i. E-SPLOST V Project~ CHANGE ORDER REQUEST ~ Construction Works, Inc. ~ #365-35 for Salem Middle School Major Building Systems Replacement ~ Change Order No. 4 ~ Owner Requested Items and Extended General Conditions (Not to exceed $430,446.23)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve:

Change Order No. 4 to Construction Works, Inc. for the Salem Middle School Major Building Systems Replacement project in a not-to-exceed amount of $430,446.23 that will be funded by budget reallocation.
E-SPLOST V budget reallocation in the amount of $430,446.23 from Program Contingency to the Contractor cost code.
Why: Approval of the budget reallocation and Change Order No. 4 will provide additional funds for the Owner (DeKalb County School District - DCSD) requested items, unforeseen conditions and extended general conditions (extended construction schedule) as outlined in the Change Order No. 4 documents for the Salem Middle School Major Building Systems Replacement project.

Approval of Change Order No. 4 meets Strategic Goal Area 6: Organizational Excellence
Details: On September 21, 2022, the Board of Education approved a firm fixed price contract for Construction Works Inc., to perform the general contracting work as outlined by the proposal documents and an E-SPLOST V budget reallocation of $9,763.167.37 from Program Contingency to fund the award of RFP 22-752-020 for General Contractor Services to Construction Works, Inc. The budget reallocation was applied as follows:


Salem Middle School - $5,166,440
Redan Middle School - $2,356,281
Fairington Elementary School - $2,240,466.37


Change Order No. 04 for Salem Middle School Major Building Systems Replacement provides for the Owner requested items recommended by the project’s design and construction professionals and/or requested by DCSD Facilities to fulfill program-wide initiatives, unforeseen conditions and an extended construction schedule.

Specific details related to the original scope of work for this project can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/.
Financial impact: The financial impact of Change Order No. 4 for the total amount of $430,446.23 for the Construction Works, Inc. Change Order No. 4 due to Owner -requested items unforeseen conditions, and extended general conditions (extended construction schedule), will be allocated from the general contractor cost code (SP5FACCON.36535.GENCONTR) under the voter-approved E-SPLOST V program.

A budget reallocation of $430,446.23 from program contingency (SP5MANG.60235.PRGCONTIN) to the general contractor cost code will fund the Change Order No. 4.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
                                  E-SPLOST V Project 60235: Program Contingency Budget Adjustments
                                                                                                             Program
MUNIS EFFECTIVE To/From Project
                                                              To/From Project Name                         Contingency     Board Approval
     DATE            Num
                                                                                                              Amount
    5/11/2017        60235        Program Contingency Beginning Balance                                   +$20,600,000.00    3/20/2017
   12/12/2017        51135        Support Vehicle Purchase                                                     -$75,000.00       N/A
   12/10/2018        22235        New ES for Cross Keys North                                              -$6,710,566.00    11/5/2018
   10/22/2019        22135        John Lewis ES                                                                -$98,000.00       N/A
   10/22/2019        22235        New ES for Cross Keys North                                                -$370,000.00    10/7/2019
    2/20/2020        20235        Freedom MS                                                               +$8,235,000.00    1/13/2020
    2/20/2020        21135        Cedar Grove HS                                                           -$4,200,000.00    1/13/2020
    2/20/2020        22335        Indian Creek ES                                                         -$14,340,000.00    1/13/2020
    3/4/2020         20135        Cross Keys HS                                                            +$6,925,000.00    2/10/2020
    3/4/2020         20335        Peachtree MS                                                            +$13,750,000.00    2/10/2020
    3/4/2020         21235        Chamblee HS                                                             +$20,390,000.00    2/10/2020
    3/4/2020         21335        Clarkston HS                                                            +$16,390,000.00    2/10/2020
    3/4/2020         21435        New Cross Keys HS                                                       +$84,000,000.00    2/10/2020
    3/4/2020         21535        Dunwoody HS                                                             +$15,390,000.00    2/10/2020
    3/4/2020         21635        Lakeside HS                                                             +$25,390,000.00    2/10/2020
    3/6/2020         10135        Sprinkler Installation A                                                 -$7,446,915.00    2/10/2020
    3/6/2020         10235        Sprinkler Installation B                                                 -$8,421,848.00    2/10/2020
    3/6/2020         10335        Sprinkler Installation C                                                 -$8,670,355.00    2/10/2020
    3/6/2020         11135        Fence installation A                                                         -$39,566.00   2/10/2020
    3/6/2020         11235        Fence installation B                                                       -$460,115.00    2/10/2020
    3/6/2020         11335        Fence installation C                                                       -$375,957.00    2/10/2020
