Agenda Item

v. E-SPLOST V Project ~ Final Guaranteed Maximum Price (GMP), Budget Reallocation, and Amendment Request ~ #21435 ~ Cross Keys High School New Addition and Modernization ~ Evergreen Construction Company and Cooper Carry, Inc. ~ Final GMP Approval, Budget Reallocation, and Amendment No. 8-A/E Fee Adjustment (Not to exceed –$148,421,607) ~ Updated 3.3.2025

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School District Board of Education (“the Board”) approve the below:


Approve the established Guaranteed Maximum Price (“GMP”) of $143,484,535 for the construction of the Cross Keys High School New Addition and Modernization E-SPLOST V project per the terms set forth in the Construction Manager at Risk (“CM@Risk”) contract previously awarded to Evergreen Construction Company (General Contractor- “GC”).
It is also requested to approve a Budget Reallocation of $99,065,458 from E-SPLOST V program contingency to fund this project.
It is further requested that the Board approve Amendment No. 08 to Cooper Carry, Inc. (Architectural & Engineering - “A/E”) in a Not -to-Exceed amount of $4,937,072 for added design services.
Why: Approval of the Guaranteed Maximum Price (GMP) of $143,484,535 and budget reallocation of $99,065,458 for the construction of the Cross Keys High School New Addition and Modernization E-SPLOST V project as per the CM@Risk contract approved by the Board, May 6, 2024, to Evergreen Construction Company ensures the completion of this project supporting a safe and healthy teaching and learning environment for students and staff.

Approval of Amendment No. 8 to amend the agreement with Cooper Carry, Inc. in the amount of $4,937,072 for the Addition and Modernization of Cross Keys High School project will provide the necessary funds for the revised scope of work and additional design and engineering fee outlined in the Proposal for Additional Services documents.

Approval of the Final Guaranteed Maximum Price (GMP), budget reallocation, and Amendment No. 08 meets Strategic Goal Area 6: Organizational Excellence
Details: On November 5, 2018, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Evergreen Construction Company for the completion of the Addition and Modernization of Cross Keys High School project and for Pre-Construction Services in the amount of $90,000.00.

On May 6, 2024, the Board approved the Component Guaranteed Maximum Price #01 Early Release Package of $44,419,077 for enabling work associated with the construction of the Addition and Modernization of Cross Keys High School SPLOST V project.

Pursuant to that agreement, the Design Professional (Cooper Carry), CM@R (Evergreen), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and a Final GMP in the best interest of the DeKalb County School District (“DCSD”).

This action establishes a Final Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached -Cross Keys HS Exhibit M - GMP Amendment document.
Financial impact: Amendment No. 8 for Cooper Carry, Inc will be funded by the Architect cost code of Project 21435 - SPFACCON.21435.ARCHITECT

The total contract amount for the Final GMP -Addition and Modernization of Cross Keys High School project in the amount of $143,484,535 will be allocated as follows:


$44,419,077.00 - previously funded - Initial GMP approved by the Board (5/6/2024)



$24,490,923.00 - Existing budget in E-SPLOST V Project 21435 cost code (SP5FACCON.21435.GENCONTR)



$39,000,000.00 - New budget added to E-SPLOST V program for E-SPLOST V Project 21435 cost code (SP5FACCON.21435.GENCONTR)



$35,574,535.00 - New budget added to E-SPLOST VI program for E-SPLOST VI Project 40736 cost code (SP5FACCON.21435.GENCONTR)


under the voter-approved E-SPLOST V program. The Final GMP will require a budget reallocation of $99,065,458.00 from E-SPLOST V program contingency to fund this project.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval and Fully Executed Documents
                                             EXHIBIT M
         GMP AMENDMENT TO AGREEMENT BETWEEN OWNER AND
                   CONSTRUCTION CONTRACTOR

            AMENDMENT NO. 2 TO AGREEMENT BETWEEN OWNER AND
          CONSTRUCTION CONTRACTOR FOR Cross Keys High School
                        AGREEMENT NO. 423.71.04.00.214423.752.0000
        Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
 (“Agreement”), dated 11/19/2018    , between The School Board of DeKalb County, Georgia
 (“Owner”) and Evergreen Construction
 (“Construction Contractor”), with respect to the construction of Owner’s
     Cross Keys High School                             (“Project”), Owner and Construction
 Contractor hereby agree to amend and modify the Agreement by this Amendment No. 2 and
 establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
 capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
 unless otherwise noted.

                                              ARTICLE 1


                                          SCOPE OF WORK
 The scope of the Work consists of the construction of a Renovation and Modernization to Cross Keys
High School at 1626 N Druid Hills Rd, Atlanta, GA 30319,
                                                     in accordance with the Agreement, this
 Amendment and the other Contract Documents listed as Attachments 1 through 5 below, which
 are hereby incorporated into and made a part of the Amendment by this reference:

Attachment No.          Description                          Pages                       Date

List of Drawings, Specifications and Addendums
1.                      Allowances                             1
                                                             _____ through _____
                                                                             1           1/23/25

2.                      Assumptions and Clarifications       _____
                                                               1   through _____
                                                                             5           1/23/25

3.                      Completion Schedule                  _____
                                                              1    through _____
                                                                             1           1/23/25
4.                      Schedule of Values                   _____
                                                               1             8
                                                                   through _____         1/23/25

5.                      List of Itemized General Conditions _____
                                                             1              18
                                                                  through _____          1/23/25

6.                      List of Subcontractors and           _____ through _____
                        Major Suppliers
7.                      Alternates                           _____ through _____



                                                       M-1
                                                ARTICLE 2


                                 GUARANTEED MAXIMUM PRICE


            2.1    Construction Contractor’s Guaranteed Maximum Price (“GMP”) for the Work,
  including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
  Construction Management Fee as defined in Section 4 of the       defined in Section
                                                                      Agreement,       4 ofhundred
                                                                                   is One   the    forty three
million four hundred eighty four thousand five hundred thirty five  ($  143,484,535        ).

         2.2    The Construction Management Fee for the entire Work anticipated on this Project
  is hereby established as a lump sum amount of Six million ninety three thousand nine hundred eighty two
  ($_ 6,093,982 ), said lump sum amount is included within the above noted GMP.

          2.3    The general condition expenses for the entire Work anticipated on this Project are
  hereby established as a lump sum amount of Twelve million eight hundred fifty five thousand nine hundred thirteen
  ($ 12,855,913 ), said lump sum amount is included within the above noted GMP (“General
  Conditions Expenses”). The items included as General Condition Expenses are listed in the List
  of Itemized General Conditions attached hereto and incorporated herein as Attachment No. 5 .
  Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
  Change Order or Construction Change Directive, Construction Contractor acknowledges and
  agrees that Owner shall have no liability for any General Condition expenses beyond payment of
  the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
  to receive any additional compensation from Owner for the General Conditions beyond the above
  lump sum amount. There shall be no additional General Conditions Expenses payable to
  Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
  of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
  this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
  Change Directive Work). Further, there shall be no mark-up for a subcontractor’s General
  Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
  Change Order and Construction Change Directive Work to be performed by such subcontractor.

