EXHIBIT M
GMP AMENDMENT TO AGREEMENT BETWEEN OWNER AND
CONSTRUCTION CONTRACTOR
AMENDMENT NO. 2 TO AGREEMENT BETWEEN OWNER AND
CONSTRUCTION CONTRACTOR FOR Cross Keys High School
AGREEMENT NO. 423.71.04.00.214423.752.0000
Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
(“Agreement”), dated 11/19/2018 , between The School Board of DeKalb County, Georgia
(“Owner”) and Evergreen Construction
(“Construction Contractor”), with respect to the construction of Owner’s
Cross Keys High School (“Project”), Owner and Construction
Contractor hereby agree to amend and modify the Agreement by this Amendment No. 2 and
establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
unless otherwise noted.
ARTICLE 1
SCOPE OF WORK
The scope of the Work consists of the construction of a Renovation and Modernization to Cross Keys
High School at 1626 N Druid Hills Rd, Atlanta, GA 30319,
in accordance with the Agreement, this
Amendment and the other Contract Documents listed as Attachments 1 through 5 below, which
are hereby incorporated into and made a part of the Amendment by this reference:
Attachment No. Description Pages Date
List of Drawings, Specifications and Addendums
1. Allowances 1
_____ through _____
1 1/23/25
2. Assumptions and Clarifications _____
1 through _____
5 1/23/25
3. Completion Schedule _____
1 through _____
1 1/23/25
4. Schedule of Values _____
1 8
through _____ 1/23/25
5. List of Itemized General Conditions _____
1 18
through _____ 1/23/25
6. List of Subcontractors and _____ through _____
Major Suppliers
7. Alternates _____ through _____
M-1
ARTICLE 2
GUARANTEED MAXIMUM PRICE
2.1 Construction Contractor’s Guaranteed Maximum Price (“GMP”) for the Work,
including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
Construction Management Fee as defined in Section 4 of the defined in Section
Agreement, 4 ofhundred
is One the forty three
million four hundred eighty four thousand five hundred thirty five ($ 143,484,535 ).
2.2 The Construction Management Fee for the entire Work anticipated on this Project
is hereby established as a lump sum amount of Six million ninety three thousand nine hundred eighty two
($_ 6,093,982 ), said lump sum amount is included within the above noted GMP.
2.3 The general condition expenses for the entire Work anticipated on this Project are
hereby established as a lump sum amount of Twelve million eight hundred fifty five thousand nine hundred thirteen
($ 12,855,913 ), said lump sum amount is included within the above noted GMP (“General
Conditions Expenses”). The items included as General Condition Expenses are listed in the List
of Itemized General Conditions attached hereto and incorporated herein as Attachment No. 5 .
Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
Change Order or Construction Change Directive, Construction Contractor acknowledges and
agrees that Owner shall have no liability for any General Condition expenses beyond payment of
the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
to receive any additional compensation from Owner for the General Conditions beyond the above
lump sum amount. There shall be no additional General Conditions Expenses payable to
Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
Change Directive Work). Further, there shall be no mark-up for a subcontractor’s General
Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
Change Order and Construction Change Directive Work to be performed by such subcontractor.
2.4 Monthly installment payment of the Construction Management Fee and the General
Condition Expenses shall be based upon the percent completion of the designated portion of the
Work for each particular month.
2.5 In order to efficiently and timely address any unknown or unanticipated conditions
that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
of the Work, but excluding all items that are to be reimbursed under the lump sum General
Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
Five million one hundred seventy
contingency within the GMP in an amount not-to-exceed amount of seven thousand one hundred fifty and
four
/100 Dollars ($ 5,177,154 ) (“Owner’s Contingency”). Owner’s Contingency
funds shall be used to cover costs that may result from incomplete design and unanticipated costs
that arise during construction that are not identified by the construction documents. Construction
M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner’s Contingency without first obtaining Owner’s express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner’s Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor’s Work compensated within the
GMP and not chargeable against Owner’s Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner’s Contingency expenditures. Further, the work that
is the subject of any Owner’s Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner’s Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner’s Contingency.
2.6 In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above,Sixthe parties have agreed to
million four hundred seventy
establish a contingency within the GMP in an amount not-to-exceedtwo and
one thousand four hundred forty
/100
Dollars ($6,471,442 ) (“Contractor’s Contingency”). Construction Contractor shall not proceed
with any portion of the Work which it intends to charge against the Contractor’s Contingency
without first obtaining Owner’s express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor’s
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor’s Work compensated within the GMP and not chargeable against
Contractor’s Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor’s Contingency expenditures. Further, the work that is the subject of any Owner’s
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor’s Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor’s Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of % of
the Cost of the Work charged against the Contractor’s Contingency.
2.7 The parties have agreed to establish an allowance within the GMP for
See allowances log in the amount of and /100 Dollars ($ 4,848,200 ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance (“Allowance Work”) without first obtaining Owner’s express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments 1 through. Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenever costs are more
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.
M-3
2.8 Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
payment is made to Construction Contractor the total Cost of the Work has been increased by
approved Change Orders in an amount causing the original GMP as set forth in this Amendment
to be exceeded by more than and /100 Dollars ($ ), then
Construction Contractor shall be entitled to an increase in the Construction Management Fee in
the amount of and /100 Dollars ( %) of the amount exceeding the sum of
and /100 Dollars ($ _) plus that original GMP amount.
2.9 Construction Contractor recognizes that the Contract includes work for trench
excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
set forth by all federal, state and local requirements. Construction Contractor certifies that the
required trench safety standards will be in effect during the period of construction of the Project
and Construction Contractor agrees to comply with all such required trench safety standards.
2.10.1 The amount of Zero and /100 Dollars
($ 0 ) has been separately identified for the cost of compliance with the required trench
safety standards; said amount is included within the GMP.
2.10 At the completion of the Work, should the actual amount of “General
Requirements” expenses be less than the amount included therefor in the Schedule of Values
approved by Owner, the resulting “savings” shall accrue to the benefit of Owner and a deductive
Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
separate guaranteed maximum price for such expenses and any overruns in General Requirements
expenses shall be borne by Construction Contractor without reimbursement from Owner.
2.11 By executing this Amendment and furnishing Owner with a GMP based on a
detailed Schedule of Values and a Master Project Schedule, Construction Contractor represents
and warrants that the Contract Documents, including the Construction Documents, as well as other
materials, and information furnished Construction Contractor as of the date of this Amendment
have described the scope, construction requirements, and design intent of the Work in detail
sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
Project Schedule. To the extent that the Construction Documents are anticipated to require further
development, Construction Contractor has provided in the GMP for such further development
consistent with the Contract Documents and reasonably inferable therefrom.
2.12 Savings will be computed as of the date of final completion of the Work and shall
consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
benefit of Owner.
M-4
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
CIVIL
C1.0 Cover Sheet & General Notes 8/7/2024
Boundary, Topographic, Utility & Tree Survey 3/6/2023
Boundary, Topographic, Utility & Tree Survey 3/6/2023
C2.0 Overall Demolition Plan 8/7/2024
C2.1 Demolition Plan II 8/7/2024
C2.2 Demolition Plan II 8/7/2024
C3.0 Overall Layout & Staking Plan 8/7/2024
C3.1 Layout & Staking Plan I 8/7/2024
C3.2 Layout & Staking Plan II 8/7/2024
C3.3 N. Druid Hills Rd NE & Curtis Drive Intersection Blow Up 8/7/2024
C4.0 Overall Grading Plan 8/7/2024
C4.1 Grading Plan I 8/7/2024
C4.2 Grading Plan II 8/7/2024
C4.3 Drainage Plan I 8/7/2024
C4.4 Drainage Plan II 8/7/2024
C4.5 Stormwater Details I 8/7/2024
C4.6 Stormwater Details II 8/7/2024
C5.0 Overall Utility Plan 8/7/2024
C5.1 Utility Plan I 8/7/2024
C5.2 Utility Plan II 8/7/2024
C5.3 Fire Site Access Plan 8/7/2024
C6.0 Profile Plan 8/7/2024
C6.1 Profile Plan 8/7/2024
C6.2 Profile Plan 8/7/2024
C6.3 Sanitary Sewer Profile Plan 8/7/2024
C7.0 Construction Details 8/7/2024
C7.1 Construction Details 8/7/2024
C7.2 Construction Details 8/7/2024
C7.3 Construction Details 8/7/2024
C7.4 Construction Details 8/7/2024
C7.5 Construction Details 8/7/2024
C7.6 Construction Details 8/7/2024
C7.7 ES&PC Notes 8/7/2024
EC1.0 ES&PC Notes 8/7/2024
EC1.1 ES&PC Notes 8/7/2024
EC1.2 ES&PC Notes 8/7/2024
EC1.3 ES&PC Notes 8/7/2024
EC2.0 Initial ES&PC Plan 8/7/2024
EC3.0 Intermediate ES&PC Plan 8/7/2024
EC4.0 Final ES&PC Plan 8/7/2024
EC5.0 ES&PC Details 8/7/2024
EC5.1 ES&PC Details 8/7/2024
EC5.2 ES&PC Details 8/7/2024
EC5.3 ES&PC Details 8/7/2024
EC5.4 ES&PC Details 8/7/2024
EC5.5 ES&PC Details 8/7/2024
EC5.6 ES&PC Details 8/7/2024
L0.00 Landscape General Notes 8/7/2024
L0.01 Tree Removal Plan 8/7/2024
L0.02 Tree Removal Schedule 8/7/2024
L0.03 Offsite Tree Replanting Plan - Ashford Park ES 8/7/2024
L0.04 Offsite Tree Replanting Plan - John Lewis ES 8/7/2024
L0.05 Offsite Tree Replanting Plan - Montclair ES 8/7/2024
L1.01 Hardscape Plan 8/7/2024
L1.02 Hardscape Plan 8/7/2024
L1.03 Hardscape Plan 8/7/2024
L1.04 Hardscape Plan 8/7/2024
L1.05 Hardscape Plan 8/7/2024
L2.01 Hardscape Details 7/25/2024
L2.02 Hardscape Details 8/7/2024
L3.01 Overall Landscape Plan 8/7/2024
L3.02 Landscape Plan 8/7/2024
L3.03 Landscape Plan 8/7/2024
L3.04 Landscape Plan 8/7/2024
L3.05 Landscape Plan 8/7/2024
L4.00 Landscape Details 8/7/2024
G0.00-1 Cover Sheet LDP + Phase 1 8/7/2024
A1.20 Enlarged Site Plan and Detials - Bus Loop Canopy 8/7/2024
A1.21 Enlarged Site Plan and Detials - Bus Loop Canopy 8/7/2024
S10.01 Site Retaining Walls 8/7/2024
S10.02 Bus Loop Canopy Foundation Plan and Sections 8/7/2024
E0.01 Electrical Phase 1 Bus Canopy 8/7/2024
GENERAL - VOLUME 1
G0.00 COVER SHEET 10/30/2024
G0.01 DRAWING INDEX 10/30/2024
G0.02 DRAWING INDEX 10/30/2024
G0.03 GENERAL INFORMATION 10/30/2024
G1.00 OCCUPANT LOAD SCHEDULES 10/30/2024
1 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
G1.01 MEANS OF EGRESS PLAN - LEVEL 1 10/30/2024
G1.02 MEANS OF EGRESS PLAN - LEVEL 2 & 3 10/30/2024
G1.03 MEANS OF EGRESS PLAN - LEVEL 1 ALTERNATE 10/30/2024
G2.00 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.01.1 CONSTRUCTION PHASING DIAGRAM AND FIRE SAFETY PLAN 10/30/2024
G2.01.2 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.02 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.02.1 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.02.2 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.03 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
G2.04 CONSTRUCTION PHASING DIAGRAMS 10/30/2024
CIVIL
C1.0B COVER SHEET & GENERAL NOTES 10/30/2024
SURVEY I SITE SURVEY I 10/30/2024
SURVEY II SITE SURVEY II 10/30/2024
C2.0B OVERALL DEMOLITION PLAN 10/30/2024
C2.1B DEMOLITION PLAN I 10/30/2024
C2.2B DEMOLITION PLAN II 10/30/2024
C3.0B OVERALL LAYOUT & STAKING PLAN 10/30/2024
