Chapel Hill MS - FH Paschen Change Order 1

AID 1842871 · View on Simbli

Agenda Item

i. Capital Improvement Project (CIP) ~ Change Order Request ~ F.H. Paschen, S.N. Nielsen & Associates, LLC ~ Chapel Hill Middle School HVAC and Controls Replacement Project ~ Change Order No. 1 ~ Owner Requested Items and Unforeseen Conditions ~ Change Order No. 1 (Not to Exceed $185,490)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve Change Order No. 1 to F.H. Paschen, S.N. Nielsen & Associates, LLC, for the Chapel Hill Middle School HVAC and Controls Replacement Project in the not to exceed amount of $185,490.
Why: Approval of the budget reallocation and Change Order No. 1 will provide necessary funds for unforeseen conditions at the existing facility, and Owner (DeKalb County School District- “DCSD”) requested items as outlined in the Change Order No. 1 for Chapel Hill Middle School facility. Approval will support further needed improvements related to safety, security, and health. The additional scope of work was recommended by the project’s design and construction professionals and/or requested by DCSD Operations to fulfill program-wide.
Details: On November 13, 2023, the Board of Education approved a firm fixed-price contract to F.H. Paschen, S.N. Nielsen & Associates, LLC, to perform the design and general contracting work as outlined by the proposal documents.

This Change Order No. 01 covers the approved additional scope for the Owner - DeKalb County School District-requested items.
Specific details related to the original scope of work for this Request for Proposal can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/
Financial impact: The total budget of Change Order No. 1 for the additional scope of work outlined for the Chapel Hill Middle School Roof, HVAC and Controls Replacement project is a not-to-exceed amount of $185,490 allocated to the General Contractor cost code (F300CIP.01030.GENCONTR.0193).
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-0168
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
                                THE DEKALB COUNTY BOARD OF EDUCATION
                                    CONSTRUCTION CONTRACT CHANGE ORDER
                                                        (General Contractor)



Project Name: Chapel Hill Middle School HVAC and Controls Replacement
Project No.: F300CIP.01030.GENCONTR .0193
Change Order No.:01
Date: 7/1/2025

Contractor:                         FH Paschen
                                    1371 Southland Cir NW
                                    Atlanta, GA 30318
                                                                                           (the “Contractor”)

Project Description: Chapel Hill Middle School Roof, HVAC, and Controls Replacement

Reason for Change: Existing conditions, Changes requested by owner.

The Contract for the above-referenced Project is hereby amended to provide for the following described change(s)
upon the terms set forth below:
Scope of Work (for this change):
1. Replacement of Deteriorating Roof duct work - $185,490.00

Total: $185,490.00


Contract Amount:            Original Contract Price:                             $ 9,641,860.00
                            Previous Change Orders (Nos. 0):                     $         0.00
                            Current Contract Price (with Change(s)):             $ 9,641,860.00
                            Amount of this Change Order:                         $ 185,490.00
                            Revised Contract Price:                              $ 9,827,350.00

Contract Time:              Original Substantial Completion Date:                             August 14, 2024
                            Increase/(Decrease) in calendar days by previous Change Order(s):         0
                            Increase/(Decrease) in calendar days by this Change Order:                0
                            Revised Substantial Completion Date:                              August 14, 2025

Attachments (Incorporated by Reference): Proposal from Contractor

CLAIM IDENTIFICATION OR WAIVER
The Contractor has no claims arising out of or related to the Project for any (i) costs, expenses, profit, overhead, direct
damages, consequential damages or increase in the Contract Price or (ii) delay or impact to the Contractor or the Project
except as identified as follows:



and any and all claims that are not identified hereinabove by the Contractor are hereby waived by the Contractor.

                              Signatures are included on the following page.




Contractor Change Order (07/2025)                                                                                      1
Change Order No. 01
As changed hereinabove, the Contract for the above-referenced Project shall continue in full force and effect.