         2.4    Monthly installment payment of the Construction Management Fee and the General
  Condition Expenses shall be based upon the percent completion of the designated portion of the
  Work for each particular month.

          2.5     In order to efficiently and timely address any unknown or unanticipated conditions
  that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
  of the Work, but excluding all items that are to be reimbursed under the lump sum General
  Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
                                                                            Five million one hundred seventy
  contingency within the GMP in an amount not-to-exceed amount of seven thousand one hundred fifty and
                                                                            four
     /100 Dollars ($ 5,177,154                ) (“Owner’s Contingency”). Owner’s Contingency
  funds shall be used to cover costs that may result from incomplete design and unanticipated costs
  that arise during construction that are not identified by the construction documents. Construction

                                                         M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner’s Contingency without first obtaining Owner’s express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner’s Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor’s Work compensated within the
GMP and not chargeable against Owner’s Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner’s Contingency expenditures. Further, the work that
is the subject of any Owner’s Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner’s Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner’s Contingency.

                2.6     In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above,Sixthe            parties have agreed to
                                                                             million four hundred seventy

establish a contingency within the GMP in an amount not-to-exceedtwo                                    and
                                                                          one thousand four hundred forty
                                                                                                             /100
Dollars ($6,471,442 ) (“Contractor’s Contingency”). Construction Contractor shall not proceed
with any portion of the Work which it intends to charge against the Contractor’s Contingency
without first obtaining Owner’s express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor’s
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor’s Work compensated within the GMP and not chargeable against
Contractor’s Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor’s Contingency expenditures. Further, the work that is the subject of any Owner’s
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor’s Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor’s Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of                        % of
the Cost of the Work charged against the Contractor’s Contingency.

        2.7     The parties have agreed to establish an allowance within the GMP for
 See allowances log          in the amount of                and /100 Dollars ($ 4,848,200          ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance (“Allowance Work”) without first obtaining Owner’s express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments 1 through. Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenever costs are more
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.




                                                         M-3
       2.8    Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
payment is made to Construction Contractor the total Cost of the Work has been increased by
approved Change Orders in an amount causing the original GMP as set forth in this Amendment
to be exceeded by more than                       and     /100 Dollars ($                 ), then
Construction Contractor shall be entitled to an increase in the Construction Management Fee in
the amount of and /100 Dollars (                           %) of the amount exceeding the sum of
            and /100 Dollars ($                  _) plus that original GMP amount.

        2.9    Construction Contractor recognizes that the Contract includes work for trench
excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
set forth by all federal, state and local requirements. Construction Contractor certifies that the
required trench safety standards will be in effect during the period of construction of the Project
and Construction Contractor agrees to comply with all such required trench safety standards.

               2.10.1 The amount of                Zero                      and /100         Dollars
($ 0              ) has been separately identified for the cost of compliance with the required trench
safety standards; said amount is included within the GMP.

        2.10 At the completion of the Work, should the actual amount of “General
Requirements” expenses be less than the amount included therefor in the Schedule of Values
approved by Owner, the resulting “savings” shall accrue to the benefit of Owner and a deductive
Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
separate guaranteed maximum price for such expenses and any overruns in General Requirements
expenses shall be borne by Construction Contractor without reimbursement from Owner.

        2.11 By executing this Amendment and furnishing Owner with a GMP based on a
detailed Schedule of Values and a Master Project Schedule, Construction Contractor represents
and warrants that the Contract Documents, including the Construction Documents, as well as other
materials, and information furnished Construction Contractor as of the date of this Amendment
have described the scope, construction requirements, and design intent of the Work in detail
sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
Project Schedule. To the extent that the Construction Documents are anticipated to require further
development, Construction Contractor has provided in the GMP for such further development
consistent with the Contract Documents and reasonably inferable therefrom.

        2.12 Savings will be computed as of the date of final completion of the Work and shall
consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
benefit of Owner.



                                                    M-4
List of Drawings, Specifications and Addendums


        INDEX OF DRAWINGS                                                                       DESCRIPTION    DATED
                                     CIVIL
C1.0                                 Cover Sheet & General Notes                                               8/7/2024
                                     Boundary, Topographic, Utility & Tree Survey                              3/6/2023
                                     Boundary, Topographic, Utility & Tree Survey                              3/6/2023
C2.0                                 Overall Demolition Plan                                                   8/7/2024
C2.1                                 Demolition Plan II                                                        8/7/2024
C2.2                                 Demolition Plan II                                                        8/7/2024
C3.0                                 Overall Layout & Staking Plan                                             8/7/2024
C3.1                                 Layout & Staking Plan I                                                   8/7/2024
C3.2                                 Layout & Staking Plan II                                                  8/7/2024
C3.3                                 N. Druid Hills Rd NE & Curtis Drive Intersection Blow Up                  8/7/2024
C4.0                                 Overall Grading Plan                                                      8/7/2024
C4.1                                 Grading Plan I                                                            8/7/2024
C4.2                                 Grading Plan II                                                           8/7/2024
C4.3                                 Drainage Plan I                                                           8/7/2024
C4.4                                 Drainage Plan II                                                          8/7/2024
C4.5                                 Stormwater Details I                                                      8/7/2024
C4.6                                 Stormwater Details II                                                     8/7/2024
C5.0                                 Overall Utility Plan                                                     8/7/2024
C5.1                                 Utility Plan I                                                            8/7/2024
C5.2                                 Utility Plan II                                                           8/7/2024
C5.3                                 Fire Site Access Plan                                                     8/7/2024
C6.0                                 Profile Plan                                                              8/7/2024
C6.1                                 Profile Plan                                                              8/7/2024
C6.2                                 Profile Plan                                                              8/7/2024
C6.3                                 Sanitary Sewer Profile Plan                                               8/7/2024
C7.0                                 Construction Details                                                      8/7/2024
C7.1                                 Construction Details                                                      8/7/2024
C7.2                                 Construction Details                                                      8/7/2024
C7.3                                 Construction Details                                                      8/7/2024
C7.4                                 Construction Details                                                      8/7/2024
C7.5                                 Construction Details                                                      8/7/2024
C7.6                                 Construction Details                                                      8/7/2024
C7.7                                 ES&PC Notes                                                               8/7/2024
EC1.0                                ES&PC Notes                                                               8/7/2024
EC1.1                                ES&PC Notes                                                               8/7/2024
EC1.2                                ES&PC Notes                                                               8/7/2024
EC1.3                                ES&PC Notes                                                               8/7/2024
EC2.0                                Initial ES&PC Plan                                                        8/7/2024
EC3.0                                Intermediate ES&PC Plan                                                   8/7/2024
EC4.0                                Final ES&PC Plan                                                          8/7/2024
EC5.0                                ES&PC Details                                                             8/7/2024
EC5.1                                ES&PC Details                                                             8/7/2024
EC5.2                                ES&PC Details                                                             8/7/2024
EC5.3                                ES&PC Details                                                             8/7/2024
EC5.4                                ES&PC Details                                                             8/7/2024
EC5.5                                ES&PC Details                                                             8/7/2024
EC5.6                                ES&PC Details                                                             8/7/2024
L0.00                                Landscape General Notes                                                   8/7/2024
L0.01                                Tree Removal Plan                                                         8/7/2024
L0.02                                Tree Removal Schedule                                                     8/7/2024
L0.03                                Offsite Tree Replanting Plan - Ashford Park ES                            8/7/2024
L0.04                                Offsite Tree Replanting Plan - John Lewis ES                              8/7/2024
L0.05                                Offsite Tree Replanting Plan - Montclair ES                               8/7/2024
L1.01                                Hardscape Plan                                                            8/7/2024
L1.02                                Hardscape Plan                                                            8/7/2024
L1.03                                Hardscape Plan                                                            8/7/2024
L1.04                                Hardscape Plan                                                            8/7/2024
L1.05                                Hardscape Plan                                                            8/7/2024
L2.01                                Hardscape Details                                                        7/25/2024
L2.02                                Hardscape Details                                                         8/7/2024
L3.01                                Overall Landscape Plan                                                    8/7/2024
L3.02                                Landscape Plan                                                            8/7/2024
L3.03                                Landscape Plan                                                            8/7/2024
L3.04                                Landscape Plan                                                            8/7/2024
L3.05                                Landscape Plan                                                            8/7/2024
L4.00                                Landscape Details                                                         8/7/2024
G0.00-1                              Cover Sheet LDP + Phase 1                                                 8/7/2024
A1.20                                Enlarged Site Plan and Detials - Bus Loop Canopy                          8/7/2024
A1.21                                Enlarged Site Plan and Detials - Bus Loop Canopy                          8/7/2024
S10.01                               Site Retaining Walls                                                      8/7/2024
S10.02                               Bus Loop Canopy Foundation Plan and Sections                              8/7/2024
E0.01                                Electrical Phase 1 Bus Canopy                                             8/7/2024