    3/6/2020         11535        Security Vestibules A                                                    -$1,013,902.00    2/10/2020
    3/6/2020         11635        Security Vestibules B                                                      -$861,902.00    2/10/2020
    3/6/2020         12135        Druid Hills HS                                                           -$1,742,566.00    2/10/2020
    3/6/2020         12235        Hambrick ES                                                              -$1,442,972.00    2/10/2020
    3/6/2020         21135        Cedar Grove HS                                                           -$2,206,250.00    2/10/2020
    3/6/2020         22135        John Lewis ES                                                              -$102,000.00    2/10/2020
    3/6/2020         22235        New ES for Cross Keys North                                                -$275,271.00    2/10/2020
    3/6/2020         30135        Turf Installation A                                                      -$1,886,111.00    2/10/2020
    3/6/2020         30235        Turf Installation B                                                      -$1,696,111.00    2/10/2020
    3/6/2020         32235        Redan MS                                                                 -$2,473,587.00    2/10/2020
    3/6/2020         34335        Druid Hills MS                                                             -$705,667.00    2/10/2020
    3/6/2020         34435        Midvale ES                                                               -$1,468,549.00    2/10/2020
    3/6/2020         38135        Parking Addition                                                           -$854,026.00    2/10/2020
    3/6/2020         40235        Technology: ERP/Finance/HR System                                        -$1,500,000.00    2/10/2020
    3/6/2020         60535        Program Consultants                                                      -$2,000,000.00    2/10/2020
    3/9/2020         11135        Fence installation A                                                       -$619,893.00    2/10/2020
    3/9/2020         22435        New Dunwoody / Chamblee ES                                              -$35,000,000.00    2/10/2020
    3/9/2020         30335        Set aside for Track with Turf Installation                               -$4,500,000.00    2/10/2020
    3/9/2020         34535        Former John Lewis Facility                                               -$1,000,000.00    2/10/2020
    3/9/2020         36735        Set-aside for Additional Contingency for Capital Renewal Projects       -$38,000,000.00    2/10/2020
    3/9/2020         38235        Set aside or resurfacing existing parking at parking addition schools    -$7,500,000.00    2/10/2020
    3/9/2020         60635        Revenue Reserve                                                         -$13,000,000.00    5/11/2020
    4/20/2020        20235        Freedom MS                                                               +$8,235,000.00    1/13/2020
    4/20/2020        22335        Indian Creek ES                                                         -$14,000,000.00    1/13/2020
    6/9/2020         22235        New ES for Cross Keys North                                                -$600,000.00    4/15/2020
    7/8/2020         21435        New Cross Keys HS                                                          -$450,000.00     6/8/2020
    9/2/2020         34535        Former John Lewis Facility                                                 -$385,000.00    7/13/2020
    9/4/2020         21435        New Cross Keys HS                                                          -$450,000.00     6/8/2020
   12/21/2020        41235        Technology: Computer Refresh B                                           -$4,181,169.00    12/7/2020
                                  Technology: Telecommunications
   12/21/2020        42135                                                                                  +$589,569.00     12/7/2020
                                  Upgrade
   12/21/2020        43135        Technology: Safety and Security                                            +$420,000.00    12/7/2020
   12/21/2020        44135        Technology: Active Boards A                                                +$178,600.00    12/7/2020
   12/21/2020        44235        Technology: Active Boards B                                              +$1,993,000.00    12/7/2020
    1/21/2021        53135        Portables                                                                  -$237,168.95    12/7/2020

DCSD Operations                                                     5/30/2025                                                        1 of 5
                                  E-SPLOST V Project 60235: Program Contingency Budget Adjustments
                                                                                                          Program
MUNIS EFFECTIVE To/From Project
                                                             To/From Project Name                      Contingency     Board Approval
     DATE            Num
                                                                                                          Amount
   1/28/2021         40235        Technology: ERP/Finance/HR System                                    -$4,000,000.00     12/7/2020
   2/4/2021          35435        E. L. Miller ES                                                      -$2,957,000.00     12/7/2020
   2/10/2021         20235        Freedom MS                                                             -$250,000.00     5/11/2020
   3/2/2021          34535        Former John Lewis Facility                                               -$42,790.00       N/A
   3/2/2021          35335        Former Nancy Creek                                                   -$2,455,000.00     12/7/2020
