Kingsley Elementary Long Lead Time Schedule

AID 1867337 · View on Simbli

Agenda Item

i. E-SPLOST V ~ Capital Improvement Project ~ Contract ~ Guaranteed Maximum Price (GMP) ~ Equipment Purchase for Project # 36335 ~ Kingsley Elementary School HVAC System Replacement and Renovations ~ Evergreen Construction, Inc. (Not to exceed $1,581,100)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve the Equipment Purchase Guaranteed Maximum Price (GMP), not to exceed $1,581,100 for the Capital Improvement Project #36335 - Kingsley Elementary School HVAC System Replacement and Renovations.
Why: Approval of the Guaranteed Maximum Price (GMP) with Evergreen Construction for the Equipment Purchase is necessary for the Capital Improvement Project #36335 - Kingsley Elementary School HVAC System Replacement and Renovations. There are currently extended lead times on shipping equipment. For the project to remain on schedule, all equipment for the HVAC renovation project must be ordered for construction completion by Summer 2026.
Details: On May 12, 2025, the Board approved the award of a Construction Manager at Risk (“CMAR”) contract to Evergreen Construction for the Capital Improvement Project #36335 - Kingsley Elementary School HVAC System Replacement and Renovations.

Pursuant to that agreement, the Design Professional (SSOE | Stevens & Wilkinson), Construction Manager (Evergreen), Program Manager (HPM), and DCSD Operations collaborated on an equipment order and equipment GMP in the best interest of the DeKalb County School District.

This action establishes the Equipment Purchase GMP for all the Work set forth in the attached “Exhibit M” for Kingsley ES.
Financial impact: The total contract amount for these services will be allocated from the E-SPLOST V Capital Improvement Project #36335 -Kingsley Elementary School HVAC System Replacement and Renovations budget in the not to exceed amount of $1,581,100. Cost Code: SP5FACCON.36335.GENCONTR
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1470
Mr. Hans Williams, Director. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
Activity Name                                                   Original Start        Finish      2025                                                          2026                                  2027
                                                               Duration
                                                                                                    Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
     Kingsley Elementary School Procurement                        278 14-Aug-25 A 01-Jun-26

        Preconstruction                                              50 14-Aug-25 A 16-Oct-25
           Construction Documents                                     0 14-Aug-25 A                       Construction Documents
           Early Release GMP                                         14 28-Aug-25     10-Sep-25               Early Release GMP
           Subcontractor Bidding                                     28 29-Aug-25     25-Sep-25                  Subcontractor Bidding
           GMP Preparation                                            7 26-Sep-25     02-Oct-25                   GMP Preparation
           GMP Review & Approval                                     14 03-Oct-25     16-Oct-25                     GMP Review & Approval

        DCSD Board Meetings                                          82 10-Sep-25     01-Dec-25
           Deadline for October Board Meeting                         0               10-Sep-25*              Deadline for October Board Meeting
           October School Board Meeting                               0 06-Oct-25*                                October School Board Meeting
           Early Release GMP Execution                               57 06-Oct-25     01-Dec-25                               Early Release GMP Execution
           November School Board Meeting                              0 10-Nov-25*                                         November School Board Meeting

        Material Procurement                                       239 06-Oct-25      01-Jun-26

           Electrical Components                                   239 06-Oct-25      01-Jun-26
                Electrical Switchgear Submittals                      2 06-Oct-25     07-Oct-25                    Electrical Switchgear Submittals
                Switchgear Review & Approvals                        14 08-Oct-25     21-Oct-25                      Switchgear Review & Approvals
                Switchgear Fabrication & Delivery                  182 02-Dec-25      01-Jun-26                                                                 Switchgear Fabrication & Delivery
                Release Switchgear for Fabrication                    0 02-Dec-25                                              Release Switchgear for Fabrication
           HVAC Equipment                                          197 06-Oct-25      20-Apr-26
                ERU/DOA Submittal Preparation                        14 06-Oct-25     19-Oct-25                      ERU/DOA Submittal Preparation
                WSHP Submittal Preparation                           14 06-Oct-25     19-Oct-25                      WSHP Submittal Preparation
                RTU Submittal Preparation                            14 06-Oct-25     19-Oct-25                      RTU Submittal Preparation
                Pumps Submittal Preparation                          14 06-Oct-25     19-Oct-25                      Pumps Submittal Preparation
                Cooling Tower Submittal Preparation                  14 06-Oct-25     19-Oct-25                      Cooling Tower Submittal Preparation
                ERU/DOA Submittal Review & Approval                  14 20-Oct-25     02-Nov-25                           ERU/DOA Submittal Review & Approval
                WSHP Submittal Review & Approval                     14 20-Oct-25     02-Nov-25                           WSHP Submittal Review & Approval
                RTU Submittal Review & Approval                      14 20-Oct-25     02-Nov-25                           RTU Submittal Review & Approval
                Pumps Submittal Review & Approval                    14 20-Oct-25     02-Nov-25                           Pumps Submittal Review & Approval
                Cooling Tower Submittal Review & Approval            14 20-Oct-25     02-Nov-25                           Cooling Tower Submittal Review & Approval
                RTU Fabrication & Delivery                           56 03-Nov-25     28-Dec-25                                    RTU Fabrication & Delivery
                Pumps Fabrication & Delivery                         70 03-Nov-25     11-Jan-26                                       Pumps Fabrication & Delivery
                Cooling Tower Fabrication & Delivery                 70 03-Nov-25     11-Jan-26                                       Cooling Tower Fabrication & Delivery
                ERU/DOA Fabrication & Delivery                     140 02-Dec-25      20-Apr-26                                                         ERU/DOA Fabrication & Delivery
                WSHP Fabrication & Delivery                        126 02-Dec-25      06-Apr-26                                                       WSHP Fabrication & Delivery
                Release Long Lead HVAC Equipment for Fabrication      0 02-Dec-25                                              Release Long Lead HVAC Equipment for Fabrication




                                                                                       Kingsley Elementary School                                                                                 8/28/25
                                                                                 Preconstruction & Procurement Schedule                                                                        Page 1 of 1