                                     GENERAL - VOLUME 1
G0.00                                COVER SHEET                                                              10/30/2024
G0.01                                DRAWING INDEX                                                            10/30/2024
G0.02                                DRAWING INDEX                                                            10/30/2024
G0.03                                GENERAL INFORMATION                                                      10/30/2024
G1.00                                OCCUPANT LOAD SCHEDULES                                                  10/30/2024




                                                                                                    1 of 11
List of Drawings, Specifications and Addendums


          INDEX OF DRAWINGS                                                         DESCRIPTION     DATED
G1.01                                MEANS OF EGRESS PLAN - LEVEL 1                                10/30/2024
G1.02                                MEANS OF EGRESS PLAN - LEVEL 2 & 3                            10/30/2024
G1.03                                MEANS OF EGRESS PLAN - LEVEL 1 ALTERNATE                      10/30/2024
G2.00                                CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.01.1                              CONSTRUCTION PHASING DIAGRAM AND FIRE SAFETY PLAN             10/30/2024
G2.01.2                              CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.02                                CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.02.1                              CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.02.2                              CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.03                                CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
G2.04                                CONSTRUCTION PHASING DIAGRAMS                                 10/30/2024
                                     CIVIL
C1.0B                                COVER SHEET & GENERAL NOTES                                   10/30/2024
SURVEY I                             SITE SURVEY I                                                 10/30/2024
SURVEY II                            SITE SURVEY II                                                10/30/2024
C2.0B                                OVERALL DEMOLITION PLAN                                       10/30/2024
C2.1B                                DEMOLITION PLAN I                                             10/30/2024
C2.2B                                DEMOLITION PLAN II                                            10/30/2024
C3.0B                                OVERALL LAYOUT & STAKING PLAN                                 10/30/2024
C3.1B                                LAYOUT & STAKING PLAN I                                       10/30/2024
C3.2B                                LAYOUT & STAKING PLAN II                                      10/30/2024
C4.0B                                GRADING PLAN                                                  10/30/2024
C4.1B                                GRADING PLAN I                                                10/30/2024
C4.2B                                GRADING PLAN II                                               10/30/2024
C4.3B                                DRAINAGE PLAN I                                               10/30/2024
C4.4B                                DRAINAGE PLAN II                                              10/30/2024
C5.0B                                UTILITY PLAN                                                  10/30/2024
C5.1B                                UTILITY PLAN I                                                10/30/2024
C5.2B                                UTILITY PLAN II                                               10/30/2024
C5.3B                                FIRE SITE ACCESS PLAN                                         10/30/2024
C6.0B                                PROFILE PLAN                                                  10/30/2024
C6.1B                                PIPE CHART                                                    10/30/2024
C6.2B                                SANITARY SEWER PROFILE PLAN                                   10/30/2024
C7.0B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.1B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.2B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.3B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.4B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.5B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.6B                                CONSTRUCTION DETAILS                                          10/30/2024
C7.7B                                CONSTRUCTION DETAILS                                          10/30/2024
EC1.0B                               ES&PC NOTES                                                   10/30/2024
EC1.1B                               ES&PC NOTES                                                   10/30/2024
EC1.2B                               ES&PC NOTES                                                   10/30/2024
EC1.3B                               ES&PC NOTES                                                   10/30/2024
EC2.0B                               INITIAL ES&PC PLAN                                            10/30/2024
EC3.0B                               INTERMEDIATE ES&PC PLAN                                       10/30/2024
EC4.0B                               FINAL ES&PC PLAN                                              10/30/2024
EC5.0B                               ES&PC DETAILS                                                 10/30/2024
EC5.1B                               ES&PC DETAILS                                                 10/30/2024
EC5.2B                               ES&PC DETAILS                                                 10/30/2024
EC5.3B                               ES&PC DETAILS                                                 10/30/2024
EC5.4B                               ES&PC DETAILS                                                 10/30/2024
EC5.5B                               ES&PC DETAILS                                                 10/30/2024
EC5.6B                               ES&PC DETAILS                                                 10/30/2024
                                     LANDSCAPE
L0.00                                GENERAL NOTES                                                 10/30/2024
L1.01                                OVERALL HARDSCAPE PLAN                                        10/30/2024
L1.02                                HARDSCAPE PLAN                                                10/30/2024
L1.03                                HARDSCAPE PLAN                                                10/30/2024
L1.04                                HARDSCAPE PLAN                                                10/30/2024
L1.05                                HARDSCAPE PLAN                                                10/30/2024
L1.06                                HARDSCAPE ENLARGEMENT PLAN                                    10/30/2024
L1.07                                HARDSCAPE ENLARGEMENT PLAN                                    10/30/2024
L1.08                                HARDSCAPE ENLARGEMENT PLAN                                    10/30/2024
L1.09                                TRACK AND FIELD ENLARGEMENT PLAN                              10/30/2024
L1.10                                GRADING PLAN - ENLARGEMENTS                                   10/30/2024
L1.11                                GRADING PLAN - ENLARGEMENTS                                   10/30/2024
L1.12                                GRADING PLAN - ENLARGEMENTS                                   10/30/2024
L1.13                                GRADING PLAN - ENLARGEMENTS                                   10/30/2024
L1.21                                OVERALL SITE LIGHTING PLAN                                    10/30/2024
L2.01                                HARDSCAPE DETAILS                                             10/30/2024
L2.02                                HARDSCAPE DETAILS                                             10/30/2024
L2.04                                HARDSCAPE DETAILS                                             10/30/2024
L2.04                                HARDSCAPE DETAILS                                             10/30/2024
L2.05                                HARDSCAPE DETAILS                                             10/30/2024
L3.00A                               TREE REMOVAL PLAN                                             10/30/2024
L3.00B                               TREE REMOVAL SCHEDULE                                         10/30/2024
L3.01                                OVERALL LANDSCAPE PLAN                                        10/30/2024
L3.02                                LANDSCAPE PLAN                                                10/30/2024




