding this matter.
       All permit fees for this project will be waived by DeKalb County School District.
       Any special inspections will be performed by Owner’s contracted third-party Inspector.
       No signage work is included in this GMP, since it was not listed in the drawings or specs.
       P&P Bond will be provided per school basis.
       The warranty period will commence once the substantial completion has been achieved
        for this project/contract.

                                                                                       16 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



       Construction contractor's fee associated to any portion of the Work which it intends to
        charge against the Owner's Contingency will be reviewed and included by the time the
        change order or PCO is submitted for review and approval.
       The commencement date of the construction phase and the substantial completion date
        are contingent upon the approval of this GMP and the issuance of the Notice to Proceed.
        Therefore, Article No. 3 of Exhibit “M” remains blank at this time.




                                                                                    17 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                    ATTACHMENT 3
                                  Completion Schedule

                          CMAR – Group 2 Security Vestibules
Find schedule attached. The lead times used in this preliminary schedule are place holder based
on preliminary feedback received from our subcontractors that will be updated once orders are
placed. During the construction process, LEFKO will consider all time saving processes and/or
ideas to ensure completion on time and on budget. The compliance of this schedule will be
conditioned to current lead times and availability by the time of approval of this GMP.




                                                                                    18 | P A G E
LEFKO CONSTRUCTION
                                                       DeKalb County School District - CMAR for Group 2 Security Vestibules
                                                                                       PRELIMINARY MASTER PROJECT SCHEDULE
ID        Task Name                                          Duration   Start          Finish         Feb '25 Mar '25   Apr '25   May '25    Jun '25   Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25   Jan '26   Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26   Oct '26   Nov '26  Dec '26
                                                                                                        101724 3 10172431 7 14 2128 5 121926 2 9 16 2330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 14 21
     1    Group 2 - Pre-Construction Phase Services          236 days   Fri 3/28/25    Fri 2/20/26                                                  Group 2 - Pre-Construction Phase Services
                                                                                                               3/28                                                                                                                2/20


     2      Pre-Construction Phase                           236 days   Fri 3/28/25    Fri 2/20/26                                                            Pre-Construction Phase
                                                                                                               3/28                                                                                                                2/20


     3         100 % Drawings & Specs                        0 days     Fri 3/28/25    Fri 3/28/25       100 % Drawings & Specs
                                                                                                              3/28   3/28


     4         Guaranteed Maximum Price Prep and Submittal   45 days    Thu 4/24/25    Wed 6/25/25            Guaranteed Maximum Price Prep and Submittal
                                                                                                                      4/24                  6/25


     5         Guaranteed Maximum Price Approval             0 days     Mon 8/18/25 Mon 8/18/25                                                Guaranteed Maximum Price Approval
                                                                                                                                                          8/18  8/18


     6         POs, Contract Amendment, Notice to Proceed    20 days    Mon 8/18/25 Fri 9/12/25                                                POs, Contract Amendment, Notice to Proceed
                                                                                                                                                            8/18        9/12
                                                                                                                                                                       0%
     7         Submittals & approvals                        45 days    Mon 9/15/25 Fri 11/14/25                                                                         Submittals & approvals
                                                                                                                                                                      9/15                    11/14


     12        Lead Times                                    70 days    Mon 11/17/25 Fri 2/20/26                                                                                                           Lead Times
                                                                                                                                                                                          11/17                                    2/20


     13          Storefront materials lead time              14 wks     Mon 11/17/25 Fri 2/20/26                                                                                               Storefront materials lead time
                                                                                                                                                                                          11/17                              2/20
                                                                                                                                                                                                                0%
     14   Construction Phase                                 280 days   Fri 10/24/25   Fri 11/20/26                                                                                                                                            Construction Phase
                                                                                                                                                                                  10/24                                                                                                                                    11/20


     15     SUB-GROUP 1                                      115 days   Fri 10/24/25   Fri 4/3/26                                                                                                           SUB-GROUP 1
                                                                                                                                                                                  10/24                                                          4/3


     16        Chapel Hill Middle School                     100 days   Fri 10/24/25   Fri 3/13/26                                                                                                  Chapel Hill Middle School
                                                                                                                                                                                  10/24                                                   3/13


     17          First Phase                                 12 days    Fri 10/24/25   Tue 11/11/25                                                                                   First Phase
                                                                                                                                                                                  10/24         11/11


     29          Second Phase                                15 days    Fri 2/20/26    Fri 3/13/26                                                                                                                         Second Phase
                                                                                                                                                                                                                         2/20        3/13


     48        Chapel Hill Elementary School                 100 days   Fri 10/24/25   Fri 3/13/26                                                                                                Chapel Hill Elementary School
                                                                                                                                                                                  10/24                                                   3/13


     49          First Phase                                 12 days    Fri 10/24/25   Tue 11/11/25                                                                                   First Phase
                                                                                                                                                                                  10/24         11/11


     61          Second Phase                                15 days    Fri 2/20/26    Fri 3/13/26                                                                                                                         Second Phase
                                                                                                                                                                                                                         2/20        3/13


     80        Cedar Grove Middle School                     103 days   Tue 11/11/25 Fri 4/3/26                                                                                                         Cedar Grove Middle School
                                                                                                                                                                                       11/11                                                     4/3


     81          First Phase                                 12 days    Tue 11/11/25 Thu 11/27/25                                                                                          First Phase
                                                                                                                                                                                       11/11         11/27




                                                                                                                                                Page 19
                                                      DeKalb County School District - CMAR for Group 2 Security Vestibules
                                                                                     PRELIMINARY MASTER PROJECT SCHEDULE
ID        Task Name                                         Duration   Start         Finish        Feb '25 Mar '25   Apr '25   May '25    Jun '25   Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25   Jan '26   Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26   Oct '26   Nov '26  Dec '26
                                                                                                     101724 3 10172431 7 14 2128 5 121926 2 9 16 2330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 14 21
     93          Second Phase                               15 days    Fri 3/13/26   Fri 4/3/26                                                                                                                                Second Phase
                                                                                                                                                                                                                             3/13        4/3


 112           Columbia Middle School                       103 days   Tue 11/11/25 Fri 4/3/26                                                                                                         Columbia Middle School
                                                                                                                                                                                    11/11                                                     4/3


 113             First Phase                                12 days    Tue 11/11/25 Thu 11/27/25                                                                                        First Phase
                                                                                                                                                                                    11/11         11/27


 125             Second Phase                               15 days    Fri 3/13/26   Fri 4/3/26                                                                                                                                Second Phase
                                                                                                                                                                                                                             3/13        4/3


 144        SUB-GROUP 2                                     121 days   Thu 11/27/25 Fri 5/15/26                                                                                                                       SUB-GROUP 2
                                                                                                                                                                                          11/27                                                            5/15


 145           Ronald Mcnair Middle School                  106 days   Thu 11/27/25 Fri 4/24/26                                                                                                          Ronald Mcnair Middle School
                                                                                                                                                                                          11/27                                                     4/24


 146             First Phase                                12 days    Thu 11/27/25 Mon 12/15/25                                                                                              First Phase
                                                                                                                                                                                          11/27         12/15


 158             Second Phase                               15 days    Fri 4/3/26    Fri 4/24/26                                                                                                                                      Second Phase
                                                                                                                                                                                                                                     4/3        4/24


 177           Dekalb School of Arts at Avondale MS         106 days   Thu 11/27/25 Fri 4/24/26                                                                                                      Dekalb School of Arts at Avondale MS
                                                                                                                                                                                          11/27                                                     4/24


 178             First Phase                                12 days    Thu 11/27/25 Mon 12/15/25                                                                                              First Phase
                                                                                                                                                                                          11/27         12/15


 190             Second Phase                               15 days    Fri 4/3/26    Fri 4/24/26                                                                                                                                      Second Phase
                                                                                                                                                                                                                                     4/3        4/24


 209           Towers High School                           109 days   Mon 12/15/25 Fri 5/15/26                                                                                                                      Towers High School
                                                                                                                                                                                               12/15                                                       5/15


 210             First Phase                                12 days    Mon 12/15/25 Wed 12/31/25                                                                                                   First Phase
                                                                                                                                                                                               12/15         12/31


 222             Second Phase                               15 days    Fri 4/24/26   Fri 5/15/26                                                                                                                                             Second Phase
                                                                                                                                                                                                                                           4/24        5/15


 241           Snapfinger Elementary School                 109 days   Mon 12/15/25 Fri 5/15/26                                                                                                                Snapfinger Elementary School
                                                                                                                                                                                               12/15                                                       5/15


 242             First Phase                                12 days    Mon 12/15/25 Wed 12/31/25                                                                                                   First Phase
                                                                                                                                                                                               12/15         12/31


 254             Second Phase                               15 days    Fri 4/24/26   Fri 5/15/26                                                                                                                                             Second Phase
                                                                                                                                                                                                                                           4/24        5/15


 273        SUB-GROUP 3                                     127 days   Wed 12/31/25 Fri 6/26/26                                                                                                                                   SUB-GROUP 3
                                                                                                                                                                                                    12/31                                                                6/26


 274           Fairington Elementary School                 112 days   Wed 12/31/25 Fri 6/5/26                                                                                                                       Fairington Elementary School
                                                                                                                                                                                                    12/31                                                         6/5




                                                                                                                                             Page 20
                                                DeKalb County School District - CMAR for Group 2 Security Vestibules
                                                                               PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                                      Duration   Start         Finish        Feb '25 Mar '25   Apr '25   May '25    Jun '25   Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25   Jan '26   Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26   Oct '26   Nov '26  Dec '26
                                                                                               101724 3 10172431 7 14 2128 5 121926 2 9 16 2330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 14 21
 275          First Phase                             12 days    Wed 12/31/25 Fri 1/16/26                                                                                                          First Phase
                                                                                                                                                                                               12/31         1/16


 287          Second Phase                            15 days    Fri 5/15/26   Fri 6/5/26                                                                                                                                                    Second Phase
                                                                                                                                                                                                                                           5/15        6/5


 306        South West Dekalb High School             112 days   Wed 12/31/25 Fri 6/5/26                                                                                                                      South West Dekalb High School
                                                                                                                                                                                              12/31                                                         6/5


 307          First Phase                             12 days    Wed 12/31/25 Fri 1/16/26                                                                                                         First Phase
                                                                                                                                                                                              12/31         1/16


 319          Second Phase                            15 days    Fri 5/15/26   Fri 6/5/26                                                                                                                                                    Second Phase
                                                                                                                                                                                                                                           5/15        6/5


 338        Miller Grove Middle School                115 days   Fri 1/16/26   Fri 6/26/26                                                                                                                             Miller Grove Middle School
                                                                                                                                                                                                     1/16                                                          6/26


 339          First Phase                             12 days    Fri 1/16/26   Tue 2/3/26                                                                                                               First Phase
                                                                                                                                                                                                     1/16         2/3


 351          Second Phase                            15 days    Fri 6/5/26    Fri 6/26/26                                                                                                                                                           Second Phase
                                                                                                                                                                                                                                                    6/5        6/26


 370        Mary Mcleod Bethune Middle School         115 days   Fri 1/16/26   Fri 6/26/26                                                                                                                        Mary Mcleod Bethune Middle School
                                                                                                                                                                                                     1/16                                                          6/26


 371          First Phase                             12 days    Fri 1/16/26   Tue 2/3/26                                                                                                               First Phase
                                                                                                                                                                                                     1/16         2/3


 383          Second Phase                            15 days    Fri 6/5/26    Fri 6/26/26                                                                                                                                                           Second Phase
                                                                                                                                                                                                                                                    6/5        6/26


 402     SUB-GROUP 4                                  148 days   Tue 2/3/26    Fri 8/28/26                                                                                                                                                 SUB-GROUP 4
                                                                                                                                                                                                            2/3                                                                        8/28


 403        Redan Elementary School                   118 days   Tue 2/3/26    Fri 7/17/26                                                                                                                                    Redan Elementary School
                                                                                                                                                                                                            2/3                                                           7/17


 404          First Phase                             12 days    Tue 2/3/26    Thu 2/19/26                                                                                                                    First Phase
                                                                                                                                                                                                            2/3         2/19


 416          Second Phase                            15 days    Fri 6/26/26   Fri 7/17/26                                                                                                                                                                 Second Phase
                                                                                                                                                                                                                                                         6/26        7/17


 435        Woodward Elementary School                118 days   Tue 2/3/26    Fri 7/17/26                                                                                                                                  Woodward Elementary School
                                                                                                                                                                                                            2/3                                                           7/17


 436          First Phase                             12 days    Tue 2/3/26    Thu 2/19/26                                                                                                                    First Phase
                                                                                                                                                                                                            2/3         2/19


 448          Second Phase                            15 days    Fri 6/26/26   Fri 7/17/26                                                                                                                                                                 Second Phase
                                                                                                                                                                                                                                                         6/26        7/17


 467        Eagle Wood Academy / GNETS                121 days   Thu 2/19/26   Fri 8/7/26                                                                                                                                        Eagle Wood Academy / GNETS
                                                                                                                                                                                                                2/19                                                             8/7




                                                                                                                                       Page 21
                                               DeKalb County School District - CMAR for Group 2 Security Vestibules
                                                                              PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                                     Duration   Start         Finish        Feb '25 Mar '25   Apr '25   May '25    Jun '25   Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25   Jan '26   Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26   Oct '26   Nov '26  Dec '26
                                                                                              101724 3 10172431 7 14 2128 5 121926 2 9 16 2330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 14 21
 468          First Phase                            12 days    Thu 2/19/26   Mon 3/9/26                                                                                                                          First Phase
                                                                                                                                                                                                               2/19         3/9


 480          Second Phase                           15 days    Fri 7/17/26   Fri 8/7/26                                                                                                                                                                         Second Phase
                                                                                                                                                                                                                                                               7/17        8/7


 499        Redan Middle School                      121 days   Thu 2/19/26   Fri 8/7/26                                                                                                                                              Redan Middle School
                                                                                                                                                                                                               2/19                                                            8/7


 500          First Phase                            12 days    Thu 2/19/26   Mon 3/9/26                                                                                                                          First Phase
                                                                                                                                                                                                               2/19         3/9


 512          Second Phase                           15 days    Fri 7/17/26   Fri 8/7/26                                                                                                                                                                         Second Phase
                                                                                                                                                                                                                                                               7/17        8/7


 531        Rowland Elementary School                124 days   Mon 3/9/26    Fri 8/28/26                                                                                                                                               Rowland Elementary School
                                                                                                                                                                                                                      3/9                                                             8/28


 532          First Phase                            12 days    Mon 3/9/26    Wed 3/25/26                                                                                                                               First Phase
                                                                                                                                                                                                                      3/9         3/25


 544          Second Phase                           15 days    Fri 8/7/26    Fri 8/28/26                                                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                                       8/7        8/28


 563        Redan High School                        124 days   Mon 3/9/26    Fri 8/28/26                                                                                                                                                    Redan High School
                                                                                                                                                                                                                      3/9                                                             8/28


 564          First Phase                            12 days    Mon 3/9/26    Wed 3/25/26                                                                                                                               First Phase
                                                                                                                                                                                                                      3/9         3/25


 576          Second Phase                           15 days    Fri 8/7/26    Fri 8/28/26                                                                                                                                                                               Second Phase
                                                                                                                                                                                                                                                                       8/7        8/28


 595     SUB-GROUP 5                                 142 days   Wed 3/25/26 Fri 10/9/26                                                                                                                                                                  SUB-GROUP 5
                                                                                                                                                                                                                          3/25                                                                      10/9


 596        Pine Ridge Elementary School             127 days   Wed 3/25/26 Fri 9/18/26                                                                                                                                                      Pine Ridge Elementary School
                                                                                                                                                                                                                          3/25                                                               9/18


 597          First Phase                            12 days    Wed 3/25/26 Fri 4/10/26                                                                                                                                      First Phase
                                                                                                                                                                                                                          3/25         4/10


 609          Second Phase                           15 days    Fri 8/28/26   Fri 9/18/26                                                                                                                                                                                     Second Phase
                                                                                                                                                                                                                                                                            8/28        9/18


 628        Stone Mountain Elementary School         127 days   Wed 3/25/26 Fri 9/18/26                                                                                                                                                   Stone Mountain Elementary School
                                                                                                                                                                                                                          3/25                                                               9/18


 629          First Phase                            12 days    Wed 3/25/26 Fri 4/10/26                                                                                                                                      First Phase
                                                                                                                                                                                                                          3/25         4/10


 641          Second Phase                           15 days    Fri 8/28/26   Fri 9/18/26                                                                                                                                                                                     Second Phase
                                                                                                                                                                                                                                                                            8/28        9/18


 660        Evansdale Elementary School              130 days   Fri 4/10/26   Fri 10/9/26                                                                                                                                                          Evansdale Elementary School
                                                                                                                                                                                                                               4/10                                                                 10/9




                                                                                                                                      Page 22
                                               DeKalb County School District - CMAR for Group 2 Security Vestibules
                                                                               PRELIMINARY MASTER PROJECT SCHEDULE
ID     Task Name                                     Duration   Start          Finish         Feb '25 Mar '25   Apr '25   May '25    Jun '25   Jul '25   Aug '25   Sep '25  Oct '25   Nov '25   Dec '25   Jan '26   Feb '26  Mar '26  Apr '26   May '26   Jun '26  Jul '26   Aug '26   Sep '26   Oct '26   Nov '26  Dec '26
                                                                                                101724 3 10172431 7 14 2128 5 121926 2 9 16 2330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229 6 132027 3 10172431 7 142128 5 121926 2 9 162330 7 14 21
 661          First Phase                            12 days    Fri 4/10/26    Tue 4/28/26                                                                                                                                          First Phase
                                                                                                                                                                                                                                 4/10         4/28


 673          Second Phase                           15 days    Fri 9/18/26    Fri 10/9/26                                                                                                                                                                                             Second Phase
                                                                                                                                                                                                                                                                                     9/18        10/9


 692        Montclair Elementary School              12 days    Fri 4/10/26    Tue 4/28/26                                                                                                                                 Montclair Elementary School
                                                                                                                                                                                                                               4/10          4/28


 693          First Phase                            12 days    Fri 4/10/26    Tue 4/28/26                                                                                                                                          First Phase
                                                                                                                                                                                                                                 4/10         4/28


 705        Second Phase                             15 days    Fri 9/18/26    Fri 10/9/26                                                                                                                                                                                             Second Phase
                                                                                                                                                                                                                                                                                     9/18        10/9


 724     SUB-GROUP 6                                 148 days   Tue 4/28/26    Fri 11/20/26                                                                                                                                                                             SUB-GROUP 6
                                                                                                                                                                                                                                       4/28                                                                         11/20


 725        Oakcliff Theme Elementary School         133 days   Tue 4/28/26    Fri 10/30/26                                                                                                                                                              Oakcliff Theme Elementary School
                                                                                                                                                                                                                                       4/28                                                                 10/30


 726          First Phase                            12 days    Tue 4/28/26    Thu 5/14/26                                                                                                                                                First Phase
                                                                                                                                                                                                                                       4/28         5/14


 738          Second Phase                           15 days    Fri 10/9/26    Fri 10/30/26                                                                                                                                                                                                   Second Phase
                                                                                                                                                                                                                                                                                            10/9        10/30


 757        Montgomery Elementary School             133 days   Tue 4/28/26    Fri 10/30/26                                                                                                                                                               Montgomery Elementary School
                                                                                                                                                                                                                                       4/28                                                                 10/30


 758          First Phase                            12 days    Tue 4/28/26    Thu 5/14/26                                                                                                                                                First Phase
                                                                                                                                                                                                                                       4/28         5/14


 770          Second Phase                           15 days    Fri 10/9/26    Fri 10/30/26                                                                                                                                                                                                   Second Phase
                                                                                                                                                                                                                                                                                            10/9        10/30


 789        Huntley Hills Elementary School          136 days   Thu 5/14/26    Fri 11/20/26                                                                                                                                                                     Huntley Hills Elementary School
                                                                                                                                                                                                                                            5/14                                                                    11/20


 790          First Phase                            12 days    Thu 5/14/26    Mon 6/1/26                                                                                                                                                      First Phase
                                                                                                                                                                                                                                            5/14         6/1


 802          Second Phase                           15 days    Fri 10/30/26   Fri 11/20/26                                                                                                                                                                                                         Second Phase
                                                                                                                                                                                                                                                                                                 10/30        11/20


 821        Peachtree Middle School                  136 days   Thu 5/14/26    Fri 11/20/26                                                                                                                                                                         Peachtree Middle School
                                                                                                                                                                                                                                            5/14                                                                    11/20


 822          First Phase                            12 days    Thu 5/14/26    Mon 6/1/26                                                                                                                                                      First Phase
                                                                                                                                                                                                                                            5/14         6/1


 834          Second Phase                           15 days    Fri 10/30/26   Fri 11/20/26                                                                                                                                                                                                         Second Phase
                                                                                                                                                                                                                                                                                                 10/30        11/20


 853     Project Finish                              0 days     Fri 11/20/26   Fri 11/20/26                                                                                                                                                                                                              Project Finish
                                                                                                                                                                                                                                                                                                        11/20     11/20




                                                                                                                                        Page 23
Commercial Construction
& General Contractor



                                     ATTACHMENT 4
                                    Schedule of Values

                          CMAR – Group 2 Security Vestibules
CHAPEL HILL MS

                                                                  GMP FOR DCSD - CHAPEL
      DIVISION                      ACTIVITY
                                                                        HILL MS
         D01      GENERAL REQUIREMENTS                            $           113,204.50
         D02      EXISTING CONDITIONS (INTERIOR DEMO)             $            13,845.14
         D03      CONCRETE                                        $             3,658.00
         D04      MASONRY                                         $            12,558.00
         D08      OPENINGS (GLAZING)                              $           189,049.00
         D08      OPENINGS (SAFETY AND SECURITY FILM)             $           162,771.00
         D09      FINISHES (DRYWALL / ACT)                        $            35,603.84
         D09      FINISHES (FLOORING)                             $             3,500.00
         D09      FINISHES (PAINTING)                             $             4,900.00
         D21      FIRE SUPRESSION                                 $             5,119.00
         D23      HVAC                                            $            14,544.00
         D26      ELECTRICAL                                      $            11,363.25
         D27      LOW VOLTAGE                                     $            24,272.98
                                                 GMP SUB TOTAL    $           594,388.71
                                                  GMP FEE (10%)   $            59,438.87
                                      OWNER'S CONTINGENCY (5%)    $            29,719.44
                                CONTRACTOR'S CONTINGENCY (5%)     $            29,719.44
                                                 TOTAL GMP $               713,266.45