C3.1B LAYOUT & STAKING PLAN I 10/30/2024
C3.2B LAYOUT & STAKING PLAN II 10/30/2024
C4.0B GRADING PLAN 10/30/2024
C4.1B GRADING PLAN I 10/30/2024
C4.2B GRADING PLAN II 10/30/2024
C4.3B DRAINAGE PLAN I 10/30/2024
C4.4B DRAINAGE PLAN II 10/30/2024
C5.0B UTILITY PLAN 10/30/2024
C5.1B UTILITY PLAN I 10/30/2024
C5.2B UTILITY PLAN II 10/30/2024
C5.3B FIRE SITE ACCESS PLAN 10/30/2024
C6.0B PROFILE PLAN 10/30/2024
C6.1B PIPE CHART 10/30/2024
C6.2B SANITARY SEWER PROFILE PLAN 10/30/2024
C7.0B CONSTRUCTION DETAILS 10/30/2024
C7.1B CONSTRUCTION DETAILS 10/30/2024
C7.2B CONSTRUCTION DETAILS 10/30/2024
C7.3B CONSTRUCTION DETAILS 10/30/2024
C7.4B CONSTRUCTION DETAILS 10/30/2024
C7.5B CONSTRUCTION DETAILS 10/30/2024
C7.6B CONSTRUCTION DETAILS 10/30/2024
C7.7B CONSTRUCTION DETAILS 10/30/2024
EC1.0B ES&PC NOTES 10/30/2024
EC1.1B ES&PC NOTES 10/30/2024
EC1.2B ES&PC NOTES 10/30/2024
EC1.3B ES&PC NOTES 10/30/2024
EC2.0B INITIAL ES&PC PLAN 10/30/2024
EC3.0B INTERMEDIATE ES&PC PLAN 10/30/2024
EC4.0B FINAL ES&PC PLAN 10/30/2024
EC5.0B ES&PC DETAILS 10/30/2024
EC5.1B ES&PC DETAILS 10/30/2024
EC5.2B ES&PC DETAILS 10/30/2024
EC5.3B ES&PC DETAILS 10/30/2024
EC5.4B ES&PC DETAILS 10/30/2024
EC5.5B ES&PC DETAILS 10/30/2024
EC5.6B ES&PC DETAILS 10/30/2024
LANDSCAPE
L0.00 GENERAL NOTES 10/30/2024
L1.01 OVERALL HARDSCAPE PLAN 10/30/2024
L1.02 HARDSCAPE PLAN 10/30/2024
L1.03 HARDSCAPE PLAN 10/30/2024
L1.04 HARDSCAPE PLAN 10/30/2024
L1.05 HARDSCAPE PLAN 10/30/2024
L1.06 HARDSCAPE ENLARGEMENT PLAN 10/30/2024
L1.07 HARDSCAPE ENLARGEMENT PLAN 10/30/2024
L1.08 HARDSCAPE ENLARGEMENT PLAN 10/30/2024
L1.09 TRACK AND FIELD ENLARGEMENT PLAN 10/30/2024
L1.10 GRADING PLAN - ENLARGEMENTS 10/30/2024
L1.11 GRADING PLAN - ENLARGEMENTS 10/30/2024
L1.12 GRADING PLAN - ENLARGEMENTS 10/30/2024
L1.13 GRADING PLAN - ENLARGEMENTS 10/30/2024
L1.21 OVERALL SITE LIGHTING PLAN 10/30/2024
L2.01 HARDSCAPE DETAILS 10/30/2024
L2.02 HARDSCAPE DETAILS 10/30/2024
L2.04 HARDSCAPE DETAILS 10/30/2024
L2.04 HARDSCAPE DETAILS 10/30/2024
L2.05 HARDSCAPE DETAILS 10/30/2024
L3.00A TREE REMOVAL PLAN 10/30/2024
L3.00B TREE REMOVAL SCHEDULE 10/30/2024
L3.01 OVERALL LANDSCAPE PLAN 10/30/2024
L3.02 LANDSCAPE PLAN 10/30/2024
2 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
L3.03 LANDSCAPE PLAN 10/30/2024
L3.04 LANDSCAPE PLAN 10/30/2024
L3.05 LANDSCAPE PLAN 10/30/2024
L3.06 LANDSCAPE PLAN 10/30/2024
L3.07 LANDSCAPE PLAN 10/30/2024
L4.00 LANDSCAPE NOTES AND DETAILS 10/30/2024
DEMOLITION
D1.00 DEMOLITION SITE PLAN 10/30/2024
D2.01 OVERALL LEVEL 1 DEMOLITION PLAN 10/30/2024
D2.04 DEMOLITION ROOF PLAN 10/30/2024
D2.11D DEMOLITION FLOOR PLAN - 100 WING - AREA D 10/30/2024
D2.11E DEMOLITION FLOOR PLAN - 200 WING - AREA E 10/30/2024
D2.11F DEMOLITION FLOOR PLAN - 300 WING + 400 WING - AREA F + G 10/30/2024
D2.11H DEMOLITION FLOOR PLAN - CTAE - AREA H 10/30/2024
D2.11J DEMOLITION FLOOR PLAN - GYMNASIUM 10/30/2024
D2.11K DEMOLITION FLOOR PLAN - GYMNASIUM 10/30/2024
D6.01 DEMOLITION SECTIONS & DETAILS 10/30/2024
ARCHITECTURE
A1.00 ARCHITECTURAL SITE PLAN 10/30/2024
A1.20 ENLARGED SITE PLANS AND DETAILS - BUS LOOP CANOPY 10/30/2024
A1.21 ENLARGED SITE PLANS AND DETAILS - BUS LOOP CANOPY 10/30/2024
A2.01 OVERALL LEVEL 1 FLOOR PLAN 10/30/2024
A2.02 OVERALL LEVEL 2 & 3 FLOOR PLAN 10/30/2024
A2.04 ROOF PLAN 10/30/2024
A2.11A LEVEL 1 FLOOR PLAN - AREA A 10/30/2024
A2.11B LEVEL 1 FLOOR PLAN - AREA B 10/30/2024
A2.11C LEVEL 1 FLOOR PLAN - AREA C 10/30/2024
A2.11D LEVEL 1 FLOOR PLAN - AREA D 10/30/2024
A2.11E LEVEL 1 FLOOR PLAN - AREA E 10/30/2024
A2.11F LEVEL 1 FLOOR PLAN - AREA F/G 10/30/2024
A2.11H LEVEL 1 FLOOR PLAN - AREA H 10/30/2024
A2.11J LEVEL 1 FLOOR PLAN - AREA J 10/30/2024
A2.11K LEVEL 1 FLOOR PLAN - AREA K/L 10/30/2024
A2.11M LEVEL 1 FLOOR PLAN - AREA M 10/30/2024
A2.11N LEVEL 1 FLOOR PLAN - AREA N 10/30/2024
A2.12A LEVEL 2 FLOOR PLAN - AREA A 10/30/2024
A2.12B LEVEL 2 FLOOR PLAN - AREA B 10/30/2024
A2.12C LEVEL 2 FLOOR PLAN - AREA C 10/30/2024
A2.13A LEVEL 3 FLOOR PLAN - AREA A 10/30/2024
A2.13B LEVEL 3 FLOOR PLAN - AREA B 10/30/2024
A2.13C LEVEL 3 FLOOR PLAN - AREA C 10/30/2024
A2.14A ROOF PLAN - AREA A 10/30/2024
A2.14B ROOF PLAN - AREA B 10/30/2024
A2.14C ROOF PLAN - AREA C 10/30/2024
A2.14G ROOF PLAN - AREA G 10/30/2024
A2.14H ROOF PLAN - AREA H 10/30/2024
A2.14K ROOF PLAN - AREA K 10/30/2024
A2.14M ROOF PLAN - AREA M 10/30/2024
A2.14N ROOF PLAN - AREA N 10/30/2024
A2.30 LEVEL 1 - SLAB ELEVATION DIAGRAM 10/30/2024
A2.31A LEVEL 1 EDGE-OF-SLAB PLAN - AREA A 10/30/2024
A2.31B LEVEL 1 EDGE-OF-SLAB PLAN - AREA B 10/30/2024
A2.31C LEVEL 1 EDGE-OF-SLAB PLAN - AREA C 10/30/2024
A2.31D LEVEL 1 EDGE-OF-SLAB PLAN - AREA D 10/30/2024
A2.31E LEVEL 1 EDGE-OF-SLAB PLAN - AREA E 10/30/2024
A2.31F LEVEL 1 EDGE-OF-SLAB PLAN - AREA F/G 10/30/2024
A2.31H LEVEL 1 EDGE-OF-SLAB PLAN - AREA H 10/30/2024
A2.31J LEVEL 1 EDGE-OF-SLAB PLAN - AREA J 10/30/2024
A2.31K LEVEL 1 EDGE-OF-SLAB PLAN - AREA K/L 10/30/2024
A2.31M LEVEL 1 EDGE-OF-SLAB PLAN - AREA M 10/30/2024
A2.31N LEVEL 1 EDGE-OF-SLAB PLAN - AREA N 10/30/2024
A2.32A LEVEL 2 EDGE-OF-SLAB PLAN - AREA A 10/30/2024
A2.32B LEVEL 2 EDGE-OF-SLAB PLAN - AREA B 10/30/2024
A2.32C LEVEL 2 EDGE-OF-SLAB PLAN - AREA C 10/30/2024
A2.33A LEVEL 3 EDGE-OF-SLAB PLAN - AREA A 10/30/2024
A2.33B LEVEL 3 EDGE-OF-SLAB PLAN - AREA B 10/30/2024
A2.33C LEVEL 3 EDGE-OF-SLAB PLAN - AREA C 10/30/2024
A2.34A ROOF - EDGE-OF-DECK PLAN - AREA A 10/30/2024
A2.34B ROOF - EDGE-OF-DECK PLAN - AREA B 10/30/2024
A2.34C ROOF - EDGE-OF-DECK PLAN - AREA C 10/30/2024
A2.34D ROOF - EDGE-OF-DECK PLAN - AREA G 10/30/2024
A2.34E ROOF - EDGE-OF-DECK PLAN - AREA H 10/30/2024
A2.34F ROOF - EDGE-OF-DECK PLAN - AREA K 10/30/2024
A2.34G ROOF - EDGE-OF-DECK PLAN - AREA M 10/30/2024
A2.34H ROOF - EDGE-OF-DECK PLAN - AREA N 10/30/2024
A2.40A OVERALL LEVEL 1 REFLECTED CEILING PLAN 10/30/2024
A2.40B OVERALL LEVEL 2 AND 3 REFLECTED CEILING PLANS 10/30/2024
A2.41A LEVEL 1 REFLECTED CEILING PLAN - AREA A 10/30/2024
A2.41B LEVEL 1 REFLECTED CEILING PLAN - AREA B 10/30/2024
A2.41C LEVEL 1 REFLECTED CEILING PLAN - AREA C 10/30/2024
3 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
A2.41D LEVEL 1 REFLECTED CEILING PLAN - AREA D 10/30/2024
A2.41E LEVEL 1 REFLECTED CEILING PLAN - AREA E 10/30/2024
A2.41F LEVEL 1 REFLECTED CEILING PLAN - AREA F/G 10/30/2024
A2.41H LEVEL 1 REFLECTED CEILING PLAN - AREA H 10/30/2024
A2.41J LEVEL 1 REFLECTED CEILING PLAN - AREA J 10/30/2024
A2.41K LEVEL 1 REFLECTED CEILING PLAN - AREA K/L 10/30/2024
A2.41M LEVEL 1 REFLECTED CEILING PLAN - AREA M 10/30/2024
A2.41N LEVEL 1 REFLECTED CEILING PLAN - AREA N 10/30/2024
A2.42A LEVEL 2 REFLECTED CEILING PLAN - AREA A 10/30/2024
A2.42B LEVEL 2 REFLECTED CEILING PLAN - AREA B 10/30/2024
A2.42C LEVEL 2 REFLECTED CEILING PLAN - AREA C 10/30/2024
A2.43A LEVEL 3 REFLECTED CEILING PLAN - AREA A 10/30/2024
A2.43B LEVEL 3 REFLECTED CEILING PLAN - AREA B 10/30/2024
A2.43C LEVEL 3 REFLECTED CEILING PLAN - AREA C 10/30/2024
A2.44 ENLARGED CEILING PLANS 10/30/2024
A2.50A FINISH SCHEDULES 10/30/2024
A2.50B TYPICAL INTERIOR DETAILS 10/30/2024
A2.51A LEVEL 1 FINISH PLAN - AREA A 10/30/2024
A2.51B LEVEL 1 FINISH PLAN - AREA B 10/30/2024
A2.51C LEVEL 1 FINISH PLAN - AREA C 10/30/2024
A2.51D LEVEL 1 FINISH PLAN - AREA D 10/30/2024
A2.51E LEVEL 1 FINISH PLAN - AREA E 10/30/2024
A2.51F LEVEL 1 FINISH PLAN - AREA F/G 10/30/2024
A2.51H LEVEL 1 FINISH PLAN - AREA H 10/30/2024
A2.51J LEVEL 1 FINISH PLAN - AREA J 10/30/2024
A2.51K LEVEL 1 FINISH PLAN - AREA K/L 10/30/2024
A2.51M LEVEL 1 FINISH PLAN - AREA M 10/30/2024
A2.51N LEVEL 1 FINISH PLAN - AREA N 10/30/2024
A2.52A LEVEL 2 FINISH PLAN - AREA A 10/30/2024
A2.52B LEVEL 2 FINISH PLAN - AREA B 10/30/2024
A2.52C LEVEL 2 FINISH PLAN - AREA C 10/30/2024
A2.53A LEVEL 3 FINISH PLAN - AREA A 10/30/2024
A2.53B LEVEL 3 FINISH PLAN - AREA B 10/30/2024
A2.53C LEVEL 3 FINISH PLAN - AREA C 10/30/2024
A2.61A LEVEL 1 FURNITURE PLAN - AREA A 10/30/2024
A2.61B LEVEL 1 FURNITURE PLAN - AREA B 10/30/2024
A2.61C LEVEL 1 FURNITURE PLAN - AREA C 10/30/2024
A2.61D LEVEL 1 FURNITURE PLAN - AREA D 10/30/2024
A2.61E LEVEL 1 FURNITURE PLAN - AREA E 10/30/2024
A2.61F LEVEL 1 FURNITURE PLAN - AREA F/G 10/30/2024
A2.61H LEVEL 1 FURNITURE PLAN - AREA H 10/30/2024
A2.61J LEVEL 1 FURNITURE PLAN - AREA J 10/30/2024
A2.61K LEVEL 1 FURNITURE PLAN - AREA K/L 10/30/2024
A2.61M LEVEL 1 FURNITURE PLAN - AREA M 10/30/2024
A2.61N LEVEL 1 FURNITURE PLAN - AREA N 10/30/2024
A2.62A LEVEL 2 FURNITURE PLAN - AREA A 10/30/2024
A2.62B LEVEL 2 FURNITURE PLAN - AREA B 10/30/2024
A2.62C LEVEL 2 FURNITURE PLAN - AREA C 10/30/2024
A2.63A LEVEL 3 FURNITURE PLAN - AREA A 10/30/2024
A2.63B LEVEL 3 FURNITURE PLAN - AREA B 10/30/2024
A2.63C LEVEL 3 FURNITURE PLAN - AREA C 10/30/2024
A2.70 SIGNAGE DETAILS 10/30/2024
A2.71 OVERALL SIGNAGE LOCATION PLAN - LEVEL 1 10/30/2024
A2.71A SIGNAGE LOCATION PLAN - LEVEL 1 - AREA A, B, & C 10/30/2024
A2.71D SIGNAGE LOCATION PLAN - LEVEL 1 - AREA D & E 10/30/2024
A2.71F SIGNAGE LOCATION PLAN - LEVEL 1 - AREA F, G, & H 10/30/2024
A2.71J SIGNAGE LOCATION PLAN - LEVEL 1 - AREA J, K, L, M, & N 10/30/2024
A2.72 SIGNAGE LOCATION PLAN - LEVEL 2 10/30/2024
A2.73 SIGNAGE LOCATION PLAN - LEVEL 3 10/30/2024
A3.00 TYPICAL PLUMBING PLANS, ACCESSORIES & DETAILS 10/30/2024
A3.01 ENLARGED RESTROOM PLANS 10/30/2024
A3.02 ENLARGED RESTROOM PLANS 10/30/2024
A3.03 ENLARGED RESTROOM PLANS 10/30/2024
A3.04 ENLARGED RESTROOM PLANS 10/30/2024
A3.05 ENLARGED RESTROOM PLANS 10/30/2024
A3.06 ENLARGED RESTROOM PLANS 10/30/2024
A3.07 ENLARGED RESTROOM PLANS 10/30/2024
A3.10 ENLARGED CLASSROOM PLANS 10/30/2024
A3.21 ENLARGED TEACHER PLANNING ROOMS 10/30/2024
A3.22 ENLARGED HOME LIVING CENTER & LTSE CLASSROOM 10/30/2024
A3.23 ENLARGED SAFE CENTER 10/30/2024
A3.31 ENLARGED BAND SUITE 10/30/2024
A3.32 ENLARGED ORCHESTRA SUITE 10/30/2024
A3.34 ENLARGED KEYBOARD & PRACTICE ROOMS 10/30/2024
A3.37 ENLARGED BLACK BOX THEATER, CONCESSIONS & TICKETING 10/30/2024
A3.38 ENLARGED DIGITAL ART LAB 10/30/2024
A3.40 ENLARGED CAREER CENTER 10/30/2024
A3.44 ENLARGED JROTC SUITE 10/30/2024
A3.47 ENLARGED CULINARY LAB 10/30/2024
A3.50 ENLARGED MEDIA CENTER 10/30/2024
4 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
A3.51 INTERIOR ELEVATIONS - RECEPTION & MEDIA CENTER 10/30/2024
A3.52 INTERIOR ELEVATIONS - MEDIA CENTER 10/30/2024
A3.53 INTERIOR ELEVATIONS - MEDIA CENTER 10/30/2024
A3.60 ENLARGED GYMNASIUM 10/30/2024
A3.61 GYMNASIUM STRIPING PLAN 10/30/2024
A3.62 ENLARGED AUX GYMNASIUM 10/30/2024
A3.64 INTERIOR ELEVATIONS - GYMNASIUM 10/30/2024
A3.65 INTERIOR ELEVATIONS - GYMNASIUM 10/30/2024
A3.66 ENLARGED GYMNASIUM LOCKER ROOMS & TRAINING ROOM 10/30/2024
A3.67 ENLARGED WRESTLING ROOM 10/30/2024
A3.68 ENLARGED WEIGHT ROOM 10/30/2024
A3.69 ENLARGED HEALTH ROOMS 10/30/2024
A3.70 ENLARGED DINING/COMMONS 10/30/2024
A3.72 INTERIOR ELEVATIONS - DINING / COFFEE BAR LOUNGE 10/30/2024
A3.73 INTERIOR ELEVATIONS - DINING / COFFEE BAR LOUNGE 10/30/2024
A3.90 ENLARGED AUDITORIUM 10/30/2024
A3.91 INTERIOR ELEVATIONS - AUDITORIUM 10/30/2024
A3.92 ENLARGED AUDITORIUM DRESSING ROOMS 10/30/2024
A3.94 ENLARGED EXTENDED LEARNING 10/30/2024
A3.95 INTERIOR ELEVATIONS - EXTENDED LEARNING 10/30/2024
A3.96 INTERIOR ELEVATIONS - CLASSROOM CORRIDORS 10/30/2024
A4.00 EXTERIOR ELEVATIONS 10/30/2024
A4.01 EXTERIOR ELEVATIONS 10/30/2024
A4.02 EXTERIOR ELEVATIONS 10/30/2024
A4.03 EXTERIOR ELEVATIONS 10/30/2024
A4.04 EXTERIOR ELEVATIONS 10/30/2024
A4.10 BUILDING SECTIONS 10/30/2024
A4.11 BUILDING SECTIONS 10/30/2024
A5.01 EXTERIOR WALL SECTIONS - AREA A 10/30/2024
A5.02 EXTERIOR WALL SECTIONS - AREA A 10/30/2024
A5.03 EXTERIOR WALL SECTIONS - AREA A 10/30/2024
A5.04 EXTERIOR WALL SECTIONS - AREA A 10/30/2024
A5.07 EXTERIOR WALL SECTIONS - AREA A 10/30/2024
A5.08 EXTERIOR WALL SECTIONS - AREA B 10/30/2024
A5.09 EXTERIOR WALL SECTIONS - AREA C 10/30/2024
A5.10 EXTERIOR WALL SECTIONS - AREA C 10/30/2024
A5.11 EXTERIOR WALL SECTIONS - AREA H 10/30/2024
A5.12 EXTERIOR WALL SECTIONS - AREA K 10/30/2024
A5.13 EXTERIOR WALL SECTIONS - AREA M 10/30/2024
A5.14 EXTERIOR WALL SECTIONS - AREA N 10/30/2024
A5.15 EXTERIOR WALL SECTIONS - AREA N 10/30/2024
A5.16 EXTERIOR WALL SECTIONS - AREA N 10/30/2024
A5.17 EXTERIOR WALL SECTIONS - AREA N 10/30/2024
A6.00 EXTERIOR ASSEMBLIES 10/30/2024
A6.01 PLAN DETAILS 10/30/2024
A6.02 PLAN DETAILS 10/30/2024
A6.11 SECTION DETAILS 10/30/2024
A6.12 SECTION DETAILS 10/30/2024
A6.13 SECTION DETAILS 10/30/2024
A6.14 SECTION DETAILS 10/30/2024
A6.15 SECTION DETAILS 10/30/2024
A6.16 SECTION DETAILS 10/30/2024
A6.17 SECTION DETAILS 10/30/2024
A6.18 SECTION DETAILS 10/30/2024
A6.19 SECTION DETAILS 10/30/2024
A6.20 TYPICAL BRICK DETAILS 10/30/2024
A6.21 TYPICAL PARAPET DETAILS 10/30/2024
A6.22 TYPICAL CURTAINWALL DETAILS 10/30/2024
A6.23 TYPICAL STOREFRONT DETAILS 10/30/2024
A6.24 SECTION DETAILS 10/30/2024
A6.30 ROOF DETAILS 10/30/2024
A6.31 ROOF DETAILS 10/30/2024