                                                                                         2 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                             DESCRIPTION         DATED
L3.03                                LANDSCAPE PLAN                                                       10/30/2024
L3.04                                LANDSCAPE PLAN                                                       10/30/2024
L3.05                                LANDSCAPE PLAN                                                       10/30/2024
L3.06                                LANDSCAPE PLAN                                                       10/30/2024
L3.07                                LANDSCAPE PLAN                                                       10/30/2024
L4.00                                LANDSCAPE NOTES AND DETAILS                                          10/30/2024
                                     DEMOLITION
D1.00                                DEMOLITION SITE PLAN                                                 10/30/2024
D2.01                                OVERALL LEVEL 1 DEMOLITION PLAN                                      10/30/2024
D2.04                                DEMOLITION ROOF PLAN                                                 10/30/2024
D2.11D                               DEMOLITION FLOOR PLAN - 100 WING - AREA D                            10/30/2024
D2.11E                               DEMOLITION FLOOR PLAN - 200 WING - AREA E                            10/30/2024
D2.11F                               DEMOLITION FLOOR PLAN - 300 WING + 400 WING - AREA F + G             10/30/2024
D2.11H                               DEMOLITION FLOOR PLAN - CTAE - AREA H                                10/30/2024
D2.11J                               DEMOLITION FLOOR PLAN - GYMNASIUM                                    10/30/2024
D2.11K                               DEMOLITION FLOOR PLAN - GYMNASIUM                                    10/30/2024
D6.01                                DEMOLITION SECTIONS & DETAILS                                        10/30/2024
                                     ARCHITECTURE
A1.00                                ARCHITECTURAL SITE PLAN                                              10/30/2024
A1.20                                ENLARGED SITE PLANS AND DETAILS - BUS LOOP CANOPY                    10/30/2024
A1.21                                ENLARGED SITE PLANS AND DETAILS - BUS LOOP CANOPY                    10/30/2024
A2.01                                OVERALL LEVEL 1 FLOOR PLAN                                           10/30/2024
A2.02                                OVERALL LEVEL 2 & 3 FLOOR PLAN                                       10/30/2024
A2.04                                ROOF PLAN                                                            10/30/2024
A2.11A                               LEVEL 1 FLOOR PLAN - AREA A                                          10/30/2024
A2.11B                               LEVEL 1 FLOOR PLAN - AREA B                                          10/30/2024
A2.11C                               LEVEL 1 FLOOR PLAN - AREA C                                          10/30/2024
A2.11D                               LEVEL 1 FLOOR PLAN - AREA D                                          10/30/2024
A2.11E                               LEVEL 1 FLOOR PLAN - AREA E                                          10/30/2024
A2.11F                               LEVEL 1 FLOOR PLAN - AREA F/G                                        10/30/2024
A2.11H                               LEVEL 1 FLOOR PLAN - AREA H                                          10/30/2024
A2.11J                               LEVEL 1 FLOOR PLAN - AREA J                                          10/30/2024
A2.11K                               LEVEL 1 FLOOR PLAN - AREA K/L                                        10/30/2024
A2.11M                               LEVEL 1 FLOOR PLAN - AREA M                                          10/30/2024
A2.11N                               LEVEL 1 FLOOR PLAN - AREA N                                          10/30/2024
A2.12A                               LEVEL 2 FLOOR PLAN - AREA A                                          10/30/2024
A2.12B                               LEVEL 2 FLOOR PLAN - AREA B                                          10/30/2024
A2.12C                               LEVEL 2 FLOOR PLAN - AREA C                                          10/30/2024
A2.13A                               LEVEL 3 FLOOR PLAN - AREA A                                          10/30/2024
A2.13B                               LEVEL 3 FLOOR PLAN - AREA B                                          10/30/2024
A2.13C                               LEVEL 3 FLOOR PLAN - AREA C                                          10/30/2024
A2.14A                               ROOF PLAN - AREA A                                                   10/30/2024
A2.14B                               ROOF PLAN - AREA B                                                   10/30/2024
A2.14C                               ROOF PLAN - AREA C                                                   10/30/2024
A2.14G                               ROOF PLAN - AREA G                                                   10/30/2024
A2.14H                               ROOF PLAN - AREA H                                                   10/30/2024
A2.14K                               ROOF PLAN - AREA K                                                   10/30/2024
A2.14M                               ROOF PLAN - AREA M                                                   10/30/2024
A2.14N                               ROOF PLAN - AREA N                                                   10/30/2024
A2.30                                LEVEL 1 - SLAB ELEVATION DIAGRAM                                     10/30/2024
A2.31A                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA A                                   10/30/2024
A2.31B                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA B                                   10/30/2024
A2.31C                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA C                                   10/30/2024
A2.31D                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA D                                   10/30/2024
A2.31E                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA E                                   10/30/2024
A2.31F                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA F/G                                 10/30/2024
A2.31H                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA H                                   10/30/2024
A2.31J                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA J                                   10/30/2024
A2.31K                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA K/L                                 10/30/2024
A2.31M                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA M                                   10/30/2024
A2.31N                               LEVEL 1 EDGE-OF-SLAB PLAN - AREA N                                   10/30/2024
A2.32A                               LEVEL 2 EDGE-OF-SLAB PLAN - AREA A                                   10/30/2024
A2.32B                               LEVEL 2 EDGE-OF-SLAB PLAN - AREA B                                   10/30/2024
A2.32C                               LEVEL 2 EDGE-OF-SLAB PLAN - AREA C                                   10/30/2024
A2.33A                               LEVEL 3 EDGE-OF-SLAB PLAN - AREA A                                   10/30/2024
A2.33B                               LEVEL 3 EDGE-OF-SLAB PLAN - AREA B                                   10/30/2024
A2.33C                               LEVEL 3 EDGE-OF-SLAB PLAN - AREA C                                   10/30/2024
A2.34A                               ROOF - EDGE-OF-DECK PLAN - AREA A                                    10/30/2024
A2.34B                               ROOF - EDGE-OF-DECK PLAN - AREA B                                    10/30/2024
A2.34C                               ROOF - EDGE-OF-DECK PLAN - AREA C                                    10/30/2024
A2.34D                               ROOF - EDGE-OF-DECK PLAN - AREA G                                    10/30/2024
A2.34E                               ROOF - EDGE-OF-DECK PLAN - AREA H                                    10/30/2024
A2.34F                               ROOF - EDGE-OF-DECK PLAN - AREA K                                    10/30/2024
A2.34G                               ROOF - EDGE-OF-DECK PLAN - AREA M                                    10/30/2024
A2.34H                               ROOF - EDGE-OF-DECK PLAN - AREA N                                    10/30/2024
A2.40A                               OVERALL LEVEL 1 REFLECTED CEILING PLAN                               10/30/2024
A2.40B                               OVERALL LEVEL 2 AND 3 REFLECTED CEILING PLANS                        10/30/2024
A2.41A                               LEVEL 1 REFLECTED CEILING PLAN - AREA A                              10/30/2024
A2.41B                               LEVEL 1 REFLECTED CEILING PLAN - AREA B                              10/30/2024
A2.41C                               LEVEL 1 REFLECTED CEILING PLAN - AREA C                              10/30/2024