                                                                                  24 | P A G E
LEFKO CONSTRUCTION
Commercial Construction
& General Contractor



                                       ATTACHMENT 5
                             Itemized General Conditions Expenses

                              CMAR – Group 2 Security Vestibules
                                                                                      UNIT
                          ACTIVITY                                 UNIT    QUANT                    TOTAL
                                                                                      PRICE
                                                                   LUMP
 Bond                                                                         1.00   8,740.00   $     8,740.00
                                                                    SUM
                                                                   LUMP
 Builder's Risk Ins.                                                          1.00   1,672.00   $     1,672.00
                                                                    SUM
                                                                   LUMP
 Tech Fee (Procore)                                                           1.00   1,406.00   $     1,406.00
                                                                    SUM
                                                                   LUMP
 General Liability Insurance & Umbrella                                       1.00   3,952.00   $     3,952.00
                                                                    SUM
 Supervision: Pre construction / Project engineer
                                                                  WEEKS       3.00   2,500.00   $     7,500.00
 (Construction phase)
 Supervision: Project Manager                                     WEEKS       3.00   3,500.00   $    10,500.00
 Supervision: Assistant PM                                        WEEKS       4.00   2,800.00   $    11,200.00
 Supervision: Superintendent                                      WEEKS       3.00   3,000.00   $     9,000.00
 Supervision: Assistant Superintendent                            WEEKS      12.00   2,400.00   $    28,800.00
                                                                  LUMP
 Transportation & Vehicle Insurance                                           1.00   7,515.00   $     7,515.00
                                                                   SUM
                                                                  LUMP
 Project scheduling                                                           1.00   4,000.00   $     4,000.00
                                                                   SUM
 Interior site preparation (Minor protection, plastic, layout     LUMP
                                                                              1.00   2,500.00   $     2,500.00
 and others).                                                      SUM
                                                                   LUMP
 Exterior Site Preparation (Container / Storage)                              1.00 1,950.00     $     1,950.00
                                                                    SUM
                                                                   LUMP
 Portable Potties                                                             1.00 2,020.00     $     2,020.00
                                                                    SUM
                                                                   LUMP
 Permit fees                                                                  1.00 3,000.00     $     3,000.00
                                                                    SUM
                                                                   LUMP
 Copies, documents and misc. during contract process                          1.00   729.50     $       729.50
                                                                    SUM
                                                                   LUMP
 Dumpsters                                                                    1.00 5,720.00     $     5,720.00
                                                                    SUM
                                                                   LUMP
 Final cleaning & Misc.                                                       1.00 3,000.00     $     3,000.00
                                                                    SUM
                                                                TOTAL GENERAL REQUIREMENTS      $   113,204.50




                                                                                                    25 | P A G E
LEFKO CONSTRUCTION
 Commercial Construction
 & General Contractor



                                             ATTACHMENT 6
                                          List of subcontractors
                                     CMAR – Group 2 Security Vestibules
               PORTION OF THE          SUBCONTRACTOR            CONTACT                          ADDRESS
DIV #
                     WORK                     NAME               PERSON                           PHONE
              Existing conditions         Atlanta Cargo                            P.O. Box 360218. Decatur, GA 30036
                                                              Yolanda Shields
            (Furniture relocation)     Transportation, co.                                Phone: 404-329-4505
                                                                                 1901 Indian Wood Circle. Maumee, OH,
              Existing conditions      Ground Penetrating        Jonathan
                                                                                                  43537
D02          (Concrete Scanning)       Radar Systems, inc.        Deputy
                                                                                          Phone: 419-843-9804
                                                                                   3141 N Woods Trail Douglasville, GA
             Existing conditions
                                      Figozz Masonry, LLC     Fidel Gonzalez                      30135
              (Interior Demo)
                                                                                          Phone: 678-598-1319
D03               Concrete                                                       3141 N Woods Trail Douglasville 30135
                                      Figozz Masonry, LLC     Fidel Gonzalez
D04               Masonry                                                                 Phone: 678-598-1319
                                                                                9192 Tara Blvd. Building D. Jonesboro, GA
                                       Atlanta Storefronts,
D08          Openings (Glazing)                                Victor Garcia                      30236
                                               LLC
                                                                                          Phone: 678-294-6501
            Openings (Safety and       Safe Haven Defense                           P.O. Box 218. Manning, SC 29102.
D08                                                            Frank Jones
               Security Film)               Southeast                                     Phone: 803-225-5194
                                                                                1750 Veterans Memorial Hwy. Austell, GA
D09         Finishes (ACT/Drywall)     Alamo Drywall, Inc.    Roderic Guillen                     30168
                                                                                          Phone: 770-739-9671
                                                                                    4461 Cary Dr. Snellville, GA 30039
D09           Finishes (Painting)      Modern Paint, co.       Jorlin Mejia
                                                                                          Phone: 678-900-6479
                                                                                1890 West Oak Pkwy. Marietta, GA 30062
D09           Finishes (Flooring)       Select Floors, inc.     Sam Nasr
                                                                                          Phone: 770-218-3462
                                                                                  205 Bell Place Suite C. Woodstock, GA
              Fire Suppression          Chattanooga Fire
D21                                                           David Hendrix                       30188
                 (Sprinklers)            Protection, inc.
                                                                                          Phone: 470-246-8145
                                                                                415 Gees Mill Business Court. Convers, GA
                                       Strictly Mechanical,
D23                 HVAC                                      Kevin Beasley                       30013
                                                inc.
                                                                                          Phone: 770-880-0132
                                         Lost Mountain                                      1825 Corner Road
D26               Electrical               Electrical           Ted Scott               Powder Springs, GA 30127
                                        Contractors, Inc.                                  Phone: 404-867-3298
                                                                                   1955 Evergreen Boulevard, Suite 50,
             Low Voltage (Safety                                   Brian
                                           Convergint                                        Duluth, GA 30096
                and Security)                                   Sturdevant
                                                                                          Phone: 678-977-0790
                                           Integrated                                       5108 Minola Drive.
              Low Voltage (Data
D27                                     Communication           Otis Sams                   Lithonia, GA 30038
                  Cabling)
                                         Networks (ICN)                                   Phone: 678-300-3861
                                         South Western                            3630 Shallowford Rd NE. Doraville, GA
            Low Voltage (Intercom
                                       Communications of      Blake Schindler                     30340
                  Vendor)
                                         Atlanta (SWC)                                    Phone: 404-787-5420
            Find Qualified subcontractor proposals attached.
                                                                                                          26 | P A G E
 LEFKO CONSTRUCTION
Commercial Construction
& General Contractor




                              INTERIOR DEMO
                          Selected price: Figozz Masonry, LLC (Interior demo)




LEFKO CONSTRUCTION
QUOTE
Date:         05/18/2025                              FIGOZZ MASONRY
Quote No.:    126                                     7231 Capps Ferry Rd Douglasville ,GA 30135
                                                      678-598-1319
                                                      figozzmasonryllc@yahoo.com



Bill To:                                                              Ship To:
LEFKO CONSTRUCTION                                                    Project:CHAPEL HILL MS 4
INC.                                                                  @ 3535 Dogwood Farm Rd
105 Mansell Circle Roswell                                            Decatur Ga 30034
GA 30075
office 404-846-6372                                                   DEMO ,CONCRETE
                                                                      ,MASONRY

 Qty Item             Description                                         Unit Price               Total
   1   DEMO           Demo including ( AD1.00 )keynotes                   $8,250.00            $8,250.00
                      (C02,D03,D07,D13,F01,W01) including light
                      cleaning while demo ,including dumster and
                      disposal .NOT INCLUDING ANY
                      ELECTRICAL DEMO
   1   CONCRETE       Concrete scope including (A1.00) concrete           $3,658.00            $3,658.00
                      footings for new CMU walls ,labor and
                      materials .
   1   MASONRY        Masonry including (A1.00) cmu walls ,patch          $3,558.00            $3,558.00
                      as necesary for new window and door frame
                      .Including labor and materials ,Including
                      dumster and disposal for masonry trash .
   0                  NOT INCLUDING ANY STEEL ANGLE AND
                      ANY DOOR AND WINDOW FRAME .




                                                                                       Total   $15,466.00

                             Please contact me if you have any question

                                    Thank you for your business.
Commercial Construction
& General Contractor




                               INTERIOR DEMO
                 Selected price: Atlanta Cargo Transportation, co. (Furniture relocation)




LEFKO CONSTRUCTION
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                             Estimate
      Decatur, GA 30036                                                                                    DATE      ESTIMATE #
      404-329-4505
                                                                                                         5/15/2025      2644



          NAME / ADDRESS

       Lefko Group




                                                      P.O. NO.                TERMS            PROJECT        RELOCATION SPEC.




                          DESCRIPTION                                              QTY            COST               TOTAL


Avondale MS - Secure vestibule, reception/admin suite, security                          4.5             165.50           744.75
room and main lobby
Installer, Driver, Vehicle, 2 helpers
Return items to original location                                                        6.5             165.50          1,075.75

Cedar Grove MS - Secure vestibule, reception room, SRO office                            4.5             165.50            744.75
Return items to original location                                                        6.5             165.50          1,075.75

Chapell Hill ES - Secure vestibule, reception room, storage room,                         8              165.50          1,324.00
vault, two restrooms, principal office, teachers’ lounge, staff lounge,
principal assistant office and office 158
Return items to original location                                                         9              165.50          1,489.50

Chapell Hill MS - Secure vestibule and waiting/reception room                            4.5             165.50           744.75
Return items to original location                                                        5.5             165.50           910.25

Columbia MS - Secure vestibule, reception/admin suite, security                          4.5             165.50           744.75
room
Return items to original location                                                        6.5             165.50          1,075.75

Eagle Woods Academy - Corridor, secure vestibule, main office                            5.5             165.50            910.25
Return items to original location                                                          7             165.50          1,158.50

Evansdale ES - Secure vestibule, general office, lounge, corridor                         7              165.50          1,158.50
Return items to original location                                                         9              165.50          1,489.50

Fairington ES - Secure vestibule, corridor, reception                                    5.5             165.50            910.25
Return items to original location                                                          7             165.50          1,158.50

We appreciate your business. Have a blessed day.
                                                                                               TOTAL




                                                                          Page 1
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                        Estimate
      Decatur, GA 30036                                                                               DATE      ESTIMATE #
      404-329-4505
                                                                                                    5/15/2025      2644



          NAME / ADDRESS

       Lefko Group




                                                     P.O. NO.            TERMS            PROJECT        RELOCATION SPEC.




                          DESCRIPTION                                         QTY            COST               TOTAL

Huntley Hill ES - Main lobby, admin/reception, storage, vault,                       9              165.50          1,489.50
toilet, principal, storage, classroom, secure vestibule
Return items to original location                                                   11              165.50          1,820.50

Mary Mcleod Bethune - Secure vestibule, reception, corridor, and                    4.5             165.50           744.75
security office
Return items to original location                                                   6.5             165.50          1,075.75

McNair MS - Secure vestibule, reception lobby adm                                   4.5             165.50            744.75
Return items to original location                                                   6.5             165.50          1,075.75

Miller Grove MS - Secure vestibule (2), corridor                                    4.5             165.50           744.75
Return items to original location                                                   4.5             165.50           744.75

Montclair ES - Parent center, office (2), secured vestibule,                         7              165.50          1,158.50
bookkeeper, admin/reception, storage (2), vault
Return items to original location                                                    9              165.50          1,489.50

Montgomery ES - Secure vestibule, corridor, and admin office                        4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Oakcliff ES - Corridor, secure vestibule, admin office                              4.5             165.50           744.75
Return items to original location                                                     6             165.50           993.00

Peachtree MS - Security office, admin vestibule, secure vestibule,                  6.5             165.50          1,075.75
attendance room, admin suite
Return items to original location                                                   7.5             165.50          1,241.25

Pine Ridge ES - Secure vestibule, corridor, admin/reception                         5.5             165.50            910.25
Return items to original location                                                     7             165.50          1,158.50
We appreciate your business. Have a blessed day.
                                                                                          TOTAL




                                                                     Page 2
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                           Estimate
      Decatur, GA 30036                                                                                  DATE      ESTIMATE #
      404-329-4505
                                                                                                       5/15/2025      2644



          NAME / ADDRESS

       Lefko Group




                                                    P.O. NO.                TERMS            PROJECT        RELOCATION SPEC.




                          DESCRIPTION                                            QTY            COST               TOTAL


Redan ES - Secure vestibule, corridor, office                                          5.5             165.50            910.25
Return items to original location                                                        7             165.50          1,158.50

Redan HS - Secure vestibule, corridor, gym lobby                                       5.5             165.50            910.25
Return items to original location                                                        7             165.50          1,158.50

Redan MS - Security vestibule, SRO office, corridor, receipt room                      4.5             165.50           744.75
Return items to original location                                                        6             165.50           993.00

Rowland ES - Admin/reception & secure vestibule                                        4.5             165.50           744.75
Return items to original location                                                        6             165.50           993.00

Snapfinger ES - Storage, performance coach office, closet (2),                          9              165.50          1,489.50
restroom, office, admin/reception, principal, secured vestibule, work
room
Return items to original location                                                      11              165.50          1,820.50

Southwest Dekalb HS - Secure vestibule, lobby, tickets                                  6              165.50           993.00
Return items to original location                                                       6              165.50           993.00

Stone Mountain ES - Secure vestibule, main office                                      4.5             165.50           744.75
Return items to original location                                                        6             165.50           993.00

Towers HS - Secure vestibule, lobby, main office                                       4.5             165.50           744.75
Return items to original location                                                        6             165.50           993.00




We appreciate your business. Have a blessed day.
                                                                                             TOTAL




                                                                        Page 3
 Leslie Regis, Inc. dba Atlanta Cargo Transportation Co.
      P.O. Box 360218                                                                                 Estimate
      Decatur, GA 30036                                                                       DATE       ESTIMATE #
      404-329-4505
                                                                                             5/15/2025      2644



         NAME / ADDRESS

       Lefko Group




                                                   P.O. NO.       TERMS          PROJECT          RELOCATION SPEC.




                         DESCRIPTION                                   QTY          COST                 TOTAL

Additional Supplies                                                          1             2,453.00          2,453.00
25 rolls of tape = $45
8 rolls of Shrink Wrap = $208
15 Speed packs = $450
625 boxes = $1750

15% Contingency                                                                            8,175.41          8,175.41




We appreciate your business. Have a blessed day.
                                                                                 TOTAL                     $62,678.16




                                                              Page 4
Commercial Construction
& General Contractor




                               INTERIOR DEMO
               Selected price: Ground Penetrating Radar Systems, inc. (Concrete Scanning)




LEFKO CONSTRUCTION
                                LEFKO CONSTRUCTION
PROPOSAL




GPRS is the nation’s premier company specializing in the detection of
underground utilities and underground storage tanks, video pipe inspection,
leak detection and the imaging of concrete structures. Our services enable
your projects to stay safe, on time and on budget.

SIM-CERTIFIED FIELD STAFF
Our SIM-Certified Project Managers are equipped with the latest technology, industry
leading training and a methodology that has produced over 99.8% accuracy on over
300,000 projects. Visit SIMSPEC.ORG today for details.

NATIONWIDE FOOTPRINT
GPRS is the largest company of our kind. With highly trained Project Managers
across America we can provide rapid response to your job site — wherever it
may be located.

CONSULTATIVE APPROACH
GPRS Project Managers are trained to help you remove barriers that could impact
your project being safe, on time and on budget. They provide industry-leading
deliverables such as CAD, 3D drawings, NASSCO reports, and a .KMZ and .PDF
map is included with every utility locating project which accelerates planning,
organizes operations and increases communication.




                           VISUALIZING
                           THE BUILT  WORLD
                                                        TM



                               ABOVE BELOW GROUND
                                        AND




                                                                                      GPRSINC.COM
 June 9, 2025                                                                                                                                     Submitted By:
 Client: LEFKO CONSTRUCTION                                                                                                                           Macy Ross
 Project Address: 2112 Seaman Circle Chamblee, GA 30341                                                                               To schedule, please email:
 Quote Number: GPRSQUOTE-209431                                                                                                        georgiainfo@gprsinc.com
 GPRS Opportunity Name/Number: CMAR - DCSD - Group 2 Security Vestibules - Concrete
 Scanning



GPRS appreciates the opportunity to provide this proposal. We encourage you to visit our website (www.gprsinc.com) and contact any of
the numerous references listed. Our insurance certificate and W-9 can also be downloaded here. Please feel free to contact us if you have
any questions or need additional information. Visit for an overview of our industry-leading best practices.

SCOPE OF WORK
General Concrete Scan: We understand the scope of work on this project is to scan for conduits and utilities embedded in or just beneath a
concrete slab in an area totaling up to 326 SF. The scan area(s) should be laid out, marked, and cleared of obstructions prior to our arrival to
avoid additional charges. Our findings will be marked directly onto the surface using a permanent marker when acceptable or other
methods depending on the site conditions or as directed by the client. The depth of detected conduits and pipes will be marked when
possible, but these measurements are only estimates. We do not recommend that you saw cut over the top of any marked conduits/pipes.
GPR cannot determine the diameters of conduits/pipes so avoid all markings by at least 3” (or more if possible.) Please visit
www.simspec.org for an overview of our industry-leading best practices that will be applied to this project.

• GPRS is not responsible for housekeeping. Any debris, equipment, or other obstructions in the area at the time of scanning could potentially block out needed data.
• All of our technicians have OSHA-10 safety training or greater. Site-specific safety training is not included in this quote. Please notify us if this project requires
  additional safety training.

EQUIPMENT
• Concrete Scanning GPR Antenna. This GPR Antenna is handheld and rolls over the surface. The device displays scan data on a screen, and
  the operator marks detected objects on the surface in real-time. The antenna needs a reasonably smooth, unobstructed surface for
  scanning and cannot scan within 2”-4” of obstructions such as walls and metal tracks. Ideally, the client removes obstacles such as these
  before our work begins. The total effective scan depth can be as much as 18” or more with this antenna but can vary depending on the
  concrete conditions, composition, and other factors such as the spacing of the reinforcing. Depth accuracy depends on obtaining a precise
  depth calibration for the concrete. This device does not emit harmful radiation and can be safely operated while people are in close
  proximity. For more information, please visit Link
• Electromagnetic Pipe Locator. This receiver can passively detect the signals from live AC power or radio signals traveling along some
  conductive utilities. Operators can connect a transmitter directly to accessible metallic pipes, risers, or tracer wires to generate a current
  at a specific frequency. The receiver can then detect the resulting signal along the pipe or tracer wire. Various factors may impact this
  device's effectiveness, including (but not limited to) access to the utility, conductivity, grounding, and interference from other utilities.
  The depths provided should always be treated as estimates as their accuracy can be affected by multiple factors. For more information,
  please visit: Link




 GPRSQUOTE-209431 v.1                                                                                                                                     Page 2 of 3
PROJECT COSTS
                    SERVICE                                                                          DESCRIPTION
 FIELD SERVICES                                    Described on Page 2
 JOB SUMMARY REPORT                                PDF including a brief description of equipment used, findings, limitations, and site photos sent at
                                                   the conclusion of every job.
 TOTAL                                                                                                                                                       $700.00

GENERAL TERMS & CONDITIONS
This proposal is subject to the General Terms and Conditions for Services of Ground Penetrating Radar Systems, LLC posted at Link (the
“Terms and Conditions”) and is hereby incorporated by reference into and made a part of this proposal. Customer acknowledges it has
read and agrees to be bound by such Terms and Conditions. In the event of any conflict between the terms of this proposal and the Terms
and Conditions, the Terms and Conditions will prevail. Customer also acknowledges that Ground Penetrating Radar Systems, LLC may,
from time to time and at its discretion, modify the Terms and Conditions and Customer agrees to be bound by such Terms and Conditions
as modified.

1.    Customer agrees to meet and perform all requirements described in this document and has fully read and understands all items listed within this document.
2.    It is the customer’s responsibility to prepare the site for scanning, including clearly identifying areas to be scanned, securing access to all areas required for
      scanning, removing and keeping these areas clear and free of obstructions. Delays caused by customer’s failure to do so may result in an increased price.
3.    GPRS does not conduct an investigation, analysis, or interpretation of soil composition, soil/concrete conditions, or geophysical, geological, engineering, or land
      surveying information. The customer acknowledges understanding that we are merely reporting retrieved data and that we do NOT provide geophysical,
      geological, engineering, or land surveying services. Customer should contact a professional in those fields if such services are needed. Data collected during may
      only be suitable for use within the scope of this proposal.
4.    If any work to be performed is within a road or street, unless specifically included by GPRS within this proposal, it is the customer’s responsibility to provide
      adequate traffic control to allow GPRS’ personnel to safely and efficiently work in the road/street.
5.    Time-on-site in excess of 8-hours will be billed at overtime rates.
6.    This price assumes that we will be given access to perform the work during normal, weekday business hours. Work performed outside of 6am-5pm Monday-
      Friday will be billed at overtime rates.
7.    These rates assume that there are no certified payroll or prevailing wage requirements for this work. If GPRS receives notice that any of these conditions exist,
      there will be additional costs.
8.    If this proposal is not accepted within 90 days of June 9, 2025, then the pricing may be subject to review.
9.    If for some reason the technician arrives on site and the work is cancelled there will be a charge of $500 per requested technician.
10.   If your project is in WV, SD, NM, or HI: State sales tax is not included in the total on this proposal, but will be included on the invoice.
11.   Payment Terms are Net 30; or as specified if a current Master Service Agreement is in place.

ACCEPTED AND AGREED
Print Name:_____________________ Signature:_____________________ Date:________________

Company Phone/Email:___________________________ PO #:___________ Job #:______________




 GPRSQUOTE-209431 v.1                                                                                                                                      Page 3 of 3
Commercial Construction
& General Contractor




                             CONCRETE
                          Selected price: Figozz Masonry, LLC




LEFKO CONSTRUCTION
QUOTE
Date:         05/04/2025                                FIGOZZ MASONRY
Quote No.:    118                                       7231 Capps Ferry Rd Douglasville ,GA 30135
                                                        678-598-1319
                                                        figozzmasonryllc@yahoo.com



Bill To:                                                               Ship To:
LEFKO CONSTRUCTION                                                     Project:CHAPEL HILL MS 4
INC.                                                                   Address 3535 Dogwood Farm
105 Mansell Circle Roswell                                             rd Decatur ga 30034
GA 30075
office 404-846-6372                                                    DEMO,CONCRETE,MASONR
                                                                       Y

 Qty Item             Description                                         Unit Price               Total
   1   DEMO           Demo including ( AD1.00) keynotes                    $7,508.00           $7,508.00
                      (C02,D02,D13,F01,W01) including light
                      cleaning while demo ,including dumster and
                      disposal. NOT INCLUDING ANY
                      ELECTRICAL DEMO .
   1   CONCRETE       Concrete scope including (A1.00) concrete            $3,658.00           $3,658.00
                      footing for CMU walls ,Labor and materials .
   1   MASONRY        Masonry Including ( A1.00) cmu walls ,patch          $3,558.00           $3,558.00
                      as necesary for new window and door
                      frame.Inluding labor and materials . Including
                      dumster and disposal of masonry trash .
   1                  NOT INCLUDING ANY STEEL ANGLE AND
                      ANY DOOR AND WINDOW FRAME .




