vii. Easement Request for New Dresden Elementary School Site ~ Catholic Education of North Georgia, Inc. (St. Pius X Catholic HS) ~ Temporary Construction Easement and Parking and Access Easement~ New Dresden Elementary School Site Overflow Parking Lot

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that DeKalb County Board of Education (“the Board”) approve a temporary construction easement and a parking and access easement from Catholic Education of North Georgia, Inc. to DeKalb County School District (“DCSD”) to facilitate construction of the New Dresden Elementary School.
Why: Approval of the easement requests will allow the DCSD to perform temporary construction activities during the construction of the New Dresden Elementary School. The parking and access easement provides for a temporary parking lot supporting overflow parking and access on the St. Pius X Catholic High School back lot during construction of the New Dresden Elementary School. This overflow parking lot request is connected to the Capital Improvement Project#21836 - New Dresden Elementary School.
Details: On August 31, 2023, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Winter Construction Company for the completion of the New Elementary School at Dresden Project. The Capital Improvement Project #21836 - New Dresden ES is currently under construction and is anticipated to be completed by August 31, 2027.

The Dresden Elementary School site is a small, 9-acre site with construction on an active school site. The District has maintained a great relationship with the neighboring St. Pius X Catholic High School. During the design and construction of the new Dresden site, St. Pius has been tremendously helpful and approved the overflow parking lot plan.

The temporary construction easement will allow the contractors for the New Dresden ES rebuild to perform temporary construction activities and construct the overflow parking lot. The temporary construction easement will expire upon completion of the new school.

The parking and access easement is a perpetual easement facilitating ingress and egress to the construction site and parking lot. The easement consists of the use of eighty-eight (88) unreserved, non-exclusive parking spaces within the parking easement area. Once construction is complete and the new school is open, St. Pius will reserve the right to retain the parking lot as a surplus lot or request that the DCSD return the lot to its previous vegetation state.
Financial impact: No Financial Impact to the District
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676.1470
Mr. Hans G. Williams, Director of Planning & E-SPLOST Programming, Division of Operations, 678.676.158
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
                                                                                     Approx. Location of GA Power Easement



                                  Front Entry Enabling Work



                                                              School Access Remains Open




                                                              Temporary Road for Fire Truck Access
                                     Material Laydown Area
                                                              Gym Remaining Through Phase 3
                            Relocated Playground Equipment


                                                              Modular Classrooms Prep Work
 Phase 1A
 Temporary Fire Lane to Backside of Gym                       Temporary Fence Around Modulars
 Construction Fence Installation
 Material Laydown
 UG Sitework/Prep at Modular Classroom Staging Area
 Relocate Playground Equipment to East Green Space

Dresden Elementary School
Site Logistics – Phase 1A
                                                                                           Approx. Location of GA Power Easement
                                            Construction Entrance

                                                Construction Road




                                                                    School Access Remains Open




                                     Winter Construction Office
                                                                    Temporary Road for Fire Truck Access
                                            Material Laydown Area
                                                                    Gym Remaining Through Phase 3
                              Relocated Playground Equipment
                                                                    Modular Classrooms – 8 Rooms

                                                                    New Concrete Walkway Installed

                                                                    Modular Classrooms – 12 Rooms
 Phase 1B
 Winter Construction Trailer Mobilization
 Modular Classroom Mobilization

Dresden Elementary School
Site Logistics – Phase 1B
                                                                                         Approx. Location of GA Power Easement




                               Temporary Construction Fencing

    Install Shoring Against Existing School Prior to Construction   School Access Remains Open



                                   Demolish Existing Structures

                                Phase 2 West Hardscape Work

                                                                                Exit Path During Construction
               Mobile Crane – Phase 1 Erection South to North



                                                                                Proposed Drive and Added Staff Parking Easement
                                     Winter Construction Office
                                                                                Temporary Road for Fire Truck Access

                                                                                Gym Remaining Through Phase 3
                              Relocated Playground Equipment
                                                                                Modular Classrooms – 8 Rooms

                                                                                Walkway Between Modulars
 Phase 2
 Shoring
                                                                                Modular Classrooms – 12 Rooms
 Phase 1 Demolition
 Mobile Crane
 Erect Phase 1
 East Loop Paving, Curbing, and Striping

Dresden Elementary School
Site Logistics – Phase 2
                                                                          Approx. Location of GA Power Easement


                                           Construction Road
                                                                 Construction Entrance



                                                                 Construction Fence

                                                                 Erect Phase 2 New Structure


                                                                 Demolish Phase 2 Existing Structures

                      Phase 2 West Hardscape Work Finished



                                Exit Path During Construction
                                                                 Phase 3 Hardscape

                                                                 Proposed Drive and Added Staff Parking Easement
                                    Winter Construction Office
                                                                 Temporary Road for Fire Truck Access

                                                                 Gym Remaining Through Phase 3
                            Relocated Playground Equipment
                                                                 Modular Classrooms – 8 Rooms

                                                                 Walkway Between Modulars

 Phase 3                                                         Modular Classrooms – 12 Rooms
 Phase 2 Demolition
 Relocation of Construction Fence
 Construction Road
 Erect Phase 2

Dresden Elementary School
Site Logistics – Phase 3
                                                                                                Approx. Location of GA Power Easement




                                                                       Final Coat and Striping of all Permanent Asphalt Areas




                                                                                      Proposed Drive and Added Staff Parking Easement

                                  Winter Construction Office Removed

                                                                                      Demolish Fire Truck Turnaround
    Balance of Site & Existing Playground Equipment Removal                           Demolish Gymnasium

                                                                                      Phase 4 Fencing Once Modulars / Trailer Removed

                                                                                      Modular Classrooms – Demobilization
 Phase 4
 Modular Classroom Demobilization
 Gym Demolition
 Remaining Sitework at Modular Classroom Staging Area
 Balance of Paving, Curbing, and Striping

Dresden Elementary School
Site Logistics – Phase 4