A6.32 ROOF DETAILS 10/30/2024
A6.41 EXPANSION JOINT - DETAILS 10/30/2024
A6.42 EXPANSION JOINT - DETAILS 10/30/2024
A6.43 EXPANSION JOINT - DETAILS 10/30/2024
A6.44 EXPANSION JOINT - DETAILS 10/30/2024
A6.45 EXPANSION JOINT - DETAILS 10/30/2024
A6.61 EXTERIOR CANOPY - AREA A - SECTIONS AND DETAILS 10/30/2024
A6.62 EXTERIOR CANOPY - AREA A - SECTIONS AND DETAILS 10/30/2024
A6.63 EXTERIOR CANOPY - AREA C - SECTIONS AND DETAILS 10/30/2024
A6.64 EXTERIOR CANOPY - AREA N - SECTIONS AND DETAILS 10/30/2024
A6.81 INTERIOR SECTION DETAILS 10/30/2024
A6.82 INTERIOR SECTION DETAILS 10/30/2024
A7.01 STAIR PLANS & SECTIONS - STAIR 1 10/30/2024
A7.01A STAIR PLANS & SECTIONS - STAIR 1 10/30/2024
A7.02 STAIR PLANS & SECTIONS - STAIR 2 10/30/2024
A7.03 STAIR PLANS & SECTIONS - STAIR 3 10/30/2024
A7.04 STAIRS AND RAMPS PLANS & SECTIONS 10/30/2024
A7.05 STAIRS AND RAMPS PLANS & SECTIONS 10/30/2024
5 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
A7.06 STAIRS AND RAMPS PLANS & SECTIONS 10/30/2024
A7.07 METAL PAN STAIR & RAILING DETAILS 10/30/2024
A7.08 RAILING DETAILS 10/30/2024
A7.10 ELEVATOR PLANS, ELEVATIONS, SECTIONS & DETAILS 10/30/2024
A8.00 DOOR TYPES 10/30/2024
A8.01 DOOR SCHEDULE 10/30/2024
A8.02 DOOR SCHEDULE 10/30/2024
A8.10 DOOR DETAILS 10/30/2024
A8.20 WINDOW SCHEDULE 10/30/2024
A8.21 WINDOW SCHEDULE 10/30/2024
A8.22 WINDOW SCHEDULE 10/30/2024
A8.23 WINDOW SCHEDULE 10/30/2024
A9.01 INTERIOR PARTITIONS 10/30/2024
A9.02 INTERIOR PARTITIONS 10/30/2024
A9.11 FIRE PROTECTION DETAILS 10/30/2024
A9.12 FIRE PROTECTION DETAILS 10/30/2024
A9.13 FIRE PROTECTION DETAILS 10/30/2024
A10.01 MILLWORK DETAILS 10/30/2024
A10.02 MILLWORK DETAILS 10/30/2024
A10.03 MILLWORK DETAILS 10/30/2024
A10.04 MILLWORK DETAILS 10/30/2024
LAB FURNISHINGS
LF1.00 GENERAL LAB NOTES 10/30/2024
LF1.01 LAB EXHAUST, SINK & EQUIPMENT SCHEDULES 10/30/2024
LF3.01 ENLARGED WET LAB 10/30/2024
LF3.02 ENLARGED DRY LAB 10/30/2024
LF3.11 ENLARGED ENGINEERING LAB 10/30/2024
LF3.21 ENLARGED MAKER SPACE 10/30/2024
LF3.31 ENLARGED SCENE SHOP 10/30/2024
LF4.01 LAB DETAILS 10/30/2024
LF4.02 LAB DETAILS 10/30/2024
FOOD SERVICE
QF0.0 FOODSERVICE GENERAL NOTES 10/30/2024
QF0.1 FOODSERVICE EQUIPMENT STANDARD DETAILS 10/30/2024
QF0.2 FOODSERVICE EQUIPMENT STANDARD DETAILS 10/30/2024
QF0.3 FOODSERVICE EQUIPMENT STANDARD DETAILS 10/30/2024
QF0.4 FOODSERVICE EQUIPMENT STANDARD DETAILS 10/30/2024
QF0.5 FOODSERVICE EQUIPMENT STANDARD DETAILS 10/30/2024
QF1.0 FOODSERVICE EQUIPMENT PLAN - OVERALL 10/30/2024
QF1.1 FOODSERVICE EQUIPMENT PLAN - OVERALL KITCHEN 10/30/2024
QF1.2 FOODSERVICE EQUIPMENT PLAN - KITCHEN NORTH 10/30/2024
QF1.3 FOODSERVICE EQUIPMENT PLAN - KITCHEN SOUTH 10/30/2024
QF1.4 FOODSERVICE EQUIPMENT SCHEDULE - KN 10/30/2024
QF1.5 FOODSERVICE EQUIPMENT SCHEDULE - KS 10/30/2024
QF1.6 FOODSERVICE EQUIPMENT SCHEDULE - KS CONT. 10/30/2024
QF1.7 FOODSERVICE EQUIPMENT PLAN - CONCESSION STANDS 10/30/2024
QF1.8 FOODSERVICE EQUIPMENT PLAN - CULINARY CLASSROOM 10/30/2024
QF1.9 FOODSERVICE EQUIPMENT SCHEDULE - CULINARY CLASSROOM 10/30/2024
QF2.1 FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - KN 10/30/2024
QF2.2 FOODSERVICE EQUIPMENT ELEVATIONS - KN 10/30/2024
QF2.3 FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - KS 10/30/2024
QF2.4 FOODSERVICE EQUIPMENT ELEVATIONS - KS 10/30/2024
QF2.5 FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - CL 10/30/2024
QF2.6 FOODSERVICE EQUIPMENT ELEVATIONS - CL 10/30/2024
QF2.7 FOODSERVICE EQUIPMENT ISOMETRIC VIEWS 10/30/2024
QF2.8 FOODSERVICE EQUIPMENT ISOMETRIC VIEWS 10/30/2024
QF3.1 FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN KN 10/30/2024
QF3.2 FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN KS 10/30/2024
QF3.3 FOODSERVICE EQUIPMENT PLUMBING DRAIN KN 10/30/2024
QF3.4 FOODSERVICE EQUIPMENT PLUMBING DRAIN KS 10/30/2024
QF3.5 FOODSERVICE EQUIPMENT PLUMBING CS 10/30/2024
QF3.6 FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN CL 10/30/2024
QF3.7 FOODSERVICE EQUIPMENT PLUMBING DRAIN PLAN CL 10/30/2024
QF4.1 FOODSERVICE EQUIPMENT ELETRICAL PLAN KN 10/30/2024
QF4.2 FOODSERVICE EQUIPMENT ELETRICAL PLAN KS 10/30/2024
QF4.3 FOODSERVICE EQUIPMENT ELETRICAL SCHEDULE - KS 10/30/2024
QF4.4 FOODSERVICE EQUIPMENT ELETRICAL PLAN CS 10/30/2024
QF4.5 FOODSERVICE EQUIPMENT ELETRICAL PLAN CL 10/30/2024
QF5.1 FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN KN 10/30/2024
QF5.2 FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN KS 10/30/2024
QF5.3 FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN CL 10/30/2024
QF6.01 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.02 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.03 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.04 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.05 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.06 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.07 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.08 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.09 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
6 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
QF6.10 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.11 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.12 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.13 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.14 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.15 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.16 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.17 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.18 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.19 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.20 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.21 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.22 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.23 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.24 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.25 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.26 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.27 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.28 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF6.29 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 10/30/2024
QF7.1 FOODSERVICE WALK-IN VENDOR DETAILS 10/30/2024
QF7.2 FOODSERVICE REFRIGERATION SYSTEM VENDOR DETAILS 10/30/2024
QF7.3 FOODSERVICE REFRIGERATION SYSTEM VENDOR DETAILS 10/30/2024
QF8.1 FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN KITCHEN NORTH 10/30/2024
QF8.2 FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN KITCHEN SOUTH 10/30/2024
QF8.3 FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN CULINARY KITCHEN 10/30/2024
QF8.4 FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN CONCESSION STANDS 10/30/2024
GENERAL - VOLUME 2
G0.01 COVER SHEET 10/30/2024
G0.02 DRAWING INDEX 10/30/2024
STRUCTURAL
S0.00 GENERAL NOTES 10/30/2024
S0.01 GENERAL NOTES 10/30/2024
S0.02 3D VIEWS 10/30/2024
S0.03 LOAD MAP 10/30/2024
S0.04 LOAD MAP 10/30/2024
S1.01 TYPICAL SECTIONS AND DETAILS 10/30/2024
S1.02 TYPICAL SECTIONS AND DETAILS 10/30/2024
S1.03 TYPICAL CMU WALL DETAILS 10/30/2024
S1.04 TYPICAL CMU WALL DETAILS 10/30/2024
S1.05 TYPICAL CMU WALL DETAILS 10/30/2024
S1.06 TYPICAL COMPOSITE SLAB DETAILS 10/30/2024
S1.07 TYPICAL COMPOSITE SLAB DETAILS 10/30/2024
S1.08 TYPICAL COMPOSITE SLAB DETAILS 10/30/2024
S1.09 TYPICAL STEEL BEAM DETAILS 10/30/2024
S1.10 TYPICAL STEEL JOIST DETAILS 10/30/2024
S1.11 TYPICAL ROOF DETAILS 10/30/2024
S2.01 OVERALL LEVEL 1 FOUNDATION PLAN 10/30/2024
S2.02 OVERALL LEVEL 2 FRAMING PLAN 10/30/2024
S2.03 OVERALL LEVEL 3 FRAMING PLAN 10/30/2024
S2.04 OVERALL ROOF FRAMING PLAN 10/30/2024
S2.11A LEVEL 1 FOUNDATION PLAN - NEW BUILDING SOUTH 10/30/2024
S2.11C LEVEL 1 FOUNDATION PLAN - NEW BUILDING NORTH 10/30/2024
S2.11G LEVEL 1 FOUNDATION PLAN - NEW BUILDING NORTH AREA G 10/30/2024
S2.11H LEVEL 1 & ROOF PLANS - HALLWAY H 10/30/2024
S2.11J LEVEL 1 FOUNDATION PLAN - AREA J 10/30/2024
S2.11K LEVEL 1 FOUNDATION PLAN - AREA K 10/30/2024
S2.11L LEVEL 1 FOUNDATION PLAN - AREA L 10/30/2024
S2.11M LEVEL 1 FOUNDATION PLAN - MUSIC SUITES 10/30/2024
S2.11N LEVEL 1 FOUNDATION PLAN - AUDITORIUM 10/30/2024
S2.12A LEVEL 2 FRAMING PLAN - NEW BUILDING SOUTH 10/30/2024
S2.12C LEVEL 2 FRAMING PLAN - NEW BUILDING NORTH 10/30/2024
S2.12G LEVEL 2 FRAMING PLAN - NEW BUILDING NORTH AREA G 10/30/2024
S2.13A LEVEL 3 FRAMING PLAN - NEW BUILDING SOUTH 10/30/2024
S2.13C LEVEL 3 FRAMING PLAN - NEW BUILDING NORTH 10/30/2024
S2.14A ROOF FRAMING PLAN - NEW BUILDING SOUTH 10/30/2024
S2.14C ROOF FRAMING PLAN - NEW BUILDING NORTH 10/30/2024
S2.14K ROOF FRAMING PLAN - AREA K 10/30/2024
S2.14L ROOF FRAMING PLAN - AREA L 10/30/2024
S2.14M ROOF PLAN - MUSIC SUITES 10/30/2024
S2.14N ROOF PLAN - AUDITORIUM 10/30/2024
S3.01 FOUNDATION SECTIONS AND DETAILS 10/30/2024
S3.02 FOUNDATION SECTIONS AND DETAILS 10/30/2024
S3.03 FOUNDATION SECTIONS AND DETAILS 10/30/2024
S3.04 FOUNDATION SECTIONS AND DETAILS 10/30/2024
S3.10 FOUNDATION SECTIONS AND DETAILS 10/30/2024
S4.01 NEW NORTH BUILDING STEEL COLUMN SCHEDULE 10/30/2024
S4.02 NEW SOUTH BUILDING STEEL COLUMN SCHEDULE 10/30/2024
S4.03 NEW SOUTH BUILDING STEEL COLUMN SCHEDULE 10/30/2024
7 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
S4.04 AUDITORIUM AND MUSIC SUITES STEEL COLUMN SCHEDULE 10/30/2024
S4.05 AUDITORIUM AND MUSIC SUITES STEEL COLUMN SCHEDULE 10/30/2024
S4.11 BRACED FRAME TYPICAL DETAILS 10/30/2024
S4.12 BRACED FRAME ELEVATIONS 10/30/2024
S5.01 SECTIONS AND DETAILS 10/30/2024
S5.02 SECTIONS AND DETAILS 10/30/2024
S5.03 SECTIONS AND DETAILS 10/30/2024
S5.04 SECTIONS AND DETAILS 10/30/2024
S5.10 SECTIONS AND DETAILS 10/30/2024
S5.11 SECTIONS AND DETAILS 10/30/2024
S5.12 SECTIONS AND DETAILS 10/30/2024
S6.01 NEW BUILDING CANOPIES 10/30/2024
S7.01 JOIST LOADING DIAGRAMS 10/30/2024
S9.00 FRP SECTIONS & DETAILS 10/30/2024
S9.01 FRP SECTIONS & DETAILS 10/30/2024
S10.01 SITE RETAINING WALLS 10/30/2024
S10.02 BUS LOOP CANOPY FOUNDATION PLAN AND SECTIONS 10/30/2024
MECHANICAL
M0.01 HVAC GENERAL NOTES & LEGEND 10/30/2024
M1.01 HVAC DEMO WORK - LEVEL 1 - AREA A 10/30/2024
M1.02 HVAC DEMO WORK - LEVEL 1 - AREA B 10/30/2024
M1.03 HVAC DEMO WORK - LEVEL 1 - AREA C 10/30/2024
M1.04 HVAC DEMO WORK - LEVEL 1 - AREA D 10/30/2024
M1.05 HVAC DEMO WORK - LEVEL 1 - AREA E 10/30/2024
M1.06 HVAC DEMO WORK - LEVEL 1 - AREA F 10/30/2024
M1.07 HVAC DEMO WORK - LEVEL 1 - AREA G 10/30/2024
M1.08 HVAC DEMO WORK - LEVEL 1 - AREA H 10/30/2024
M1.09 HVAC DEMO WORK - LEVEL 1 - AREA J 10/30/2024
M1.10 HVAC DEMO WORK - MEZZANINE - AREA J 10/30/2024
M1.11 HVAC DEMO WORK - LEVEL 1 - AREA K 10/30/2024
M1.12 HVAC DEMO WORK - LEVEL 1 - AREA L 10/30/2024
M1.13 HVAC DEMO WORK - LEVEL 1 - AREA M 10/30/2024
M1.14 HVAC DEMO WORK - LOW ROOF - AREA A, B, & C 10/30/2024
M1.15 HVAC DEMO WORK - LOW ROOF - AREA D & E 10/30/2024
M1.16 HVAC DEMO WORK - LOW ROOF - AREA F, G, H 10/30/2024
M1.17 HVAC DEMO WORK - MID ROOF - AREA J, K, & L 10/30/2024
M1.18 PIPING DEMO WORK - LEVEL 1 - AREA A 10/30/2024
M1.19 PIPING DEMO WORK - LEVEL 1 - AREA B 10/30/2024
M1.20 PIPING DEMO WORK - LEVEL 1 - AREA C 10/30/2024
M1.21 PIPING DEMO WORK - LEVEL 1 - AREA D 10/30/2024
M1.22 PIPING DEMO WORK - LEVEL 1 - AREA E 10/30/2024
M1.23 PIPING DEMO WORK - LEVEL 1 - AREA F 10/30/2024
M1.24 PIPING DEMO WORK - LEVEL 1 - AREA G 10/30/2024
M1.25 PIPING DEMO WORK - LEVEL 1 - AREA H 10/30/2024
M2.01 HVAC NEW WORK - LEVEL 1 - AREA A 10/30/2024
M2.02 HVAC NEW WORK - LEVEL 1 - AREA B 10/30/2024
M2.03 HVAC NEW WORK - LEVEL 1 - AREA C 10/30/2024
M2.04 HVAC NEW WORK - LEVEL 1 - AREA D 10/30/2024
M2.05 HVAC NEW WORK - LEVEL 1 - AREA E 10/30/2024
M2.06 HVAC NEW WORK - LEVEL 1 - AREA F 10/30/2024
M2.07 HVAC NEW WORK - LEVEL 1 - AREA G 10/30/2024
M2.08 HVAC NEW WORK - LEVEL 1 - AREA H 10/30/2024
M2.09 HVAC NEW WORK - LEVEL 1 - AREA J 10/30/2024
M2.10 HVAC NEW WORK - MEZZANINE - AREA J 10/30/2024
M2.11 HVAC NEW WORK - LEVEL 1 - AREA K 10/30/2024
M2.12 HVAC NEW WORK - LEVEL 1 - AREA L 10/30/2024
M2.13 HVAC NEW WORK - LEVEL 1 - AREA M 10/30/2024
M2.14 HVAC NEW WORK - LEVEL 1 - AREA N 10/30/2024
M2.15 HVAC NEW WORK - LEVEL 2 - AREA A 10/30/2024
M2.16 HVAC NEW WORK - LEVEL 2 - AREA B 10/30/2024
M2.17 HVAC NEW WORK - LEVEL 2 - AREA C 10/30/2024
M2.18 HVAC NEW WORK - LEVEL 3 - AREA A 10/30/2024
M2.19 HVAC NEW WORK - LEVEL 3 - AREA B 10/30/2024
M2.20 HVAC NEW WORK - LEVEL 3 - AREA C 10/30/2024
M2.21 HVAC NEW WORK - HIGH ROOF - AREA A, B, & C 10/30/2024
M2.22 HVAC NEW WORK - LOW ROOF - AREA D & E 10/30/2024
M2.23 HVAC NEW WORK - LOW ROOF - AREA F, G, & H 10/30/2024
M2.24 HVAC NEW WORK - MID ROOF - AREA J, K, & L 10/30/2024
M2.25 HVAC NEW WORK - MID ROOF - AREA M & N 10/30/2024
M3.01 PIPING NEW WORK - LEVEL 1 - AREA A 10/30/2024
M3.02 PIPING NEW WORK - LEVEL 1 - AREA B 10/30/2024
M3.03 PIPING NEW WORK - LEVEL 1 - AREA C 10/30/2024