                                                                                                3 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                              DESCRIPTION      DATED
A2.41D                               LEVEL 1 REFLECTED CEILING PLAN - AREA D                            10/30/2024
A2.41E                               LEVEL 1 REFLECTED CEILING PLAN - AREA E                            10/30/2024
A2.41F                               LEVEL 1 REFLECTED CEILING PLAN - AREA F/G                          10/30/2024
A2.41H                               LEVEL 1 REFLECTED CEILING PLAN - AREA H                            10/30/2024
A2.41J                               LEVEL 1 REFLECTED CEILING PLAN - AREA J                            10/30/2024
A2.41K                               LEVEL 1 REFLECTED CEILING PLAN - AREA K/L                          10/30/2024
A2.41M                               LEVEL 1 REFLECTED CEILING PLAN - AREA M                            10/30/2024
A2.41N                               LEVEL 1 REFLECTED CEILING PLAN - AREA N                            10/30/2024
A2.42A                               LEVEL 2 REFLECTED CEILING PLAN - AREA A                            10/30/2024
A2.42B                               LEVEL 2 REFLECTED CEILING PLAN - AREA B                            10/30/2024
A2.42C                               LEVEL 2 REFLECTED CEILING PLAN - AREA C                            10/30/2024
A2.43A                               LEVEL 3 REFLECTED CEILING PLAN - AREA A                            10/30/2024
A2.43B                               LEVEL 3 REFLECTED CEILING PLAN - AREA B                            10/30/2024
A2.43C                               LEVEL 3 REFLECTED CEILING PLAN - AREA C                            10/30/2024
A2.44                                ENLARGED CEILING PLANS                                             10/30/2024
A2.50A                               FINISH SCHEDULES                                                   10/30/2024
A2.50B                               TYPICAL INTERIOR DETAILS                                           10/30/2024
A2.51A                               LEVEL 1 FINISH PLAN - AREA A                                       10/30/2024
A2.51B                               LEVEL 1 FINISH PLAN - AREA B                                       10/30/2024
A2.51C                               LEVEL 1 FINISH PLAN - AREA C                                       10/30/2024
A2.51D                               LEVEL 1 FINISH PLAN - AREA D                                       10/30/2024
A2.51E                               LEVEL 1 FINISH PLAN - AREA E                                       10/30/2024
A2.51F                               LEVEL 1 FINISH PLAN - AREA F/G                                     10/30/2024
A2.51H                               LEVEL 1 FINISH PLAN - AREA H                                       10/30/2024
A2.51J                               LEVEL 1 FINISH PLAN - AREA J                                       10/30/2024
A2.51K                               LEVEL 1 FINISH PLAN - AREA K/L                                     10/30/2024
A2.51M                               LEVEL 1 FINISH PLAN - AREA M                                       10/30/2024
A2.51N                               LEVEL 1 FINISH PLAN - AREA N                                       10/30/2024
A2.52A                               LEVEL 2 FINISH PLAN - AREA A                                       10/30/2024
A2.52B                               LEVEL 2 FINISH PLAN - AREA B                                       10/30/2024
A2.52C                               LEVEL 2 FINISH PLAN - AREA C                                       10/30/2024
A2.53A                               LEVEL 3 FINISH PLAN - AREA A                                       10/30/2024
A2.53B                               LEVEL 3 FINISH PLAN - AREA B                                       10/30/2024
A2.53C                               LEVEL 3 FINISH PLAN - AREA C                                       10/30/2024
A2.61A                               LEVEL 1 FURNITURE PLAN - AREA A                                    10/30/2024
A2.61B                               LEVEL 1 FURNITURE PLAN - AREA B                                    10/30/2024
A2.61C                               LEVEL 1 FURNITURE PLAN - AREA C                                    10/30/2024
A2.61D                               LEVEL 1 FURNITURE PLAN - AREA D                                    10/30/2024
A2.61E                               LEVEL 1 FURNITURE PLAN - AREA E                                    10/30/2024
A2.61F                               LEVEL 1 FURNITURE PLAN - AREA F/G                                  10/30/2024
A2.61H                               LEVEL 1 FURNITURE PLAN - AREA H                                    10/30/2024
A2.61J                               LEVEL 1 FURNITURE PLAN - AREA J                                    10/30/2024
A2.61K                               LEVEL 1 FURNITURE PLAN - AREA K/L                                  10/30/2024
A2.61M                               LEVEL 1 FURNITURE PLAN - AREA M                                    10/30/2024
A2.61N                               LEVEL 1 FURNITURE PLAN - AREA N                                    10/30/2024
A2.62A                               LEVEL 2 FURNITURE PLAN - AREA A                                    10/30/2024
A2.62B                               LEVEL 2 FURNITURE PLAN - AREA B                                    10/30/2024
A2.62C                               LEVEL 2 FURNITURE PLAN - AREA C                                    10/30/2024
A2.63A                               LEVEL 3 FURNITURE PLAN - AREA A                                    10/30/2024
A2.63B                               LEVEL 3 FURNITURE PLAN - AREA B                                    10/30/2024
A2.63C                               LEVEL 3 FURNITURE PLAN - AREA C                                    10/30/2024
A2.70                                SIGNAGE DETAILS                                                    10/30/2024
A2.71                                OVERALL SIGNAGE LOCATION PLAN - LEVEL 1                            10/30/2024
A2.71A                               SIGNAGE LOCATION PLAN - LEVEL 1 - AREA A, B, & C                   10/30/2024
A2.71D                               SIGNAGE LOCATION PLAN - LEVEL 1 - AREA D & E                       10/30/2024
A2.71F                               SIGNAGE LOCATION PLAN - LEVEL 1 - AREA F, G, & H                   10/30/2024
A2.71J                               SIGNAGE LOCATION PLAN - LEVEL 1 - AREA J, K, L, M, & N             10/30/2024
A2.72                                SIGNAGE LOCATION PLAN - LEVEL 2                                    10/30/2024
A2.73                                SIGNAGE LOCATION PLAN - LEVEL 3                                    10/30/2024
A3.00                                TYPICAL PLUMBING PLANS, ACCESSORIES & DETAILS                      10/30/2024
A3.01                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.02                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.03                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.04                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.05                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.06                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.07                                ENLARGED RESTROOM PLANS                                            10/30/2024
A3.10                                ENLARGED CLASSROOM PLANS                                           10/30/2024
A3.21                                ENLARGED TEACHER PLANNING ROOMS                                    10/30/2024
A3.22                                ENLARGED HOME LIVING CENTER & LTSE CLASSROOM                       10/30/2024
A3.23                                ENLARGED SAFE CENTER                                               10/30/2024
A3.31                                ENLARGED BAND SUITE                                                10/30/2024
A3.32                                ENLARGED ORCHESTRA SUITE                                           10/30/2024
A3.34                                ENLARGED KEYBOARD & PRACTICE ROOMS                                 10/30/2024
A3.37                                ENLARGED BLACK BOX THEATER, CONCESSIONS & TICKETING                10/30/2024
A3.38                                ENLARGED DIGITAL ART LAB                                           10/30/2024
A3.40                                ENLARGED CAREER CENTER                                             10/30/2024
A3.44                                ENLARGED JROTC SUITE                                               10/30/2024
A3.47                                ENLARGED CULINARY LAB                                              10/30/2024
A3.50                                ENLARGED MEDIA CENTER                                              10/30/2024