                                                                                       Total   $14,724.00

                             Please contact me if you have any question

                                    Thank you for your business.
Commercial Construction
& General Contractor




                              MASONRY
                          Selected price: Figozz Masonry, LLC




LEFKO CONSTRUCTION
QUOTE
Date:         05/04/2025                                FIGOZZ MASONRY
Quote No.:    118                                       7231 Capps Ferry Rd Douglasville ,GA 30135
                                                        678-598-1319
                                                        figozzmasonryllc@yahoo.com



Bill To:                                                               Ship To:
LEFKO CONSTRUCTION                                                     Project:CHAPEL HILL MS 4
INC.                                                                   Address 3535 Dogwood Farm
105 Mansell Circle Roswell                                             rd Decatur ga 30034
GA 30075
office 404-846-6372                                                    DEMO,CONCRETE,MASONR
                                                                       Y

 Qty Item             Description                                         Unit Price               Total
   1   DEMO           Demo including ( AD1.00) keynotes                    $7,508.00           $7,508.00
                      (C02,D02,D13,F01,W01) including light
                      cleaning while demo ,including dumster and
                      disposal. NOT INCLUDING ANY
                      ELECTRICAL DEMO .
   1   CONCRETE       Concrete scope including (A1.00) concrete            $3,658.00           $3,658.00
                      footing for CMU walls ,Labor and materials .
   1   MASONRY        Masonry Including ( A1.00) cmu walls ,patch          $3,558.00           $3,558.00
                      as necesary for new window and door
                      frame.Inluding labor and materials . Including
                      dumster and disposal of masonry trash .
   1                  NOT INCLUDING ANY STEEL ANGLE AND
                      ANY DOOR AND WINDOW FRAME .




                                                                                       Total   $14,724.00

                             Please contact me if you have any question

                                    Thank you for your business.
QUOTE
Date:        05/11/2025                                 FIGOZZ MASONRY
Quote No.:   118                                        7231 Capps Ferry Rd Douglasville ,GA 30135
                                                        678-598-1319
                                                        figozzmasonryllc@yahoo.com



Bill To:                                                                 Ship To:
LEFKO CONSTRUCTION                                                       Project: GROUP 2
INC.                                                                     SECURITY VESTIBULES (
105 Mansell Circle Roswell                                               25 schools )
GA 30075                                                                 Address;
office 404-846-6372
                                                                         STEEL ANGLES

 Qty Item             Description                                           Unit Price           Total
   1   AVONDALE       Steel angle with anchors to cmu wall ,detail          $4,350.00        $4,350.00
       MS             (C) (A0.50) including materials and installation
   1   CEDAR          Steel angle with anchors to cmu wall ,detail          $2,050.00        $2,050.00
       GROVE MS       (C) (A0.50) including materiasl and installation

   1   CHAPEL HILL    Steel angle with anchors to cmu wall ,detail          $6,370.00        $6,370.00
       ES             (C)(A0.50) including materials and installation
   1   CHAPEL HILL    Steel angle with anchors to cmu wall ,detail          $1,250.00        $1,250.00
       MS             (C) (A0.50) including materials and installation
   1   COLUMBIA       Steel angle with anchors to cmu wall ,detail          $3,460.00        $3,460.00
       MS             (C) (A0.50) including materials and installation
   1   EAGLE          Steel angle with anchors to cmu wall ,detail          $1,450.00        $1,450.00
       WOODS          (C) (A0.50) including materials and installation
       ACADEMY
   1   EVANSDALE      Steel angle with anchors to cmu wall ,detail
       ES             (C) (A0.50) including materials and installation
                      NOT REQUIRED
   1   FAIRINGTON     Steel angle with anchors to cmu wall ,detail          $1,450.00        $1,450.00
       ES             (C) (A0.50) including materials and installation
   1   HUNTLEY        Steel angle with anchors to cmu wall ,detail          $9,320.00        $9,320.00
       HILLS ES       (C) (A0.50) including materials and installation
   1   MARY           Steel angle with anchors to cmu wall ,detail          $3,350.00        $3,350.00
       MCLEOD         (C) (A0.50) including materials and installation
       BETHUNE MS
   1   MCNAIR MS      Steel angle with anchors to cmu wall ,detail
                      (C) (A0.50) including materials and installation
                      NOT REQUIRED
   1   MILLER         Steel angle with anchors to cmu wall ,detail          $4,875.00        $4,875.00
       GROVE MS       (C) (A0.50) including materials and installation
   1   MONTCLAIR      Steel angle with anchors to cmu wall ,detail          $6,880.00        $6,880.00
       ES             (C) (A0.50) including materials and installation
   1   MONTGOMER      Steel angle with anchors to cmu wall ,detail
       Y ES           (C) (A0.50) including materials and installation
                      NOT REQUIRED
   1   OAKCLIFF ES    Steel angle with anchors to cmu wall ,detail          $1,575.00        $1,575.00
                      (C) (A0.50) including materials and installation
   1   PEACHTREE      Steel angle with anchors to cmu wall ,detail          $8,425.00        $8,425.00
       MS             (C) (A0.50) including materials and installation
   1   PINE RIDGE     Steel angle with anchors to cmu wall ,detail          $2,800.00        $2,800.00
       ES             (C) (A0.50) including materials and installation




                                                                                     Quote #118, Page 1
Qty Item          Description                                         Unit Price                Total
 1   REDAN ES     Steel angle with anchors to cmu wall ,detail        $1,350.00            $1,350.00
                  (C) (A0.50) including materials and installation
 1   REDAN HS     Steel angle with anchors to cmu wall ,detail        $4,400.00            $4,400.00
                  (C) (A0.50) including materials and installation
 1   REDAN MS     Steel angle with anchors to cmu wall ,detail        $3,320.00            $3,320.00
                  (C) (A0.50) including materials and installation
 1   ROWLAND ES   Steel angle with anchors to cmu wall ,detail
                  (C) (A0.50) including materials and installation
                  NOT REQUIRED
 1   SNAPFINGER   Steel angle with anchors to cmu wall ,detail        $4,160.00            $4,160.00
     ES           (C) (A0.50) including materials and installation
 1   SOUTH WEST   Steel angle with anchors to cmu wall ,detail        $2,770.00            $2,770.00
     DEKALB HS    (C) (A0.50) including materials and installation
 1   STONE        Steel angle with anchors to cmu wall ,detail        $1,350.00            $1,350.00
     MOUNTAIN     (C) (A0.50) including materials and installation
     ES
 1   TOWERS HS    Steel angle with anchors to cmu wall ,detail
                  (C) (A0.50) including materials and installation
                  NOT REQUIRED




                                                                                   Total   $74,955.00

                         Please contact me if you have any question

                                Thank you for your business.




                                                                                     Quote #118, Page 2
                     B & H Masonry Specialist, LLC
                            2044 Grant Road, SW
                           Atlanta, Georgia 30331
                   404-349-6002 (Phone) 770-907-3822 (Fax)
                         bhmasonry2044@gmail.com

                        SUBCONTRACTOR BID
         IF AWARDED INDIVIDUAL CONTRACTS FOR EACH SCHOOL


COMPANY NAME:               Lefko Group


ATTENTION:                  Cristina Martinez


EMAIL:                      cristina@lefkogroup.com


PROJECT TO BID:             RFP for CMAR – DCSD – Group 2 Security Vestibules
                            Chapel Hill Middle School
                            3535 Dogwood Farm Road
                            Decatur, GA 30034


ITEMS TO BE BID:            Labor, Material, and Equipment
                            8” Block, Brick, Grouted Fully, Rebar, Mortar, Sand,
                            All Reinforcements, All Blocks Ready for Paint

INCLUSION:                  $3,256.00


EXCLUSION:                  N/A


CERTIFICATION:              Marta – Vendor ID Code 2HB500


NOTE:                       EMPLOYEES ARE E-VERIFIED

B & H MASONRY SPECIALIST, LLC PROVIDES GENERAL LIABILITY AND
WORKERS COMP INSURANCE, HOWEVER WAIVER OF SUBROGATIONS IF
REQUIRED IS NOT INCLUDED IN PRICE AND WILL BE ADDED TO THE PRICE IF
REQUIRED BY GENERAL CONTRACTOR


SUBMITTED BY:               B & H Masonry Specialist, LLC
                            April 30, 2025
                            404-273-0009 (Main) or 404-787-7707
                            404-349-6002 (Office)
Commercial Construction
& General Contractor




                                  GLAZING
                          Selected price: Atlanta Storefronts, LLC




LEFKO CONSTRUCTION
                 ATLANTA STOREFRONTS, LLC



May 10 2025

Cristina Martinez
LEFKO Construction
1056 Mansell Circle
Roswell, Ga. 30075

RE: Chapel Hill MS
    084113 Aluminum Framed Entrances And Storefronts
    085653 Security Windows
    087100 Door Hardware
    088000 Glazing

Cristina,
As per your request, the following Bid Proposal outlines Atlanta Storefronts Scope Of
Work at the above referenced facility in accordance with Plans and Specifications
dated March 28 2025 and Addendum #1 and 2.

                                  SCOPE OF WORK
1. Supply and Install Oldcatle Series 3000 Thermal MultiPlane, 2” x 4-1/2” Front Plane
   Glazed Exterior Aluminum Storefront System finished in Class 1 clear anodized in
   Exterior opening marked 2/A3.10 = 28’5”” x 10’8”, with 3 Pair of Doors 6’-0” x 7’-0”
   with transom #100A, #100B, #100C. The doors leafs are Thermal Clad, 2-1/4” thick,
   with 5” Wide Stiles, 10” bottom rails, 6-1/2” mid rails and 6-1/2” top rails. We include
   Hardware for our doors per specifications. #100A = Group No. 19, #100B = Group
   No. 20, and 100C = Group No. 21.
   The frames and doors are glazed with Type IG-1T = 1” Insulated Clear tempered
   glass units. The frames and doors up to 7’-0” are labeled to have BO1 Safety and
   Security film installed by Safe Haven.

2. Supply and Install Oldcastle Series 3000 Non thermal 2 x 4-1/2”, center glazed
   Aluminum Storefront system finished in Class 1 clear anodized in Interior openings
   marked 3/A3.10 = 28’-5” x 10’-8”, with 3 Pair of Doors 6’-0” x 7’-0” with
   Transom’s, #100D and 100E, and 100F. The doors leafs are 1-3/4” thick, with 5” Wide
   Stiles, 10” bottom rails, 6-1/2”mid rails and 6-1/2” top rails. We include SF Door
   Hardware for our doors = #100D = Group No. 22. , and 100E = Group No. 23. and
   100F = Group No. 24.
   4/A3.10 = Door #102A 1 Single 3’-0” x 7’-0” including Hardware Group 50.
                   ATLANTA STOREFRONTS, LLC




     The frames and doors are glazed with Type GL-5T = 3/8” clear tempered glass.
     The frames and doors up to 7’-0” are labeled to have B01 Safety film installed by
     Safe Haven.

3. Supply and Install 1- 3’-0”x 3’-0” Level 3 BR Transaction Security Ticket Window by
   QuikServ with 1-1/4” Acrylic Glazing, natural Speak-Around clear anodized framing
   and SS 36” x 12” x 2” Base with Integrated Deal Tray.

4. Demolish and put in GC dumpster, 3/AD1.00 3 Pair and side lites, 4/AD1.00, 1 single
   and side lites

5. Per page AD1.00 and Note W4 remove existing glazing and replace with 3/8” clear
   Tempered glass Type GL-5T at 10 windows = 19 pieces of glass and 144 SF.

6. Per page A1.100 remove existing glazing and replace with GL-5T , 3/8” clear
   Tempered glass in 9 Pair, 10 Single doors, and 28 lite kits.

7. Supply and Install sealant to the Exterior and Interior perimeters of all the
   new aluminum frames, The caulk color will match the frames.

8. We Include a daily clean up of our debris and one final clean of our installed
   materials.

9. We include the protection of our installed materials by wrapping them with brown
   paper held on with non residue tape.

10. Included are PE Reviewed and Stamped Shop Drawings, Submittal Data, Samples,
    and Existing test reports.

11. The aluminum finish warranty is 10 years and Workmanship warranty is 2 Years.

Items Not Included in this Proposal :
1.   Bond, if needed ADD $5,400
2.   Pre construction Mockup that is Not part of the permanent work.
4.   Hiring of a Testing Agency or supplying supervision or equipment for testing.
5.   Designing of Field Quality-Control Inspection reports or programs.
6.   Free glass replacement if “ broken” or “scratched” by others after installed.
                 ATLANTA STOREFRONTS, LLC



7. “Delegated Design”, the shop drawings will be reviewed, calculated, and
    stamped by a PE licensed in the state of Georgia.
8. In the areas we do demolition we do not include any repair or patching of surfaces,
   or demo of Partitions
9. Purchasing of Safe Haven Film.

Lead Times and Installation
1)   Shop drawings and submittals are a 4 week lead time
2)   PE Review and Stamp is a 4 week lead time.
3)   The Custom Aluminum Doors and Hardware have a 10 week lead time.
4)   Fab of aluminum is 2 weeks
5)   Installation duration is 4 weeks.


BASE BID          $183,369

Alternate
1. To Supply Low E glass in all Exterior frames and doors will Add $280 to base bid.



Note : This Quote will remain valid as long as we receive a written commitment
       within 90 days.

If there is any other information you require, please do not hesitate to call me. We
look forward to the opportunity of working with you,

Thank You

Respectfully submitted,
Chuck Morris
Senior PM
Atlanta Storefronts LLC
Atlanta Interior Glazing Inc.
                                                                                                         Estimate
9760 Feaagin Road
Suite C                                                                                           Date          Estimate #
Jonesboro GA 30236                                                                             5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                      Project

                                                                                     CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                                 Total

Revised 5-21-25 per Addendum 1 & 2
Aluminum entrances and storefront
Framing system to be Old Castle BE 3000 series
Finish is to match existing.
Glass is to match existing
Doors are to be 3'0" x 7'0" Medium stile w/ Specified hardware per HW schedule.
Quikserv pass thru sliders 3'0' x 3'0" T1-3636 BR

1. Avondale MS @ 3131 Old Rockbridge Road Avondale Estates, GA, 30002                                            143,145.00
Doors @ 100 A, 100B, 100C & 100D
2 each Quikserv pass thrus
N - 1 each 20 fire rated door insert ( Door and trim by others ) @ 100E
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 5-21-25                                                                                       142,245.00
2. Cedar Grove MS @ 2300 Wildcat Road Decatur, GA, 30034
Doors 101A, 101B, 101C & 101D
2 each Quikserve pass thrus
N - 1 each 20 fire rated door insert ( Door and trim by others )
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                         Total


                                                                   Page 1
Atlanta Interior Glazing Inc.
                                                                                                             Estimate
9760 Feaagin Road
Suite C                                                                                               Date          Estimate #
Jonesboro GA 30236                                                                                 5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                          Project

                                                                                         CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                                     Total

Revised 5-21-25 Addendum 1                                                                                            90,445.00
3. Chapel Hill ES @ 3536 Radcliffe Boulevard Decatur, GA, 30034
Doors @ 100A, 100B, 100C, 100D, 100E & 100F
1 each Quikserv pass thru
1 each 3'0" x 3'4" window as detailed 4/A3.10
1 each 2'4" x 3'4" glass insert set in 20-HM01 HM frame @ 103 (HM frame by others )
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 5-21-25                                                                                           198,645.00
4. Chapel Hill MS @ 3535 Dogwood Farm Road Decatur, GA, 30034
Door @ 100A, 100B, 100C, 100d, 100E & 100F
Door 102 HW set 50
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

5. Columbia MS @ 3001 Columbia Dr Decatur, GA, 30034                                                                 140,175.00
Doors @ 100A, 100B, 100C & 100D
2 each Quikserv pass thrus
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                             Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                 Estimate
9760 Feaagin Road
Suite C                                                                                   Date          Estimate #
Jonesboro GA 30236                                                                     5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                              Project

                                                                             CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                         Total

6. Eagle Woods Academy/GNETS @ 5931 Shadow Rock Dr Lithonia, GA, 30058                                    82,775.00
Door @ 101 A & 101B
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

7. Evansdale ES @ 2914 Evans Woods Dr. Doraville, GA, 30340                                               79,295.00
Doors @ 100 A & 100B
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

8. Fairington ES@ 5505 hillip Bradley Dr Lithonia, GA, 30038                                              81,085.00
Doors @ 101A & 101B
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                 Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                            Estimate
9760 Feaagin Road
Suite C                                                                                              Date          Estimate #
Jonesboro GA 30236                                                                                5/23/2025           9031


     Phone #             678-834-7806

       Fax #             678-843-7827

            jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                         Project

                                                                                        CMAR - DCSD - Group 2 Security Vestibu...


                                                      Description                                                   Total

Revised Addendum 1 5-21-25                                                                                           87,205.00
9. Huntley Hills ES @ 2112 Seaman Circle Chamblee, GA, 30341
Doors @ 100A & 100B
Includes insulated panels @ exterior storefront
W1 - 1 each Quikserv pass thru
W2 - 1 each
N - 1 each 20 fire rated door insert ( Door and trim by others )
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

10. Mary McLeod Bethune MS @ 5200 Covington Hwy Decatur, GA, 30035                                                  140,275.00
Doors @ 101A, 101B, 101C & 101D
2 each Quikserv pass thrus
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 & 2 5-21-25                                                                                       52,075.00
11.Ronald McNair Sr. MS @ 2190 Wallingford Drive Decatur, GA, 30032
Replace existing glass in curtain wall and storefront as detailed 2, 3 & 4 / A3.10
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                            Total


                                                                    Page
Atlanta Interior Glazing Inc.
                                                                                                                     Estimate
9760 Feaagin Road
Suite C                                                                                                     Date            Estimate #
Jonesboro GA 30236                                                                                       5/23/2025            9031


     Phone #             678-834-7806

       Fax #             678-843-7827

            jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                                  Project

                                                                                              CMAR - DCSD - Group 2 Security Vestibu...


                                                      Description                                                           Total

Add Alternate 1 Ronald McNair SR MS
  lease provide additive alternate 1, including to remove existing      glazing at doors and where existing
sidelites flank existing doors and windows, including gasket, anchors, and putty at perimeter of glazing for
door/s to limits no higher than door leaf height at horizontal mullion or head. Clean glazing channels, prepare
and install new 3/8 tempered glazing in the courtyard, per drawing A1.10. Add to base $7500.00

12. Miller Grove MS @ 2215 Miller Rd Decatur, GA, 30035                                                                     202,145.00
Doors @ 100A, 100B, 100C, 100D, 101A, 101B & 101G
Included Break metal at storefront columns
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00


Revised Addendum 1 5-21-25                                                                                                   90,545.00
13. Montclair ES @ 1680 Clairmont lace, NE Atlanta, GA, 30329
Doors @ 100A, 100B, 100C, 100D, 100E & 100F
1 each Quikserv pass thru
1 each 2'4" x 3'4" glass insert set in 20-HM01 HM frame @ 103 (HM frame by others )
N - 1 each 20 fire rated door insert ( Door and trim by others )
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                                Total


                                                                    Page
Atlanta Interior Glazing Inc.
                                                                                                 Estimate
9760 Feaagin Road
Suite C                                                                                   Date          Estimate #
Jonesboro GA 30236                                                                     5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                              Project

                                                                             CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                         Total

14. Montgomery ES @ 3995 Ashford-Dunwoody Rd. Atlanta, GA, 30319                                          93,735.00
Door @ 101A, 101B, 101C, 101D, 101E & 101F
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

15. Oakcliff ES @ 3150 Willow Oak Way Doraville, GA, 30340                                               117,915.00
Doors @ 201A, 201B, 201C & 201D
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 5-21-25                                                                               218,805.00
16. eachtree MS @ 4664 North eachtree Road Atlanta, GA, 30338
Doors @ 100A, 100B, 100C & 100D
Doors @ 100E, 100F & 101A
Included Break metal at storefront columns
2 Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                 Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                 Estimate
9760 Feaagin Road
Suite C                                                                                   Date          Estimate #
Jonesboro GA 30236                                                                     5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                              Project

                                                                             CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                         Total

17. ine Ridge ES @ 750 ine Ridge Drive Stone Mountain, GA, 30087                                         139,685.00
Doors @ 100A, 100B, 100C & 100D
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

18. Redan ES @ 1914 Stone Mountain-Lithonia Road Lithonia, GA, 30058                                     130,145.00
Doors @ 101A, 101B, 102A & 102B
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 5-21-25                                                                               161,175.00
19. Redan HS @ 5247 Redan Road Stone Mountain, GA, 30088
Doors @ 001A, 001B, 001C, 001D, 400A, 400B & 400C
1 each Quikserv ticket window ( 3 panel BR )
Includes Break metal @ Storefront
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                 Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                          Estimate
9760 Feaagin Road
Suite C                                                                                            Date          Estimate #
Jonesboro GA 30236                                                                              5/23/2025           9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                       Project

                                                                                      CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                                  Total

20. Redan MS@ 1775 oung Rd Lithonia, GA, 30058                                                                    146,725.00
Doors @ 101A, 101B, 101C & 101D
2 each Quikserv pass thrus
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

21. Rowland ES @ 1317 S. Indian Creek Drive Stone Mountain, GA. 30083                                              91,345.00
Doors @ 100A, 100B, 100C, 100D, 100E & 100F
1 each Quikserv pass thrus
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

Revised Addendum 1 5-21-25                                                                                        100,145.00
22. Snapfinger ES @ 1365 Snapfinger Road Decatur, GA, 30032
Doors @ 100A, 100B, 100C & 100D
1 each Quikserv pass thrus
2 each 2'4" x 3'4" glass insert set in 20-HM01 HM frame @ 109A & 111 (HM frame by others )
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                        Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                                 Estimate
9760 Feaagin Road
Suite C                                                                                                   Date        Estimate #
Jonesboro GA 30236                                                                                   5/23/2025          9031


     Phone #            678-834-7806

       Fax #            678-843-7827

           jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                            Project

                                                                                          CMAR - DCSD - Group 2 Security Vestibu...