M3.04 PIPING NEW WORK - LEVEL 1 - AREA D 10/30/2024
M3.05 PIPING NEW WORK - LEVEL 1 - AREA E 10/30/2024
M3.06 PIPING NEW WORK - LEVEL 1 - AREA F 10/30/2024
M3.07 PIPING NEW WORK - LEVEL 1 - AREA G 10/30/2024
M3.08 PIPING NEW WORK - LEVEL 1 - AREA H 10/30/2024
M3.09 PIPING NEW WORK - LEVEL 1 - AREA J 10/30/2024
M3.10 PIPING NEW WORK - LEVEL 1 - AREA K 10/30/2024
M3.11 PIPING NEW WORK - LEVEL 1 - AREA L 10/30/2024
8 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
M3.12 PIPING NEW WORK - LEVEL 1 - AREA M 10/30/2024
M3.13 PIPING NEW WORK - LEVEL 1 - AREA N 10/30/2024
M3.14 PIPING NEW WORK - LEVEL 2 - AREA A 10/30/2024
M3.15 PIPING NEW WORK - LEVEL 2 - AREA B 10/30/2024
M3.16 PIPING NEW WORK - LEVEL 2 - AREA C 10/30/2024
M3.17 PIPING NEW WORK - LEVEL 3 - AREA A 10/30/2024
M3.18 PIPING NEW WORK - LEVEL 3 - AREA B 10/30/2024
M3.19 PIPING NEW WORK - LEVEL 3 - AREA C 10/30/2024
M4.01 HVAC SECTIONS 10/30/2024
M4.02 HVAC SECTIONS 10/30/2024
M4.03 HVAC SECTIONS 10/30/2024
M4.04 HVAC SECTIONS 10/30/2024
M4.05 HVAC LARGE SCALE PLANS 10/30/2024
M4.06 HVAC ADDITIONAL VIEWS 10/30/2024
M5.01 HVAC DETAILS 10/30/2024
M5.02 HVAC DETAILS 10/30/2024
M5.03 HVAC DETAILS 10/30/2024
M5.04 HVAC DETAILS 10/30/2024
M6.01 HVAC SCHEDULES 10/30/2024
M6.02 HVAC SCHEDULES 10/30/2024
M6.03 HVAC SCHEDULES 10/30/2024
M7.01 HVAC CONTROLS 10/30/2024
M7.02 HVAC CONTROLS 10/30/2024
M7.03 HVAC CONTROLS 10/30/2024
M7.04 HVAC CONTROLS 10/30/2024
M7.05 HVAC CONTROLS 10/30/2024
M7.06 HVAC CONTROLS 10/30/2024
PLUMBING
P0.01 PLUMBING NOTES & SCHEDULES 10/30/2024
P0.02 PLUMBING DETAILS 10/30/2024
P0.03 PLUMBING DETAILS 10/30/2024
P0.04 NATURAL GAS RISER - EXISTING/TEMPORARY 10/30/2024
P0.05 NATURAL GAS RISER - DEMOLITION 10/30/2024
P0.06 NATURAL GAS RISER - NEW WORK 10/30/2024
P1.00 PLUMBING OVERALL DEMOLITION PLAN - LEVEL 1 10/30/2024
P1.01 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA A 10/30/2024
P1.02 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA B 10/30/2024
P1.03 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA C 10/30/2024
P1.04 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA D 10/30/2024
P1.05 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA E 10/30/2024
P1.06 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA F & G 10/30/2024
P1.07 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA H 10/30/2024
P1.08 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA J 10/30/2024
P1.09 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA K & L 10/30/2024
P1.10 PLUMBING DEMOLITION PLAN - ROOF - AREA A, B & C 10/30/2024
P1.11 PLUMBING DEMOLITION PLAN - ROOF - AREA D & E 10/30/2024
P1.12 PLUMBING DEMOLITION PLAN - ROOF - AREA F, G & H 10/30/2024
P1.13 PLUMBING DEMOLITION PLAN - ROOF - AREA J, K & L 10/30/2024
P2.00 PLUMIBNG OVERALL NEW WORK PLAN - LEVEL 1 10/30/2024
P2.01 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA A 10/30/2024
P2.02 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA B 10/30/2024
P2.03 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA C 10/30/2024
P2.04 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA D 10/30/2024
P2.05 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA E 10/30/2024
P2.06 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA F & G 10/30/2024
P2.07 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA H 10/30/2024
P2.08 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA J 10/30/2024
P2.09 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA K & L 10/30/2024
P2.10 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA M 10/30/2024
P2.11 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA N 10/30/2024
P2.12 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA A 10/30/2024
P2.13 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA B 10/30/2024
P2.14 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA C 10/30/2024
P2.15 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA A 10/30/2024
P2.16 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA B 10/30/2024
P2.17 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA C 10/30/2024
P2.18 PLUMBING NEW WORK PLAN - ROOF - AREA A, B & C 10/30/2024
P2.19 PLUMBING NEW WORK PLAN - ROOF - AREA D & E 10/30/2024
P2.20 PLUMBING NEW WORK PLAN - ROOF - AREA F, G & H 10/30/2024
P2.21 PLUMBING NEW WORK PLAN - ROOF - AREA J, K & L 10/30/2024
P2.22 PLUMBING NEW WORK PLAN - ROOF - AREA M & N 10/30/2024
P3.01 PLUMBING PART PLANS - KITCHEN DRAINAGE 10/30/2024
P3.02 PLUMBING PART PLANS - KITCHEN SUPPLY 10/30/2024
P3.03 PLUMBING PART PLANS - AREA A RESTROOMS 10/30/2024
P3.04 PLUMBING PART PLANS - AREA B RESTROOMS 10/30/2024
P3.05 PLUMBING PART PLANS - LEVEL 2 & 3 - AREA A 10/30/2024
P3.06 PLUMBING PART PLANS - LEVEL 2 - AREA B 10/30/2024
P3.07 PLUMBING PART PLANS - LEVEL 3 - AREA B 10/30/2024
P3.08 PLUMBING PART PLANS - LEVEL 2 - AREA C - DRAINAGE 10/30/2024
P3.09 PLUMBING PART PLANS - LEVEL 3 - AREA C - DRAINAGE 10/30/2024
9 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
P3.10 PLUMBING PART PLANS - LEVEL 2 - AREA C - SUPPLY 10/30/2024
P3.11 PLUMBING PART PLANS - LEVEL 3 - AREA C - SUPPLY 10/30/2024
P3.12 PLUMBING PART PLANS 10/30/2024
P3.13 PLUMBING PART PLANS 10/30/2024
P4.01 PLUMBING RISERS - GREASE WASTE & VENT 10/30/2024
P4.02 PLUMBING RISERS - LAB WASTE & VENT 10/30/2024
P4.03 PLUMBING RISERS - DRAINAGE 10/30/2024
P4.04 PLUMBING RISERS - DRAINAGE 10/30/2024
FIRE PROTECTION
FP0.01 FIRE PROTECTION NOTES & DETAILS 10/30/2024
FP1.00 FIRE PROTECTION OVERALL PLAN - LEVEL 1 10/30/2024
FP1.01 FIRE PROTECTION OVERALL PLAN - LEVEL 2 & 3 10/30/2024
FP2.01 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA A, B, D & E 10/30/2024
FP2.02 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA J, K & L 10/30/2024
FP2.03 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA C, F, G & H 10/30/2024
FP2.04 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA M & N 10/30/2024
FP2.11 FIRE PROTECTION NEW WORK PLAN - LEVEL 2 - AREA A, B & C 10/30/2024
FP2.12 FIRE PROTECTION NEW WORK PLAN - LEVEL 3 - AREA A, B & C 10/30/2024
FP3.00 FIRE PROTECTION STANDPIPE SECTIONS 10/30/2024
ELECTRICAL
E1.00 ELECTRICAL LEGEND, NOTES, SCHEDULES AND DETAILS 10/30/2024
E2.01 ELECTRICAL OVERALL SITE PLAN 10/30/2024
E2.02 ELECTRICAL BUS CANOPY PLAN 10/30/2024
E3.11A ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA A 10/30/2024
E3.11B ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA B 10/30/2024
E3.11C ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA C 10/30/2024
E3.11D ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA D 10/30/2024
E3.11E ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA E 10/30/2024
E3.11F ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA F & G 10/30/2024
E3.11H ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA H 10/30/2024
E3.11J ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA J 10/30/2024
E3.11K ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA K & L 10/30/2024
E3.11M ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA M 10/30/2024
E3.11N ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA N 10/30/2024
E3.12A ELECTRICAL LIGHTING PLAN LEVEL 2 – AREA A 10/30/2024
E3.12B ELECTRICAL LIGHTING PLAN LEVEL 2 – AREA B & C 10/30/2024
E3.13A ELECTRICAL LIGHTING PLAN LEVEL 3 – AREA A 10/30/2024
E3.13B ELECTRICAL LIGHTING PLAN LEVEL 3 – AREA B & C 10/30/2024
E3.21 ELECTRICAL ENLARGED LIGHTING PLANS 10/30/2024
E4.11A ELECTRICAL POWER PLAN LEVEL 1 – AREA A 10/30/2024
E4.11B ELECTRICAL POWER PLAN LEVEL 1 – AREA B 10/30/2024
E4.11C ELECTRICAL POWER PLAN LEVEL 1 – AREA C 10/30/2024
E4.11D ELECTRICAL POWER PLAN LEVEL 1 – AREA D 10/30/2024
E4.11E ELECTRICAL POWER PLAN LEVEL 1 – AREA E 10/30/2024
E4.11F ELECTRICAL POWER PLAN LEVEL 1 – AREA F & G 10/30/2024
E4.11H ELECTRICAL POWER PLAN LEVEL 1 – AREA H 10/30/2024
E4.11J ELECTRICAL POWER PLAN LEVEL 1 – AREA J 10/30/2024
E4.11K ELECTRICAL POWER PLAN LEVEL 1 – AREA K & L 10/30/2024
E4.11M ELECTRICAL POWER PLAN LEVEL 1 – AREA M 10/30/2024
E4.11N ELECTRICAL POWER PLAN LEVEL 1 – AREA N 10/30/2024
E4.12A ELECTRICAL POWER PLAN LEVEL 2 – AREA A 10/30/2024
E4.12B ELECTRICAL POWER PLAN LEVEL 2 – AREA B & C 10/30/2024
E4.13A ELECTRICAL POWER PLAN LEVEL 3 – AREA A 10/30/2024
E4.13B ELECTRICAL POWER PLAN LEVEL 3 – AREA B & C 10/30/2024
E4.21 ELECTRICAL ENLARGED POWER PLAN - KITCHEN (NORTH) 10/30/2024
E4.22 ELECTRICAL ENLARGED POWER PLAN - KITCHEN (SOUTH) 10/30/2024
E4.23 ELECTRICAL ENLARGED POWER PLAN - ROBOTICS 10/30/2024
E4.24 ELECTRICAL ENLARGED POWER PLAN - SCIENCE LABS 10/30/2024
E4.25 ELECTRICAL ENLARGED POWER PLAN - SCIENCE LABS 10/30/2024
E4.26 ELECTRICAL ENLARGED POWER PLAN - CULINARY ARTS 10/30/2024
E4.31A ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA A 10/30/2024
E4.31B ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA B 10/30/2024
E4.31C ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA C 10/30/2024
E4.31D ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA D 10/30/2024
E4.31E ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA E 10/30/2024
E4.31F ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA F & G 10/30/2024
E4.31H ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA H 10/30/2024
E4.31J ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA J 10/30/2024
E4.31K ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA K & L 10/30/2024
E4.31M ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA M 10/30/2024
E4.31N ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA N 10/30/2024
E4.32A ELECTRICAL HVAC & PLUMBING PLAN LEVEL 2 - AREA A 10/30/2024
E4.32B ELECTRICAL HVAC & PLUMBING PLAN LEVEL 2 - AREA B & C 10/30/2024
E4.33A ELECTRICAL HVAC & PLUMBING PLAN LEVEL 3 - AREA A 10/30/2024
E4.33B ELECTRICAL HVAC & PLUMBING PLAN LEVEL 3 - AREA B & C 10/30/2024
E4.34A ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA A 10/30/2024
E4.34B ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA C 10/30/2024
E4.34C ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA B 10/30/2024
E4.35 ELECTRICAL HVAC AND PLUMBING SCHEDULES 10/30/2024
E5.11A ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA A 10/30/2024
10 of 11
List of Drawings, Specifications and Addendums
INDEX OF DRAWINGS DESCRIPTION DATED
E5.11B ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA B 10/30/2024
E5.11C ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 – AREA C 10/30/2024
E5.11D ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA D 10/30/2024
E5.11E ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA E 10/30/2024
E5.11F ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA F & G 10/30/2024
E5.11H ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA H 10/30/2024
E5.11J ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA J 10/30/2024
E5.11K ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA K & L 10/30/2024
E5.11M ELECTRCIAL LOW VOLTAGE PLAN LEVEL 1 - AREA M 10/30/2024
E5.11N ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA N 10/30/2024
E5.12A ELECTRICAL LOW VOLTAGE PLAN LEVEL 2 - AREA A 10/30/2024
E5.12B ELECTRICAL LOW VOLTAGE PLAN LEVEL 2 - AREA B & C 10/30/2024
E5.13A ELECTRICAL LOW VOLTAGE PLAN LEVEL 3 - AREA A 10/30/2024
E5.13B ELECTRICAL LOW VOLTAGE PLAN LEVEL 3 - AREA B & C 10/30/2024
E6.01 ELECTRICAL RISER DIAGRAM, NOTES, AND SCHEDULE 10/30/2024
E6.02 ELECTRICAL RISER DIAGRAM, NOTES, AND SCHEDULE 10/30/2024
E6.11 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.12 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.13 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.14 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.15 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.16 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.17 ELECTRICAL PANEL SCHEDULES 10/30/2024
E6.18 ELECTRICAL PANEL SCHEDULES 10/30/2024
AUDIOVISUAL
AV0.01 AUDIOVISUAL LEGENDS 10/30/2024
AV0.02 AUDIOVISUAL GENERAL INFORMATION 10/30/2024
AV0.03 AUDIOVISUAL DISPLAY SCHEDULES 10/30/2024
AV2.01 AUDIOVISUAL OVERALL LEVEL 1 FLOOR PLAN 10/30/2024
AV2.11A AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA A 10/30/2024
AV2.11B AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA B 10/30/2024
AV2.11C AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA C 10/30/2024
AV2.11J AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA J 10/30/2024
AV2.11M AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA M 10/30/2024
AV2.11N AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA N 10/30/2024
AV2.40A AUDIOVISUAL OVERALL LEVEL 1 REFLECTED CEILING PLAN 10/30/2024
AV2.41A AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA A 10/30/2024
AV2.41B AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA B 10/30/2024
AV2.41C AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA C 10/30/2024
AV2.41J AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA J 10/30/2024