                                                                                              4 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                        DESCRIPTION      DATED
A3.51                                INTERIOR ELEVATIONS - RECEPTION & MEDIA CENTER               10/30/2024
A3.52                                INTERIOR ELEVATIONS - MEDIA CENTER                           10/30/2024
A3.53                                INTERIOR ELEVATIONS - MEDIA CENTER                           10/30/2024
A3.60                                ENLARGED GYMNASIUM                                           10/30/2024
A3.61                                GYMNASIUM STRIPING PLAN                                      10/30/2024
A3.62                                ENLARGED AUX GYMNASIUM                                       10/30/2024
A3.64                                INTERIOR ELEVATIONS - GYMNASIUM                              10/30/2024
A3.65                                INTERIOR ELEVATIONS - GYMNASIUM                              10/30/2024
A3.66                                ENLARGED GYMNASIUM LOCKER ROOMS & TRAINING ROOM              10/30/2024
A3.67                                ENLARGED WRESTLING ROOM                                      10/30/2024
A3.68                                ENLARGED WEIGHT ROOM                                         10/30/2024
A3.69                                ENLARGED HEALTH ROOMS                                        10/30/2024
A3.70                                ENLARGED DINING/COMMONS                                      10/30/2024
A3.72                                INTERIOR ELEVATIONS - DINING / COFFEE BAR LOUNGE             10/30/2024
A3.73                                INTERIOR ELEVATIONS - DINING / COFFEE BAR LOUNGE             10/30/2024
A3.90                                ENLARGED AUDITORIUM                                          10/30/2024
A3.91                                INTERIOR ELEVATIONS - AUDITORIUM                             10/30/2024
A3.92                                ENLARGED AUDITORIUM DRESSING ROOMS                           10/30/2024
A3.94                                ENLARGED EXTENDED LEARNING                                   10/30/2024
A3.95                                INTERIOR ELEVATIONS - EXTENDED LEARNING                      10/30/2024
A3.96                                INTERIOR ELEVATIONS - CLASSROOM CORRIDORS                    10/30/2024
A4.00                                EXTERIOR ELEVATIONS                                          10/30/2024
A4.01                                EXTERIOR ELEVATIONS                                          10/30/2024
A4.02                                EXTERIOR ELEVATIONS                                          10/30/2024
A4.03                                EXTERIOR ELEVATIONS                                          10/30/2024
A4.04                                EXTERIOR ELEVATIONS                                          10/30/2024
A4.10                                BUILDING SECTIONS                                            10/30/2024
A4.11                                BUILDING SECTIONS                                            10/30/2024
A5.01                                EXTERIOR WALL SECTIONS - AREA A                              10/30/2024
A5.02                                EXTERIOR WALL SECTIONS - AREA A                              10/30/2024
A5.03                                EXTERIOR WALL SECTIONS - AREA A                              10/30/2024
A5.04                                EXTERIOR WALL SECTIONS - AREA A                              10/30/2024
A5.07                                EXTERIOR WALL SECTIONS - AREA A                              10/30/2024
A5.08                                EXTERIOR WALL SECTIONS - AREA B                              10/30/2024
A5.09                                EXTERIOR WALL SECTIONS - AREA C                              10/30/2024
A5.10                                EXTERIOR WALL SECTIONS - AREA C                              10/30/2024
A5.11                                EXTERIOR WALL SECTIONS - AREA H                              10/30/2024
A5.12                                EXTERIOR WALL SECTIONS - AREA K                              10/30/2024
A5.13                                EXTERIOR WALL SECTIONS - AREA M                              10/30/2024
A5.14                                EXTERIOR WALL SECTIONS - AREA N                              10/30/2024
A5.15                                EXTERIOR WALL SECTIONS - AREA N                              10/30/2024
A5.16                                EXTERIOR WALL SECTIONS - AREA N                              10/30/2024
A5.17                                EXTERIOR WALL SECTIONS - AREA N                              10/30/2024
A6.00                                EXTERIOR ASSEMBLIES                                          10/30/2024
A6.01                                PLAN DETAILS                                                 10/30/2024
A6.02                                PLAN DETAILS                                                 10/30/2024
A6.11                                SECTION DETAILS                                              10/30/2024
A6.12                                SECTION DETAILS                                              10/30/2024
A6.13                                SECTION DETAILS                                              10/30/2024
A6.14                                SECTION DETAILS                                              10/30/2024
A6.15                                SECTION DETAILS                                              10/30/2024
A6.16                                SECTION DETAILS                                              10/30/2024
A6.17                                SECTION DETAILS                                              10/30/2024
A6.18                                SECTION DETAILS                                              10/30/2024
A6.19                                SECTION DETAILS                                              10/30/2024
A6.20                                TYPICAL BRICK DETAILS                                        10/30/2024
A6.21                                TYPICAL PARAPET DETAILS                                      10/30/2024
A6.22                                TYPICAL CURTAINWALL DETAILS                                  10/30/2024
A6.23                                TYPICAL STOREFRONT DETAILS                                   10/30/2024
A6.24                                SECTION DETAILS                                              10/30/2024
A6.30                                ROOF DETAILS                                                 10/30/2024
A6.31                                ROOF DETAILS                                                 10/30/2024
A6.32                                ROOF DETAILS                                                 10/30/2024
A6.41                                EXPANSION JOINT - DETAILS                                    10/30/2024
A6.42                                EXPANSION JOINT - DETAILS                                    10/30/2024
A6.43                                EXPANSION JOINT - DETAILS                                    10/30/2024
A6.44                                EXPANSION JOINT - DETAILS                                    10/30/2024
A6.45                                EXPANSION JOINT - DETAILS                                    10/30/2024
A6.61                                EXTERIOR CANOPY - AREA A - SECTIONS AND DETAILS              10/30/2024
A6.62                                EXTERIOR CANOPY - AREA A - SECTIONS AND DETAILS              10/30/2024
A6.63                                EXTERIOR CANOPY - AREA C - SECTIONS AND DETAILS              10/30/2024
A6.64                                EXTERIOR CANOPY - AREA N - SECTIONS AND DETAILS              10/30/2024
A6.81                                INTERIOR SECTION DETAILS                                     10/30/2024
A6.82                                INTERIOR SECTION DETAILS                                     10/30/2024
A7.01                                STAIR PLANS & SECTIONS - STAIR 1                             10/30/2024
A7.01A                               STAIR PLANS & SECTIONS - STAIR 1                             10/30/2024
A7.02                                STAIR PLANS & SECTIONS - STAIR 2                             10/30/2024
A7.03                                STAIR PLANS & SECTIONS - STAIR 3                             10/30/2024
A7.04                                STAIRS AND RAMPS PLANS & SECTIONS                            10/30/2024
A7.05                                STAIRS AND RAMPS PLANS & SECTIONS                            10/30/2024




