ii. E-SPLOST V Project ~ Change Order Request ~ Evergreen Construction ~ #360-35 DeKalb High School of Technology ~ South Major Building Systems Replacement ~ Change Order No. 4 ~ Owner Requested Items and Unforeseen Conditions (Not to exceed $1,150,394)
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve:
Change Order No. 4 to Evergreen Construction for the DeKalb High School of Technology-South Major Building Systems Replacement project in an amount not-to-exceed $1,150,394.
A budget reallocation in the amount of $1,150,394.00 from Program Contingency to the Contractor cost code to fund Change Order No. 4.
Why: Approval of the budget reallocation and Change Order No. 4 will provide additional funds for the additional scope of work recommended by the project’s design and construction professionals and DCSD Operations staff to fulfill program wide initiatives. The additional scope and further needed improvements will enhance safety, security, and health of staff and students.
Approval of Change Order No. 4 meets Strategic Goal Area 6: Organizational Excellence
Details: On September 11, 2023, the Board of Education approved the award of General Contracting Services to Evergreen Construction for the DeKalb High School of Technology-South Major Building Systems Replacement project in the not-to-exceed amount of $9,972,000.
This Change Order No. 04 covers the approved additional scope for the DeKalb County School District requested items.
Specific details related to the original scope of work for this project can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/.
Financial impact: The total amount of $1,150,394 for Evergreen Construction Change Order No. 4 will be allocated from the general contractor cost code (SP5FACCON.36035.GENCONTR) under the voter-approved E-SPLOST V program. A budget reallocation of $1,150,394 from program contingency is required to fund this Change Order No. 4.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-0168
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval and Fully Executed Documents
Status: Approved by the Office of Legal Affairs
DeKalb High School Technology-South
Change Order No. 1 - 4 Breakdown
PCO # Description Cost Unforeseen Condition AHJ Revisions Errors/Omissions Owner Request Allowance Change Order #1 Change Order #2 Change Order #3 Change Order #4
1 RFI #001 - Missing VAV Information $ 11,866 $ 11,866.00 $ 11,866.00
2 Issued for Construction Documents, received on 11/8/23 $ 1,175 $ 1,175.00 $ 1,175.00
3 RFI #004 - Overhead Door Power Connections $ 17,699 $ 17,699.00 $ 17,699.00
6 Abatement Unit Rates Associated with ACM Reports Provided by DCSD Unit Rates $ - Unit Rates
7 ASI #001 - Roof Framing for DOAS and RTU, issued 1/29/24 $ 3,894 $ 3,894.00 $ 3,894.00
9 Furnish and Install New Classroom Identification Signage $ 10,899 $ 10,899.00 $ 10,899.00
10 RFI #019 - Existing Air Handling Units $ 15,921 $ 15,921.00 $ 15,921.00
13 RFI #015 - New Window Sill Counterflashing Detail $ 5,420 $ 5,420.00 $ 5,420.00
14 ASI #02 - Switchgear Location $ 265,787 $ 265,787.00 $ 265,787.00
15 Removal of Obsolete Equipment from Building per the Email Request, dated 5/10/24 $ 12,539 $ 12,539.00 $ 12,539.00
17 Reconciliation of Relocation & Cleaning Assitance Allowance $ (10) $ 199,990.00 $ (10.00)
18 Reconciliation of Permit Review Comments and Fire, Life Safety Allowance $ (712) $ 49,288.00 $ (712.00)
19 Schedule Impacts Associated with Early Access $ 259,884 $ 259,884.00 $ 259,884.00
20 Abatement of Asbestos Containing Materials $ 159,118 $ 159,118.00 $ 159,118.00
21 Floor Scanning for New Penetrations $ 5,751 $ 5,751.00 $ 5,751.00
22 Construction Lab Roll Up Door $ 12,294 $ 12,294.00 $ 12,294.00
23 Add Fireproofing Insulation to Existing PVC Roof Drains for Code Compliance $ 1,955 $ 1,955.00 $ 1,955.00
24 Temporary Power for Head End Server Room $ 1,788 $ 1,788.00 $ 1,788.00
25 Credit for Elevator Control Panel Door $ (3,367) $ (3,367.00) $ (3,367.00)
26 23 31 13-02 - HVAC Ductwork Shop Drawings - Fire Damper Adds $ 4,048 $ 4,048.00 $ 4,048.00
27 Exterior Caulking of Existing Brick Control Joints per Architects Request $ 13,564 $ 13,564.00 $ 13,564.00
29 Furnish and Install Blackout Shades in Bathrooms $ 5,234 $ 5,234.00 $ 5,234.00
31 Replacement of Existing Terrazzo Flooring at Lockers $ 1,348 $ 1,348.00 $ 1,348.00
32 AHJ Requirements for Control Connection to Existing Hot Water Heaters $ 1,908 $ 1,908.00 $ 1,908.00
33 Submittal 2309-00-01 Controls Product Data - Flow Meters for Cooling Tower Makeup Water $ 1,206 $ 1,206.00
34 Auto Lab Rework $ 38,804 $ 38,804.00 $ 38,804.00
35 RFI #025 - OAU-001 - Ductwork Penetration at Mechanical Penthouse $ 9,971 $ 9,971.00
38 Sprinkler Revisions in Auto Body Lab $ 8,148 $ 8,148.00 $ 8,148.00
40 Restoration of Security Cameras $ 15,574 $ 15,574.00 $ 15,574.00
41 ASI #003 - New Elevator and Security Vestibule Installation $ 1,126,672 $ 1,126,672.00 $ 1,126,672.00
51 Repair Existing Ductwork Discovered Following Removal of Ceiling Tile and Grid at Classroom 112 $ 1,752 $ 1,752.00 $ 1,752.00
Totals $ 2,010,130 $445,165.00 $0.00 $44,102.00 $319,458.00 $249,278.00 $94,617.00 $80,330.00 $684,789.00 $1,150,394.00 $2,010,130.00 $0.00