AV2.41M AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA M 10/30/2024
AV2.41N AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA N 10/30/2024
AV4.01 AUDIOVISUAL ELEVATIONS 10/30/2024
AV4.02 AUDIOVISUAL ELEVATIONS 10/30/2024
AV4.03 AUDIOVISUAL ELEVATIONS 10/30/2024
AV5.10 AUDIOVISUAL WIRING DIAGRAMS - AUDITORIUM 10/30/2024
AV5.11 AUDIOVISUAL WIRING DIAGRAMS - AUDITORIUM 10/30/2024
AV5.20 AUDIOVISUAL WIRING DIAGRAMS - DINING 10/30/2024
AV5.30 AUDIOVISUAL WIRING DIAGRAMS - MEDIA CENTER 10/30/2024
AV5.40 AUDIOVISUAL WIRING DIAGRAMS - GYM 10/30/2024
AV5.50 AUDIOVISUAL WIRING DIAGRAMS - BLACK BOX 10/30/2024
AV6.01 AUDIOVISUAL DETAILS 10/30/2024
AV6.02 AUDIOVISUAL DETAILS 10/30/2024
AV6.10 AUDIOVISUAL PLATE DETAILS 10/30/2024
AV6.11 AUDIOVISUAL PLATE DETAILS 10/30/2024
AV6.12 AUDIOVISUAL PLATE DETAILS 10/30/2024
AV6.20 AUDIOVISUAL RACK ELEVATIONS 10/30/2024
AV6.21 AUDIOVISUAL RACK ELEVATIONS 10/30/2024
THEATER
TLA-01 LEVEL 1 PLAN - AREA N - AUDITORIUM 10/30/2024
TLA-02 LEVEL 1 RCP - AREA N - AUDITORIUM 10/30/2024
TLA-03 STAGE LIGHTING PLOT - AUDITORIUM 10/30/2024
TLA-04 LEVEL 1 SECTION - AREA N - AUDITORIUM 10/30/2024
TLA-05 LEVEL 1 RISER - AREA N - AUDITORIUM 10/30/2024
TLA-06 THEATRICAL SCHEDULES - AUDITORIUM 10/30/2024
TLA-07 SCOPE MATRIX AUDITORIUM 10/30/2024
TLBB-01 LEVEL 1 PLAN - AREA M - BLACK BOX 10/30/2024
TLBB-02 SECTIONS - AREA M - BLACK BOX 10/30/2024
TLBB-03 RISER - AREA M - BLACK BOX 10/30/2024
TLBB-04 SCOPE MATRIX - BLACK BOX 10/30/2024
TLBB-05 EQUIPMENT SCHEDULE - BLACK BOX 10/30/2024
TLBB-06 LEVEL 1 PLAN - AREA M - BLACK BOX PLOT 10/30/2024
TLBB-07 FIXTURE SCHEDULE - BLACK BOX 10/30/2024
SPECIFICATIONS
Project Manual prepared by Cooper Carry dated October 30, 2024
11 of 11
Cross Keys High School 1/23/2025
Attachment 1 - Allowances Log
Value
1 Phase 1 Fire Marshal Egress Requirements $ 50,000.00
2 Rock and Unsuitable Soils $ 1,000,000.00
3 Temporary Utilities/Re-Routing $ 250,000.00
5 Modular Access $ 50,000.00
6 Courtyard Canopies $ 175,000.00
7 Roof Leaders $ 50,000.00
8 Repair Existing Asphalt $ 100,000.00
9 Monumental Sign $ 50,000.00
10 Caulking of Existing School $ 25,000.00
11 Educational Casework, Millwork, and Running Trim $ 1,750,000.00
12 Wood Paneling $ 100,000.00
13 Wood Ceiling $ 100,000.00
14 Wall Graphics $ 100,000.00
15 Special Coatings $ 50,000.00
16 Exterior Mural $ 60,000.00
17 Corner Guards $ 15,000.00
18 Storage Shelving $ 80,000.00
19 Wayfinding $ 50,000.00
20 Exterior Signage $ 50,000.00
21 Louvered Canopies $ 547,200.00
22 Kiln $ 15,000.00
23 Commercial Laundry Equipment (Gym) $ 30,000.00
24 Loading Dock Equipment $ 1,000.00
25 Landscape Lighting $ 100,000.00
26 Remove/Abandon Existing Utilities $ 50,000.00
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025
1. GENERAL
1.1 We have not included any costs for building permit fees, water meter and tap fees,
impact fees, or road closure permits.
1.2 We have not included any costs for materials testing, NPDES monitoring,
commissioning, building envelope testing or commissioning, or special inspections.
1.3 We have not included any in-ground dewatering. We have included rainwater control.
1.4 A construction contingency of 5% is included.
1.5 A design contingency of 4% is included.
1.6 The following allowances are included in the base contract value:
a) Phase 1 Fire Marshal Egress Requirements - $50,000
b) Rock and Unsuitable Soils - $1,000,000
c) Temporary Utilities/Re-Routing - $250,000
d) Modular Access - $50,000
e) Courtyard Canopies - $175,000
f) Roof Leaders - $50,000
g) Repair Existing Asphalt - $100,000
h) Monumental Sign - $50,000
i) Caulking of Existing School - $25,000
j) Educational Casework, Millwork, and Running Trim - $1,750,000
k) Wood Paneling – $100,000
l) Wood Ceiling - $100,000
m) Wall Graphics - $100,000
n) Special Coatings - $50,000
o) Exterior Mural - $60,000
p) Corner Guards - $15,000
q) Storage Shelving - $80,000
r) Wayfinding - $50,000
s) Exterior Signage - $50,000
t) Louvered Canopies - $150/SF
u) Kiln - $15,000
v) Commercial Laundry Equipment (Gym) - $30,000
w) Loading Dock Equipment - $1,000
x) Landscape Lighting - $100,000
y) Remove/Abandon Existing Utilities - $50,000
1.7 The 80% GMP Proposal is based on a combination of the following documents:
a) Cross Keys High School Renovation, Project Manual, Issued for Permit/GMP,
dated 10/30/2024
b) Cross Keys High School Drawings Vol. 1, Issued for Permit/GMP, Dated
10/30/2024
c) Cross Keys High School Drawings Vol. 2, Issued for Permit/GMP, Dated
10/30/2024
d) Cross Keys High School Phase 1 GMP Addendum 1, Dated 08/07/2024
e) Cross Keys High School Phase 1 LDP 2nd Re-submittal, Dated 08/07/2024
f) Cross Keys High School Temporary Classrooms Portables dated 10/28/2024
Page 1 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025
g) Precon RFI Log (file 1.04 RFI Log)
1.8 We have not included any hazardous materials abatement.
1.9 We have included relocation of furniture within the existing school to be renovated.
1.10 We have included removal, storage and re-installation of any computers, smartboards,
projectors, etc. during Summer renovations.
1.11 We have not included any monies for installation of Owner furnished items (furniture,
TVs, Smart Boards, etc.).
1.12 We have only included temporary power for the construction offices. We assume all
power running through the existing transformer or new transformer will remain in
Dekalb County School’s name.
1.13 We have included Builder’s Risk for the value of the new work. We have not insured the
value of the existing building for Builder’s Risk Insurance.
1.14 We have included cleaning of the school and modular classrooms during the summer of
2025, 2026, and 2027
1.15 We have included dismantling, relocating, and re-installing the existing 5-wide modular
classroom located on the North side of the site adjacent to North Cliff Valley Way.
1.16 We have included rental of three each 10 classroom modular classrooms as indicated in
the Cross Keys High School Temporary Classrooms Portables dated 10/28/2024.
1.17 We have included 32 months of parking at Congregation Or VeShalom at a monthly
rate of $7,000.
2. SITE CONSTRUCTION
2.1 We have included temporary irrigation for the new plantings
2.2 We have included Subsoil Termite Treatment with a five year warranty only beneath the
new slab on grades
2.3 We have included ROTC 3-person pull up station, push up bar, and high dip bar
attachment by Kompan Playground
2.4 We have not included prime coat for the asphalt paving.
2.5 We have included heavy duty asphalt paving for the parent drop-off as called out but
not shown.
2.6 We have included asphalt reclamation or complete removal and replacement of existing
GAB, Asphalt, and Track and replace with all new paving and track surfacing.
2.7 We have not included any parking lot lighting.
2.8 We have included one manual double swing gate for the back drive into the track.
2.9 We have included a fire line and new fire hydrant to the football field as required by the
Fire Marshal.
2.10 We have included demolition and discarding of all of the existing modular classrooms
(except for the five wide classroom to be relocated to the football field).
2.11 We have included grey modular block retaining walls.
2.12 We have included the retaining wall to the east of the football field as modular block in
lieu of cast-in-place concrete indicated.
2.13 We have not included 12-months of landscape maintenance as specified.
2.14 We have included sealcoating and re-striping of the parking spaces along Curtis Drive.
Page 2 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025
2.15 We have included sealcoating and re-striping of the existing parking lot to remain.
2.16 We have included a John Deere gator, lacrosse goals, four each cross mats and a discuss
net at the synthetic turf field.
3. CONCRETE
4. MASONRY
4.1 We have included Brick #1 as Watsontown Flashed Red Wirecut
4.2 We have included Brick #2 as Watsontown Light Grey Wirecut
4.3 We have included Elberton Granite Split Face for the granite veneer on retaining walls
4.4 We have not included patching any of the existing brick veneer
4.5 We have not included repointing of the existing brick veneer
5. METALS
6. WOODS & PLASTICS
7. THERMAL & MOISTURE PROTECTION
7.1 We have included re-roofing of the existing school with a 60 mil PVC KEE System for the
re-roofing.
7.2 We have included aluminum soffits as 10mm Trespa Meteon in a Wood Decors color
with a Satin Finish
7.3 We have included 4mm metal wall panels in lieu of the 6mm specified as replacement
panels for 6mm will not be available in the future as thickness is phased out by
manufacturers
7.4 Dampproofing is included as Sealmastic Type II, or equal bituminous dampproofing with
associated drainage mat, which serves as drainage and protection
7.5 We have included dampproofing at the exterior landscape CMU retaining walls. We
have not included HRS at these locations
8. DOORS AND WINDOWS
8.1 We have included an approved wood door manufacturer that no longer participates in
the AWI/QCP program. Wood Doors will be manufactured to the AWI standard but will
not have QCP labels
8.2 Double acting traffic doors are included as follows:
a) Hollow Metal Frames – knockdown construction, pre-machined, standard factory
primed
b) Double Acting Doors – Eliason SCP8, solid core HPL, manufacturer’s standard colors, pre-
fit, pre machined
8.3 Specification section 08 1416 did not clarify what edge to use on the wood doors. We
have included a Type A edge
8.4 We have included door types “QQQ” and “RRR” as flush doors
Page 3 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025
8.5 We have included acoustical seals, door bottom, and thresholds at openings 910.6,
910.7, and 920.2 per the door schedule comments. We have not included sound control
/ STC doors at these openings.
8.6 Standard storefront and curtainwall framing is included at storefront and curtainwall.
We have not included ballistic level aluminum framing.
8.7 All exterior glazing is included with 3M Ultra 800 blast resistant film.
8.8 G1 glass is included as Solarban 70.
8.9 We have included standard storefront and non-rated glass at smoke rated interior
frames. To accommodate the smoke ratings we have done the following:
a) Smoke seals at the doors
b) Caulking the perimeter of all smoke rated glazing on smoke rated side of the framing.
We have not included caulking of both sides (interior and exterior).
c) We have included sanding and refinishing of the existing wood doors to remain.
9. FINISHES
9.1 We have included an eleven-foot two color logo for the main gym
9.2 We have included Robbins Bio Cushion Classic Sprung Floor System for both the Stage
and Black Box
9.3 We have included a sprung floor for both the Black Box and Stage
9.4 We have included Robbins Bio Cushion Classic Floor System for the Mezzanine finish
9.5 We have included Ecor Beast Rolls for Resilient Athletic Flooring RRF-01
9.6 We have not included any polished concrete as this finish has been taken out of the
project
9.7 We have included Rulon Aluratone 760 wood panels in the Performing Arts Center in
lieu of the 700 series panels indicated.
9.8 We have included painting of the exterior of existing lockers. We have not included
painting of the interior of lockers.
10. SPECIALTIES
10.1 We have included Platinum Visual Solutions in lieu of Everwhite as Everwhite does not
produce glass markerboards
10.2 We have not included any horizontal sliding whiteboards
10.3 We have included the following toilet accessories not called out but shown on the
drawings:
a) We have included two 72”x36” Mirrors
b) We have included three 18” ADA Grab Bars
c) We have included ten Mop/Broom Holders with shelf
d) We have included two towel bars
10.4 We have included 4 knox boxes
10.5 We have not included any fire hose valve cabinets as there were no locations shown
10.6 We have included two fire blanket cabinets with fire blankets inside for the robotics lab
10.7 We have included all fire extinguisher and fire blanket cabinets as fully recessed per
notes on A2.11A-A2.13C
10.8 We have only used sign type F for office spaces
Page 4 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025
11. EQUIPMENT
11.1 We have included three KN-107 Dunnage Racks
11.2 We have included one KN-112 Floor Trough
11.3 We have included one KN-309 Floor Trough
11.4 We have included pricing for the culinary lab based on the equipment schedule and
drawings as there are no specifications for this area
11.5 Per drawing L1.05 we have not included tennis court bleachers in our scope
11.6 We have included Whirlpool equipment for the washer/dryers
12. FURNISHINGS
12.1 We have included Wenger AcoustiCabinets in Band and Orchestra rooms with wave grill
doors and Wenger UltraStor Cabinets in storage areas with standard grill doors.