                                                                                        5 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                         DESCRIPTION        DATED
A7.06                                STAIRS AND RAMPS PLANS & SECTIONS                               10/30/2024
A7.07                                METAL PAN STAIR & RAILING DETAILS                               10/30/2024
A7.08                                RAILING DETAILS                                                 10/30/2024
A7.10                                ELEVATOR PLANS, ELEVATIONS, SECTIONS & DETAILS                  10/30/2024
A8.00                                DOOR TYPES                                                      10/30/2024
A8.01                                DOOR SCHEDULE                                                   10/30/2024
A8.02                                DOOR SCHEDULE                                                   10/30/2024
A8.10                                DOOR DETAILS                                                    10/30/2024
A8.20                                WINDOW SCHEDULE                                                 10/30/2024
A8.21                                WINDOW SCHEDULE                                                 10/30/2024
A8.22                                WINDOW SCHEDULE                                                 10/30/2024
A8.23                                WINDOW SCHEDULE                                                 10/30/2024
A9.01                                INTERIOR PARTITIONS                                             10/30/2024
A9.02                                INTERIOR PARTITIONS                                             10/30/2024
A9.11                                FIRE PROTECTION DETAILS                                         10/30/2024
A9.12                                FIRE PROTECTION DETAILS                                         10/30/2024
A9.13                                FIRE PROTECTION DETAILS                                         10/30/2024
A10.01                               MILLWORK DETAILS                                                10/30/2024
A10.02                               MILLWORK DETAILS                                                10/30/2024
A10.03                               MILLWORK DETAILS                                                10/30/2024
A10.04                               MILLWORK DETAILS                                                10/30/2024
                                     LAB FURNISHINGS
LF1.00                               GENERAL LAB NOTES                                               10/30/2024
LF1.01                               LAB EXHAUST, SINK & EQUIPMENT SCHEDULES                         10/30/2024
LF3.01                               ENLARGED WET LAB                                                10/30/2024
LF3.02                               ENLARGED DRY LAB                                                10/30/2024
LF3.11                               ENLARGED ENGINEERING LAB                                        10/30/2024
LF3.21                               ENLARGED MAKER SPACE                                            10/30/2024
LF3.31                               ENLARGED SCENE SHOP                                             10/30/2024
LF4.01                               LAB DETAILS                                                     10/30/2024
LF4.02                               LAB DETAILS                                                     10/30/2024
                                     FOOD SERVICE
QF0.0                                FOODSERVICE GENERAL NOTES                                       10/30/2024
QF0.1                                FOODSERVICE EQUIPMENT STANDARD DETAILS                          10/30/2024
QF0.2                                FOODSERVICE EQUIPMENT STANDARD DETAILS                          10/30/2024
QF0.3                                FOODSERVICE EQUIPMENT STANDARD DETAILS                          10/30/2024
QF0.4                                FOODSERVICE EQUIPMENT STANDARD DETAILS                          10/30/2024
QF0.5                                FOODSERVICE EQUIPMENT STANDARD DETAILS                          10/30/2024
QF1.0                                FOODSERVICE EQUIPMENT PLAN - OVERALL                            10/30/2024
QF1.1                                FOODSERVICE EQUIPMENT PLAN - OVERALL KITCHEN                    10/30/2024
QF1.2                                FOODSERVICE EQUIPMENT PLAN - KITCHEN NORTH                      10/30/2024
QF1.3                                FOODSERVICE EQUIPMENT PLAN - KITCHEN SOUTH                      10/30/2024
QF1.4                                FOODSERVICE EQUIPMENT SCHEDULE - KN                             10/30/2024
QF1.5                                FOODSERVICE EQUIPMENT SCHEDULE - KS                             10/30/2024
QF1.6                                FOODSERVICE EQUIPMENT SCHEDULE - KS CONT.                       10/30/2024
QF1.7                                FOODSERVICE EQUIPMENT PLAN - CONCESSION STANDS                  10/30/2024
QF1.8                                FOODSERVICE EQUIPMENT PLAN - CULINARY CLASSROOM                 10/30/2024
QF1.9                                FOODSERVICE EQUIPMENT SCHEDULE - CULINARY CLASSROOM             10/30/2024
QF2.1                                FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - KN                    10/30/2024
QF2.2                                FOODSERVICE EQUIPMENT ELEVATIONS - KN                           10/30/2024
QF2.3                                FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - KS                    10/30/2024
QF2.4                                FOODSERVICE EQUIPMENT ELEVATIONS - KS                           10/30/2024
QF2.5                                FOODSERVICE EQUIPMENT ELEVATION KEYPLAN - CL                    10/30/2024
QF2.6                                FOODSERVICE EQUIPMENT ELEVATIONS - CL                           10/30/2024
QF2.7                                FOODSERVICE EQUIPMENT ISOMETRIC VIEWS                           10/30/2024
QF2.8                                FOODSERVICE EQUIPMENT ISOMETRIC VIEWS                           10/30/2024
QF3.1                                FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN KN                   10/30/2024
QF3.2                                FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN KS                   10/30/2024
QF3.3                                FOODSERVICE EQUIPMENT PLUMBING DRAIN KN                         10/30/2024
QF3.4                                FOODSERVICE EQUIPMENT PLUMBING DRAIN KS                         10/30/2024
QF3.5                                FOODSERVICE EQUIPMENT PLUMBING CS                               10/30/2024
QF3.6                                FOODSERVICE EQUIPMENT PLUMBING SUPPLY PLAN CL                   10/30/2024
QF3.7                                FOODSERVICE EQUIPMENT PLUMBING DRAIN PLAN CL                    10/30/2024
QF4.1                                FOODSERVICE EQUIPMENT ELETRICAL PLAN KN                         10/30/2024
QF4.2                                FOODSERVICE EQUIPMENT ELETRICAL PLAN KS                         10/30/2024
QF4.3                                FOODSERVICE EQUIPMENT ELETRICAL SCHEDULE - KS                   10/30/2024
QF4.4                                FOODSERVICE EQUIPMENT ELETRICAL PLAN CS                         10/30/2024
QF4.5                                FOODSERVICE EQUIPMENT ELETRICAL PLAN CL                         10/30/2024
QF5.1                                FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN KN                  10/30/2024
QF5.2                                FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN KS                  10/30/2024
QF5.3                                FOODSERVICE EQUIPMENT SLAB PENETRATION PLAN CL                  10/30/2024
QF6.01                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.02                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.03                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.04                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.05                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.06                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.07                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.08                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024
QF6.09                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                         10/30/2024