                                                     Description                                                      Total

23.Southwest DeKalb HS @ 2863 Kelley Chapel Road Decatur, GA, 30034                                                    91,645.00
Remove and replace door hardware @ existing doors 200.1A, 200.1B & 200.1C
Doors @ 200A & 200B
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

24. Stone Mountain ES@ 6720 James B. Rivers Dr Stone Mountain, GA, 30083                                              125,525.00
Doors @ 100A, 100B & 100C
Includes break metal @ storefront
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00

25.Towers HS @ 3919 Brookcrest Circle Decatur, GA, 30032                                                               72,545.00
Remove and replace door @ existing 100.1A & 100.1B
Remove existing glazing at doors, sidelites and windows at security vestibule 100 and main office 101,
tagged with B01 , including gasket, anchors, and putty at perimeter of glazing. Clean glazing channels,
prepare and install new 3/8 tempered glazing
1 each Quikserv pass thru
Allowance per school for after hours and weekend work @ $6625.00
Allowance for back ground checks @ $450.00
Allowance for after hours and weekend work @ $ 6625.00




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                             Total


                                                                   Page
Atlanta Interior Glazing Inc.
                                                                                                    Estimate
9760 Feaagin Road
Suite C                                                                                      Date            Estimate #
Jonesboro GA 30236                                                                        5/23/2025            9031


     Phone #             678-834-7806

       Fax #             678-843-7827

            jeff.wharton@atlantainteriorglazing.com



  Name / Address

LEFKO Construction
105 Mansell Circle
Roswell GA 30075

                                                                                                 Project

                                                                                CMAR - DCSD - Group 2 Security Vestibu...


                                                      Description                                            Total

Exclusions
Blocking as re uired for proper installation.
 -raying of the floor if re uired.
Magnetic Locks
Motion Sensors
Card Readers
 ush To Exit Buttons
Cleaning of glass.




We appreciate the opportunity to price your projects
Estimate good for 90 days                                                    Total                         $3,019,445.00



                                                                    Page 1
520 Wes Walker Memorial Drive                                                                      Revised May 28, 2025
Ball Ground, Ga 30107                                                                                      May 25, 2025
(404) 351-8724 Phone
ashley@tuxedoglass.com

Ana Cegarra
Lefko Construction
105 Mansell Circle
Roswell, GA 30075
                                                        PROPOSAL
Project: DCSD Group 2 – Chapel Hill Middle School #4
Drawings & Specifications Dated: March 28, 2025

Dear Ana,

Tuxedo Glass & Mirror is pleased to provide a proposal with the following scope of work:
Framing:        Kawneer 451T & 451 Center Set (2” x 4 1/2”)
                Clear Anodized Finish
                Exterior & Interior Vestibules

Glass:           1” IG – Energy Select28 @ Exterior Vestibule
                 3/8” Clear Tempered Glass @ Interior Vestibule
                 3/8” Clear Tempered @ 3-thus window D13
                 Note: 3/8” clear tempered glass does not meet GA Energy code requirements

Caulking:        2 lines of silicone caulk at perimeter of all aluminum framing

Doors:           Kawneer Wide Stile Exterior Doors
                            o (3) Pairs (6’-0” x 7’-0”)
                            o Doors 100A, 100B & 100C
                            o Hardware Sets 19, 20 & 21
                                 Surface Mounted Sweep included, bottom of door application not recommended
                            o Doors include glass @ both “panel material” not aluminum as shown.
                 Kawneer Wide Stile Interior Doors
                            o (3) Pairs (6’-0” x 7’-0”) & (1) Single (3’-0” x 7’-0”)
                            o Doors 100D, 100E, 100F & 102A
                            o Hardware Set 22, 23, 24 & 50
                                 Surface Mounted Sweep included, bottom of door application not recommended
                            o Doors include glass @ both “panel material” not aluminum as shown.

Security:        QuikServ Ticket Window
                              o (1) thus @ 36” x 36”
                              o Speak Around
                              o BR Deal Tray
                              o Level 3 acrylic BR glazing
                              o Clear Anodized


                                                                                                              1|Page
Demolition:       Demolition included at the following
                               o W01 – 3/AD1.00 – (3) pairs of doors & siedlites
                               o D13 – 3 exterior 3/AD1.00 & 4/A3.10
                               o Refer to notes in cover letter referencing waterproofing at openings and glass replacement.




EXCLUSIONS

    •    ACM Panel inserts (084113 1.2 A3)                               •   Brake Metal Coping and Column Wraps or its
    •    Delegated Design (084113 1.4E) outside of PE Calcs for              coordination (only included at storefront scope of
         new storefront by TGM                                               work)
    •    Safety & Security Window Laminates (088723)                     •   Casework/Millwork specialty glass/glazing, shelving,
    •    Mock Up (088000 1.7A & 08413 1.8)                                   etc.
    •    10 year water penetration warranty (084113 1.9 A D)             •   Electrical card reader & intercom systems
    •    Washing glass (088000 3.5)                                      •   Electrical (Hi or Lo) Voltage wiring or its coordination
    •    Laminated Glass (088000 1.35B,1.10 B)                           •   Final Cleaning
    •    PE Stamp on shop drawings (only PE Calcs are                    •   Fire rated caulking, framing or glass
         stamped)                                                        •   Concealed, Galvanized, and/or Stainless-Steel flashing
    •    Testing of any kind in field or laboratory (084113 2.2)             or any counterflashing (by others)
    •    Front set framing – drawings show center set (084113            •   Graphics/signage
         2.3B)                                                           •   Hollow metal framing and lite kits or glass stops at
    •    Non removeable glazing stops at doors (084113 2.4B3)                same
    •    Three way adjustable anchors (084113 2.8B)                      •   Manuf. Certs. Or Approval
    •    Maintenance agreement on new or existing doors &                •   NFRC- energy performance certificates
         hardware                                                        •   Permanent Keying/Cores (see add)
    •    Field Measuring prior to demolition                             •   Protection from damage by Other Trades
    •    Protection                                                      •   Replacement Warranties
    •    Concealed Flashing                                              •   Self-adhered flashing peel & stick
    •    3-coat, XL, or SunStorm Paint                                   •   Structural support or wood blocking at perimeter of
    •    Attic Stock                                                         windows
    •    Auto operators


QUALIFICATIONS

   •    Reference “Qualifications & Exclusions” Cover letter dated 5/21/2025 for additional qualifications & exclusions that may
        not be listed in this proposal.
   •    All performance, closeout, warranty is qualified as manufacturer’s standard paperwork & durations.
   •    TGM is not responsible for supply chain interruptions which affect the schedule.
   •    Price valid until September 2025
   •    Shop drawings will not have a PE stamp, PE calculations will be stamped.
   •    TGM does not include Mullion touch up due to damage by others.
   •    We have no testing Included. We will assist in any onsite testing provided by others.
   •    The glass (10) year warranty is for the hermetic seal of the IG unit & Coating. Breakage is not included.
   •    TGM is not responsible for landscape or sidewalk protection for any reason.
   •    If water testing is to be performed on this project, we require it to be done on the mockup and/or within the first 10% of
        the skin installation. All products used at the first water test need to be consistent throughout the building process and all
        sealant lines must be in place. We do not support one line of caulking defense only.



Base Bid……………………………………………………………………………… $ 255,876 tax incl’d
                                                                                                                       2|Page
Adds/Deducts to Base Bid:

•   ADD to replace glass @ 28 existing doors with 3/8” clear tempered           ADD $ 32,900 tax incl’d
    TGM is not responsible for damage to doors when replacing glass
    Replacement of glass stops & lite kits as needed is included.
•   ADD to replace (3) exterior storefront @ D13                                ADD $40,750 tax incl’d
    Approx 165 sq/ft
    451T framing with 1” IG ES28 glass
    Demolition of existing elevations included
    Pivot mullions included at curved area

Thank you for the opportunity to provide pricing for this project and we look forward to working with you on this project.


Sincerely,



Ashley G Bramlett

Senior Project Manager




                                                                                                                        3|Page
520 Wes Walker Memorial Drive                                                              May 25, 2025
Ball Ground, Ga 30107
(404) 351-8724 Phone
ashley@tuxedoglass.com

Ana Cegarra
Lefko Construction
105 Mansell Circle
Roswell, GA 30075
                                                       PROPOSAL
Project: DCSD Group 2
Dear Ana,
Tuxedo Glass & Mirror is pleased to provide a proposal with the following scope of work:
Permanent Keying of all doors
          -  7 pin keyed cores
          -  Factory Master Key
          -  Final Core installation
          -  Subject to change based on final approved submittals
          -  Normal working hours (8am-5pm, Monday – Friday)
          -
      School        Number of Cores Total
    #1 AVON                 14         $6,230
     #2 CGMS                14         $6,230
     #3 CHES                8          $3,560
     #4 CHMS                21         $9,345
      #5 CMS                14         $6,230
      #6 EWA                8          $3,568
     #7 EDES                8          $3,568
     #8 FAES                8          $3,568
     #9 HHES                8          $3,568
  #10 MMBMS                 14         $6,244
 #11 McNair MS              0             $0
   #12 MGMS                 20         $8,920
    #13 MCES                8          $3,568
    #14 MOES                8          $3,568
    #15 OCES                10         $4,460
    #16 PCMS                20         $8,920
    #17 PRES                14         $6,244
     #18 REES               14         $6,244
    #19 REHS                12         $5,352
    #20 REMS                14         $6,244
    #21 ROES                7          $3,122
     #22 SFES               10         $4,460
   #23 SWDHS                14         $6,244
    #24 SMES                11         $4,906
     #25 THS                16         $7,120


                                                                                            1|Page
 EXCLUSIONS

    •  Distribution to staff of any form of keys, fobs or                  •   Damage from negligence, vandalism or Force
       cards or credentials.                                                   Majeure are not subject to warranty.
   • Any temporary security, barricades, or signage.                       •   Maintenance agreement on new or existing doors &
   • All carpentry work outside of this specification                          hardware
       including drywall, paint, framing, patching of                      •   Final Cleaning
       existing holes, etc. are                                            •   Protection from damage by Other Trades
   • Any special consideration for asbestos and lead                       •   Replacement Warranties
       paint hazards.
QUALIFICATIONS

    •   Reference “Qualifications & Exclusions” Cover letter dated 5/21/2025 for additional qualifications & exclusions that may
        not be listed in this proposal.
    •   All performance, closeout, warranty is qualified as manufacturer’s standard paperwork & durations.
    •   TGM is not responsible for supply chain interruptions which affect the schedule.
    •   Price valid until September 2025



Base Bid……………………………………………………………………………… $ 131,483 tax incl’d
Thank you for the opportunity to provide pricing for this project and we look forward to working with you on this project.
Sincerely,
Ashley G Bramlett
Senior Project Manager




                                                                                                                     2|Page
Commercial Construction
& General Contractor




                SAFETY AND SECURITY FILM
                          Selected price: Safe Haven Defense Southeast




LEFKO CONSTRUCTION
                                                                                            PROPOSAL
Prepared for:                                      May 2, 2025                                           No. 2146
Lefko Construction
Attn: Marc Lefkovits
105 Mansell Cir                                    Safe Haven Defense Southeast
Roswell, GA 30075                                  P.O. Box 218, Manning, SC 29102
marc@lefkogroup.com                                P: (803) 225-5194 | frank@shdsoutheast.com
(404) 846-6372                                     www.shdsoutheast.com


Chapel Hill MS - 3535 Dogwood Farm Road, Decatur
Scope of Work                                                                                                Total
Supply & Install (735SF) Bullet Resistant Protection - Per SSOE                                     $158,030.00
Drawings (112 total panes)
 PRODUCT DESCRIPTION
 Safe Haven Defense SW440BR/SW600BR laminate offers protection for small arms bullet resistance as well as
 glass breakage due to burglaries, hurricanes, and blast. SW440BR/SW600BR provides ONE-WAY bullet resistance
 allowing bullets to pass through from the interior but stopping bullets from the exterior.
 CERTIFICATIONS
 NIJ 0108.01 - Bullet Resistance (3rd Party Lab Certified)
 UL752 - Bullet Resistance (3rd Party Lab Certified)
 USES/APPLICATION
 Safe Haven Defense SW440BR/SW600BR laminate is applied onsite, to the interior and exterior of existing
 windows/glass. Unlike traditional bullet resistant glass, no special modifications or retrofitting to the existing
 structure is required. SW440BR/SW600BR laminate can be applied over existing glass as thin as ¼ inch and will
 stop a 9mm on dual pane ¼” or 3/8” single pane.
 *Existing window must be inspected to be structurally sound.

Bond - 3%                                                                                               $4,741.00

Please advise of any special PPE, badges, identification, or additional
requirements for contractors/vendors. This project is expected to take     Grand Total:            $162,771.00
5 working days. Lead time will be 6-8 weeks. SHD will need access
after typical work hours and weekends with minimal traffic in the
work areas. SHD will need a clean/dust free working environment. This
price is valid until December 31, 2025.




  [sig|req|signer1||||240|35]                                     [sig|req|signer2||||240|35]

X                                                               X
Marc Lefkovits (Lefko Construction)                             Company Authorized Signature
                                          SCOPE OF WORK

Safe Haven Defense Georgia, LLC will work with associated stakeholders adding security laminate to
existing windows at the address stated on the proposal. The following details the responsibilities and
performance objectives of Safe Haven Defense Georgia, LLC:
1. Responsibilities and Objectives
   1.1. Visually inspect windows for pre-existing damage/deformities.
   1.2. Care will be taken not to damage any areas around the windows.
   1.3. Employees will act in a professional manner when working and interacting with
        staff/employees.
   1.4. Clean & Install Safe Haven Defense Laminate on the windows as described in the proposal.
   1.5. Secure aforementioned laminate utilizing approved and standardized anchoring method.
   1.6. Conduct quality assurance inspections daily throughout the installation process.
   1.7. Maintain an orderly workspace during installation.
2. Glass Clarity:
   2.1. Installation crews will take every necessary action possible to clean all windows prior to the
        installation of the laminate.
       2.1.1. As this installation will be completed in an active environment; minor dust particles may
              appear after the installation of the laminate as a result of airborne dust.
       2.1.2. These particles should be few and not significantly detract from clarity or aesthetics when
              looking through the glass at a distance of 6 feet.
   2.2. Laminates and films are applied with a water-based solution; therefore, it is normal for minor
        bubbling and hazing to occur during installation process before curing.
       2.2.1. This curing period is between 30-120 days depending on the level of exposure to direct
              sunlight, temperature, and thickness of laminate.
3. Safe Haven Defense Georgia, LLC is not responsible for the following actions:
   3.1. Clearing of space (inside or outside) to provide clean and unobstructed access to the target
        windows. Minor items may be an exception.
       3.1.1. Issues such as tree trimming, desk moving, and computer/electronic relocation will be
              completed prior to installation.
   3.2. Permanent structures, piping, support beams etc. which may be an obstruction to the
        installation process, and cannot be relocated, will be evaluated on a case-by-case scenario.
   3.3. Ballistic Laminate installation includes the use of liquid sprayed from high pressure tanks.
        Any item which may sustain water damage and subsequently devalue such item, shall be
        relocated prior to installation.

Safe Haven Defense Georgia, LLC is actively following CDC guidelines to the best of our abilities. Our
COVID-19 response plan includes such measures as self-reporting of illness or feeling of illness and self-
reporting of possible or confirmed exposures. If your facility requires additional precautions, please
inform our team.
Commercial Construction
& General Contractor




                          DRYWALL / ACT
                           Selected price: Alamo Drywall, Inc




LEFKO CONSTRUCTION
                                        1750 Veterans Memorial Hwy
                                             Austell GA, 30168
                                            Office: 770-739-9671


                                         PROPOSAL
     To:           LEFKO Construction                                    Date:                    06/04/2025
     Attention:    Cristina Martinez                                     Office:               678-902-7270
     Address:      105 Mansell Cir, Roswell, GA 30075


            JOB NAME                      JOB NUMBER                             JOB ADDRESS
  CMAR - DCSD - Group 2 Security
                                             20250073                    Different counties in Georgia
           Vestibules


                  PROPOSAL SUMMARY                                                 AMOUNT
    Alamo Drywall, Inc is pleased to present the following bid for CMAR - DCSD - Group 2 Security
    Vestibules, based on plans and specifications dated 05/02/2025 and subject to the following inclusions,
    exclusions and qualifications.

    Drawings Addendum #2

    Scope of work description – (1 - Avondale MS)

    Interior Package:                                                                          $15,259.00
         Wall type – C/6/SP - height 14-0”– 13 LF
         Wall type – C/8/NR - height 14-0”– 25 LF
         Wall type – C/8/NR/FTG/01 - height 14-0”– 40 LF
         Hard ceiling – 109 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

Base Bid Amount                                                                                          15,259.00
           Bid Bond 3.1%.                                                                          $473.03

    Scope of work description – (2 - Cedar Grove MS)

    Interior Package:                                                                          $11,492.00
         Wall type – C/8/SP - height 14-0”– 56 LF
         Wall type – C/8/NR/FTG - height 14-0”– 17 LF
         Hard ceiling – 115 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

Base Bid Amount                                                                                          11,492.00
           Bid Bond 3.1%.                                                                          $370.20
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671


    Scope of work description – (3 - Chapel Hill ES)

    Interior Package:                                              $25,938.00
         Wall type – B/8/6/SP - height 14-0”– 7 LF
         Wall type – B/8/SP - height 14-0”– 11 LF
         Wall type – C/8/1B/FTG - height 14-0”– 9 LF
         Wall type – C/8/NR/FTG - height 14-0”– 42 LF
         Wall type – C/8/SP - height 14-0”– 8 LF
         Wall type – G1/6/NR/02 - height 14-0”– 7 LF
         Wall type – M1/3/NR - height 14-0”– 44 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $10,663.00
        ACT-1: 1,353 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         38,601.00
         Bid Bond 3.1%.                                             $1,196.63

    Scope of work description – (4 - Chapel Hill MS)

    Interior Package:                                              $11,304.00
         Wall type – C/8/NR/FTG - height 14-0”– 57 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $14,694.00
        ACT-1: 124 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.
        MP: 198 SF – Metal panels system.
        (Patch and repair only)

Base Bid Amount                                                         25,998.00
         Bid Bond 3.1%.                                              $805.94

    Scope of work description – (5 - Columbia MS)

    Interior Package:                                              $15,461.00
         Wall type – B/8/3-5/8”/NR/FTG - height 6-0”– 64 LF
         Wall type – B/8/6/SP - height 6-0”– 4 LF
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         Wall type – C/8/SP - height 6-0”– 12 LF
         Hard ceiling – 568 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

Base Bid Amount                                                         15,491.00
         Bid Bond 3.1%.                                              $494.17

    Scope of work description – (6 - Eagle Woods Academy)

    Interior Package:                                               $9,545.00
         Wall type – C/6/ - height 14-0”– 7 LF
         Wall type – C/8/NR - height 14-0”– 25 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,000.00
        ACT-1: 93 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         10,545.00
         Bid Bond 3.1%.                                              $326.90

    Scope of work description – (7 - Evansdale ES)

    Interior Package:                                              $10,761.00
         Wall type – C/8/FTG - height 14-0”– 29 LF
         Wall type – C/8/SP - height 14-0”– 9 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,003.00
        ACT-1: 129 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         11,764.00
         Bid Bond 3.1%.                                              $364.68
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671

    Scope of work description – (8 - Fairington ES)

    Interior Package:                                               $9,456.00
         Wall type – C/8/FTG - height 14-0”– 29 LF
         Wall type – C/8/NR - height 14-0”– 13 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,155.00
        ACT-1: 135 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         10,611.00
         Bid Bond 3.1%.                                              $328.94

    Scope of work description – (9 - Huntley Hills ES)

    Interior Package:                                              $31,951.00
         Wall type – B/8/3-5/8”/1B/FTG - height 8’-0”– 64 LF
         Wall type – B/8/3-5/8”/2B - height 8’-0”– 25 LF
         Wall type – C/6/1B - height 8’-0”– 17 LF
         Wall type – C/6/SP - height 8’-0”– 11 LF
         Wall type – C/8/FTG - height 8’-0”– 29 LF
         Wall type – G1/6/Nr/01 - height 14’-0”– 7 LF
         Wall type – M1/3/NR - height 14’-0”– 16 LF
         Wall type – M1/3/NR - height 14’-0”– 18 LF
         Wall type – M1/6/NR - height 14’-0”– 7 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $14,798.00
        ACT-1: 1,914 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.
        ACT-2: 44 SF – 1/2 in x 2 ft x 2 ft USG Sheetrock Brand
        Lay-in Gypsum Square Edge Panel / White - 3260.