12.2 Musical Instrument Casework is included with standard particleboard PLAM core. Fire-
rated cores are not included
12.3 We have included Science Casework as manufactured by ICI with a 3 year warranty
12.4 We have not included loading dock equipment
12.5 We have included operable window shades at the Media Center Clerestory and manual
shades at all classroom and exterior windows.
12.6 We have not included window shades at the Lobby Curtainwall or the Dining
Curtainwall.
13. SPECIAL CONSTRUCTION
14. CONVEYING SYSTEMS
15. MECHANICAL
15.1 We have not included roof top equipment cages.
15.2 We have not included cleaning of the existing ductwork.
16. ELECTRICAL
16.1 We have not included certifications of the sound system installer.
16.2 We have included a Firelite Fire Alarm system for the new fire alarm system.
16.3 We have included junction boxes and raceways only for Voice, Data, & Security Systems.
16.4 We have included testing, design and installation of a new ERRCS system for the entire
school.
Page 5 of 5
Attachment 3 - Cross Keys High School Addition and Modernization Schedule
Dec 9 Jun 1
Phase 1 Sitework (UG Detention, North Parking, New Bus Loop)
Apr 1 Jun 1
New Modular Classrooms
Jun 1 Jul 1
Remove Existing Modulars
Jun 1
Move-Out (Existing Modulars)
Jun 1 Aug 29
Phase 2 Sitework (Preparation for 3-Story)
Jun 1 Jul 31
Phase 2 Sitework (Preparation for PAC)
Sep 1 Nov 30
Phase 2 - 3-Story Classroom Building
Dec 1 Jan 1
Move-In
Aug 1 Sep 25
Phase 2 - Performing Arts Center
Jun 1 Jul 31
Temporary Corridors (admin, media, café) Jan 3 Mar 31
Demolition of Existing Admin, Media &
Cafeteria
Apr 1 Mar 31
Jun 1 Jul 31 Phase 3 3-Story Classroom (remainder)
Summer Renovations 2026 Jan 1 Jan 31
Summer Renovations 2025 Remove New Modular Classrooms
Jun 1 Jul 31 Feb 1 Jul 31
Jun 1 Jul 31 Football field & track redevelopment
PAC Connectors
2024 2025 2026 2027 2028
Today
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Phasing Considerations
Phase 1 Fire Marshal Eggress Requirements 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Dust Partitions 7,140 SF $ 25.00 $ 178,500.00 $ 0.55
Temporary Walks 10,800 SF $ 8.00 $ 86,400.00 $ 0.27
Temporary Stairs and Ramps 5 EA $ 5,000.00 $ 25,000.00 $ 0.08
Temporary Egress Doors 12 EA $ 3,500.00 $ 42,000.00 $ 0.13
Temporary Covered Walkways 7,700 SF $ 35.00 $ 269,500.00 $ 0.83
Temporary Utilities/Re-Routing 1 ALLW $ 250,000.00 $ 250,000.00 $ 0.77
Modular Access 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Courtyard Canopies 1 ALLW $ 175,000.00 $ 175,000.00 $ 0.54
Grading & Utilities Phase 1 1 LS $ 4,971,017.00 $ 4,971,017.00 $ 15.27
Grading & Utilities Phase 2 1 LS $ 2,555,320.00 $ 2,555,320.00 $ 7.85
LDP Resubmittal #2 (North Druid Hills Accel Lane) 1 LS $ 58,225.00 $ 58,225.00 $ 0.18
Fire Hydrants at South Football Field Modulars 1 LS $ 57,000.00 $ 57,000.00 $ 0.18
Demolition Included
Curb & Gutter Included
Asphalt Paving Included
Sidewalks Included
Utilities Included
Retaining Walls Included
Tennis Courts Included
Fencing Included
Modulars 1 LS $ 180,325.00 $ 180,325.00 $ 0.55
Miscellaneous Included
Grading Included
Erosion & Sedimentation Control Included
Clearing Included
Sidewalks Included
Mass Grading Included
Strip Topsoil Included
Export Excess Included
Export Foundation Spoils 2,300 CY $ 34.00 $ 78,200.00 $ 0.24
Export Stone from Laydown & Trailers 4,315 CY $ 34.00 $ 146,721.59 $ 0.45
Cut Fill Included
Fine Grade Included
Respread Topsoil Included
Backfill Foundation Walls / Retaining Walls Included
Import Included
Storm Sewer Included
Underground Detention System Included
Double Handle Spoils Included
Roof Leaders 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Sanitary Sewer Included
Water & Fire Included
Trench Drains 1 LS $ 125,303.00 $ 125,303.00 $ 0.38
Concrete Washout 50 EA $ 800.00 $ 40,000.00 $ 0.12
Temporary Stone
Temporary Parking & Laydown 1,968 Tons $ 57.00 $ 112,182.84 $ 0.34
Crane Road (Phase 2) 1,254 Tons $ 57.00 $ 71,478.00 $ 0.22
Geotextile Fabric 4,200 SY $ 4.00 $ 16,800.00 $ 0.05
Between Phases 2 & 3 2,604 Tons $ 57.00 $ 148,404.63 $ 0.46
Water Meter By Owner
Tap Fees By Owner
Impact Fees By Owner
NOI Fees 1 LS $ 496.00 $ 496.00 $ 0.00
Rock & Unsuitable Soils 1 ALLW $ 1,000,000.00 $ 1,000,000.00 $ 3.07
NPDES Monitoring By Owner
Asphalt Paving Phase 1
Light Duty 1 LS $ 315,812.00 $ 315,812.00 $ 0.97
Heavy Duty Included
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Sealcoat Curtis Drive Parking 1,159 SY $ 2.76 $ 3,197.61 $ 0.01
Prime Coat Not Included
Asphalt Paving Phase 2
Light Duty 1 LS $ 374,470.00 $ 374,470.00 $ 1.15
Heavy Duty Included
Sealcoat Existing 1 LS $ 7,905.00 $ 7,905.00 $ 0.02
Prime Coat Not Included
Repair Existing Asphalt 1 ALLW $ 100,000.00 $ 100,000.00 $ 0.31
Curb & Gutter Phase 1
Curb & Gutter 1 LS $ 94,530.00 $ 94,530.00 $ 0.29
Roll Curb Included
Curb & Gutter Phase 2
Curb & Gutter 1 LS $ 80,560.00 $ 80,560.00 $ 0.25
Fences & Gates 1 LS $ 228,419.00 $ 228,419.00 $ 0.70
4' Retaining Wall Chain Link Fencing Included
6' Chain Link Fencing Included
8' Chain Link Fencing with Privacy Slats Included
10' Tennis Courts Chain Link Fencing & Windscreen Included
10' Chain Link Fencing Included
12' Interior Fencing Included
Dumpster Enclosure Included
Guardrail Included
Gates Included
Hardscapes 1 LS $ 2,013,094.00 $ 2,013,094.00 $ 6.18
A-101 - Concrete Stairs Included
A-102 - Concrete Ramp Included
A-103 - Vehicular Steel Bollard with Concrete Fill Included
A-103B - Removable Vehicular Bollard Included
P-101 - 4" Standard Sidewalk Included
P-101B - 4" Sidewalk with Retardant Finish Included
P-102 - Heavy Duty Concrete Included
P102B - Heavy Duty Concrete with Retardant Finish Included
P-103 - Ipe Wood Deck with drainage system Included
P-104 - Concrete Unit Paver Included
P-106 - Slate Trail Mix Included
P-109 - #57 Stone Included
P-110 - Detectable Warning Paver Included
P-111 - Grass Pave 2 Included
P-113 - 6" Concrete Header Included
P-114 - Landscape Step Stone Included
S-105 - Aluminum Edging Included
S-110 - Landscape Boulder Included
W-102 - 6" CIP Curb Included
W-103 - 8" CIP Retaining Wall Included
W-104 - Seat Wall with Wood Top Included
W-104B - CIP Concrete Seat Wall Included
HC Ramps Included
HD Concrete Dumpster Pad 196 SF $ 18.50 $ 3,626.00 $ 0.01
JROTC Practice Pad Included
JROTC Site Furnishings 1 LS $ 44,201.00 $ 44,201.00 $ 0.14
Retaining Walls
Modular Block Phase 1 1 LS $ 221,950.00 $ 221,950.00 $ 0.68
Modular Block Phase 2 1 LS $ 46,090.00 $ 46,090.00 $ 0.14
Pavement Striping & Signage 1 LS $ 44,098.00 $ 44,098.00 $ 0.14
Landscape / Irrigation 1 LS $ 602,331.00 $ 602,331.00 $ 1.85
Sod Included
Trees Included
Shrubs Included
Groundcover Included
Temporary Irrigation Included
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
12-month Maintenance Not Included
Monumental Sign 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Flagpole 1 EA $ 5,694.00 $ 5,694.00 $ 0.02
Tennis Courts 1 LS $ 162,475.00 $ 162,475.00 $ 0.50
Tennis Court Bleachers Not Included
Resurface Track & Field 1 LS $ 406,685.00 $ 406,685.00 $ 1.25
Synthetic Turf Football Field 1 LS $ 1,649,065.00 $ 1,649,065.00 $ 5.07
Football Goalpost Included
Track & Field Equipment Included
Long Jump Take-Off Board System Included
Pole Vault Box Included
Shot Put Circle Included
Discus Circle Included
Gator Included
Lacrosse Goals Included
Cross Mats (4 EA) Included
Discuss Net Included
Soccer Goal 1 LS $ 13,180.00 $ 13,180.00 $ 0.04
Demolition 1 LS $ 879,595.00 $ 879,595.00 $ 2.70
Subsoil Termite Treatment 1 LS $ 6,779.000 $ 6,779.00 $ 0.02
Concrete Foundations & SOG 1 LS $ 3,079,562.00 $ 3,079,562.00 $ 9.46
Foundation Wall Included
Elevated SOD Included
Concrete Phase 1 1 LS $ 226,039.00 $ 226,039.00 $ 0.69
Masonry
CMU Walls 1 LS $ 8,851,796.00 $ 8,851,796.00 $ 27.19
Brick Included
Stone Veneer 1 LS $ 299,117.00 $ 299,117.00 $ 0.92
Replace Existing Veneer Not Included
Structural & Misc. Metals 1 LS $ 5,966,800.00 $ 5,966,800.00 $ 18.33
Joist & Deck Included
Fly Loft Not Included
AESS Not Included
Stairs & Rails Included
Lobby Stair Premium Included
Ornamental Rails Included
Wood Overhang Soffit Included
Roof Opening Frames in Existing Included
FRP Reinforcement of Existing Structure 1 LS $ 688,500.00 $ 688,500.00 $ 2.11
Millwork 1 ALLW $ 1,750,000.00 $ 1,750,000.00 $ 5.38
Waterproofing, Dampproofing, and Caulking
Waterproofing
Elevator Pit 1 EA $ 2,015.00 $ 2,015.00 $ 0.01
Foundation Wall 1 LS $ 124,250.00 $ 124,250.00 $ 0.38
Air Barrier 1 LS $ 491,150.00 $ 491,150.00 $ 1.51
Air-Barrier on Temp Exterior Wall
Caulking 1 LS $ 196,715.00 $ 196,715.00 $ 0.60
Sidewalks Included
Sidewalks to Building Included
Exterior Openings Included
Dissimilar Materials Included
CMU Control Joints Included
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Caulking (Existing) 1 ALLW $ 25,000.00 $ 25,000.00 $ 0.08
Firestopping 1 LS $ 58,955.00 $ 58,955.00 $ 0.18
Dampproofing 1 LS $ 6,600.00 $ 6,600.00 $ 0.02
Expansion Joints 1 LS $ 164,565.00 $ 164,565.00 $ 0.51
Exterior Included
Interior Included
Fireproofing 1 LS $ 543,875.00 $ 543,875.00 $ 1.67
Intumescent Paint Included
Roofing 1 LS $ 1,799,464.00 $ 1,799,464.00 $ 5.53
Re-Roof Existing School 1 LS $ 3,684,656.00 $ 3,684,656.00 $ 11.32
Metal Wall Panels 1 LS $ 1,721,700.00 $ 1,721,700.00 $ 5.29
Perforated Metal Wall Panels 641 SF $ 165.00 $ 105,765.00 $ 0.32
Doors, Frames, & Finish Hardware 1 LS $ 1,352,625.00 $ 1,352,625.00 $ 4.16
Replace Existing Doors & HW Not Included
Refinish Existing Doors 1 LS $ 8,330.00 $ 8,330.00 $ 0.03
Door and Finish Hardware - Install 1 LS $ 78,615.00 $ 78,615.00 $ 0.24
Overhead Coiling Doors 1 LS $ 219,250.00 $ 219,250.00 $ 0.67
Scene Shop Included
Concessions Included
Fire Doors 1 LS $ 127,300.00 $ 127,300.00 $ 0.39
Exterior Glass Sectional Door 1 LS $ 109,155.00 $ 109,155.00 $ 0.34
Glass & Glazing 1 LS $ 2,410,110.00 $ 2,410,110.00
Curtainwall Included
Exterior Storefront Included
Aluminum Storefront Doors Included
Storefront Door HW 1 LS $ 225,700.00 $ 225,700.00 $ 0.69
Interior Curtainwall Included
Interior Storefront Included
Door Lites / Sidelights Included
Weight Room Mirrors 1 LS $ 8,260.00 $ 8,260.00 $ 0.03
Privacy Band at Conference Rooms 1 LS $ 1,000.00 $ 1,000.00 $ 0.00
Blast Resistant Film Included
Drywall & Acoustical 1 LS $ 3,073,650.00 $ 3,073,650.00 $ 9.44
Gyp. Board Partitions & Top Outs Included
Gyp. Ceilings & Soffits Included
ACT Ceilings Included
Ceiling Baffle at Dining Included
Radiused Ceiling at Auditorium Included
Ceiling Baffle at Auditorium Entrance Included
Ceiling Baffle at Extended Learning Included
Acoustic Ceiling Panels at Black Box Theatre Included
Acoustic Wall Panels at Auditorium Included
Acoustic Wall Panels at Gym Included
Acoustic Wall Panels at Extended Learning Included
Wood Paneling 1 ALLW $ 100,000.00 $ 100,000.00 $ 0.31
Wood Ceiling 1 ALLW $ 100,000.00 $ 100,000.00 $ 0.31
Temporary Exterior Wall 14,330 SF $ 25.00 $ 358,246.15 $ 1.10
Porch Pavers 1 LS $ 155,470.00 $ 155,470.00 $ 0.48
Hot Rubberized Asphalt WP 1 LS $ 109,835.00 $ 109,835.00 $ 0.34
Flooring
Tile
Floor Tile 1 LS $ 120,200.00 $ 120,200.00 $ 0.37
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Wall Tile Included
Carpet & Resilient Flooring
Carpet 1 LS $ 883,755.00 $ 883,755.00 $ 2.71
LVT Included
Rubber Base Included
Rubber Flooring Included
Transitions Included
Rubber Stair Treads and Risers Not Included
Wood Athletic Flooring 1 LS $ 464,202.00 $ 464,202.00 $ 1.43
Wood Flooring Included
Resilient Athletic Flooring Included
Epoxy Flooring 1 LS $ 294,530.00 $ 294,530.00 $ 0.90
Epoxy Base Included
Painting 1 LS $ 1,002,776.00 $ 1,002,776.00 $ 3.08
Walls Included
Gyp. Ceilings & Soffits Included
Wall Graphics 1 ALLW $ 100,000.00 $ 100,000.00 $ 0.31
Wall Covering Included
Sealed Concrete 1 LS $ 138,977.00 $ 138,977.00 $ 0.43
Polished Concrete Not Included
Special Coatings 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Exterior Mural 1 ALLW $ 60,000.00 $ 60,000.00 $ 0.18
Specialties
Fire Extinguishers & Cabinets 1 LS $ 20,178.00 $ 20,178.00 $ 0.06
Toilet Partitions 1 LS $ 264,353.00 $ 264,353.00 $ 0.81
Toilet Accessories Included
Corner Guards 1 ALLW $ 15,000.00 $ 15,000.00 $ 0.05
Storage Shelving 1 ALLW $ 80,000.00 $ 80,000.00 $ 0.25
36"X10"X36" Shelving Included
18" Wire Shelving Not Included
Storage Shelving with 7 Shelves Included
Athletic & Dressing Room Lockers 1 LS $ 199,000.00 $ 199,000.00 $ 0.61
Gym Equipment 1 LS $ 164,000.00 $ 164,000.00 $ 0.50
Basketball Equipment Included
Wrestling Equipment Included
Volleyball Nets Included
Floor Sleeves Included
Wall Pads Included
Combination Baseball/Softball Complex 1 LS $ 8,127,922.71 $ 8,127,922.71 $ 24.97
Scoreboards
Interior (2 Each) 1 LS $ 15,950.00 $ 15,950.00 $ 0.05
Exterior (Football Field) 1 LS $ 43,143.00 $ 43,143.00 $ 0.13
Telescoping Bleachers (Plastic) 1 LS $ 155,880.00 $ 155,880.00 $ 0.48