   3/2/2021          35935        Livsey ES                                                            -$1,900,000.00     12/7/2020
   4/29/2021         20235        Freedom MS                                                           -$8,235,000.00     12/7/2020
   4/29/2021         22335        Indian Creek ES                                                     +$14,000,000.00     2/8/2021
   5/10/2021         21135        Cedar Grove HS                                                         -$342,000.00     11/9/2020
   5/10/2021         34535        Former John Lewis Facility                                               -$55,000.00       N/A
   5/31/2021         38035        Green Forrest Drive                                                  -$3,000,000.00     4/19/2021
   6/10/2021         20235        Freedom MS                                                             +$250,000.00     2/14/2022
   6/10/2021         36735        Set-aside for Additional Contingency for Capital Renewal Projects   +$35,400,000.00     2/10/2020
   6/10/2021         36835        Laurel Ridge ES                                                      -$8,300,000.00     6/8/2020
   6/10/2021         36935        Woodridge ES                                                         -$7,300,000.00     6/8/2020
   6/10/2021         37035        Chesnut ES                                                           -$6,400,000.00     6/8/2020
   6/10/2021         37235        Ashford Park ES                                                      -$1,400,000.00     6/8/2020
   6/10/2021         37335        Montgomery ES                                                        -$1,600,000.00     6/8/2020
   6/10/2021         37435        Brockett ES                                                          -$1,300,000.00     6/8/2020
   6/10/2021         37535        Wynbrooke ES                                                         -$2,500,000.00     6/8/2020
   6/10/2021         37635        Browns Mill ES                                                       -$1,900,000.00     6/8/2020
   6/10/2021         37735        DeKalb Alternative/East Campus                                       -$3,400,000.00     6/8/2020
   6/10/2021         37835        Oak Grove ES                                                         -$1,300,000.00     6/8/2020
   6/22/2021         21435        New Cross Keys HS                                                      +$450,000.00     6/8/2020
   6/29/2021         22235        New ES for Cross Keys North                                            -$204,635.00     4/19/2021
   6/29/2021         54135        Small Kitchen Equipment                                                   -$1,000.00       N/A
   8/4/2021          37935        Update HVAC Controls                                                 -$4,500,000.00     12/7/2020
   8/22/2021         30435        Baseball facilities improvements at Druid Hills MS and Redan HS      -$2,000,000.00     5/17/2021
   12/7/2021         11435        Athletic Field Fencing                                                   -$74,117.66       N/A
   12/7/2021         11535        Security Vestibules A                                                  -$980,000.00    11/15/2021
   12/7/2021         11635        Security Vestibules B                                                  -$460,000.00    11/15/2021
   12/7/2021         34235        ADA restroom upgrades                                                  -$250,000.00    11/15/2021
   1/5/2022          11435        Athletic Field Fencing                                                 -$914,117.68     7/12/2021
   1/6/2022          11435        Athletic Field Fencing                                                 -$211,764.72     7/12/2021
   1/12/2022         11135        Fence installation A                                                 +$1,200,000.00     7/12/2021
   1/12/2022         11535        Security Vestibules A                                                  -$980,000.00    11/15/2021
   1/12/2022         11635        Security Vestibules B                                                  -$460,000.00    11/15/2021
   1/12/2022         34235        ADA restroom upgrades                                                  -$250,000.00    11/15/2021
   1/12/2022         60435        General Services                                                            -$183.96       N/A
   1/18/2022         38035        Green Forrest Drive                                                  -$3,000,000.00    12/13/2021
   1/27/2022         37435        Brockett ES                                                            -$251,000.00     8/9/2021
   1/27/2022         37835        Oak Grove ES                                                           -$241,000.00     8/9/2021
   2/17/2022         11135        Fence installation A                                                   -$600,000.00     7/12/2021
   2/17/2022         11235        Fence installation B                                                   +$600,000.00     7/13/2021
   2/17/2022         11535        Security Vestibules A                                                  +$980,000.00    11/15/2021
   2/17/2022         11635        Security Vestibules B                                                  +$460,000.00    11/15/2021
   2/17/2022         34235        ADA restroom upgrades                                                  +$250,000.00    11/15/2021
   4/14/2022         34235        ADA restroom upgrades                                                  +$250,000.00    11/15/2021
   4/28/2022         20235        Freedom MS                                                             -$250,000.00     2/14/2022
   5/6/2022          22435        New Dunwoody / Chamblee ES                                           -$1,550,000.00    11/15/2021
   5/6/2022          30135        Turf Installation A                                                    -$301,220.00