Base Bid Amount                                                         46,749.00
         Bid Bond 3.1%.                                             $1,449.22

    Scope of work description – (10 - Mary Mcleod Bethune MS)

    Interior Package:                                              $12,023.00
         Wall type – C/8/NR/FTG - height 14-0”– 44 LF
         Wall type – C/8/SP - height 14-0”– 10 LF
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         Hard ceiling – 129 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

Base Bid Amount                                                         12,023.00
         Bid Bond 3.1%.                                              $372.71

    Scope of work description – (11 - McNair MS)

    Interior Package:                                               $3,957.00
         Wall type – A3.30/1 - height 14-0”– 11 LF
         Hard ceiling – (Patch and repair) – 48 SF
         Soffit – 1,130 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,000.00
        ACT-1: 58 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                          4,957.00
         Bid Bond 3.1%.                                              $153.67

    Scope of work description – (12 - Miler Grove MS)

    Acoustic ceiling:                                               $2,494.00
        ACT-1: 324 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                          2,494.00
         Bid Bond 3.1%.                                              $77.31

    Scope of work description – (13 - Montclair ES)

    Interior Package:                                              $33,836.00
         Wall type – B/8/3-5/8”/2B/FTG - height 8’-0”–29 LF
         Wall type – C/6/NR - height 14-0”– 3 LF
         Wall type – C/6/SP - height 14-0”– 7 LF
         Wall type – C/8/NR/FTG - height 8’-0”– 26 LF
         Wall type – C/8/SP - height 8’-0”– 12 LF
         Wall type – M1/3/NR - height 14-0”– 93 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $10,847.00
        ACT-1: 1,426 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         44,683.00
         Bid Bond 3.1%.                                             $1,385.17

    Scope of work description – (14 - Montgomery ES)

    Interior Package:                                              $11,271.00
         Wall type – C/6/NR - height 14-0”– 16 LF
         Wall type – C/8/NR/FTG/01 - height 14-0”– 16 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,000.00
        ACT-1: 63 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         12,271.00
         Bid Bond 3.1%.                                              $380.40

    Scope of work description – (15 - Oakcliff ES)

    Interior Package:                                              $10,079.00
         Wall type – C/8/NR/FTG - height 14-0”– 27 LF
         Wall type – C/8/SP - height 14-0”– 8 LF
         Hard ceiling – 25,707 SF
         Soffit – 1,130 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,000.00
        ACT-1: 86 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         11,079.00
         Bid Bond 3.1%.                                              $343.45
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671

    Scope of work description – (16 - Peachtree MS)

    Interior Package:                                              $25,179.00
         Wall type – C/6/SP - height 8’-0”– 11 LF
         Wall type – C/8/NR/FTG - height 8’-0”– 101 LF
         Wall type – G1/3/NR - height 14’-0”– 16 LF
         Included:
         Detail A3.30/11 per Drawing A3.30
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $2,668.00
        ACT-1: 343 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.
        (Patch and repair only)

Base Bid Amount                                                         27,847.00
         Bid Bond 3.1%.                                              $863.25

    Scope of work description – (17 - Pine Ridge ES)

    Interior Package:                                              $14,465.00
         Wall type – C/8/1B - height 14-0”– 17 LF
         Wall type – C/8/NR/FTG/01 - height 14-0”– 45 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,149.00
        ACT-1: 140 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         15,614.00
         Bid Bond 3.1%.                                              $484.03

    Scope of work description (18 - Redan ES)

    Interior Package:                                               $9,225.00
         Wall type – C/8/NR/FTG/01 - height 14-0”– 50 LF
         Wall type – C/8/SP - height 14-0”– 3 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,367.00
        ACT-1: 162 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         13,592.00
         Bid Bond 3.1%.                                              $421.35

    Scope of work description – (19 - Redan HS)

    Interior Package:                                              $11,753.00
         Wall type – B/8/3-5/8”/NR/FTG - height 8”-0”– 41 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Patch and repair
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $5,616.00
        ACT-1: 751 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         17,369.00
         Bid Bond 3.1%.                                              $557.88

    Scope of work description – (20 - Redan MS)

    Interior Package:                                              $13,996.00
         Wall type – C/8/NR - height 8’-0”– 6 LF
         Wall type – C/8/NR/FTG/01 - height 8’-0”– 62 LF
         Wall type – C/8/SP - height 14-0”– 8’ LF
         Hard ceiling – 138 SF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

Base Bid Amount                                                         13,996.00
         Bid Bond 3.1%.                                              $433.88

    Scope of work description – (21 - Rowland ES)

    Interior Package:                                               $4,000.00
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
         Wall type – C/8/SP - height 14-0”– 4 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                               $1,000.00
        ACT-1: 57 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                          5,000.00
         Bid Bond 3.1%.                                              $155.00

    Scope of work description – (22 - Snapfinger ES)

    Interior Package:                                              $37,456.00
         Wall type – C/6/NR - height 8’-0”– 10 LF
         Wall type – C/6/SP - height 8’-0”– 21 LF
         Wall type – C/8/FTG/01 - height 8’-0”– 27 LF
         Wall type – M1/3 - height 8’-0”– 91 LF
         Wall type – G1/6/NR/02 - height 14-0”– 8 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                              $16,434.00
        ACT-1: 2,169 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                         53,890.00
         Bid Bond 3.1%.                                             $1,670.59

    Scope of work description – (23 - South Dekalb HS)

    Interior Package:                                               $8,856.00
         Wall type – C/6/SP - height 8’-0”– 3 LF
         Wall type – C/6/NR/FTG - height 8’-0”– 6 LF
         Wall type – C/6/NR/FTG/01 - height 8’-0”– 24 LF
         Hard Ceiling – 130 SF.
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
                                        1750 Veterans Memorial Hwy
                                             Austell GA, 30168
                                            Office: 770-739-9671
         Installation of HM frames.

Base Bid Amount                                                            8,856.00
         Bid Bond 3.1%.                                                $274.54

    Scope of work description – (24 - Stone Mountain ES)

    Interior Package:                                                $23,724.00
         Wall type – C/6/NR - height 14”-0”– 100 LF
         Wall type – A5.10/2 - height 14”-0”– 9 LF
         Included:
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                 $1,000.00
        ACT-1: 51 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.
        (Patch and repair only)

Base Bid Amount                                                           24,724.00
         Bid Bond 3.1%.                                                $766.44

    Scope of work description – (25 - Towers HS)

    Interior Package:                                                $10,122.00
         Wall type – C/8/FTG - height 8’-0”– 28 LF
         Wall type – C/8/SP - height 8’-0”– 8 LF
         Included:
         Detail A3.30/5 per Drawing A3.30
         Metal Stup per plan
         Insulation per plan
         5/8” Drywall
         Blocking
         Excluded
         CMU
         Installation of HM frames.

    Acoustic ceiling:                                                 $1,000.00
        ACT-1: 109 SF – 5/8 in x 2 ft x 2 ft Armstrong Dune
        15/16 in Square Lay-In Panel / White – 1772 or Similar.

Base Bid Amount                                                           11,122.00
         Bid Bond 3.1%.                                                $344.78

    Alternate #1.
    Allowance per linear meter for a standard temporary partition,
    including a temporary door.
    Wall: $45.00 per/LF.
    Door: $600.00 per/Pc.

    EXCLUSIONS
                                      1750 Veterans Memorial Hwy
                                           Austell GA, 30168
                                          Office: 770-739-9671
Engineered Shop Drawings
Installation of doors and frames,
Millwork
Demo
Wallcovering
Spray insulation
Rigid insulation
CMU
Concrete
Structural steel
Fire caulking at existing fire rated walls
Access panels
Level 5 finish unless where specified
Night work

QUALIFICATIONS
All jobs are quoted for the current month due to material increase. Please provide 15 days’ notice to
proceed.
We look forward to working with you on this project. If you have any questions, please do not hesitate to
call our Estimating Department at the number provided above.

                                   Roderic Guillen– Estimator 770-739-9671
May 26, 2025

Lefko Construction
105 Mansell Circle
Roswell GA 30075

Re: Chapel Hill MS

 We are pleased to provide pricing for the above refenced project. Plans prepared by SSOE, dated 3-28-25. Our pricing is listed
below.

Included:

     1.   Demo, patch and repair portion of acoustical ceiling With Armstrong A770 Cortega with standard 15/16” grid.
     2.   Modify existing header.
     3.   Blocking at transit window.
     4.   All supervision, equipment, material, labor, insurance, and taxes required to complete this scope of work.

Excluded:

     1.   Demo metal panel ceiling.
     2.   Spray fireproofing.
     3.   All wood and metal blocking.
     4.   All wood items.
     5.   Caulking of penetration.
     6.   Over time premium.
     7.   Trash dumpster, GC to provide.

                                                  Total: $16,334

Addendum 1 acknowledged.

Quote valid for 30 days. Please call if you have any questions.


Daniel Drake




183 Scott RD
Canton Ga 30115
Office: 470-863-5939
Commercial Construction
& General Contractor




                            FLOORING
                          Selected price: Select Floors, inc.




LEFKO CONSTRUCTION
Select Floors, Inc.
                                                                                                                 Estimate
Marietta, GA 30062
1890 West Oak Pkwy                                                                                        Date      Estimate #

                                                                                                     5/23/2025       E11224



         Name / Address

       LEFKO CONSTRUCTION
       Andrea Torres
       105 Mansell Circle,
       Roswell GA 30075




                                                                                                    Rep            Project

                                                                                                    SN

                           Description                                      Qty              Rate                   Total

 Montclair ES Diffuse and Disperse by Shaw Industries                             582                  3.69             2,147.58
 Montclair ES Match Existing Materials                                             35                 10.00               350.00
 Montclair ES Excelon, Imperial Series by Armstrong, 12" x12"                     858                  4.39             3,766.62
x1/8"
 Montclair ES Pinnacle Rubber Base by Roppe                                       400                    3.09           1,236.00
TRANSITIONS                                                                        24                    8.00             192.00

Snapfinger ES Diffuse and Disperse by Shaw Industries                             695                  3.69             2,564.55
Snapfinger ES Match Existing Materials                                             15                 10.00               150.00
Snapfinger ES Excelon, Imperial Series by Armstrong, 12" x12"                     865                  4.39             3,797.35
x1/8"
Snapfinger ES Pinnacle Rubber Base by Roppe                                       448                    3.09           1,384.32
TRANSITIONS                                                                        21                    8.00             168.00

 Chapel Hill ES Diffuse and Disperse by Shaw Industries                           632                  3.69             2,332.08
 Chapel Hill ES Match Existing Materials                                           15                 10.00               150.00
 Chapel Hill ES Excelon, Imperial Series by Armstrong, 12" x12"                   907                  4.39             3,981.73
x1/8"
 Chapel Hill ES Pinnacle Rubber Base by Roppe                                     352                    3.09           1,087.68
TRANSITIONS                                                                        15                    8.00             120.00

Huntley Hills ES Diffuse and Disperse by Shaw Industries                          733                  3.69             2,704.77
Huntley Hills ES Match Existing Materials                                          35                 10.00               350.00
Huntley Hills ES Excelon, Imperial Series by Armstrong, 12" x12"                  930                  4.39             4,082.70
x1/8"
Huntley Hills ES Pinnacle Rubber Base by Roppe                                    398                    3.09           1,229.82

                                                                                        Subtotal

                                                                                        Sales Tax (6.0%)

                                                                                        Total

         Phone #

      (770) 218-3462
                                                                   Page 1
Select Floors, Inc.
                                                                                              Estimate
Marietta, GA 30062
1890 West Oak Pkwy                                                                     Date      Estimate #

                                                                                  5/23/2025       E11224



       Name / Address

     LEFKO CONSTRUCTION
     Andrea Torres
     105 Mansell Circle,
     Roswell GA 30075




                                                                                 Rep            Project

                                                                                 SN

                        Description                      Qty              Rate                   Total

Huntley Hills ES SEALED CONCRETE                               255                    6.50           1,657.50
TRANSITIONS                                                     15                    8.00             120.00

NOTES                                                                                 0.00                0.00T
MINIMUM LABOR PER PERSON 400 / DA     MATERIALS
 10 / S.F FOR MISCELLANEOUS FLOORING MATERIALS




                                                                     Subtotal                       33,572.70

                                                                     Sales Tax (6.0%)                     0.00


                                                                     Total                          33,572.70


       Phone #

     (770) 218-3462
                                                  Page
Commercial Construction
& General Contractor




                             PAINTING
                          Selected price: Modern Paint, co.




LEFKO CONSTRUCTION
Proposal                                        4461 Cary Dr Snellville, GA 30039


Estimator: Janice 678-900-6479                 Email: Info@modernpaintpros.com

 Owner information                                                    Contractor information

 Company               Modern Paint Company                          Company               E&E

 Quote For             GCSO Office                                   Date                  5/29/2025

  Scope of work
 This project is to paint the exterior of building. We will be working closely with the contractors and the customer to provide
 the best quality work and customer satisfaction.
 This proposal is to paint walls marked BY WF01(paint walls to match existing, peel any paint that is coming off) including
 exposed metals, doors and ceiling. For schools listed below;
 Avondale MS // Cedar Grove MS // Chapel Hill ES // Chapel Hill MS // Columbia MS // Eagle Woods Academy //
 Evansdale ES // Fairington ES // Huntley Hills ES // Mary McLeod Bethune MS // Ronald McNair Sr. MS // Miller Grove MS
 // Montclair ES // Montgomery ES // Oakcliff ES // Peachtree MS // Pine Ridge ES // Redan ES // Redan HS // Redan MS
 // Rowland ES // Snapfinger ES // Southwest DeKalb HS // Stone Mountain ES // Towers HS


  Not Included:
 drywall installation, hanging ceiling, painting any areas not listed above


  Company proposal
 Our team will work closely with you throughout the process to ensure that the project is completed on time. We strive to
 give top quality work and customer satisfaction.
 Our estimated budget for this project is $118,900.00, which includes labor, material and equipment. This includes 1 coat
 of primer, 2 of finishing paint, and 20 hours touch ups per location.


                                                                     5/29/2025
 Submitted by Modern Paint                                           Date

  Owner acceptance
 I, ________________________, accept the above scope of work, proposed to be completed by ___________ for the
 amount of $118,900.00



 Submitted by Contractor                                             Date
Cost breakdown
List of materials and costs

Qty.           Column1                     Cost        Total

1              Avondale MS                 $5,000.00   $5,000.00

1              Cedar Grove MS              $5,800.00   $5,800.00

1              Chapel Hill ES              $6,000.00   $6,000.00

1              Chapel Hill MS              $4,900.00   $4,900.00

1              Columbia MS                 $5,000.00   $5,000.00

1              Eagle Woods Academy/GNETS   $4,800.00   $4,800.00

1              Evansdale ES                $5,600.00   $5,600.00

1                                          $4,500.00   $4,500.00
             Fairington ES
1              Huntley Hills ES            $4,900.00   $4,900.00

1              Mary McLeod Bethune MS      $5,000.00   $5,000.00

1              Ronald McNair Sr. MS        $5,000.00   $5,000.00

1              Miller Grove MS             $6,000.00   $6,000.00

1              Montclair ES                $5,800.00   $5,800.00

1              Montgomery ES               $5,000.00   $5,000.00

1              Oakcliff ES                 $5,000.00   $5,000.00

1              Peachtree MS                $5,000.00   $5,000.00

1              Pine Ridge ES               $4,900.00   $4,900.00

1              Redan ES                    $6,000.00   $6,000.00

1              Redan HS                    $6,000.00   $6,000.00

1              Redan MS                    $4,700.00   $4,700.00

1              Rowland ES                  $4,900.00   $4,900.00

1              Snapfinger ES               $4,800.00   $4,800.00

1              Southwest DeKalb HS         $6,100.00   $6,100.00

1              Stone Mountain ES           $6,800.00   $6,800.00
Qty.   Column1                   Cost                Total

1      Towers HS                 $5,100.00           $5,100.00

                                                     $0.00

                                                     $0.00

                                                     $0.00

                                                     $0.00

                                 Tax/Profit Margin   0.00%

                                 Tax

                                 Grand total         $118,900.00




                   Page 2 of 2
                  WHITE LION CONSTRUCTION ENTERPRISES INC


To:            LEFKO Construction                                      Date:                         04/23/2025
Attention:     Cristina Martinez                                       Office:                    678-902-7270
Address:       105 Mansell Cir, Roswell, GA 30075


               JOB NAME                          JOB NUMBER                         JOB ADDRESS
      CMAR - DCSD / Group 2 Security
                                                     20250109                         Georgia - GA
               Vestibules


                   PROPOSAL SUMMARY                                                  AMOUNT
White Lion Construction Enterprises Inc is pleased to present the following bid for CMAR - DCSD - Group 2 Security
Vestibules, based on plans and specifications dated 50/02/2025 and subject to the following inclusions, exclusions and
qualifications.

Drawings ADDENDUM #2

Scope of work description / 1 - Avondale MS

Interior Package:                                                                     $9,523.00
       Paint on walls (CMU and Drywall) – 3,289 SF
       Paint on drywall ceiling – 956 SF
       Paint on HM Framing/Doors – 1 Pc.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                   9,523.00

Scope of work description / 2 - Cedar Grove MS

Interior Package:                                                                     $9,016.00
       Paint on walls (CMU and Drywall) – 3,366 SF
       Paint on drywall ceiling – 948 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                   9,016.00


Scope of work description / 3 - Chapel Hill ES

Interior Package:                                                                    $14.244.00
       Paint on walls (CMU and Drywall) – 5,841 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company



Base Bid Amount                                                                                               14,244.00




                                             www.whitelionce.com
                  WHITE LION CONSTRUCTION ENTERPRISES INC
Scope of work description / 4 - Chapel Hill MS

Interior Package:                                                   $3,809.00
       Paint on walls (CMU and Drywall) – 1,749 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company



Base Bid Amount                                                                  3.809.00


Scope of work description / 5 - Columbia MS

Interior Package:                                                  $15,617.00
       Paint on walls (CMU and Drywall) – 3,289 SF
       Paint on drywall ceiling – 3,812 SF
       Paint on HM Framing/Doors – 7 Pcs.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                 15,617.00


Scope of work description / 6 - Eagle Woods Academy

Interior Package:                                                   $4,795.00
       Paint on walls (CMU and Drywall) – 2,101 SF
       Paint on HM Framing/Doors – 1 Pc.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  4,795.00


Scope of work description / 7 - Evansdale ES

Interior Package:                                                   $3,879.00
       Paint on walls (CMU and Drywall) – 1,793 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  3,879.00




                                             www.whitelionce.com
                  WHITE LION CONSTRUCTION ENTERPRISES INC

Scope of work description / 8 - Fairington ES

Interior Package:                                                   $5,178.00
       Paint on walls (CMU and Drywall) – 2,266 SF
       Paint on HM Framing/Doors – 1 Pc.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company



Base Bid Amount                                                                  5,178.00


Scope of work description / 9 - Huntley Hills ES

Interior Package:                                                  $20,234.00
       Paint on walls (CMU and Drywall) – 8,8679 SF
       Paint on HM Framing/Doors – 7 Pcs.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                 20,234.00


Scope of work description / 10 - Mary Mcleod Bethune MS

Interior Package:                                                  $10,502.00
       Paint on walls (CMU and Drywall) – 3,762 SF
       Paint on drywall ceiling – 949 SF
       Paint on HM Framing/Doors – 1 Pc.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                 10,502.00


Scope of work description / 11 - McNair MS

Interior Package:                                                   $1,926.00
       Paint on walls (CMU and Drywall) – 572 SF
       Paint on drywall ceiling – 331 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  1,926.00




                                             www.whitelionce.com
                  WHITE LION CONSTRUCTION ENTERPRISES INC

Scope of work description / 12 - Miler Grove MS

Interior Package:                                                    $17,173.00
       Paint on walls (CMU and Drywall) – 7,568 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company



Base Bid Amount                                                                   17,172.00


Scope of work description / 13 - Montclair ES

Interior Package:                                                    $18,386.00
       Paint on walls (CMU and Drywall) – 7,430 SF
       Paint on HM Framing/Doors – 4 Pcs.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                   18,386.00


Scope of work description / 14 - Montgomery ES

Interior Package:                                                     $3,146.00
       Paint on walls (CMU and Drywall) – 1,452 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                    3,146.00


Scope of work description / 15 - Oakcliff ES

Interior Package:                                                     $2,944.00
       Paint on walls (CMU and Drywall) – 1,364 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                    2,944.00


Scope of work description / 16 - Peachtree MS

Interior Package:                                                    $13,330.00
       Paint on walls (CMU and Drywall) – 6,150 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                   13,330.00




                                               www.whitelionce.com
                  WHITE LION CONSTRUCTION ENTERPRISES INC

Scope of work description / 17 - Pine Ridge ES

Interior Package:                                                   $6,262.00
       Paint on walls (CMU and Drywall) – 2,772 SF
       Paint on HM Framing/Doors – 7 Pcs.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  6,262.00


Scope of work description / 18 - Redan ES

Interior Package:                                                   $4,569.00
       Paint on walls (CMU and Drywall) – 2,101 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  4,569.00


Scope of work description / 19 - Redan HS

Interior Package:                                                   $5,748.00
       Paint on walls (CMU and Drywall) – 2,660 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  5,748.00


Scope of work description / 20 - Redan MS

Interior Package:                                                  $10,123.00
       Paint on walls (CMU and Drywall) – 3,597 SF
       Paint on drywall ceiling – 948 SF
       Paint on HM Framing/Doors – 7 Pcs.
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                 10,123.00


Scope of work description / 21 - Rowland ES

Interior Package:                                                   $3,090.00
       Paint on walls (CMU and Drywall) – 1,452 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                  3,090.00




                                             www.whitelionce.com
                   WHITE LION CONSTRUCTION ENTERPRISES INC



Scope of work description / 22 - Snapfinger ES

Interior Package:                                                                               $18,400.00
       Paint on walls (CMU and Drywall) – 7,440 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                            18,400.00


Scope of work description / 23 - South Dekalb HS

Interior Package:                                                                                 $3,068.00
       Paint on walls (CMU and Drywall) – 1,598 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                             3,068.00


Scope of work description / 24 - Stone Mountain ES

Interior Package:                                                                                 $9,685.00
       Paint on walls (CMU and Drywall) – 4,466 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                             9,685.00


Scope of work description / 25 - Towers HS

Interior Package:                                                                                 $6,848.00
       Paint on walls (CMU and Drywall) – 2,948 SF
       Included products:
       1. Benjamin Moore & Co.
       2. Sherwin-Williams Company

Base Bid Amount                                                                                                             6,848.00


EXCLUSIONS
Fire caulking at existing fire rated walls
Night work

QUALIFICATIONS
All jobs are quoted for the current month due to material increase. Please provide 15 days’ notice to proceed.
We look forward to working with you on this project. If you have any questions, please do not hesitate to call our Estimating
Department at the number provided above.




                                               www.whitelionce.com
Commercial Construction
& General Contractor




                                  SPRINKLERS
                          Selected price: Chattanooga Fire Protection, inc.




LEFKO CONSTRUCTION
                                                        Atlanta Branch
                                                                                                                        4-24-25
Project Name:
Group 2 Security Vestibules
Dekalb County School System
1780 Montreal Road
Tucker GA 30084
                                                          SCOPE OF WORK

     x    CFP to modify existing Automatic Fire sprinkler system per bid documents, NFPA-13, and local AHJ standards.
     x    CFP scope of work to begin at existing system.
     x    CAD drawings furnished to CFP in a timely manner at no cost.
     x    CFP to utilize black schedule 10 and 40 piping and fittings.
     x    CFP will utilize semi-recessed, or concealed sprinklers standard in color and type.
     x    CFP will provide shop drawings, and material submittals
     x    CFP will provide 1-year written warranty equipment and labor
     x    CFP to provide all necessary permits and permit fees
     x    CFP to perform this work during normal business hours

                                                             EXCLUSIONS

     x    Painting of pipe
     x    Bonding of any type
     x    Nonstandard fire sprinklers in color or type
     x    Davis-Bacon wages
     x    Work necessary due to insufficient coverage of existing shell system/sprinklers
     x    CFP not responsible for insufficient water supply to meet system demand.
     x    Raising of main system piping
     x    Fire Pump(s)
     x    Seismic bracing
     x    Freeze protection and/or Insulation
     x    Water quality analysis
     x    Any after-hours or overtime work applied
     x    No Generator
     x    Electrical wiring
     x    Fire Extinguishers
     x    Payment of any fees associated with accessing sprinkler system to complete scope of work.