Interior Signage 1 LS $ 63,551.00 $ 63,551.00 $ 0.20
Wayfinding 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Exterior Signage 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Visual Display Boards 1 LS $ 77,171.00 $ 77,171.00 $ 0.24
Markerboard Included
Install 1 LS $ 17,910.00 $ 17,910.00 $ 0.06
Parent Drop Off Canopy Included
Bus Loop Canopy Phase 1 1 LS $ 92,140.00 $ 92,140.00 $ 0.28
Bus Loop Canopy Phase 2 1 LS $ 57,265.00 $ 57,265.00 $ 0.18
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Louvered Canopies Allowance 3,648 ALLW/SF $ 150.00 $ 547,200.00 $ 1.68
Operable Partition 1 LS $ 80,150.00 $ 80,150.00 $ 0.25
Food Service Equipment 1 LS $ 2,587,184.00 $ 2,587,184.00 $ 7.95
Commercial Laundry Equipment (Gym) 1 ALLW $ 30,000.00 $ 30,000.00 $ 0.09
Residential Appliances 1 LS $ 27,698.00 $ 27,698.00 $ 0.09
Kiln 1 ALLW $ 15,000.00 $ 15,000.00 $ 0.05
Window Treatments 1 LS $ 221,725.00 $ 221,725.00 $ 0.68
Educational Casework
Educational Casework Incl. in Millwork
Science / Lab Casework 1 LS $ 1,057,660.00 $ 1,057,660.00 $ 3.25
Library Casework By Owner
Music Suite Casework 1 LS $ 105,214.00 $ 105,214.00 $ 0.32
Stage Curtains & Equipment Included
Moveable Chairs By Owner
Knox Box 4 EA $ 989.00 $ 3,956.00 $ 0.01
Loading Dock Equipment 1 ALLW $ 1,000.00 $ 1,000.00 $ 0.00
Elevator 1 LS $ 135,000.00 $ 135,000.00 $ 0.41
Final Cleaning 284,843 SF $ 0.65 $ 185,147.95 $ 0.57
Summer 2025 169,275 SF $ 0.50 $ 84,637.50 $ 0.26
Waxing 109,016 SF $ 1.05 $ 114,466.80 $ 0.35
Summer 2026 39,780 SF $ 0.50 $ 19,890.00 $ 0.06
Summer 2027 261,477 SF $ 0.50 $ 130,738.50 $ 0.40
Modulars (Summers 2025, 2026, 2027) 25,287 SF $ 1.50 $ 37,930.50 $ 0.12
Waxing (Summers 2025, 2026, 2027) 25,287 SF $ 3.15 $ 79,654.05 $ 0.24
Fire Protection 1 LS $ 1,005,000.00 $ 1,005,000.00 $ 3.09
Plumbing 1 LS $ 5,713,570.00 $ 5,713,570.00 $ 17.55
HVAC 1 LS $ 11,224,000.00 $ 11,224,000.00 $ 34.48
Test & Balance Included
Controls Included
Electrical 1 LS $ 11,100,107.00 $ 11,100,107.00 $ 34.10
Lighting Included
Theatrical Lighting & Sound Included
ERRCS 1 LS $ 153,100.00 $ 153,100.00 $ 0.47
Fire Alarm Included
Landscape Lighting Allowance 1 ALLW $ 100,000.00 $ 100,000.00 $ 0.31
Department Changes Included
Modulars 1 LS $ 4,520,350.00 $ 4,520,350.00 $ 13.89
Setup Included
Rental Included
Ramps & Steps Included
Relocation of Existing Modular Included
Design 1 LS $ 13,000.00 $ 13,000.00 $ 0.04
Temporary Stone 1,475 Tons $ 57.00 $ 84,060.32 $ 0.26
Water Line Included
Fire Line Included
Sanitary Sewer Included
Fire Protection Included
Attachment 4 - Schedule of Values
Dekalb County Schools 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Plumbing Included
Electrical Included
Remove/Abandon Existing Utilities 1 ALLW $ 50,000.00 $ 50,000.00 $ 0.15
Accepted Value Engineering (1) LS $ 1,191,429.00 $ (1,191,429.00) $ (3.66)
Total $ 107,159,614 $ 329.18
FAA Study & Permit $ 3,500 $ 0.01
Preconstruction Expenses
Survey - Land Engineering 1 LS $ 35,500.00 $ 35,500 $ 0.11
Traffic Study - A & R Engineering 1 LS $ 12,250.00 $ 12,250 $ 0.04
Combination Plat - Land Engineering 1 LS $ 4,350.00 $ 4,350 $ 0.01
Arborist - Arborguard 1 LS $ 4,135.00 $ 4,135 $ 0.01
Erosion Control & Maintenance Bond 1 LS $ 372.00 $ 372 $ 0.00
Synagogue Parking 32 MO $ 7,000.00 $ 224,000 $ 0.69
F.O.G. Permit 1 LS $ 125.00 $ 125 $ 0.00
Sitework - General Conditions $ 300,458 $ 0.92
Sitework - General Requirements $ 190,597 $ 0.59
3 Story - General Conditions $ 7,156,660 $ 21.98
3 Story - General Requirements $ 1,011,455 $ 3.11
Performing Arts - General Conditions $ 2,018,936 $ 6.20
Performing Arts - General Requirements $ 314,726 $ 0.97
Classroom Renovation - General Conditions $ 282,494 $ 0.87
Classroom Renovation - General Requirements $ 567,740 $ 1.74
Athletics - General Conditions $ 252,919 $ 0.78
Athletics - General Requirements $ 195,502 $ 0.60
Gym Renovation - General Conditions $ 290,838 $ 0.89
Gym Renovation - General Requirements $ 273,588 $ 0.84
Builders Risk Insurance $ 335,754 $ 1.03
Liability Insurance $ 214,013 $ 0.66
Subcontractor Default Insurance $ 1,607,394 $ 4.94
Payment & Performance Bonds $ 877,947 $ 2.70
Construction Manager's Fee $ 6,093,982 $ 18.72
Total $ 129,428,850 $ 397.59
Contingency
Design (4%) $ 5,177,154 $ 15.90
Construction (5%) $ 6,471,442 $ 19.88
Subtotal $ 141,077,446 $ 433.37
Sitework - Escalation (0%) $ - $ -
3 Story - Escalation (2%) $ 1,120,963 $ 3.44
Performing Arts - Escalation (1%) $ 177,139 $ 0.54
Gym Renovation - Escalation (5%) $ 333,568 $ 1.02
Athletics - Escalation (5%) $ 96,901 $ 0.30
Classroom Reno - Escalation (5%) $ 507,351 $ 1.56
CTAE Reno - Escalation (5%) $ 171,166 $ 0.53
Modulars - Escalation (0%) $ - $ -
Total $ 143,484,535 $ 440.76
Alternates
Theatrical lighting add alternates $ 185,200.00
Attachment 4 - Schedule of Values
Cross Keys High School Addition and Modernization 1/23/2025
80% GMP Value Options
Accepted
2-1 Remove the trees withing the courtyards (28,883)
2-1 Remove automation from the southeast parking lot gates (36,352)
2-3 Painted steel bollards in lieu of stainless steel bollards (18,636)
2-4 Remove the geotextile fabric and stone base beneath all sidewalks (107,694)
2-5 Remove the IPE wood deck and replace with sidewalks. (103,748)
2-6b Concrete Paving P-102 in lieu of Pavers at the roundabout circle (36,675)
2-7b Concrete Paving P-102 in lieu of Pavers at the half moon behind auditorium (18,132)
2-8 Concrete Paving P-102 in lieu of P-102B concrete paving behind auditorium (9,183)
2-9 Standard sidewalks in lieu of sidewalks with retardant finish (17,460)
2-10 Remove the wood top from the W-104 concrete seat walls. (29,161)
4-1 Utilize brick in lieu of stone at site retaining walls (51,147)
4-2 Drywall top outs in lieu of CMU top outs. CMU to one course of above highest adjacent ceiling. (324,995)
6-1 Remove 50% of the perforated screen walls from inside the building. (52,883)
7-1 60 mil PVC KEE roofing in lieu of 80 mil PVC KEE (57,280)
9-7 Delete the Acoustical Ceiling Baffle at Extended Learning (AP-01) (33,200)
9-11 Delete the Acoustical Ceiling Baffles at Learning Huddle (3,900)
15-2 Utilize schedule 40 PVC for all below slab storm, sanitary waste and vent piping in lieu of cast iron. (106,000)
15-11 Remove single zone VAV supply fans as shown in the schedule. The drawings and specifications contradict each other. (15,400)
The specs call for single zone VAV on ALL RTUs but the schedule only calls for it on some of them. We carried SZVAV on
all units on bid day to ensure we were covered so this deduct removes single zone VAV supply fans on the units that call
for “single zone CV” on the schedule.
15-12 Switch RTUs 5 tons and under to standard efficiency. Schedule calls for all units to have minimum 2-stages of cooling. (11,200)
This is standard on all RTUs 6 tons and over but bumps us to the high efficiency units on the smaller tonnages (5 tons
and under). This deduct is to switch the smaller units to standard efficiency (single stage units).
16-1 Utilize 2x4 light fixtures in the classrooms in lieu of spec'd lights (38,000)
16-5 Utilize 4wall theatrical lighting package in lieu of Barbizon (91,500)
TOTALS ($1,191,429)
*Design team review may be required to ensure code compliance, coordination, and building envelope integrity for some items listed above.
Evergreen is not responsible for such review and has not included any additional cost for such review.
TBD - To be determined
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Sitework
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 147,305 $ 54,358 $ 201,663
Assistant Project Manager (100%) 30 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Coordinator (100%) 12 Weeks $ -
Assistant Superintendent (100%) 18 Weeks $ -
Assistant Superintendent (100%) 13 Weeks $ -
Purchasing Agent (100%) 5 Weeks $ 1,920 $ 709 $ 13,143
Project Secretary (100%) 12 Weeks $ 720 $ 266 $ 11,828
Project Accountant (100%) 12 Weeks $ 1,750 $ 646 $ 28,749
Travel & Entertainment - Months $ 270 $ -
Supervision Vehicles - Months $ 1,790 $ -
Superintendent Vehicle Fuel & Repair - Months $ 4,600 $ -
Superintendent Vehicle Insurance - Months $ 562.50 $ -
Safety Program & Inspections 1 LS $ 10,000 $ 10,000
Safety Signage - LS $ 5,000 $ 1,845 $ 15,000 $ -
Drug Testing 1 LS $ 1,080 $ 1,080
Hard Hats & Safety Vests 1 LS $ 6,000 $ 6,000
Raingear & Boots 1 LS $ 1,500 $ 1,500
Eye & Ear Protection 1 LS $ 1,500 $ 1,500
Safety Harnesses and Lifelines - LS $ 1,735 $ -
First Aid Supplies - Months $ 108 $ -
Office Trailer Rental - Months $ 4,620 $ -
Tool Trailer Rental - Months $ 500 $ -
Office Equipment - LS $ 650 $ -
Computer Equipment - LS $ 15,000 $ -
Project Software - Procore - Months $ 299,986 $ -
Office Supplies & Postage - Months $ 300 $ -
Office Furniture - LS $ 15,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 1,500.00 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 500 $ -
Closeout Documents & As-Builts - LS $ 9,200 $ -
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Sitework
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Traffic Control/Flagman - Weeks $ 2,220 $ 819 $ -
Setup & Remove Field Office - LS $ 4,183 $ 1,544 $ 14,202 $ -
Setup & Remove Tool Trailer - LS $ 750 $ 277 $ 1,703 $ -
Project Signs - LS $ 2,500 $ 923 $ 4,860 $ -
Radios - LS $ - $ 6,500 $ -
Temp/Permanent Power & Gas - Months $ - $ -
Temporary Power - Months $ 1,620.00 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat - Months $ 15,000 $ -
Temporary Water - Months $ - $ -
Holding Tank - Months $ 378 $ -
Temporary Toilets - Months $ 2,000 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,104 $ -
-
Barricades 1 LS $ 24,995 $ 24,995
Ceremonies 1 LS $ - $ -
TOTAL $ 300,458
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys Hish School 1/23/2025
Sitework
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers - EA $ 100 $ -
Temporary Fence 5,067 LF $ 5 $ 2 $ 15.64 $ 113,932
Continuous Cleanup 26 Weeks $ 1,862 $ 687 $ 66,277
Dump Fees 18 Pulls $ 577 $ 10,388
Street Sweeper - Months $ 1,610 $ -
Skid Steer - Months $ 2,862 $ -
Equipment Rental - Months $ 2,100 $ -
Fuel & Lubricant - Months $ 250 $ -
Small Tools - Months $ 1,000 $ -
SF $ 0.35 $ -
TOTAL $ 190,597
1 of 1
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
3 Story Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 3,662,336 $ 1,351,461 $ 5,013,797
Senior Project Manager (100%) 110 Weeks $ -
Project Manager (100%) 165 Weeks $ -
Assistant Project Manager (100%) 165 Weeks $ -
Assistant Project Manager (100%) 165 Weeks $ -
Project Engineer (100%) 65 Weeks $ -
Project Coordinator (100%) 65 Weeks $ -
Project Coordinator (100%) 66 Weeks $ -
General Superintendent (25%) 110 Weeks $ -
Project Superintendent (100%) 165 Weeks $ -
Assistant Superintendent (100%) 165 Weeks $ -
Assistant Superintendent (100%) 165 Weeks $ -
Surveyor (100%) 1 LS $ 49,996 $ 49,996
Engineering Equipment 1 LS $ 2,500 $ 2,500
Engineering Supplies 1 LS $ 2,500 $ 2,500
Purchasing Agent (100%) 26 Weeks 1920 $ 709 $ 68,341
Project Secretary (100%) 65 Weeks 720 $ 266 $ 64,070
Project Accountant (100%) 65 Weeks 1750 $ 646 $ 155,726
Travel & Entertainment 38 Months $ 270 $ 10,260
Supervision Vehicles 46 Months $ - $ 2,051 $ 94,342
Superintendent Vehicle Fuel & Repair 46 Months $ - $ 4,600 $ 211,600
Superintendent Vehicle Insurance 46 Months $ - $ 562.50 $ 25,875
Safety Program & Inspections 1 LS $ 6,200 $ 6,200
Safety Signage 1 LS $ 5,000 $ 1,845 $ 15,000 $ 21,845
Drug Testing - LS $ 1,080 $ -
Hard Hats & Safety Vests - LS $ 6,000 $ -
Raingear & Boots - LS $ 1,500 $ -
Eye & Ear Protection - LS $ 1,500 $ -
Safety Harnesses and Lifelines 1 LS $ 1,735 $ 1,735
First Aid Supplies 38 Months $ 108 $ 4,104
Office Trailer Rental 38 Months $ 4,620 $ 175,560
Tool Trailer Rental 38 Months $ 500 $ 19,000
Office Equipment 1 LS $ 650 $ 650
Computer Equipment 1 LS $ 20,000 $ 20,000
Project Software - Procore 1 LS $ 299,986 $ 299,986
Office Supplies & Postage 38 Months $ 300 $ 11,400
Office Furniture 1 LS $ 15,000 $ 15,000
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
3 Story Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Drawings & Printing 1 LS $ 15,000 $ 15,000
CAD Files 1 LS $ 5,000 $ 5,000
Web Cam - OxBlue 38 Months $ - $ -
Daily Photos - Cupix 38 Months $ 25 $ 950
Aerial Photograghy 1 LS $ 4,004 $ 4,004
Closeout Documents & As-Builts 1 LS $ 9,200 $ 9,200
Weather Station/Service 1 LS $ 2,500 $ 2,500
Traffic Control/Flagman 165 Weeks $ 2,220 $ 819 $ 501,471
Setup & Remove Field Office 1 LS $ 4,183 $ 1,544 $ 14,202 $ 19,929
Setup & Remove Tool Trailer 1 LS $ 750 $ 277 $ 1,703 $ 2,730
Temporary Ladders 4 EA $ 200 $ 74 $ 535 $ 3,235
Project Signs 1 LS $ 1,500 $ 554 $ 3,000 $ 5,054
Radios 1 LS $ 6,500 $ 6,500
Temp/Permanent Power & Gas 6 Months $ -
Temporary Power 38 Months $ 1,620.00 $ 61,560
