iii. E-SPLOST VI Project ~ Guaranteed Maximum Price, Budget Reallocation, and Amendment Request ~ #10136 ~ New Sequoyah Middle and High School Replacement ~ The Gilbane Building Company, and Goodwyn, Mills, Cawood ~ Final Guaranteed Maximum Price, Budget Reallocation and Amendment No. 2 ~ A/E Fee Adjustment (Not to exceed $233,348,010.78)
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School Board of Education (“the Board”) approve:
Establish a Final Guaranteed Maximum Price of $228,661,425 for the construction of the New Sequoyah Middle and High School SPLOST VI project per the terms set forth in the Construction Manager at Risk contract previously awarded to The Gilbane Building Company.
A Budget Reallocation of $141,617,170 from the E-SPLOST VI program contingency to fund this project.
Amendment No. 02 to Goodwyn, Mills, Cawood, LLC for a Not -to-Exceed amount of $4,686,585.78 for added design services.
Why: Approval of the Final Guaranteed Maximum Price (GMP) of $228,661,425 and budget reallocation of $141,617,170 for the construction of the New Sequoyah Middle and High School Replacement E-SPLOST VI project as per the CM@Risk contract approved by the Board, June 12, 2023, to Gilbane Building Company, ensures the completion of this project supporting a safe and healthy teaching and learning environment for students and staff.
Approval of Amendment No. 2 to amend the agreement with Goodwyn, Mills, Cawood, LLC. in the amount of $4,686,585.78, will provide the necessary funds for the increased Stated Cost Limitation and additional scope as outlined in the Amendment to Contract for Architectural Services document (s).
Approval of the Final Guaranteed Maximum Price (GMP), budget reallocation and Amendment No. 02 meets Strategic Goal Area 6: Organizational Excellence.
Details: On June 12, 2023, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Gilbane Construction Company for the completion of the New Middle and High School at Sequoyah Project and for Pre-Construction Services in the amount of $175,000.
On May 6, 2024, the Board of Education approved the Initial Guaranteed Maximum Price of $87,044,255 for enabling work associated with the construction of the New Sequoyah Middle and High School SPLOST VI project.
On November 14, 2022, the Board approved the award of a Professional Architectural and Engineering (A/E) Services contract for the design of the New Middle and High School at Sequoyah to Goodwyn, Mills, Cawood , LLC for the amount of $9,000,000.
Pursuant to that agreement, the Design Professionals (Goodwyn, Mills, Cawood, LLC), CM@R (Gilbane), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and a Final GMP in the best interest of the DeKalb County School District.
This action establishes a Final Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached Gilbane GMP Exhibit M Amendment.
Financial impact: The total contract amount for the New Sequoyah Middle and High School project will be allocated from the general contractor construction cost code SP6NEWSCH.10136.GENCONTR under the voter-approved E-SPLOST VI program and will require a budget reallocation of $141,617,170 from E-SPLOST VI program contingency to fund this project.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
10136. Sequoyah Final GMP Proposal
Construction of New Sequoyah Middle and High School $228,661,425.00
MS & HS April 2025
Brief Description of Phase SPLOST VI Value Pending
Phase Funding Source Approved Value
Package Approval
Pre-Construction Pre-Construction Services E-SPLOST VI $175,000.00
Site work, foundations,
Early Release stormwater management, E-SPLOST VI $87,044,255.00
long lead items/equipment
New Middle and High School
Final GMP E-SPLOST VI $141,617,170.00
Buildings
Estimated Date of
Final GMP Amount Notes
Board Approval
Approved at June 2023
Board Meeting
Approved at May 2024
Board Meeting
$228,661,425.00 4/21/2025 100% CD Pricing