                                                         Cost Per Location

Avondale MS = $5,119.00
Cedar Grove MS = $5,119.00
Chapel Hill ES = $6,094.00
Chapel Hill MS = $5,119.00
Columbia MS = $5,119.00
Eagle Woods = $5,119.00

                                               Chattanooga Fire Protection
                                           205 Bell Place Woodstock GA 30188
                                              davidh@chattanoogafire.com
                                                    Cell: 470-246-8145
                                                          Fax: 678-540-2067
                                                         Office: 678-540-2063
Evansdale ES = $5,119.00
Fairington ES = $5,119.00
Huntley Hills ES = $8,863.00
Mary Mcleod = $5,119.00
Mcnair MS = $5,119.00
Miller Grove MS = $5,119.00
Montclair ES = $7,264.00
Montgomery ES = $5,119.00
Oakcliff ES = $5,119.00
Peachtree MS = $5,119.00
Pine Ridge ES = $5,119.00
Redan Es = $5,119.00
Redan HS = $6,260.00
Redan MS = $5,119.00
Rowland ES = $5,119.00
Snapfinger ES = $8,863.00
South Dekalb HS = $5,119.00
Stone Mountain ES = $5,119.00
Tower HS = $5,119.00
                                     Total Cost = $139,724.00

Respectfully Submitted,
David Hendrix




                                    Chattanooga Fire Protection
                                205 Bell Place Woodstock GA 30188
                                   davidh@chattanoogafire.com
                                         Cell: 470-246-8145
                                          Fax: 678-540-2067
                                         Office: 678-540-2063
                                                                                                                                   -RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3
                                                                                                                                   'HNDOE7HFKQRORJ\3DUNZD\b
                                                                                                                                   'RUDYLOOHbb*$bb
                                                                                                                                   b




                                                            -RKQVRQ&RQWUROV)LUH3URWHFWLRQ/34XRWDWLRQ

                   7R                                                                            3URMHFWb'(.$/%&2817<02'6&34b
                   LEFKO GROUP                                                                    -RKQVRQ&RQWUROV5HIHUHQFHb
                   0DQVHOO&LUb                                                               3URSRVDObb
                   5RVZHOOb*$bb                                                             'DWHbb
                                                                                                  3DJHbbRIbb




                                          -RKQVRQ&RQWUROVLVSOHDVHGWRRIIHUIRU\RXUFRQVLGHUDWLRQWKLVTXRWDWLRQIRUWKHDERYHSURMHFW


                                                                            7RWDOQHWVHOOLQJSULFHb

                                                                                        6FRSHRI:RUN

                   'HNDOE&RXQW\6FKRRO0RGLILFDWLRQV9HVWLEXOH&HLOLQJ&KDQJHVEXLOGLQJV$GGDQGUHORFDWHH[LVWLQJSHQGDQWV
                   b




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            AVONDALE
            Scope of work : ADD 9 DEMO 7

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                      1HWVHOOLQJSULFHIRUb$921'$/()2%VKLSSLQJSRLQW $7,143.27

            CEDAR GROVE
            Scope of work : ADD 3 DEMO 2

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /,)76b
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION


                                                   1HWVHOOLQJSULFHIRUb&('$5*529()2%VKLSSLQJSRLQW $8,882.20

            CHAPPLE HILL MS
            Scope of work : ADD 24 DEMO 17

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                               1HWVHOOLQJSULFHIRUb&+$33/(+,//06)2%VKLSSLQJSRLQW $14,457.89

            COLUMBIA




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            Scope of work : ADD 7 DEMO 8

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

                                                       1HWVHOOLQJSULFHIRUb&2/80%,$)2%VKLSSLQJSRLQW $7,960.65

            EAGLE WOOD
            Scope of work : ADD 6 PENDANTS DEMO 6 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                    1HWVHOOLQJSULFHIRUb($*/(:22')2%VKLSSLQJSRLQW $9,104.99

            EVANSDALE
            Scope of work : ADD 6 PENDANTS DEMO 6

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                     1HWVHOOLQJSULFHIRUb(9$16'$/()2%VKLSSLQJSRLQW $6,740.19

            FAIRINGTON
            Scope of work : ADD 10 PENDANTS DEMO 10 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


                                                     1HWVHOOLQJSULFHIRUb)$,5,1*721)2%VKLSSLQJSRLQW $9,568.44

            HUNTLY HILLS
            Scope of work : ADD 24 DEMO 24 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                  1HWVHOOLQJSULFHIRUb+817/<+,//6)2%VKLSSLQJSRLQW $17,469.50

            MARY MCLOAD
            Scope of work : ADD 8 DEMO 8 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

                                                   1HWVHOOLQJSULFHIRUb0$5<0&/2$')2%VKLSSLQJSRLQW $7,730.23

            MCNAIR
            Scope of work : DEMO 4 ADD 4 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                         1HWVHOOLQJSULFHIRUb0&1$,5)2%VKLSSLQJSRLQW $7,228.99

            MILLER GROVE
            Scope of work : ADD 12 PENDANTS DEMO 12

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /,)7b
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

                                                   1HWVHOOLQJSULFHIRUb0,//(5*529()2%VKLSSLQJSRLQW $8,746.01

            MONT CLAIR
            Scope of work : ADD 24 DEMO 31 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                    1HWVHOOLQJSULFHIRUb0217&/$,5)2%VKLSSLQJSRLQW $13,107.60

            MONTGOMERY
            Scope of work : ADD 4 DEMO 4 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

                                                   1HWVHOOLQJSULFHIRUb0217*20(5<)2%VKLSSLQJSRLQW $6,876.82

            OAK CLIFF

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                       1HWVHOOLQJSULFHIRUb2$.&/,)))2%VKLSSLQJSRLQW $7,682.47

            PINE RIDGE
            Scope of work : ADD 10 DEMO 10 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                      1HWVHOOLQJSULFHIRUb3,1(5,'*()2%VKLSSLQJSRLQW $9,751.55

            REDAN ES
            Scope of work : ADD 12 DEMO 12 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




                                                       1HWVHOOLQJSULFHIRUb5('$1(6)2%VKLSSLQJSRLQW $9,528.86

            REDAN MS
            Scope of work : ADD 8 PENDANTS DEMO 8

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                       1HWVHOOLQJSULFHIRUb5('$106)2%VKLSSLQJSRLQW $9,515.24

            REDAN HS
            Scope of work : ADD 12 DEMO 14 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

                                                      1HWVHOOLQJSULFHIRUb5('$1+6)2%VKLSSLQJSRLQW $10,419.97

            ROWLAND
            Scope of work : ADD 12 DEMO 12 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                      1HWVHOOLQJSULFHIRUb52:/$1')2%VKLSSLQJSRLQW $10,349.81

            SNAP FINGER




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            Scope of work : ADD 60 DEMO 60 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION


                                                   1HWVHOOLQJSULFHIRUb61$3),1*(5)2%VKLSSLQJSRLQW $29,034.55

            SOUTH DEKALB
            Scope of work : ADD 8 DEMO 8 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '368%b                                 0LVFHOODQHRXV b
                             '369&b                                3HUPLWVb

                                                  1HWVHOOLQJSULFHIRUb6287+'(.$/%)2%VKLSSLQJSRLQW $8,164.38

            STONE MTN
            Scope of work : ADD 9 DEMO 9 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                      1HWVHOOLQJSULFHIRUb6721(071)2%VKLSSLQJSRLQW $9,062.46

            TOWERS HS
            Scope of work : ADD 10 DEMO 10 PENDANTS

            QTY              MODEL NUMBER                          DESCRIPTION




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                             3URMHFWb'(.$/%&2817<02'6&34b
                                                                                             -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                             3URSRVDObb
                                                                                             'DWHbb
                                                                                             3DJHbbRIbb




            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                     1HWVHOOLQJSULFHIRUb72:(56+6)2%VKLSSLQJSRLQW $9,212.64

            CHAPPEL HILL 2
            Scope of work : DEMO 12 ADD 12

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '35(17$/b                             /LIW(TXLS5HQWDOb
                             '369&b                                3HUPLWVb

                                                  1HWVHOOLQJSULFHIRUb&+$33(/+,//)2%VKLSSLQJSRLQW $8,868.00

            PEACHTREE
            Scope of work : DEMO 9 ADD 9 PENDANT

            QTY              MODEL NUMBER                          DESCRIPTION


            QTY              MODEL NUMBER                          DESCRIPTION

                             '36363&/b                            635,1./(563&/0$7/b

            QTY              MODEL NUMBER                          DESCRIPTION

                             '369&b                                3HUPLWVb

                                                     1HWVHOOLQJSULFHIRUb3($&+75(()2%VKLSSLQJSRLQW $1,464.91

            To the extent applicable, Johnson Controls has included an estimate only for all state and local sales tax for this quote. The actual sales
            tax due will be calculated and billed upon issuance of an invoice, unless a valid exemption and/or resale certificate is received by
            Johnson Controls. Any additional taxes, duties, tariffs or similar items imposed prior to shipment will be charged.




                                                                          )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                               Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
                                                                                                          3URMHFWb'(.$/%&2817<02'6&34b
                                                                                                          -RKQVRQ&RQWUROV5HIHUHQFHb
                                                                                                          3URSRVDObb
                                                                                                          'DWHbb
                                                                                                          3DJHbbRIbb


                                                                                           ,03257$17127,&(72&86720(5
                         This Agreement is contingent on credit approval, which may be checked at JCI’s discretion and requires final approval of a JCI authorized manager before any equipment/
                         services may be provided. Should credit and/or approval be declined, this Agreement will be terminated and JCI’s only obligation to customer will be to notify Customer of such
                         termination and refund any amounts paid in advance.


                         For Customers located in Canada, this Fire Domain Sale and Installation Agreement has been drawn up and executed in English at the request of and with the full concurrence
                         of Customer. Ce contrat a été rédigé en anglais à la demande et avec l’assentiment du client.



                            CUSTOMER ACCEPTANCE:
                            In accepting this Agreement, Customer agrees to the terms and conditions contained herein including those on the
                            following page(s) of this Proposal and any attachments or riders attached hereto that contain additional terms and
                            conditions. It is understood that these terms and conditions shall prevail over any variation in terms and conditions
                            on any purchase order or other document that Customer may issue. Any changes requested by Customer after the
                            execution of this Agreement shall be paid for by the Customer and such changes shall be authorized by the parties
                            in writing. ATTENTION IS DIRECTED TO THE LIMITATION OF LIABILITY, WARRANTY, INDEMNITY AND
                            OTHER CONDITIONS CONTAINED IN THIS AGREEMENT.

                            Customer agrees to pay Johnson Controls pursuant to the progress-based billing schedule of values set forth
                            below. If the schedule of values includes an upfront deposit, it will be paid within 30 days of contract signing and
                            Johnson Controls will not commence work until the upfront deposit is received. Customer agrees to pay for
                            materials, goods, and equipment (ordered, delivered, or stored) pursuant to the schedule of values, prior to
                            installation commencement. The remaining portion of the total price will be progress billed through completion of
                            the work. Johnson Controls progress based billing can also include any services performed on-site or off-site. All
                            invoices will be delivered via Email(), paid via Electronic Funds Transfer and are due PWP (Pay When Paid) from
                            the date of invoice. Electronic Funds Transfer details will be provided upon contract execution. The proposed total
                            price is contingent upon Customer agreeing to these payment and invoicing terms.


                                                                 Planned Monthly Progress Billing Schedule of Values
                                  Item #                                                                Description                                                                      %

                                      1                                                                    Deposit                                                           30%

                                      2                                                                 Mobilization                                                         10%

                                      3                                                                 Engineering                                                          TBD*

                                      4                                                                    Material                                                          TBD*

                                      5                                                                  Installation                                                        TBD*

                                      6                                                              Commissioning                                                           TBD*

                           *To be mutually agreed upon in writing at a later date




                                                                            )LUH6HFXULW\&RPPXQLFDWLRQV6DOHV 6HUYLFH
                                                                 Offices & Representatives in Principal Cities throughout North America
bbbbbk-RKQVRQ&RQWUROV)LUH3URWHFWLRQ/3$//5,*+765(6(59('
Commercial Construction
& General Contractor




                                      HVAC
                          Selected price: Strictly Mechanical, inc.




LEFKO CONSTRUCTION
                                                                    PROPOSAL
                                                    STRICTLY MECHANICAL, INC.
                                                       415 GEES MILL BUSINESS CT., NE
                                                             CONYERS, GA 30013
                                                             Phone (770) 981-2325
                                                                                                                  Page ___1   of ___1__
PROPOSAL SUBMITTED TO                                                                                                     DATE
                                                                                                                          5/2/25
STREET                                                                        JOB NAME
                                                                              CMAR – DCSD – GROUP 2
CITY, STATE AND ZIP CODE                                                      JOB LOCATION

ATTN:




Furnish & install HVAC systems as shown on SSOE M drawings . Plus written specifications aside
from those on prints.
                                            See Next Page for Bldg breakdown & Pricing
All Bldgs:
   • Includes selective demo as shown on M drawings only.
   • Includes ductwork/air distribution as shown. Includes CCI controls for each school.
   • Includes condensate/refrigerant piping for MC equipment only as shown.
   • Includes rigging, startup, permit & warranty.
Clarifications:
Any duct cleaning or work on existing to remain equip or duct -        included       not included
Test & balance -       included       not included
Any louvers or fire dampers not shown on mechanical drawings -           included      not included
Concrete equipment pads/any concrete work -          included     not included
Any gas pipe, gas regulators/med gas piping -        included     not included
Any grading, underground or earthmoving -          included     not included
Any shop drawings -       included       not included
Any service agreement not stated aside from standard one year warranty -          included       not included
Building/roof/wall/floor coring or patches or wall/ceiling access doors -       included      not included
P&P bond -      included       not included – Please add 1% to prices below if needed.
Any ceiling/grid work -      included       not included
Any Davis Bacon wages or federal certified wage scale increases -         included      not included
Any exterior caulking or waterproofing -        included     not included
Any electrical wiring, temporary power, line voltage or disconnects -        included       not included
Any structural steel/structural framing/roof flashing -     included      not included
Any plumbing/floor drains/ or piping that are normally by plumber -         included       not included
Any painting -     included     not included
Payment to be made as follows:
                                                      PROGRESS DRAWS MONTHLY

All material is guaranteed to be as specified. All work to be completed in a workmanlike
manner according to standard practices. Any alteration or deviation from above
specifications involving extra costs will be executed only upon written orders, and will   Authorized Signature    Kevin Beasley
become an extra charge over and above the estimate. All agreements contingent upon
strikes, accidents or delays beyond our control. Owner to carry fire, tornado and other
necessary insurance. Our workers are fully covered by Workman’s Compensation               Note: This proposal may be withdrawn by us if
Insurance.                                                                                 not accepted within 30 days.
Avondale MS – Incl equip/install of 1 EH & slot relocation- $14,450.
Cedar Grove MS – Incl equip/install of 1 EH & slot relocation - $14,450.
Chapel Hill ES – Incl equip/install of 1 AHU split & 1 EF - $65,900.
Chapel Hill MS – Incl equip/install of 1 EH. - $14,400.
Columbia MS – Incl equip/install of 1 EH - $14,250.
Eagle Woods Academy – Add A/D - $13,400.
Evansdale ES – EH Op check - $8,500.
Fairington ES – EF Op check & Add A/D - $14,500.
Huntley Hills – Incl equip/install of 1 AHU split, 1 DSS, VAV relocate & 1 EF - $89,600.
Mary Mcleod MS – Incl equip/install of 1 EH. - $13,600.
McNair MS – A/D Op check - $7,500.
Miler Grove MS – Incl equip/install of 1 EH - $14,200.
Montclair ES – Incl equip/install of 1 AHU split - $68,800.
Montgomery ES – Add A/D - $12,800.
Oakcliff ES – EH Op check - $9,800.
Peachtree MS – A/D Op check & Add A/D- $10,900.
Pine Ridge ES – A/D Op check & Add A/D - $10,900.
Redan ES – A/D Op check & Add 1 EH - $15,500.
Redan HS – A/D Op check & Add 1 EH - $14,500.
Redan MS – A/D Op check & Add 1 EH - $14,800.
Rowland ES – EH & A/D Op check - $9,800.
Snapfinger ES – Incl equip/install of 1 AHU split & 1 EF - $78,900.
South Dekalb HS – A/D Op check - $9,600.
Stone Mountain ES – Incl equip/install of 1 EH - $14,100.
Tower HS – Incl equip/install of 1 EH - $13,600.
                                                                                                         Estimate
                                                                                                DATE        ESTIMATE NO.

                                                                                               5/16/2025      41719-1793B
                                                www.covingtonairsystems.com


  NAME / ADDRESS

Lefko Construction
105 Mansell Circle
Roswell, GA 30075




                                                                                            REP              PROJECT

                                                                                             BH          CMAR DCSD Grou...

                           DESCRIPTION                                        QTY     COST                   TOTAL

CMAR DCSD Group 2

Dekalb School of Arts Avondale MS                                                        11,000.00               11,000.00
Cedar Grove MS                                                                           11,000.00               11,000.00
Columbia MS                                                                              11,000.00               11,000.00
Redan MS                                                                                 11,000.00               11,000.00
Redan ES                                                                                 11,000.00               11,000.00
Above includes
1 unit heater
relocate existing linear grill; and connecting duct work
pre and post Test and balance on heater and grills being relocated
DDC controls
                                                                                                  0.00                0.00

Chapel Hill MS                                                                               9,000.00             9,000.00
Mary McLeod MS                                                                               9,000.00             9,000.00
Miller Grove MS                                                                              9,000.00             9,000.00
Towers HS                                                                                    9,000.00             9,000.00
Above Include
1 new unit heater
DDC Control
NO Test and balance provided on these
cleaning grills if required on M drawings

Fairington ES                                                                                4,000.00             4,000.00
Eagle Woods Academy                                                                          4,000.00             4,000.00
Montgomery ES                                                                                4,000.00             4,000.00
Pine Ridge ES                                                                                4,000.00             4,000.00
above includes
cleaning existing grills


                                                                                    TOTAL

                     P.O. Box 1526 Covington, GA 30015 / 770-385-0068 / Fax: 770-385-0499


                                                                     Page 1
                                                                                              Estimate
                                                                                      DATE       ESTIMATE NO.

                                                                                     5/16/2025     41719-1793B
                                              www.covingtonairsystems.com


  NAME / ADDRESS

Lefko Construction
105 Mansell Circle
Roswell, GA 30075




                                                                                REP               PROJECT

                                                                                   BH         CMAR DCSD Grou...

                          DESCRIPTION                           QTY         COST                  TOTAL

supply and install transfer duct
supply and install transfer duct grill
NO Test and Balance in these schools
NO DDC controls

Rowland ES                                                                         3,000.00            3,000.00
Oakcliff ES                                                                        3,000.00            3,000.00
Evansdale ES                                                                       3,000.00            3,000.00
SW Dekalb HS                                                                       3,000.00            3,000.00
                                                                                       0.00                0.00
NO DDC Controls                                                                        0.00                0.00
above includes
cleaning grills
check for deficiencies in heaters if required
NO Test and Balance included in these estimates

Stone Mtn ES                                                                       9,000.00            9,000.00
Redan HS                                                                           9,000.00            9,000.00
1 new unit heater
DDC Control
NO Test and balance provided on these
cleaning grills if required on M drawings


Chapel Hill ES                                                                 4 ,000.00              4 ,000.00
Includes
demo as shown on M drawing
1 new split system
all duct work
all smoke dampers


                                                                       TOTAL

                     P.O. Box 1526 Covington, GA 30015 / 770-385-0068 / Fax: 770-385-0499


                                                         Page
                                                                                           Estimate
                                                                                    DATE       ESTIMATE NO.

                                                                                   5/16/2025    41719-1793B
                                             www.covingtonairsystems.com


  NAME / ADDRESS

Lefko Construction
105 Mansell Circle
Roswell, GA 30075




                                                                                REP            PROJECT

                                                                                   BH      CMAR DCSD Grou...

                          DESCRIPTION                          QTY          COST                TOTAL

DDC Controls
2 relief hoods
roof condenser equipment rails
roof pitch pocket with cover
1 exhaust fan
all duct insulation
cleaning of grills indicated on M drawings
certified test and balance



Huntley Hills ES                                                               69,000.00           69,000.00
Includes
demo as shown on M drawings
1 mini split system
1 split system
all duct work
all grills and registers
1 roof hood
all dampers
2 certified test and balances
start-up
DDC Controls
roof equipment rails and pitch pockets

Montclaire ES                                                                  56,000.00           56,000.00
Includes
1 demo
1 Certified test and balance
1 new split system


                                                                      TOTAL

                     P.O. Box 1526 Covington, GA 30015 / 770-385-0068 / Fax: 770-385-0499


                                                        Page
                                                                                                Estimate
                                                                                         DATE       ESTIMATE NO.

                                                                                        5/16/2025    41719-1793B
                                                   www.covingtonairsystems.com


  NAME / ADDRESS

Lefko Construction
105 Mansell Circle
Roswell, GA 30075




                                                                                    REP             PROJECT

                                                                                        BH      CMAR DCSD Grou...

                          DESCRIPTION                                QTY         COST                TOTAL

DDC Controls
all duct work
all duct insulation
1 relief vent
clean AH and grills and registers
start-up and test

Snapfinger ES                                                                       57,000.00           57,000.00
Includes
1 demo
2 Certified test and balances
1 new split system
DDC Controls
all duct work
1 relief hood
clean existing AH and grills
start-up and test


Peachtree Charter MS                                                                20,000.00           20,000.00
Includes
1 mini split system
roof equipment rails
roof pitch pan
refrigerant piping
condensate piping
DDC controls
start-up
to add certified test and balance add   1,200.00



                                                                            TOTAL

                     P.O. Box 1526 Covington, GA 30015 / 770-385-0068 / Fax: 770-385-0499


                                                              Page
                                                                                                    Estimate
                                                                                             DATE       ESTIMATE NO.

                                                                                            5/16/2025    41719-1793B
                                                www.covingtonairsystems.com


  NAME / ADDRESS

Lefko Construction
105 Mansell Circle
Roswell, GA 30075




                                                                                           REP          PROJECT

                                                                                            BH      CMAR DCSD Grou...