Temporary Power Setup (Georgia Power) 1 LS $ 25,000 $ 25,000
Temporary Heat 4 Months $ 15,000 $ 60,000
Temporary Water 38 Months $ -
Holding Tank 38 Months $ 378 $ 14,364
Temporary Toilets 38 Months $ 2,000 $ 76,000
Sanitary Supplies 38 Months $ 159 $ 6,042
Ice, Cups, and Water 38 Months $ 159 $ 6,042
Telecom System & Installation (Internet) 1 LS $ 650 $ 650
Telecom Service (Internet & Cell Phones) 38 Months $ 1,104 $ 41,943
Barricades - LS $ 25,000 $ -
Ceremonies 1 LS $ 15,000 $ 15,000
TOTAL $ 7,156,660
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
3 Story Addition
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 25 EA $ 100 $ 2,463
Temporary Fence 1,636 LF $ 5 $ 2 $ 15.64 $ 36,792
Continuous Cleanup 165 Weeks $ 1,862 $ 687 $ 420,603
Dump Fees 160 Pulls $ 577 $ 92,094
Lull 12 Months $ 4,957.00 $ 59,484
Street Sweeper 35 Months $ 1,610 $ 56,350
Skid Steer 35 Months $ 2,862 $ 100,170
Equipment Rental 35 Months $ 2,100 $ 73,500
Fuel & Lubricant 35 Months $ 2,000 $ 70,000
Small Tools 35 Months $ 1,000 $ 35,000
Cupix 1 LS $ 15,000.00 $ 15,000
Protect New Work 1 LS $ 50,000 $ 50,000
TOTAL $ 1,011,455
1 of 1
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Performing Arts Center
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 1,209,231 $ 446,226 $ 1,655,457
Senior Project Manager (100%) 55 Weeks
Project Manager (100%) 70 Weeks
Assistant Project Manager (100%) 70 Weeks
Project Engineer (100%) 52 Weeks
Project Engineer (100%) 52 Weeks
Project Coordinator (100%) 52 Weeks
General Superintendent (25%) 55 Weeks
Project Superintendent (100%) 70 Weeks
Assistant Superintendent (100%) 70 Weeks
Surveyor (100%) 1 LS $ 49,999 $ 49,999
Purchasing Agent (100%) 20 Weeks 1920 $ 709 $ 52,570
Project Secretary (100%) 52 Weeks 720 $ 266 $ 51,256
Project Accountant (100%) 52 Weeks 1750 $ 646 $ 124,580
Travel & Entertainment - Months $ 270
Supervision Vehicles - Months $ 1,790 $ -
Superintendent Vehicle Fuel & Repair - Months $ 4,600 $ -
Superintendent Vehicle Insurance - Months $ 562.50 $ -
Safety Program & Inspections - LS $ 16,200 $ -
Safety Signage 1 LS $ 5,000 $ 1,845 $ 15,000 $ 21,845
Drug Testing - LS $ 1,080 $ -
Hard Hats & Safety Vests - LS $ 6,000 $ -
Raingear & Boots - LS $ 1,500 $ -
Eye & Ear Protection - LS $ 1,500 $ -
Safety Harnesses and Lifelines - LS $ 1,735 $ -
First Aid Supplies - Months $ 108 $ -
Office Trailer Rental - Months $ 4,620 $ -
Tool Trailer Rental - Months $ 500 $ -
Office Equipment - LS $ 650 $ -
Computer Equipment - LS $ 15,000 $ -
Project Software - Procore - Months $ 299,986 $ -
Office Supplies & Postage - Months $ 300 $ -
Office Furniture - LS $ 15,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 1,500.00 $ -
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Performing Arts Center
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 500 $ -
Closeout Documents & As-Builts - LS $ 9,200 $ -
Traffic Control/Flagman - Weeks $ 2,220 $ 819 $ -
Setup & Remove Field Office - LS $ 4,183 $ 1,544 $ 14,202 $ -
Setup & Remove Tool Trailer - LS $ 750 $ 277 $ 1,703 $ -
Temporary Ladders - EA $ 200 $ 74 $ 535 $ -
Project Signs 1 LS $ 1,000 $ 369 $ 1,860 $ 3,229
Radios - LS $ 6,500 $ -
Temp/Permanent Power & Gas 4 Months $ -
Temporary Power - Months $ 1,620.00 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat 4 Months $ 15,000 $ 60,000
Temporary Water - Months $ -
Holding Tank - Months $ 378 $ -
Temporary Toilets - Months $ 2,000 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,104 $ -
Barricades - LS $ 25,000 $ -
Ceremonies - LS $ - $ -
TOTAL $ 2,018,936
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Performing Arts
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 7 EA $ 100 $ 656
Temporary Fence 1,006 LF $ 5 $ 2 $ 15.64 $ 22,621
Continuous Cleanup 70 Weeks $ 1,862 $ 687 $ 178,438
Dump Fees 43 Pulls $ 577 $ 24,545
Street Sweeper 3 Months $ 1,610 $ 4,830
Skid Steer 3 Months $ 2,862 $ 8,586
Equipment Rental 3 Months $ 2,100 $ 6,300
Fuel & Lubricant 3 Months $ 250 $ 750
Small Tools 3 Months $ 1,000 $ 3,000
Cupix 1 LS $ 15,000.00 $ 15,000
Protect New Work 1 LS $ 50,000 $ 50,000
TOTAL $ 314,726
1 of 1
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Classroom Renovation
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 157,508 $ 58,123 $ 215,631
Assistant Project Manager (100%) 26 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Coordinator (100%) 12 Weeks $ -
Assistant Superintendent (100%) 26 Weeks $ -
Field Engineer (100%) 24 Weeks $ -
Purchasing Agent (100%) 10 Weeks $ 1,920 $ 709 $ 26,285
Project Secretary (100%) 12 Weeks $ 720 $ 266 $ 11,828
Project Accountant (100%) 12 Weeks $ 1,750 $ 646 $ 28,749
Travel & Entertainment - Months $ 270
Supervision Vehicles - Months $ 1,790 $ -
Superintendent Vehicle Fuel & Repair - Months $ 4,600 $ -
Superintendent Vehicle Insurance - Months $ 562.50 $ -
Safety Program & Inspections - LS $ 16,200 $ -
Safety Signage - LS $ 5,000 $ 1,845 $ 15,000 $ -
Drug Testing - LS $ 1,080 $ -
Hard Hats & Safety Vests - LS $ 6,000 $ -
Raingear & Boots - LS $ 1,500 $ -
Eye & Ear Protection - LS $ 1,500 $ -
Safety Harnesses and Lifelines - LS $ 1,735 $ -
First Aid Supplies - Months $ 108 $ -
Office Trailer Rental - Months $ 4,620 $ -
Tool Trailer Rental - Months $ 500 $ -
Office Equipment - LS $ 650 $ -
Computer Equipment - LS $ 15,000 $ -
Project Software - Procore - Months $ 299,986 $ -
Office Supplies & Postage - Months $ 300 $ -
Office Furniture - LS $ 15,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 1,500.00 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 500 $ -
Closeout Documents & As-Builts - LS $ 9,200 $ -
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Classroom Renovation
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Traffic Control/Flagman - Weeks $ 2,220 $ 819 $ -
Setup & Remove Field Office - LS $ 4,183 $ 1,544 $ 14,202 $ -
Setup & Remove Tool Trailer - LS $ 750 $ 277 $ 1,703 $ -
Temporary Ladders - EA $ 200 $ 74 $ 535 $ -
Project Signs - LS $ 2,500 $ 923 $ 4,860 $ -
Radios - LS $ 6,500 $ -
Temp/Permanent Power & Gas - Months $ -
Temporary Power - Months $ 1,620.00 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat - Months $ 15,000 $ -
Temporary Water - Months $ -
Holding Tank - Months $ 378 $ -
Temporary Toilets - Months $ 2,000 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,104 $ -
Barricades - LS $ 25,000 $ -
Ceremonies - LS $ - $ -
TOTAL $ 282,494
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Classroom Renovation
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 12 EA $ 100 $ 1,240
Temporary Fence - LF $ 5 $ 2 $ 6.24 $ -
Continuous Cleanup 24 Weeks $ 3,724 $ 1,374 $ 122,357
Dump Fees 80 Pulls $ 577 $ 46,413
Street Sweeper - Months $ 1,610 $ -
Skid Steer - Months $ 2,862 $ -
Equipment Rental - Months $ 2,100 $ -
Fuel & Lubricant - Months $ 250 $ -
Small Tools - Months $ 1,000 $ -
Cupix 1 LS $ 15,000.00 $ 15,000
Relocate Existing Furniture 100,035 SF $ 1.00 $ 100,035
Relocate Existing Technology 100,035 SF $ 1.00 $ 100,035
Protect New Work 1 LS $ 49,948.00 $ 49,948
Protect Existing Facility 100,035 SF 0.56 0.21 $ 0.56 $ 132,711
TOTAL $ 567,740
1 of 1
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Athletics
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 145,505 $ 53,694 $ 199,199
Assistant Project Manager (100%) 30 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Coordinator (100%) 12 Weeks $ -
Assistant Superintendent (100%) 17 Weeks $ -
Assistant Superintendent (100%) 13 Weeks $ -
Purchasing Agent (100%) 5 Weeks $ 1,920 $ 709 $ 13,143
Project Secretary (100%) 12 Weeks $ 720 $ 266 $ 11,828
Project Accountant (100%) 12 Weeks $ 1,750 $ 646 $ 28,749
Travel & Entertainment - Months $ 270
Supervision Vehicles - Months $ 1,790 $ -
Superintendent Vehicle Fuel & Repair - Months $ 4,600 $ -
Superintendent Vehicle Insurance - Months $ 562.50 $ -
Safety Program & Inspections - LS $ 16,200 $ -
Safety Signage - LS $ 5,000 $ 1,845 $ 15,000 $ -
Drug Testing - LS $ 1,080 $ -
Hard Hats & Safety Vests - LS $ 6,000 $ -
Raingear & Boots - LS $ 1,500 $ -
Eye & Ear Protection - LS $ 1,500 $ -
Safety Harnesses and Lifelines - LS $ 1,735 $ -
First Aid Supplies - Months $ 108 $ -
Office Trailer Rental - Months $ 4,620 $ -
Tool Trailer Rental - Months $ 500 $ -
Office Equipment - LS $ 650 $ -
Computer Equipment - LS $ 15,000 $ -
Project Software - Procore - Months $ 299,986 $ -
Office Supplies & Postage - Months $ 300 $ -
Office Furniture - LS $ 15,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 1,500.00 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 500 $ -
Closeout Documents & As-Builts - LS $ 9,200 $ -
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Athletics
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Traffic Control/Flagman - Weeks $ 2,220 $ 819 $ -
Setup & Remove Field Office - LS $ 4,183 $ 1,544 $ 14,202 $ -
Setup & Remove Tool Trailer - LS $ 750 $ 277 $ 1,703 $ -
Project Signs - LS $ 2,500 $ 923 $ 4,860 $ -
Radios - LS $ 6,500 $ -
Temp/Permanent Power & Gas - Months $ -
Temporary Power - Months $ 1,620.00 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat - Months $ 15,000 $ -
Temporary Water - Months $ -
Holding Tank - Months $ 378 $ -
Temporary Toilets - Months $ 2,000 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,104 $ -
-
Barricades - LS $ 25,000 $ -
Ceremonies 1 LS $ - $ -
TOTAL $ 252,919
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Athletics
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Temporary Fence 3,114 LF $ 5 $ 2 $ 15.64 $ 70,022
Continuous Cleanup 26 Weeks $ 1,862 $ 687 $ 66,277
Dump Fees 91 Pulls $ 577 $ 52,507
Street Sweeper - Months $ 1,610 $ -
Skid Steer - Months $ 2,862 $ -
Equipment Rental 2 Months $ 2,100 $ 4,200
Fuel & Lubricant 2 Months $ 248 $ 496
Small Tools 2 Months $ 1,000 $ 2,000
TOTAL $ 195,502
1 of 1
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Gym Renovation
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 163,603 $ 60,372 $ 223,975
Assistant Project Manager (100%) 26 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Coordinator (100%) 12 Weeks $ -
Assistant Superintendent (100%) 26 Weeks $ -
Field Engineer (100%) 24 Weeks $ -
Purchasing Agent (100%) 10 Weeks $ 1,920 $ 709 $ 26,285
Project Secretary (100%) 12 Weeks $ 720 $ 266 $ 11,828
Project Accountant (100%) 12 Weeks $ 1,750 $ 646 $ 28,749
Travel & Entertainment - Months $ 270
Supervision Vehicles - Months $ 1,790 $ -
Superintendent Vehicle Fuel & Repair - Months $ 4,600 $ -
Superintendent Vehicle Insurance - Months $ 562.50 $ -
Safety Program & Inspections - LS $ 16,200 $ -
Safety Signage - LS $ 5,000 $ 1,845 $ 15,000 $ -
Drug Testing - LS $ 1,080 $ -
Hard Hats & Safety Vests - LS $ 6,000 $ -
Raingear & Boots - LS $ 1,500 $ -
Eye & Ear Protection - LS $ 1,500 $ -
Safety Harnesses and Lifelines - LS $ 1,735 $ -
First Aid Supplies - Months $ 108 $ -
Office Trailer Rental - Months $ 4,620 $ -
Tool Trailer Rental - Months $ 500 $ -
Office Equipment - LS $ 650 $ -
Computer Equipment - LS $ 15,000 $ -
Project Software - Procore - Months $ 299,986 $ -
Office Supplies & Postage - Months $ 300 $ -
Office Furniture - LS $ 15,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 1,500.00 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 500 $ -
Closeout Documents & As-Builts - LS $ 9,200 $ -
1 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Gym Renovation
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Traffic Control/Flagman - Weeks $ 2,220 $ 819 $ -
Setup & Remove Field Office - LS $ 4,183 $ 1,544 $ 14,202 $ -
Setup & Remove Tool Trailer - LS $ 750 $ 277 $ 1,703 $ -
Temporary Ladders - EA $ 200 $ 74 $ 535 $ -
Project Signs - LS $ 2,500 $ 923 $ 4,860 $ -
Radios - LS $ 6,500 $ -
Temp/Permanent Power & Gas - Months $ -
Temporary Power - Months $ 1,620.00 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat - Months $ 15,000 $ -
Temporary Water - Months $ -
Holding Tank - Months $ 378 $ -
Temporary Toilets - Months $ 2,000 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,104 $ -
Barricades - LS $ 25,000 $ -
Ceremonies - LS $ - $ -
TOTAL $ 290,838
2 of 2
Attachment 5 - List of Itemized General Conditions
Cross Keys High School 1/23/2025
Gym Renovation
General Requirements Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 8 EA $ 100 $ 839
Temporary Fence - LF $ 5 $ 2 $ 6.24 $ -
Continuous Cleanup 26 Weeks $ 1,862 $ 687 $ 66,294
Dump Fees 54 Pulls $ 577 $ 31,365
Street Sweeper - Months $ 1,610 $ -
Skid Steer - Months $ 2,862 $ -
Equipment Rental - Months $ 2,100 $ -
Fuel & Lubricant - Months $ 250 $ -
Small Tools - Months $ 1,000 $ -
Cupix 1 LS $ 15,000.00 $ 15,000
Relocate Existing Furniture 43,621 SF $ 1 $ 43,621
Relocate Existing Technology 43,621 SF $ 1 $ 43,621
Protect New Work 1 LS $ 14,978.00 $ 14,978
Protect Existing Facility 43,621 SF 0.56 0.21 $ 0.56 $ 57,870
TOTAL $ 273,588