Agreed to by the Contractor:




                                                         7/3/2025
Lance McRae – FH Paschen                                 Date
Senior Project Manager


Recommended for Acceptance by Architect:



                                                         7/3/2025
Kevin Bonkowski– Raymond Engineering                     Date
Project Manager

Recommended for Acceptance by Project Manager:



                                                         7/7/2025
Donta’ Collins                                           Date
Project Manager



Chante Lemon                                             Date
Senior Project Manager



Keith Ball                                               Date
Executive Director – Capital Improvements & Facilities



Erick Hofstetter                                         Date
Chief Operating Officer



Approved by The DeKalb County Board of Education:



Dr. Devon Q. Horton                                      Date
Superintendent




Mrs. Deirdre P. Pierce                                   Date
Board Chair


Board of Education Approval:        Date:   N/A            Item No.:    N/A
(Required Over $100,000)
Contractor Change Order (07/2025)                                                                                2
Change Order No. 01
                                   F.H. Paschen                                                                       Project: 1852 - Dekalb County School District - Chapel Hill Middle School Roof,
                                   6605 Abercorn St (Ste 109-E)                                                                                                         HVAC, Controls Replacement
                                   Savannah, Georgia 31405                                                                                                                 3535 Dogwood Farm Road
                                                                                                                                                                              Decatur, Georgia 30034



CHANGE EVENT #013 - Roof Duct replacement
Origin:                     Meeting #3: FHP_OAC Meeting
Date Created:               7/7/2025                                                                 Created By:                   Lance McRae
Status:                     09 - Internal Issue                                                      Scope:                        TBD
Type:                       Potential Change Request                                                 Change Reason:                Changed Conditions
Description:
Attachments:                   Chapel Hill Duct Replacement Proposal 05132025.pdf


CHANGE EVENT LINE ITEMS

                                                                                              Revenue                                                       Cost

                                                                                                                        Latest                                                                 Over/ Budget
Budget Code                 Vendor / Contract                 UOM      QTY    Unit Cost          ROM Prime PCO                   QTY     Unit Cost          ROM     RFQ Commit. Latest Cost
                                                                                                                         Price                                                                 Under   Mod.

1.9 -STL                                                                1.0 $162,000.00 $162,000.00                $162,000.00    1.0 $162,000.00 $162,000.00                    $162,000.00
LABOR.Other-Sub to Let
Description:
MaxAir

REV.REV                                                                 1.0   $2,430.00      $2,430.00               $2,430.00    1.0    $2,430.00      $2,430.00                  $2,430.00
Bond
Description:
Insurance

1.9 -STL                                                                1.0   $9,720.00      $9,720.00               $9,720.00    1.0    $9,720.00      $9,720.00                  $9,720.00
LABOR.Other-Sub to Let
Description:
Burden

6.9 -STL                                                                1.0   $11,340.00    $11,340.00              $11,340.00    1.0    $11,340.00    $11,340.00                 $11,340.00
MATERIAL.Other-Sub to Let
Description:
FHP OHP

Grand Totals                                                                               $185,490.00       $0.00 $185,490.00                        $185,490.00 $0.00    $0.00 $185,490.00   $0.00   $0.00




F.H. Paschen                                                                                   Page 1 of 1                                                                Printed on: 7/7/2025 at 13:46 EDT
                                                                             814 Livingston Court
                                                                             Marietta, GA 30067
                                                                             770.956.1200

Date:       May 13, 2025                                                        Ga. Reg. #CN210671
Subject:    Chapel Hill Elementary School RTU Duct Replacement
Location: 3535 Dogwood Farm Road, Decatur, GA 30034
Drawings: N/A
We are pleased to present this proposal for the construction work related to this project.

HVAC: $162,000.00
  1. Demo existing duct from Mechanical Room to RTUs on (4) units.
  2. Furnish and install new duct from Mechanical Room to (4) units. The RA will be routed as
      necessary.
  3. Furnish and install new duct supports as required.
  4. Furnish and install new insulation as required.
  5. A boom truck will be required to get the old duct off the roof and the new duct up to the roof.
  6. Duct heaters will need to be disconnected by Electrical if required.
  7. Pricing excludes controls and test & balance.
  8. Pricing includes normal working hours.
  9. HVAC permit excluded.


Clarifications:
    1. Only work listed above is included in our scope.
    2. Pricing excludes after hours work.
    3. Pricing excludes repairs, maintenance, cleaning, or replacement of any existing system or component.
    4. Pricing assumes existing plumbing fixtures are code-compliant and excludes any cleaning,
         modifications, repairs, or replacements.
    5. Pricing excludes OCIP, CCIP, LEED, BIM, bonding, phasing, and commissioning.
    6. Pricing is based upon mutually agreeable terms and conditions.
    7. Due to the unprecedented volatility in material and equipment pricing, we are unable to hold
         pricing for any period of time. Equipment lead times and final pricing will be assessed at the time
         of award, and then again at the time, the submittals are approved for release. All price increases
         incurred during this period will be considered reimbursable and will be added to the final price.

Respectfully,

Mike Mason
mmason@maxairmech.com