Agenda Item
ii. E-SPLOST V Project~ CHANGE ORDER REQUEST ~ Construction Works, Inc. ~ #322-35 for Redan Middle School Major Building Systems Replacement ~ Change Order No. 3 ~ Owner Requested Items and Extended General Conditions (Not to exceed $180,798.15)
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve:
Change Order No. 3 to Construction Works, Inc. for the Redan Middle School Major Building Systems Replacement project in a not-to-exceed amount of $180,798.15 that will be funded by budget reallocation.
E-SPLOST V budget reallocation in the amount of $180,798.15 from Program Contingency to the Contractor cost code.
Why: Approval of the budget reallocation and Change Order No. 3 will provide additional funds for Owner (DeKalb County School District - DCSD) requested items, unforeseen conditions and extended general conditions (extended construction schedule) as outlined in the Change Order No. 3 documents for the Redan Middle School Major Building Systems Replacement project.
Approval of Change Order No. 3 meets Strategic Goal Area 6: Organizational Excellence
Details: On September 21, 2022, the Board of Education approved a firm fixed price contract for Construction Works Inc., to perform the general contracting work as outlined by the proposal documents and an E-SPLOST V budget reallocation of $9,763.167.37 from Program Contingency to fund the award of RFP 22-752-020 for General Contractor Services to Construction Works, Inc. The budget reallocation was applied as follows:
Salem Middle School - $5,166,440
Redan Middle School - $2,356,281
Fairington Elementary School - $2,240,466.37
Change Order No. 03 for Redan Middle School Major Building Systems Replacement provides for the Owner requested items recommended by the project’s design and construction professionals and/or requested by DCSD Facilities to fulfill program-wide initiatives, unforeseen conditions and an extended construction schedule.
Specific details related to the original scope of work for this project can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/.
Financial impact: The financial impact of Change Order No. 3 for the total amount of $180,798.15 for Construction Works, Inc. Change Order No. 3 due to Owner -requested items, unforeseen conditions, and extended general conditions (extended construction schedule) will be allocated from the general contractor cost code (SP5FACCON.32235.GENCONTR) under the voter-approved E-SPLOST V program.
A budget reallocation of $180,798.15 from program contingency (SP5MANG.60235.PRGCONTIN) is required to fund this Change Order No. 3.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
DATE RECEIVED: ______________
MATTER ASSIGNED TO: ________
Request for Legal Assistance
DCSD Office of Legal Affairs
ATTORNEY – CLIENT COMMUNICATION
PLEASE SUBMIT COMPLETED REQUEST FORM TO
DCSD OFFICE OF LEGAL AFFAIRS.
*** This request is a confidential communication and should be treated as such ***
DESCRIPTION OF REQUEST
Title of Item/Topic: __Legal Review and Approval – Change Order Request_________
(e.g., contract review, policy matter, etc.)
Date of request: ___5/14/2025______________ Due Date: __5/19/2025__________3 to 5 business
days)
Background information/Detail: E-SPLOST V Project~ Change Order Request ~
Construction Works, Inc. ~ #36535 for Redan Middle School Major Building
Systems Replacement ~ Change Order No. 3 ~ Owner Requested Items and
Extended General Conditions- Not to Exceed $180,798.15.
PROCUREMENT DETAILS (if applicable)
Include details confirming that all applicable DCSD procurement policies and requirements have been
adhered to: _________________________________________________________________________________
____________________________________________________________________________________________
SUPPORTING DOCUMENTATION
Please attach/include any additional supporting documentation that are relevant to your request.
Description of supporting documentation, if any _________________________________________________
REQUIRED AUTHORIZATION
Requested by: ___Darlene Y. Hughes, Esq______________________________________________
Email: _darlene_hughes@dekalbschoolsga.org___________ Telephone: __678-676-1447_____________
Department: ______Operations Division__________________________________________________
Cabinet Member authorizing the request: _____Erick Hofstetter_______________________________________
LEGAL APPROVAL
Approved as to form by the DCSD Office of Legal Affairs? ☐ Yes ☐ No
-OR- (check one only)
Approved as to form by Outside Legal Counsel? ☐ Yes ☐ No
*Referrals to Outside Legal Counsel must be coordinated and approved by the DCSD Legal Dept .
Approving Attorney (and law firm if Outside Counsel) _____________________________
Comments: ____________________________________________________________________________
______________________________________________________________________________________