   5/6/2022          34235        ADA restroom upgrades                                                  -$250,000.00    11/15/2021
   5/6/2022          36735        Set-aside for Additional Contingency for Capital Renewal Projects    -$1,000,000.00     2/25/2022
   5/6/2022          54135        Small Kitchen Equipment                                                   +$1,000.00       N/A
   5/6/2022          60435        General Services                                                            +$183.96       N/A
   5/11/2022         30335        Set aside for Track with Turf Installation                           +$4,500,000.00     8/9/2021

DCSD Operations                                                    5/30/2025                                                     2 of 5
                                  E-SPLOST V Project 60235: Program Contingency Budget Adjustments
                                                                                                          Program
MUNIS EFFECTIVE To/From Project
                                                             To/From Project Name                      Contingency     Board Approval
     DATE            Num
                                                                                                          Amount
    5/11/2022        37335        Montgomery ES                                                        +$1,600,000.00    2/25/2022
    5/11/2022        37635        Browns Mill ES                                                       +$1,900,000.00    2/25/2022
    5/11/2022        60635        Revenue Reserve                                                     +$13,000,000.00    2/25/2022
    5/26/2022        21435        New Cross Keys HS                                                   -$10,700,000.00    2/25/2022
    5/31/2022        60235        Program Contingency Budget Addition to E-SPLOST V                   +$69,300,000.00    2/25/2022
    6/1/2022         21435        New Cross Keys HS                                                   -$69,300,000.00    2/25/2022
    6/2/2022         21735        Design New Sequoyah MS & HS                                         -$10,000,000.00    2/25/2022
    9/7/2022         11135        Fence installation A                                                   +$445,651.00    8/10/2022
    9/7/2022         11235        Fence installation B                                                   +$395,855.00    8/10/2022
    9/7/2022         11335        Fence installation C                                                   +$750,609.00    8/10/2022
    9/7/2022         20135        Cross Keys HS                                                        +$2,769,026.53    8/10/2022
    9/7/2022         20335        Peachtree MS                                                           +$121,909.67    8/10/2022
    9/7/2022         22135        John Lewis ES                                                          +$278,390.39    8/10/2022
    9/7/2022         22235        New ES for Cross Keys North                                            +$406,758.33    8/10/2022
    9/7/2022         32135        Plumbing fixture replacement                                         +$1,504,209.00    8/10/2022
    9/7/2022         35635        Cary Reynolds ES                                                     +$5,622,960.00    8/10/2022
    10/6/2022        10935        Life Safety Set-aside                                                +$2,570,000.00    9/12/2022
    10/6/2022        32235        Redan MS                                                             -$2,572,575.00    2/25/2022
    10/6/2022        35435        E. L. Miller ES                                                      -$1,100,000.00    9/12/2022
    10/6/2022        36135        Fairington ES                                                        -$2,355,787.37    2/25/2022
    10/6/2022        36535        Salem MS                                                             -$5,483,551.00    2/25/2022
    10/6/2022        36835        Laurel Ridge ES                                                      -$1,030,000.00    9/12/2022
    10/6/2022        36935        Woodridge ES                                                           -$910,000.00    9/12/2022
    10/6/2022        37035        Chesnut ES                                                             -$630,000.00    9/12/2022
   10/25/2022        34535        Former John Lewis Facility                                             -$402,216.00    7/11/2022
   10/25/2022        50135        School Bus Purchase A                                                   +$66,068.00    2/25/2020
   10/25/2022        50235        School Bus Purchase B                                                    -$66,068.00   2/25/2020
   10/26/2022        30435        Baseball facilities improvements at Druid Hills MS and Redan HS          -$82,350.00      N/A
    11/1/2022        30435        Baseball facilities improvements at Druid Hills MS and Redan HS        -$584,622.00    9/12/2022
    12/1/2022        34435        Midvale ES                                                           -$2,350,000.00    2/25/2022
    12/1/2022        36435        Hawthorne ES                                                           -$330,000.00    2/25/2022
    12/1/2022        36635        Rock Chapel ES                                                       -$2,320,000.00    2/25/2022
    8/24/2023        34535        Former John Lewis Facility                                               -$44,000.00      N/A
    8/28/2023        30435        Baseball facilities improvements at Druid Hills MS and Redan HS          -$96,000.00      N/A
    9/12/2023        10935        Life Safety Set-aside                                                  +$958,949.94    8/23/2023
    9/12/2023        11135        Fence installation A                                                    +$10,000.00       N/A