                          DESCRIPTION                                        QTY     COST                TOTAL

Ronald McNair                                                                           56,000.00           56,000.00
In the addendum s for this school Montclaire ES hvac is in the file
I quoted this the same as Montclaire due to the M drawings in the
addendum file
Please review to see if this is correct




                                                                                   TOTAL                   443,000.00


                     P.O. Box 1526 Covington, GA 30015 / 770-385-0068 / Fax: 770-385-0499


                                                                      Page
Date: 23 April, 2024                                                                H&H Mechanical
To: General Contractors                                                       3270 Humphries Hill Rd
Re: DCSD Vestibule                                                                 Austell, Ga 30106
                                                                                      770-941-5149
                                                                                   www.hhmec.com




H & H Mechanical, Inc is please to offer the following proposal for your consideration:

HVAC Scope of Work:

   1. Avondale MS                               $5700.00
      - Relocate (2) Slot Diffusers
      - Provide Test and Balance, pre and post
      - Provide and install (1) Unit Heater
   2. Cedar Grove MS                            $4550.00
      - Relocate (1) Slot Diffuser
      - Clean (1) Existing Slot Diffuser
      - Provide and install (1) Unit Heater
   3. Chapel Hill ES                            $34675.00
      - Demo existing units as specified
      - Demo existing air distribution as specified
      - Provide and install CU-2/AHU2 with associated air distribution
      - Provide and install modifications to existing air distribution as specified
      - Provide and install new EF-1 and associated ductwork
      - Provide test and balance
      - ADD – Condensate pump for AHU-2
   4. Chapel Hill MS                            $4475.00
      - Clean (2) existing grills
      - Provide and install (1) Unit Heater
   5. Columbia MS                               $4550.00
      - Relocate (1) existing slot diffuser
      - Clean (1) Existing Slot Diffuser
      - Provide and install (1) Unit Heater
   6. Eagle Woods                               $2,555.00
      - Clean (2) existing grills
      - Add (1) Transfer duct with 2 grills
   7. Evansdale ES                              $782.00
      - Check operation of existing heater
   8. Fairington ES                             $2,720.00
      - Clean (1) existing grill
      - Clean and test (1) existing EF
      - Add (1) Transfer duct with 2 grills
Date: 23 April, 2024                                                                H&H Mechanical
To: General Contractors                                                       3270 Humphries Hill Rd
Re: DCSD Vestibule                                                                 Austell, Ga 30106
                                                                                      770-941-5149
                                                                                   www.hhmec.com



   9. Huntley Hills                              $47,630.00
       - Provide Test and Balance, pre and post
       - Demo EF to roof and cap
       - Demo exiting air distribution as specified
       - Relocate existing VAV-3 to new location
       - Demo existing wall mounted heater
       - Provide and install CU-4/AHU4 with associated air distribution
       - Provide and install modifications to existing air distribution as specified
       - Provide and install new EF-1 and associated ductwork
       - ADD – Provide and install (2) Fire Dampers
       - ADD - Hot water piping to VAV
   10. Mary Mcleod                               $4,575.00
       - Provide and install (1) Unit Heater
   11. McNair                                    $1,410.00
       - Clean (3) existing grills
   12. Miller Grove                              $4,475.00
       - Clean (1) existing grill
       - Provide and install (1) Unit Heater
   13. Montclair ES                              $33,950.00
       - Demo existing units as specified
       - Demo existing air distribution as specified
       - Provide and install CU-2/AHU2 with associated air distribution
       - Provide and install modifications to existing air distribution as specified
       - Provide test and balance
   14. Montgomery                                $2,628.00
       - Clean (1) existing supply
       - Add (1) Transfer duct with 2 grills
   15. Oakcliff ES                               $490.00
       - Check operation of existing heater
   16. Peachtree MS                              $13,422.00
       - Clean (4) existing sidewall grills
       - Add (1) R/A lay in
       - ADD - (1) 6000BTU Mini Split system
   17. Pine Ridge                                $2,315.00
       - Clean (4) existing supply diffusers
       - Relocate (1) supply diffuser
       - Add (1) Transfer duct with 2 grills
   18. Redan ES                                  $4,575.00
       - Provide and install (1) Unit Heater
       - Relocate (2) supply diffuser
       - Clean (6) existing grills
Date: 23 April, 2024                                                                     H&H Mechanical
To: General Contractors                                                            3270 Humphries Hill Rd
Re: DCSD Vestibule                                                                      Austell, Ga 30106
                                                                                           770-941-5149
                                                                                        www.hhmec.com
        -
    19. Redan HS                                  $4,475.00
        - Clean (3) existing grills
        - Provide and install (1) Unit Heater
    20. Redan MS                                  $5,725.00
        - Provide test and balance
        - Clean (1) Existing Slot Diffuser
        - Provide and install (1) Unit Heater
    21. Rowland ES                                $1,410.00
        - Clean (2) existing grills
        - Clean and Check (1) heater
    22. Snapfinger ES                             $41,850.00
        - Demo existing unit as specified
        - Clean existing FCU-1 & RTU-6
        - Demo existing air distribution as specified
        - Provide and install CU-2/AHU2 with associated air distribution
        - Provide and install modifications to existing air distribution as specified
        - Provide test and balance
    23. South Dekalb                              $832.00
        - Clean (2) existing grills
    24. Stone Mountain                            $4,475.00
        - Demo existing wall heater
        - Provide and install new ceiling heater
    25. Towers                                    $4,475.00
        - Provide and install new ceiling heater

Clarifications/Exclusions:
   Anything not explicitly included this the HVAC Scope of Work is excluded including but not limited to
    engineering, power wiring, roofing, VFD’s, starters, disconnects, controls other than thermostat, DDC
    controls, BACnet controls, sheetrock cutting/patching, filter change-outs, shop drawings, fire and
    smoke dampers, concrete scanning/cutting/coring/pouring, payment bonds, performance bonds,
    and/or painting, test and balance not specified.
   Others to open, close, and made leak proof all roof penetrations
   Others to terminate HVAC RTU power in factory install service disconnect
   Others to terminate exhaust fan power in service disconnect/switch
   Wall scanning and coring by others
   H&H to provide crane as required to complete HVAC Scope of Work
   H&H to provide scissor lift as required to complete HVAC Scope of Work


Price: $ 238,719.00
Date: 23 April, 2024                                                                  H&H Mechanical
To: General Contractors                                                         3270 Humphries Hill Rd
Re: DCSD Vestibule                                                                   Austell, Ga 30106
                                                                                        770-941-5149
                                                                                     www.hhmec.com


   Price is held for 30 days
   Payment schedule beyond downpayment to be negotiated at contract award
   Payment terms are net thirty days unless otherwise specified

Thank you for considering H&H Mechanical for your HVAC needs. Please call or email with any
questions.




Craig Haldane
Project Manager
chaldane@hhmec.com
Commercial Construction
& General Contractor




                                       ELECTRICAL
                          Selected price: Lost Mountain Electrical Contractors, inc.




LEFKO CONSTRUCTION
    ESTIM ATE
    Lost Mountain Electrical    tedscott@lmecinc.com
    Contractors, Inc            +1 (404) 867-3298
    1825 Corner Road
    POWDER SPRINGS, GA
    301274917




    LEFKO:DCSD Secure Vestibules
    Bill to                                                                               Ship to
    DCSD Secure Vestibules                                                                DCSD Secure Vestibules




    Estimate details
    Estimate no.: 5542
    Estimate date: 05/20/2025




#       Product or service              Description                                             Qty           Rate     Amount


1.                                      If you need breakdowns on these numbers
                                        let me know.
                                        THE FIRE ALARM,ACCESS CONTROL OR
                                        SECURITY WIRING IS NOT INCLUDED.
                                        We did include the boxes and conduits as
                                        needed for everything shown on the
                                        drawings.
                                        We did include the data cables
                                        WE DID NOT INCLUDE ANY PATCH
                                        PANELS
                                        All new lights and controls are included
                                        Reinstalling the existing lights that are being
                                        reused is included


2.      z                               Avondale MS                                                 1     $6,400.00    $6,400.00


3.      z                               Bethune MS                                                  1     $8,550.00    $8,550.00


4.      z                               McNair MS                                                   1     $2,500.00    $2,500.00


5.      z                               Miller Grove MS                                             1     $7,850.00    $7,850.00


6.      z                               Montclair ES                                                1    $43,000.00   $43,000.00
                                        Includes relocating the generator annc, fire
                                        alarm back boxes, conduits and 120 volt
                                        power and relocate the time clock


7.      z                               Montclair ES Relocate panel B                               1     $4,000.00    $4,000.00


8.      z                               Montgomery ES                                               1     $3,900.00    $3,900.00


9.      z                               Oakcliff ES                                                 1     $4,200.00    $4,200.00
10. z                                            Peachtree MS                                           1    $6,850.00    $6,850.00


11. z                                            Pineridge ES                                           1    $2,400.00    $2,400.00


12. z                                            Redan ES                                               1    $7,200.00    $7,200.00


13. z                                            Redan HS                                               1   $10,250.00   $10,250.00


14. z                                            Redan MS                                               1    $8,850.00    $8,850.00


15. Services                                     Cedargrove MS                                          1    $8,300.00    $8,300.00


16. z                                            Rowland ES                                             1    $6,200.00    $6,200.00


17. z                                            Snapfinger ES                                          1   $57,000.00   $57,000.00
                                                 Includes fire alarm back boxes, conduits
                                                 and 120 volt power


18. z                                            South Dekalb MS                                        1   $12,600.00   $12,600.00


19. Services                                     Stone Mtn ES                                           1    $7,750.00    $7,750.00


20. Services                                     Towers HS                                              1    $8,900.00    $8,900.00


21. Services                                     Chapel Hill ES                                         1   $37,250.00   $37,250.00
                                                 Includes fire alarm back boxes, conduits
                                                 and 120 volt power and relocate the time
                                                 clock


22. z                                            Chapel Hill MS                                         1   $10,250.00   $10,250.00


23. z                                            Columbia MS                                            1    $9,400.00    $9,400.00


24. Services                                     Eagle Woods Academy                                    1    $5,800.00    $5,800.00


25. z                                            Evansville ES                                          1    $5,500.00    $5,500.00


26. Services                                     Fairington ES                                          1    $5,600.00    $5,600.00


27. z                                            Huntley Hill                                           1   $70,800.00   $70,800.00
                                                 Includes relocating the generator annc, fire
                                                 alarm back boxes, conduits and 120 volt
                                                 power and relocate the time clock


                                                                                                Total                $361,300.00

    Note to customer
    Let me know if you have any questions,

    Thank you,

    Ted Scott
    Lost Mountain Electrical Contractors, Inc.
    404-867-3298
ESTIM ATE
J & I Cordon Electric, LLC,               quickbooks@cordonelectric.com
License # EN216439                        +1 (770) 682-1706
2996 Lawrenceville Hwy                    www.cordonelectric.com
Lawrenceville, Georgia 30044




Lefko Development INC - Lefko Construction
Bill to                                                                         Ship to
Mr. Tomas Lefko                                                                 CMAR - DCSD - Group 2 Security
105 Mansell Circle,                                                             Vestibules
Roswell,, GA 30075
United States of America




Estimate details
Estimate no.: 24964
Estimate date: 05/16/2025




    Description                                                           Qty                Rate                Amount

    J&I Cordon Electric, LLC. is grateful for the opportunity to                                                   $0.00
    provide a proposal for the above-mentioned project. This
    proposal is solely based on the contract documents that
    includes a stamped & conformed set of drawings &
    specifications supplied by the Architect, Engineer or General
    Contractor. All work will be performed as per 2020 National
    Electrical Code. As Per Electrical Drawings Dated 12/29/2024.


    All the following are inclusions in the base bid:
    • All permitting related to our scope of work. Including any
    subcontractors that J&I Cordon Electric has subcontracted.
    • Project management team is composed of experienced
    project managers and project coordinators.
    • Project manager will run the project and serve as your Single
    Point of Contact (SPOC) for the project lifecycle.
    • Provide & Install receptacles, outlets and switches.
    • Electrical devices rated a per specifications and grounding.
    • Equipment bonding.
    • All inspections.
    • Pricing includes all taxes.


    All the following are exclusions:


    • Material expedition is not included; all material shipments will
    be at the ground shipment or freight level.
    • Service and Maintenance is not included in this contract;
    however, encourages adherence to the manufacturer’s
    recommended maintenance and routine care to ensure
    performance and extend the life of your electrical systems.
    • J&I Cordon Electric, LLC. can provide a separate Service &
    Maintenance Agreement built-to-suit if desired; otherwise,
    additional onsite needs or technical support will be billed as
Time and Mater
• Install Lighting fixture package that meets design
requirements.
• Provide & Install Electrical Gear as per drawings &
specifications.
• Temporary power pole and temporary trailer power up to 1x
installation
• If required all trenching compaction & back-fill. No
replacement of asphalt or concrete.
• All slab conduit runs.
• All Low Voltage Stub Ups & Boxes.
• Fire caulking all of our penetrations.
• Equipment & storage.
• Directional Boring & Coring to be provided by others
• Omissions from Electrical Drawings or Specifications.
• Division 27 (Communication)
• Division 28 (Safety & Security)
• All, except what is listed above, low voltage to be provided by
other.
• Bond is not Included.


Avondale MS                                                         1     $8,943.29     $8,943.29


Cedar Grove MS                                                      1     $7,230.51     $7,230.51


Chapel Hill ES                                                      1    $45,284.15    $45,284.15


Chapel Hill MS                                                      1     $6,288.37     $6,288.37


Columbia MS                                                         1     $8,008.13     $8,008.13


Eagle Woods Academy                                                 1     $4,864.17     $4,864.17


Evansdale ES                                                        1     $6,645.15     $6,645.15


Fairington ES                                                       1     $5,317.05     $5,317.05


Huntley Hills ES                                                    1   $112,754.42   $112,754.42


Mary Mcleod Bethune MS                                              1     $6,873.97     $6,873.97


McNair MS                                                           1     $5,559.67     $5,559.67


Miler Grove MS                                                      1     $9,405.43     $9,405.43


Montclair ES                                                        1    $72,678.62    $72,678.62


Montgomery ES                                                       1     $7,082.18     $7,082.18


Oakcliff ES                                                         1     $5,284.48     $5,284.48


Peachtree MS                                                        1     $6,904.25     $6,904.25


Pine Ridge ES                                                       1     $6,993.83     $6,993.83


Redan ES                                                            1     $6,027.25     $6,027.25


Redan HS                                                            1     $7,945.48     $7,945.48
Redan MS                                                               1    $7,953.98    $7,953.98


Rowland ES                                                             1    $6,247.52    $6,247.52


Snapfinger ES                                                          1   $61,494.42   $61,494.42


South Dekalb HS                                                        1    $9,654.27    $9,654.27


Stone Mountain ES                                                      1    $6,157.94    $6,157.94


Towers HS                                                              1   $11,793.30   $11,793.30


Warranty:


• J&I Cordon Electric, LLC. is committed to providing defect-
free goods and services to its customers. Training, inspection,
testing, documentation, and other processes are followed to
ensure all applicable standards are met.
• J&I Cordon Electric, LLC. warrants all labor to be free of
workmanship defects for a period of 12 months from the date of
substantial completion. During this 12-month period, J&I Cordon
Electric, LLC. will promptly repair, at no cost to the owner.


Hazardous Materials:
• It is the obligation of the General Contractor to determine if the
structure covered by this contract contains asbestos and/or
other hazardous materials. This proposal and contract does not
include any provision (neither monetary provisions nor time-
schedule provisions) to cover the unforeseen hazards or
additional work necessitated by removal of asbestos and/or
other hazardous materials. If asbestos and/or other hazardous
materials are discovered after work is already in progress, and
if the asbestos and/or other hazardous materials represent a
changed condition from those described in the contract
documents, conformed set of drawings & specifications
supplied by the Architect, Engineer or General Contractor. Then
J&I Cordon Electric, LLC. shall be entitled to additional
compensation and an increase in time for completion of the
project.


All agreements contingent upon strikes, accidents, or delays
outside of J&I Cordon Electric's control.
This proposal was prepared according to the information
provided at the time of the proposal; any elements not
specifically identified within this scope of work or provided
information will be considered, ‘Out-of-Scope’, and subject to
the Change Order process.


All the following are Responsibilities:


• Provide adequate manpower to keep up with job progress
and schedule.
• Provide material in a timely manner for a smooth work flow.
• Agree to adhere to SEC standards, provide supervision of
manpower, attend weekly job-site progress meetings, and
follow all job-site and OSHA requirements regarding site safety,
OSHA Regulations, and personal protection equipment.
• Daily job-site cleanup. Trash disposed of in proper containers
daily
• Will caulk all electrical wiring penetrations.
***PLEASE NOTE***


Due to current delays in material manufacturing and shipping, th
is proposal and the scope of work are subject to
change. These items may also result in completion delays and/
or cost adjustments by J&I Cordon Electric at
any time.
Upon receipt of a purchase order and/or subcontract agreeme
nt, and prior to an order acceptance by
J&I Cordon
Electric, this scope of work and the associated Bill of Materials
will be reviewed to confirm
availability of ALL proposed items.
If any items are NOT readily available and/or if a shipment date
cannot be provided by the manufacturer upon receipt
of a purchase order, J&I Cordon
Electric will immediately notify the customer. Once a shipment d
ate is provided,
J&I Cordon
Electric will invoice the project to the customer at the time of mat
erial release and it’s purchase.
Due to the above listed information, J&I Cordon
Electric shall NOT be held liable for any liquidated damages at
any time.


                                                                       Total   $443,391.83




Accepted date                                         Accepted by
                           284 Lakestone Pkwy Woodstock, GA 30188

May 20, 2025
                                 Chapel Hill MS Secure Vestibule
                                   3535 Dogwood Farm Road
                                      Decatur, GA 30034

This Proposal is to furnish the labor and materials necessary for Bass Electric Inc. to install a
complete electrical system per the Plans and Specifications.
Bass Electric Inc. will install a complete electrical system, as mentioned above, for the price of
($25,000.00) Twenty-five thousand dollars and zero cents.

This Proposal includes:
   ●​ Remove any power from demolition area and relocate all other devices to nearby
       suitable location
   ●​ Re-tie lighting once reinstalled to existing lighting circuit
   ●​ Tie new exit sign circuit into nearby existing exit sign circuit
   ●​ Tie new power connection for ID scanner to nearby existing receptacle circuit

Exclusions:
   ●​ Fire alarm systems
   ●​ Parking lot lighting
   ●​ Low voltage (intercom, paging, HVAC controls, security access control, Voice/Data,
      Sound/speakers, security cameras, CATV)
   ●​ Cut-saw and patch pavement and concrete for new conduit
   ●​ Patching, finishing, and painting of drywall

If you have any questions or concerns, please feel free to contact me. Thank you for your
consideration.

                                                                                  Taeed Noparast
                                                                     hossein@basselectricinc.com
                                                                            Office: 678-994-9949
Commercial Construction
& General Contractor




                                 LOW VOLTAGE
                    Selected price: Convergint Technologies, LLC (Safety and Security)




LEFKO CONSTRUCTION
                                                         1955 Evergreen Blvd, Duluth, Georgia 30096
                                                                              Mobile (404) 643-9113
                                                                       paul.franco@convergint.com

 May 29, 2025

Dekalb County School District (“Customer” or “You”)             Quotation:     PF00813954P
DeKalb School of the Arts
1192 Clarendon Ave Avondale Estates, Georgia 30002

Reference: DCSD Group 2 Vestibules
           Rev 2.0

 On behalf of Convergint’s global network of colleagues, I would like to personally thank
 you for providing Convergint with the opportunity to present this proposal addressing your
 electronic security needs.

 The following security proposal is specifically designed to meet your needs. As your single
 point of contact, please feel free to contact me with any additional questions you may
 have. Thank you again for trusting Convergint as your partner.

Scope of Work
   •   Provide and install security equipment for the expansion of access control system
       (ACS), IP video surveillance, and intrusion detection system (IDS) at the following
       locations:
          1. Avondale Middle School                        14. Montgomery Elementary
          2. Cedar Grove Middle School                         School
          3. Chapel Hill Elementary                        15. Oakcliff Elementary School
              School                                       16. Peachtree Middle School
          4. Chapel Hill Middle School                     17. Pine Ridge Elementary
          5. Columbia Middle School                            School
          6. Eagle Woods Academy                           18. Redan Elementary School
          7. Evansdale Elementary                          19. Redan High School
              School                                       20. Redan Middle School
          8. Fairington Elementary                         21. Rowland Elementary
              School                                           School
          9. Huntley Hills Elementary                      22. Snapfinger Elementary
              School                                           School
          10. Mary McCleod Bethune                         23. Southwest DeKalb High
              Middle School                                    School
          11. McNair Middle School                         24. Stone Mountain Elementary
          12. Miller Grove Middle School                       School
          13. Montclair Elementary                         25. Towers High School
              School
•   For all card reader doors added:
        o Convergint to provide and install card readers, access control cabling
        o Electrical Contractor to provide one (1) single-gang box for card reader (42”
            A.F.F.) and conduit stub-up to accessible ceiling.
        o Others to provide one (1) exit device with electric latch retraction hardware
            set on the active leaf closest to the card reader. Convergint to provide lock
            power supply.
                 Electrical contractor to mount and connect 120VAC to lock power
                   supply above accessible ceiling near new vestibule card reader
                   door.
                 Electrical contractor to provide pathway with string within new door
                   frame for electric door hardware.
                 Convergint to provide low-voltage cabling and connect the electrified
                   exit device to the associated lock power supply and ACS.
        o One (1) door contact per leaf
        o Cabling to ACS enclosure (existing or new depending on availability).
                 Convergint to provide and install low-voltage cabling and connect
                   the electric lock power supply to the electric latch retraction
                   hardware.
                 Convergint to provide a two-door controller to connect the door to
                   the LenelS2 OnGuard ACS.
•   Convergint to provide and install two (2) remote release buttons to unlock
    vestibule interior card reader door.
        o One (1) located to the right of the transaction window.
                 Electrical Contractor to provide one (1) single-gang box for release
                   button (42” A.F.F. and/or 8-10” above desk) and conduit stub-up to
                   accessible ceiling.
        o One (1) located by front staff desk(s).
                 Exact location to be determined in coordination with the principal.
                 Electrical Contractor to provide one (1) single-gang box for release
                   button (42” A.F.F. or 0-10” above desk and conduit stub-up to
                   accessible ceiling.
•   For all cameras added:
        o Convergint to provide, device harden, and install IP Video camera.
        o Convergint to surface mount on the drop ceiling interior cameras and
            surface mount exterior cameras.
        o Others to provide and install CAT6 network cabling.
•   Existing equipment to remain as-is, where applicable.
•   All required licensing is included.
•   Cabling and connections to automatic door openers is included, where applicable.
   Device Hardening (reduce cyber risk)
    Convergint may provide Device Hardening services for certain qualifying and scoped
    equipment. Services may include disabling unused & non-essential device features,
    disabling unused network comms (e.g., services, ports), changing default passwords,
    and updating firmware. The hardening services provided will depend on the equipment
    being installed, equipment capabilities, and manufacturer-provided permissions and
    recommendations. Not all equipment may receive hardening. Ask your Convergint
    contact for details on qualifying equipment and the hardening services being provided.

     These are one-time services — ask your Convergint contact for information on how
     Convergint can provide ongoing support.

     Convergint cannot guarantee the security of the devices it installs or of Customer’s
     IT environment, no networked system is completely secure, and Customer remains
     ultimately responsible for its IT environment.