    9/12/2023        11435        Athletic Field Fencing                                                 +$208,365.14    8/23/2023
    9/12/2023        12135        Druid Hills HS                                                       +$1,708,196.97    8/23/2023
    9/12/2023        21235        Chamblee HS                                                            +$354,304.26    8/23/2023
    9/12/2023        21535        Dunwoody HS                                                          +$1,015,864.65    8/23/2023
    9/12/2023        21635        Lakeside HS                                                             +$91,326.96       N/A
    9/12/2023        22135        John Lewis ES                                                             +$8,225.44      N/A
    9/12/2023        22335        Indian Creek ES                                                      +$2,976,679.83    8/23/2023
    9/12/2023        30135        Turf Installation A                                                    +$778,255.11    8/23/2023
    9/12/2023        30235        Turf Installation B                                                    +$399,387.65    8/23/2023
    9/12/2023        31135        Playground replacement                                                  +$55,836.70    2/25/2022
    9/12/2023        33135        Water Quality Set-Aside                                                +$923,000.00    8/23/2023
    9/12/2023        34135        Accessibility improvements and plumbing fixtures at 4 schools        +$1,422,018.75    8/23/2023
    9/12/2023        34235        ADA restroom upgrades                                                   +$40,529.00       N/A
    9/12/2023        36235        Dresden ES                                                           +$1,226,860.00    8/23/2023
    9/12/2023        36735        Set-aside for Additional Contingency for Capital Renewal Projects    +$3,600,000.00    8/23/2023
    9/12/2023        37135        Bus Parking Pavement                                                    +$25,626.80    2/25/2022
    9/12/2023        37235        Ashford Park ES                                                        +$159,129.42    8/23/2023
    9/12/2023        37435        Brockett ES                                                            +$127,907.48    8/23/2023
    9/12/2023        37535        Wynbrooke ES                                                           +$671,238.67    8/23/2023
    9/12/2023        37735        DeKalb Alternative/East Campus                                       +$1,336,571.83    8/23/2023

DCSD Operations                                                    5/30/2025                                                     3 of 5
                                  E-SPLOST V Project 60235: Program Contingency Budget Adjustments
                                                                                                              Program
MUNIS EFFECTIVE To/From Project
                                                              To/From Project Name                         Contingency     Board Approval
     DATE            Num
                                                                                                              Amount
    9/12/2023        37935        Update HVAC Controls                                                     +$4,499,780.00     8/23/2023
    9/12/2023        38135        Parking Addition                                                         -$5,000,000.00     8/23/2023
    9/12/2023        38235        Set aside or resurfacing existing parking at parking addition schools    +$7,500,000.00     8/23/2023
    9/12/2023        40235        Technology: ERP/Finance/HR System                                          -$147,224.00     8/23/2023
    9/12/2023        41235        Technology: Computer Refresh B                                           +$1,385,342.52     8/23/2023
    9/12/2023        44235        Technology: Active Boards B                                                +$200,923.66     8/23/2023
    9/12/2023        45135        Technology: Infrastructure                                               +$1,430,332.65     8/23/2023
    9/12/2023        50235        School Bus Purchase B                                                      +$276,315.00     8/23/2023
    9/12/2023        60535        Program Consultants                                                      +$1,059,177.25     8/23/2023
    9/18/2023        34335        Druid Hills MS                                                             -$340,661.00     8/14/2023
    9/18/2023        36435        Hawthorne ES                                                             -$5,338,350.00     8/14/2023
    9/18/2023        36835        Laurel Ridge ES                                                          -$2,762,265.00     9/12/2022
    9/18/2023        36935        Woodridge ES                                                             -$1,850,000.00     8/14/2023
    9/18/2023        37035        Chesnut ES                                                               -$2,050,000.00     8/14/2023
    10/4/2023        11535        Security Vestibules A                                                         -$9,500.00       N/A
    10/4/2023        11635        Security Vestibules B                                                        -$16,419.52       N/A
   11/14/2023        35135        Henderson Mill ES                                                        -$1,787,300.00    10/16/2023
   11/14/2023        35735        Briar Vista ES                                                             -$555,100.00    10/16/2023
    3/1/2024         32235        Redan MS                                                                 -$1,631,221.84     2/12/2024
    3/1/2024         34435        Midvale ES                                                               -$5,340,435.00     9/11/2023