   Pricing Structure

                                   Description                                        Price
PROJECT BASE (Select A or B)
A. New Interior Vestibule Wall and Door: includes 2 release buttons, door access
                                                                                         $13,885.00
  hardware, cabling, and existing camera and/or intrusion device relocation
B. New Exterior Vestibule Wall and Door: includes 2 release buttons, door access
  hardware cabling, intercom (network cabling excluded), and existing camera and/or      $15,525.00
  intrusion device relocation

PROJECT ADD-ONS
C1. New Access Control Enclosure                                                         +$3,970.00
C2. Additional Interior Card Access Door                                                 +$4,525.00
C3. Additional Exterior Card Access Door                                                 +$5,625.00
C4. Intercom (network cabling excluded)                                                  +$1,370.00
C5. Camera (network cabling excluded)                                                    +$1,370.00
C6. New Intrusion Keypad                                                                 +$1,000.00
C7. New Electronic Panic Lock Power Supply                                                +$,840.00
C8. ADA Automatic door opener interconnect                                                +$300.00
     School Breakdown

 #          School             A       B   C1   C2   C3    C4    C5   C6      C7   C8       Price
1    Avondale MS                   1                         1    2            1           $ 18,835.00
2    Cedar Grove MS                1                              2            1           $ 17,465.00
3    Chapel Hill ES                1                              1            1           $ 16,095.00
4    Chapel Hill MS                1                              2            2           $ 18,305.00
5    Columbia MS                   1                              2            1           $ 17,465.00
6    Eagle Woods Academy           1                              1            1           $ 16,095.00
7    Evansdale ES                  1                              1            1           $ 16,095.00
8    Fairington ES                 1        1                1    1            1           $ 21,435.00
9    Huntley Hills ES              1                         1    2            1           $ 23,360.00
10   Mary McCleod Bethune MS       1                         1    2            1           $ 18,835.00
11   McNair MS                                                    1                        $ 1,370.00
12   Miller Grove MS               1                              1            1           $ 16,095.00
13   Montclair ES                  1                         1    2       1    1           $ 19,835.00
14   Montgomery ES                 1                              2            1           $ 17,465.00
15   Oakcliff ES                   1                         1    1            1           $ 17,465.00
16   Peachtree MS                  1        1    1                2            1    1      $ 26,260.00
17   Pine Ridge ES                 1        1                1    1            1           $ 21,435.00
18   Redan ES                      1        1                     1            1           $ 20,065.00
19   Redan HS                      1        1                                  1           $ 18,695.00
20   Redan MS                      1        1                     2            1           $ 21,435.00
21   Rowland ES                    1                              4            1           $ 20,205.00
22   Snapfinger ES                 1                         1    2       1    1           $ 19,835.00
23   Southwest DeKalb HS           1        1                     2            1           $ 21,435.00
24   Stone Mountain ES             1        1                     2            1           $ 21,435.00
25   Towers HS                     1        1                1    2            2           $ 23,645.00



                                                          Total Project        $        $ 470,660.00
                                                          Price
Materials

  Line       Part                        Description                          Manufacturer
          J7-
 1                    4DR E4M 75W 4 LOCK 8 AUX A Wired: 1502/M                    LifeSafety Power
         75BCP4TA
                       Input Control Module (Series three) 12/24 VDC, 16
          LNL-1100-   zone input monitor module, (32) 1K resistors (with 2
 2                                                                                           lenel
         S3           programmable output relays) , RoHS, CE, C-Tick and
                      UL294 certified
                       12V 7AH Rechargeable SLA Battery with F1
 3       738415                                                                       Power-Sonic
                      Terminal
          NC-
 4                    VANDAL RESISTANT READER HID                                       Honeywell
         OP90HON
          LNL-
 5       R11320-      BlueDiamond Mobile Enabled: US Single Gang                             lenel
         05TB
 6        AC-RP26      PANIC BUTTON SS PLT - N/O MOM                                Alarm Controls
                       PIR REQUEST TO EXIT SENSOR WITH                          Bosch Security and
 7       DS160
                      SOUNDER GRAY                                                 Safety Systems
          0E-
 8       SRFMTMG3     3-Wire Surface-Mount Magnetic - SPDT                                ADI Pro
         W
          CM-
 9                    ALL IN ONE STRIKE                                      Camden Door Controls
         CXED1689L
                       12/24 VDC OUTPUT 120 VAC2 RELAYS, POWER
 10      PS902-2RS                                                                      von duprin
                      SUPPLY
                                                                                Bosch Security and
 11      B920         2 LINE ALPHA NUMERIC KEYPAD (SD12)
                                                                                   Safety Systems
                                                                                Bosch Security and
 12      D9127U       POPIT WITH NO TAMPER SWITCH
                                                                                   Safety Systems
                                                                                Bosch Security and
 13      DS936        LOW PROFILE CEILING MOUNT PIR
                                                                                   Safety Systems
 14       444340    22-04 Overall-Shielded Stranded Plenum Wht Jkt                 Windy City Wire
 15       002380    18-04 Unshielded Stranded Plenum Wht Jkt                       Windy City Wire
 16       4461030   4 Element Composite Cable Plenum Ylw Jkt                       Windy City Wire
          SQ-
 17                 12MP Fisheye Camera; AI                                               Hanwha
         XNF9013RV
          SQ-       4K Outdoor Vandal Dome Camera; 3-10mm; AI; IR;
 18                                                                                       Hanwha
         QNVC9083R IP66
          HAN-      2MP INTERCOM, WDR,1.6MM FIXED LEN,
 19                                                                                       Hanwha
         TID600R   TOUCHLESSCALL BUILT-IN MIC
Clarifications and Exclusion


1.  All work proposed herein, shall be performed during normal business hours Monday
    through Friday 8:00 am - 5:00 pm.
2. Low voltage wiring shall be installed via open air code approved methods.
3. Provision or installation of conduit, wire, boxes, fittings or other electrical installation
    materials unless specifically listed under Inclusions or Bill of Materials.
4. Permits or associated fees are not included.
5. Customer to provide static IP addresses and network connections at panel locations.
6. Customer to provide a secured staging & storage area for project related materials.
7. Pricing assumes that electronic Auto CAD files are available from customer for our
    use in creating submittal drawings.
8. Fifty percent (50%) of the proposed sell price shall be payable to Convergint for
    project mobilization. Mobilization shall be invoiced and due upon customer
    acceptance of this proposal.
9. Proposal does not include sales tax unless otherwise noted.
10. Anything in the Contract Documents notwithstanding, in no event shall either
    Contractor or Subcontractor be liable for special, indirect, incidental or consequential
    damages, including commercial loss, loss of use, or lost profits, even if either party
    has been advised of the possibility of such damages.
11. Convergint reserves the right to negotiate mutually acceptable contract terms and
    conditions with customer by making mutually agreeable changes to the formal
    contract included in the Bid Documents.
12. Supply Chain Delays & Price Adjustments: Customer acknowledges that supply
    chain disruptions and shipping delays may occur for reasons beyond Convergint’s
    reasonable control and agrees to grant reasonable extensions for such delays.
    Pricing is based on current market conditions and excludes increases due to tariffs,
    duties, manufacturer-imposed surcharges, or other cost increases arising from trade
    policy, regulatory actions, or external factors beyond Convergint’s control. If such
    cost increases arise, Convergint will submit a formal change order, and Customer
    agrees to approve reasonable adjustments. Convergint will use commercially
    reasonable efforts to minimize such increases.

 REVIEW IMPORTANT PRODUCT SAFETY AND SERVICE INFORMATION PRIOR
 TO USING A CONVERGINT-INSTALLED SYSTEM: See the “IMPORTANT
 PRODUCT SAFETY AND SERVICE INFORMATION” documentation, available at
 convergint.com/terms.
                                          IMPORTANT NOTICE
You requested that Convergint provide you with certain security and safety products and services.
By using these products and services, you acknowledge that:
•   Under no circumstances should Convergint-provided products and services be your sole
    method of security or safety. Effective security and safety require a multi-layered approach involving
    people, processes, and technologies. Convergint-provided products and services do not guarantee
    security or safety, will not detect or prevent all threats or risks all the time (including threats they are
    designed to detect), and will not ensure overall safety and security. You are ultimately responsible for
    your people, premises, and property, including for maintaining an effective response plan and promptly
    implementing your response plan in response to alarms or threats.
•   All security products and services have limitations. No product or service can guarantee safety or
    security. It is your responsibility to ensure you are informed about product or service limitations and
    that you regularly test and validate the products and safety plans. Reach out to your Convergint
    account executive to learn how our support services can help. And if you have a service plan, you are
    responsible for promptly notifying Convergint in the event of any defect, malfunction, or performance
    issue with the products and services.
•   Various factors can impact product performance. Selecting products and settings may involve
    tradeoffs between the level of security and safety on the one hand and speed, convenience, and cost
    on the other hand. Convergint can give you guidance, but you are ultimately responsible for selecting
    products and settings based on your organization’s risk profile and tolerance.
•   The products are made by third-party manufacturers, not Convergint. You are bound by and must
    use, test, and maintain the products in accordance with the manufacturer’s terms and instructions.
    Convergint does not independently validate the accuracy of claims or statements made by
    manufacturers, and makes no assurances regarding their accuracy. You are responsible for using the
    products and services in compliance with laws and regulations applicable to you or as permitted in your
    jurisdiction.
•   All products and services are governed exclusively by a final agreement. No advertisement,
    literature, brochure, website, or statements made during the sale process or otherwise (whether orally or
    in writing) should be interpreted as a promise, warranty, or other assurance.
•   You have reviewed the “IMPORTANT PRODUCT SAFETY AND SERVICE INFORMATION”
    documentation, available at convergint.com/terms.
Total Project Investment:                                       $ 470,660.00


Thank you for considering Convergint for your Security needs. If you have any questions
or would like additional information, please don't hesitate to contact me immediately. If you
would like to proceed with the scope of work as outlined in this proposal, please sign below
and return to my attention.


Sincerely,

[{SLFN}] [{SLLN}]
Convergint
[{SLFN}] [{SLLN}]

By signing below or accepting the services described in this proposal, Customer accepts
and agrees to this proposal, including the enclosed Terms and Conditions, along with any
addendums or exhibits that may be attached or referenced therein. Any additional or
contrary terms, including on a Customer PO, are expressly rejected. By signing, you
represent and warrant that you have authority to accept this proposal on behalf of Customer.


                    [{CUCN}]                                          May 29, 2025
             Customer Name (Printed)                                       Date




               Authorized Signature                                        Title
Commercial Construction
& General Contractor




                                 LOW VOLTAGE
                 Selected price: Integrated Communication Networks, inc. (Data Cabling)




LEFKO CONSTRUCTION
 Integrated Communication Networks, Inc.

                                                                                      Quote
                                                                                      Revised 5/22/2025
                                                           PO NUMBER:
                                                           WO NUMBER:
                                                           DCSD Ticket Number

CUSTOMER:                                                  BILL TO:
Lefko Group
Chapel Hill MS


POC:
START DATE:

JOB DESCRIPTION
Install 2 data drop for new Cameras in Vestibule
Install 1 Duplex data drop for new Location.
Quoted from Drawings E1.01
No LV Demo Needed.
After hours and weekend rates included

See Attached for location and list all Hrs and work done
LABOR
 HOURS     SERVICE PERSON               DESCRIPTION               RATE                   QUANTITY             TOTAL
                                      Service              $             100.00             1             $       100.00

          0                                                                                  SUB TOTAL $          100.00

PARTS                                                                                           TOTAL     $       100.00
  ITEM        PART NUMBER             DESCRIPTION               QUANTITY                UNIT COST
    1            Yellow            Yellow Cat 6a Cam               2              $             365.00    $       730.00
                  Blue             Blue Cat 6a Data                2              $             365.00    $       730.00
                                   Wiremold                        1              $             120.00    $       120.00
                                   Misc                                           $              50.00    $          -

                                                                                  LABOR                   $        100.00
DATE                                                                              MATERIAL                $      1,580.00
                                                                                  TAX/HANDLING
TIME IN                                                                           TOTAL                   $      1,680.00

TIME OUT

CUSTOMER SIGNATURE
                                   Signature                                   Print Name
                                            5108 Minola Dr. Lithonia GA. 30038
                                      Phone: (470) 545-5425       Fax: (470) 545-5464
                                                Website: www.icnpros.com
Commercial Construction
& General Contractor




                                LOW VOLTAGE
                  Selected price: South Western Communications of Atlanta (Intercom)




LEFKO CONSTRUCTION
                       DeKalb County School District -
                          Group 2 Security Vestibules-
                                   Rauland Intercoms

                                     3630 Shallowford Rd NE
                                         Doraville, GA 30340




Proposal for
DEKALB CO SCHOOL DISTRICT
(GA)




                                          SWC of Atlanta
                              70 Crestridge Dr., Suite 100
                                     Suwanee, GA 30024


                  blake.schindler@swc.net | 404.787.5420
                                        sales@swc.net |
                                               May 21, 2025
                                      Proposal valid for 30 days.
                                          www.swc.net | 2


TABLE OF CONTENTS

Content                                            Page
Scope of Work                                            3
Cost of Proposal                                         8
Terms and Conditions                                    10




                                                               SWC of Atlanta
                       blake.schindler@swc.net | 404.787.5420
                                             sales@swc.net |
                        Confidential. Not to be shared without express written permission by SWC.
                                                                                              www.swc.net | 3




                                          Scope
SWC is pleased to offer this quote for the following systems based on bid documents:
- Rauland Legacy Intercom Systems with Rauland TCU Overlay
- Rauland TCU Hybrid Systems

Architect/Engineer: SSOE Project/reference number: 024-01028-14

Specification(s) dated:
- No specification sections applicable to SWC’s Scope of Work

Addenda, clarification(s), Add/Alternates, etc included:
- Addendum 1- 4/25/2025
- Addendum 2- 5/01/2025

Unsolicited additions/alternates included:
- Included pre and post construction tests for the Rauland Intercom System at each site. This is
needed to insure the existing systems in the front office are functioning properly before and
after the renovations in these area are made.

Notable deviations from the drawings:
- Drawings provided do not depict the speakers currently installed as well as locations of
equipment needed to keep the existing Rauland intercom systems functional. See breakdown of
proposed scope at each site below.

Additional notes or scope:
- Price does not include any conduit, back cans, coring, boring, or 110v power.
- All work is to be performed outside of normal business hours.
- Unless defied as such under per site scope below, all existing cable, speakers, call buttons, and
Rauland Intercom components will be reused as part of this project.
- All CAT6 data cable by others. Price is not covered in this proposal.
- The construction documents did not contain modifications needed to keep the existing
Rauland intercom systems functional.
- Chapel Hill ES, Huntley Hill ES, Montclair ES, and Snapfinger ES show a data rack being
relocated to the new front office. The rack depicted is the existing Rauland legacy intercom and
will be relocated as shown.
- See breakdown of proposed scope at each site below.


                                                                                                                   SWC of Atlanta
                                                                          blake.schindler@swc.net | 404.787.5420
                                                                                                sales@swc.net |
                                                                            Confidential. Not to be shared without express written permission by SWC.
                                                                                            www.swc.net | 4




                               Scope (cont)
***Many of these modifications are to systems that have been discontinued, and
replacement parts are no longer available. These systems will be referred to as Rauland
“legacy” Intercom systems. SWC will not be responsible for replacing, repairing or providing
any warranty on these Rauland legacy Intercom systems. ***

SWC Scope of work per site:
1. Dekalb Arts Academy @ Avondale MS- 3131 Old Rockbridge Road Avondale Estates, GA,
30002
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
2. Cedar Grove MS - 2300 Wildcat Road Decatur, GA, 30034
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
3. Chapel Hill ES - 3536 Radcliffe Boulevard Decatur, GA, 30034
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Relocation of the existing Rauland legacy Intercom cabinet to new front office location as
depicted on ED1.01 and E2.01. SWC will create a junction above the ceiling and install new
cabling to the new Intercom cabinet location.
• Remove and reinstall speakers as needed in renovated area on E2.01
4. Chapel Hill MS - 3535 Dogwood Farm Road Decatur, GA, 30034
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
5. Columbia MS - 3001 Columbia Dr Decatur, GA, 30034
• Pre and post construction test on the existing Rauland Legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
6. Eagle Woods Academy/GNETS - 5931 Shadow Rock Dr Lithonia, GA, 30058
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
7. Evansdale ES - 2914 Evans Woods Dr. Doraville, GA, 30340
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.0




                                                                                                                 SWC of Atlanta
                                                                         blake.schindler@swc.net | 404.787.5420
                                                                                               sales@swc.net |
                                                                          Confidential. Not to be shared without express written permission by SWC.
                                                                                             www.swc.net | 5




                                Scope (cont)
8. Farrington ES- 5505 Phillip Bradley Dr Lithonia, GA, 30038
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
9. Huntley Hills ES- 2112 Seaman Circle Chamblee, GA, 30341
• Pre and post construction test on the existing Rauland legacy Intercom system
• Relocation of the existing Rauland legacy Intercom cabinet to new front office location as
depicted on ED1.01 and E2.01. SWC will create a junction above the ceiling and install new
cabling to the new Intercom cabinet location.
• *Not included in this price*- DCSD’s preferred data contractor will need to provide five (5)
orange cat 6 cables from the IDF closet to the new intercom location.
• Relocate the existing red panic button to the new front office location.
• Furnish and install one new call button, speaker and associated cable in room 98, as
depicted on E2.01.
10. Mary McLeod Bethune MS - 5200 Covington Hwy Decatur, GA, 30035
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.02
11. Ronald McNair Sr. MS - 2190 Wallingford Drive Decatur, GA, 30032
• Pre and post construction test on the existing Rauland Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
12. Miller Grove MS- 2215 Miller Rd Decatur, GA, 30035
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.02
13. Montclair ES - 1680 Clairmont Place, NE Atlanta, GA, 30329
• Pre and post construction test on the existing Rauland legacy Intercom system
• Relocation of the existing Rauland legacy Intercom cabinet to new front office location as
depicted on ED1.01 and E2.01. SWC will create a junction above the ceiling and install new
cabling to the new Intercom cabinet location.
• *Not included in this price*- DCSD’s preferred data contractor will need to provide five (5)
orange cat 6 cables from the IDF closet to the new intercom location.
• Relocate the existing red panic button to the new front office location.
• Remove and reinstall speakers as needed in renovated area on E2.01




                                                                                                                  SWC of Atlanta
                                                                          blake.schindler@swc.net | 404.787.5420
                                                                                                sales@swc.net |
                                                                           Confidential. Not to be shared without express written permission by SWC.
                                                                                             www.swc.net | 6




                                Scope (cont)
14. Montgomery ES - 3995 Ashford-Dunwoody Rd. Atlanta, GA, 30319
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
15. Oakcliff ES - 3150 Willow Oak Way Doraville, GA, 30340
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
16. Peachtree MS- 4664 North Peachtree Road Atlanta, GA, 30338
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
17. Pine Ridge ES - 750 Pine Ridge Drive Stone Mountain, GA, 30087
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
18. Redan ES - 1914 Stone Mountain-Lithonia Road Lithonia, GA, 30058
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
19. Redan HS - 5247 Redan Road Stone Mountain, GA, 30088
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
20. Redan MS- 1775 Young Rd Lithonia, GA, 30058
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
21. Rowland ES- 1317 S. Indian Creek Drive Stone Mountain, GA. 30083
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
22. Snapfinger ES - 1365 Snapfinger Road Decatur, GA, 30032
• Pre and post construction test on the existing Rauland legacy Intercom system
• Relocation of the existing Rauland legacy Intercom cabinet to new front office location as
depicted on ED1.01 and E2.01. SWC will create a junction above the ceiling and install new
cabling to the new Intercom cabinet location.
• *Not included in this price*- DCSD’s preferred data contractor will need to provide five (5)
orange cat 6 cables from the IDF closet to the new intercom location.
• Relocate the existing red panic button to the new front office location.
• Remove and reinstall speakers as needed in renovated area on E2.01




                                                                                                                  SWC of Atlanta
                                                                          blake.schindler@swc.net | 404.787.5420
                                                                                                sales@swc.net |
                                                                           Confidential. Not to be shared without express written permission by SWC.
                                                                                         www.swc.net | 7




                              Scope (cont)
23. Southwest DeKalb HS - 2863 Kelley Chapel Road Decatur, GA, 30
• Pre and post construction test on the existing Rauland TCU Hybrid Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
24. Stone Mountain ES- 6720 James B. Rivers Dr Stone Mountain, GA, 30083
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01
25. Towers HS -3919 Brookcrest Circle Decatur, GA, 30032
• Pre and post construction test on the existing Rauland legacy Intercom system
• Remove and reinstall speakers as needed in renovated area on E1.01




                                                                                                              SWC of Atlanta
                                                                      blake.schindler@swc.net | 404.787.5420
                                                                                            sales@swc.net |
                                                                       Confidential. Not to be shared without express written permission by SWC.
                                                                                             www.swc.net | 8




                      Pricing Summary
OFFER: In accordance with the Scope of Work and Terms and Conditions attached hereto,
SWC is pleased to offer this pricing, valid through 6/20/2025, for the following project:



DeKalb County School District - Group 2
Security Vestibules                                   REF #: 64104_EST_1

 ESTIMATE GROUP                                           TOTAL PRICE
Avondale MS                                                                                  $4,255.29

Cedar Grove MS                                                                               $4,255.29

Chapel Hill ES                                                                             $28,003.29

Chapel Hill MS                                                                               $4,255.29

Columbia MS                                                                                  $4,255.29

Eagle Woods Academy                                                                          $3,095.67

Evansdale ES                                                                                 $3,095.67

Fairington ES                                                                                $3,095.67

Huntley Hills ES                                                                           $16,345.39

Mary McCleod Bethune MS                                                                      $4,255.29

McNair MS                                                                                    $4,255.29

Miller Grove MS                                                                              $4,255.29

Montclair ES                                                                               $22,459.67

Montgomery ES                                                                                $3,095.67
                                                          Pricing Summary continues next page...




                                                                                                                  SWC of Atlanta
                                                                         blake.schindler@swc.net | 404.787.5420
                                                                                               sales@swc.net |
                                                                           Confidential. Not to be shared without express written permission by SWC.
                                                                                                                                       www.swc.net | 9




                Pricing Summary (cont.)



 ESTIMATE GROUP                                                                             TOTAL PRICE
Oakcliff ES                                                                                                                            $3,095.67

Peachtree Charter MS                                                                                                                   $4,255.29

Pine Ridge ES                                                                                                                          $3,365.95

Redan ES                                                                                                                               $4,049.37

Redan HS                                                                                                                               $4,795.85

Redan MS                                                                                                                               $4,255.29

Rowland ES                                                                                                                             $3,365.95

Snapfinger ES                                                                                                                        $23,727.52

Southwest Dekalb HS                                                                                                                    $4,255.29

Stone Mountain ES                                                                                                                      $3,095.67

Towers HS                                                                                                                              $4,255.29




                                                         SUB-TOTAL:                                                                $171,495.20
                                                         TAX:                                                                        $1,317.39


                                                         TOTAL:                                                                    $172,812.59
       Per my authority as an executing agent, please accept this as an intent to award and enter into a contractual agreement with SWC.




                                                                                                                                                            SWC of Atlanta
                                                                                                                   blake.schindler@swc.net | 404.787.5420
                                                                                                                                         sales@swc.net |