    3/1/2024         36035        DeKalb HS of Technology-South                                            -$6,787,500.00     9/11/2023
    3/1/2024         36535        Salem MS                                                                 -$1,462,834.60     2/12/2024
    3/4/2024         36135        Fairington ES                                                            -$1,289,674.80     2/12/2024
    3/13/2024        34435        Midvale ES                                                                 -$100,000.00     9/11/2023
    9/5/2024         10135        Sprinkler Installation A                                                 +$7,937,248.00     5/6/2024
    9/5/2024         10235        Sprinkler Installation B                                                 +$8,811,690.00     5/6/2024
    9/5/2024         10335        Sprinkler Installation C                                                 +$9,381,630.00     5/6/2024
    9/5/2024         22435        New Dunwoody / Chamblee ES                                              +$29,158,228.25     5/6/2024
    9/6/2024         21335        Clarkston HS                                                             -$2,091,200.00     8/12/2024
    9/6/2024         35335        Former Nancy Creek                                                       -$5,371,073.00     5/6/2024
    9/6/2024         35435        E. L. Miller ES                                                            -$160,883.96     8/12/2024
    9/6/2024         35735        Briar Vista ES                                                           -$1,798,235.00     8/12/2024
    9/6/2024         35835        Champion Theme MS                                                       -$17,777,291.00     5/6/2024
    9/6/2024         60435        General Services                                                           -$320,000.00     5/6/2024
    10/3/2024        22435        New Dunwoody / Chamblee ES                                                 +$434,565.98     5/6/2024
    10/4/2024        35435        E. L. Miller ES                                                            -$160,883.96     5/6/2024
   10/11/2024        30435        Baseball facilities improvements at Druid Hills MS and Redan HS              -$29,607.00       N/A
   11/22/2024        36935        Woodridge ES                                                               -$303,313.00    11/11/2024
   11/22/2024        36835        Laurel Ridge ES                                                            -$397,176.00    11/11/2024
   11/22/2024        36335        Kingsley ES                                                                -$268,389.00    11/11/2024
   11/22/2024        36235        Dresden ES                                                               -$1,825,000.00    11/11/2024
   11/22/2024        36035        DeKalb HS of Technology-South                                              -$684,789.00     11/1/2024
   11/22/2024        35735        Briar Vista ES                                                             -$785,000.00    11/11/2024
   11/22/2024        35335        Former Nancy Creek                                                         -$335,365.00    11/11/2024
   11/22/2024        34435        Midvale ES                                                               -$1,185,031.00    11/11/2024
    1/24/2025        11535        Security Vestibules A                                                        -$25,965.00       N/A
    1/24/2025        11535        Security Vestibules A                                                      -$234,918.24    12/11/2023
    1/24/2025        35435        E. L. Miller ES                                                              -$26,833.14       N/A
    1/24/2025        35435        E. L. Miller ES                                                            -$353,522.34     5/6/2024
    2/13/2025        21235        Chamblee HS                                                                  -$19,380.00       N/A
    2/26/2025        36935        Woodridge ES                                                                 -$38,263.10       N/A
    3/10/2025        36135        Fairington ES                                                              -$138,529.00     12/9/2024
    3/10/2025        36435        Hawthorne ES                                                               -$346,293.00     12/9/2024
    3/10/2025        35935        Livsey ES                                                                -$2,452,255.00     12/9/2024
    3/10/2025        32235        Redan MS                                                                   -$433,080.00     12/9/2024
    3/10/2025        36535        Salem MS                                                                   -$433,080.00     12/9/2024

DCSD Operations                                                     5/30/2025                                                        4 of 5
                                  E-SPLOST V Project 60235: Program Contingency Budget Adjustments
                                                                                                                    Program
MUNIS EFFECTIVE To/From Project
                                                            To/From Project Name                                 Contingency     Board Approval
     DATE            Num
                                                                                                                    Amount
   3/10/2025         35235        Toney ES                                                                       -$1,784,124.00    12/9/2024
   3/10/2025         36635        Rock Chapel ES                                                                   -$100,000.00    10/7/2024
   3/10/2025         35835        Champion Theme MS                                                                -$171,204.00    12/9/2024
   3/10/2025         21435        New Cross Keys HS                                                                -$119,443.50    12/9/2024
   3/10/2025         35335        Former Nancy Creek                                                               -$111,254.00    12/9/2024
   4/14/2025         35335        Former Nancy Creek                                                                 -$83,564.55      N/A
    5/5/2025         10135        Sprinkler Installation A                                                          +$83,044.88       N/A
    5/5/2025         10235        Sprinkler Installation B                                                          +$89,619.70       N/A
    5/5/2025         10335        Sprinkler Installation C                                                          +$73,401.19       N/A
    5/5/2025         10935        Life Safety Set-aside                                                               +$1,050.06      N/A
    5/5/2025         11435        Athletic Field Fencing                                                            +$32,075.47       N/A
    5/5/2025         12135        Druid Hills HS                                                                    +$26,754.00       N/A
    5/5/2025         20235        Freedom MS                                                                        +$90,000.00       N/A
    5/5/2025         21535        Dunwoody HS                                                                       +$15,970.00       N/A
    5/5/2025         21635        Lakeside HS                                                                       +$10,000.00       N/A
    5/5/2025         22135        John Lewis ES                                                                       +$4,313.00      N/A
    5/5/2025         22235        New ES for Cross Keys North                                                       +$61,262.02       N/A
    5/5/2025         22335        Indian Creek ES                                                                     +$8,296.66      N/A
    5/5/2025         22435        New Dunwoody / Chamblee ES                                                             +$91.00      N/A
    5/5/2025         30435        Baseball facilities improvements at Druid Hills MS and Redan HS                     +$2,452.50      N/A
    5/5/2025         34135        Accessibility improvements and plumbing fixtures at 4 schools                     +$15,827.84       N/A
    5/5/2025         34235        ADA restroom upgrades                                                             +$58,608.38       N/A
    5/5/2025         34335        Druid Hills MS                                                                    +$85,172.42       N/A
    5/5/2025         34535        Former John Lewis Facility                                                        +$77,051.44       N/A
    5/5/2025         36835        Laurel Ridge ES                                                                   +$97,199.37       N/A
    5/5/2025         37035        Chesnut ES                                                                        +$16,068.01       N/A
    5/5/2025         37835        Oak Grove ES                                                                      +$78,122.98       N/A
    5/5/2025         41135        Technology: Computer Refresh A (Bond)                                             +$41,123.60       N/A
    5/5/2025         43135        Technology: Safety and Security                                                     +$1,114.52      N/A
    5/5/2025         51135        Support Vehicle Purchase                                                          +$49,947.40       N/A
    5/5/2025         54135        Small Kitchen Equipment                                                           +$20,887.77       N/A
   5/13/2025         36935        Woodridge ES                                                                       -$21,021.00      N/A
   In Process        35835        Champion Theme MS                                                              -$1,987,229.00    4/21/2025
   In Process        36035        DeKalb HS of Technology-South                                                  -$1,150,394.00    4/21/2025
   In Process        21735        Design New Sequoyah MS & HS                                                    -$4,686,585.78    4/21/2025
   In Process        11635        Security Vestibules B                                                            +$440,891.91    5/12/2025
   In Process        12235        Hambrick ES                                                                      +$355,135.67    5/12/2025
   In Process        21135        Cedar Grove HS                                                                   +$662,542.15    5/12/2025
   In Process        60435        General Services                                                                 +$786,450.94    5/12/2025
   In Process        60535        Program Consultants                                                              +$574,713.75    5/12/2025
                                                                                                Ending Balance   $11,829,359.75

                                  June Board Meeting:
                                  Fairington ES CO #04                                                             -$143,905.06
                                  Redan ES CO #03                                                                  -$180,798.15
                                  Salem MS CO #04                                                                  -$430,446.23
                                  Midvale CO #05                                                                   -$192,283.00
                                                                                   June Board Meeting Total        -$947,432.44
                                                                     Updated Program Contingency Balance:        $10,881,927.31