                                                                                           6 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                           DESCRIPTION        DATED
QF6.10                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.11                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.12                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.13                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.14                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.15                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.16                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.17                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.18                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.19                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.20                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.21                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.22                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.23                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.24                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.25                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.26                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.27                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.28                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF6.29                               FOODSERVICE EXHAUST HOOD VENDOR DETAILS                           10/30/2024
QF7.1                                FOODSERVICE WALK-IN VENDOR DETAILS                                10/30/2024
QF7.2                                FOODSERVICE REFRIGERATION SYSTEM VENDOR DETAILS                   10/30/2024
QF7.3                                FOODSERVICE REFRIGERATION SYSTEM VENDOR DETAILS                   10/30/2024
QF8.1                                FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN KITCHEN NORTH       10/30/2024
QF8.2                                FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN KITCHEN SOUTH       10/30/2024
QF8.3                                FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN CULINARY KITCHEN    10/30/2024
QF8.4                                FOODSERVICE EQUIPMENT SPECIAL CONDITIONS PLAN CONCESSION STANDS   10/30/2024

                                     GENERAL - VOLUME 2
G0.01                                COVER SHEET                                                       10/30/2024
G0.02                                DRAWING INDEX                                                     10/30/2024
                                     STRUCTURAL
S0.00                                GENERAL NOTES                                                     10/30/2024
S0.01                                GENERAL NOTES                                                     10/30/2024
S0.02                                3D VIEWS                                                          10/30/2024
S0.03                                LOAD MAP                                                          10/30/2024
S0.04                                LOAD MAP                                                          10/30/2024
S1.01                                TYPICAL SECTIONS AND DETAILS                                      10/30/2024
S1.02                                TYPICAL SECTIONS AND DETAILS                                      10/30/2024
S1.03                                TYPICAL CMU WALL DETAILS                                          10/30/2024
S1.04                                TYPICAL CMU WALL DETAILS                                          10/30/2024
S1.05                                TYPICAL CMU WALL DETAILS                                          10/30/2024
S1.06                                TYPICAL COMPOSITE SLAB DETAILS                                    10/30/2024
S1.07                                TYPICAL COMPOSITE SLAB DETAILS                                    10/30/2024
S1.08                                TYPICAL COMPOSITE SLAB DETAILS                                    10/30/2024
S1.09                                TYPICAL STEEL BEAM DETAILS                                        10/30/2024
S1.10                                TYPICAL STEEL JOIST DETAILS                                       10/30/2024
S1.11                                TYPICAL ROOF DETAILS                                              10/30/2024
S2.01                                OVERALL LEVEL 1 FOUNDATION PLAN                                   10/30/2024
S2.02                                OVERALL LEVEL 2 FRAMING PLAN                                      10/30/2024
S2.03                                OVERALL LEVEL 3 FRAMING PLAN                                      10/30/2024
S2.04                                OVERALL ROOF FRAMING PLAN                                         10/30/2024
S2.11A                               LEVEL 1 FOUNDATION PLAN - NEW BUILDING SOUTH                      10/30/2024
S2.11C                               LEVEL 1 FOUNDATION PLAN - NEW BUILDING NORTH                      10/30/2024
S2.11G                               LEVEL 1 FOUNDATION PLAN - NEW BUILDING NORTH AREA G               10/30/2024
S2.11H                               LEVEL 1 & ROOF PLANS - HALLWAY H                                  10/30/2024
S2.11J                               LEVEL 1 FOUNDATION PLAN - AREA J                                  10/30/2024
S2.11K                               LEVEL 1 FOUNDATION PLAN - AREA K                                  10/30/2024
S2.11L                               LEVEL 1 FOUNDATION PLAN - AREA L                                  10/30/2024
S2.11M                               LEVEL 1 FOUNDATION PLAN - MUSIC SUITES                            10/30/2024
S2.11N                               LEVEL 1 FOUNDATION PLAN - AUDITORIUM                              10/30/2024
S2.12A                               LEVEL 2 FRAMING PLAN - NEW BUILDING SOUTH                         10/30/2024
S2.12C                               LEVEL 2 FRAMING PLAN - NEW BUILDING NORTH                         10/30/2024
S2.12G                               LEVEL 2 FRAMING PLAN - NEW BUILDING NORTH AREA G                  10/30/2024
S2.13A                               LEVEL 3 FRAMING PLAN - NEW BUILDING SOUTH                         10/30/2024
S2.13C                               LEVEL 3 FRAMING PLAN - NEW BUILDING NORTH                         10/30/2024
S2.14A                               ROOF FRAMING PLAN - NEW BUILDING SOUTH                            10/30/2024
S2.14C                               ROOF FRAMING PLAN - NEW BUILDING NORTH                            10/30/2024
S2.14K                               ROOF FRAMING PLAN - AREA K                                        10/30/2024
S2.14L                               ROOF FRAMING PLAN - AREA L                                        10/30/2024
S2.14M                               ROOF PLAN - MUSIC SUITES                                          10/30/2024
S2.14N                               ROOF PLAN - AUDITORIUM                                            10/30/2024
S3.01                                FOUNDATION SECTIONS AND DETAILS                                   10/30/2024
S3.02                                FOUNDATION SECTIONS AND DETAILS                                   10/30/2024
S3.03                                FOUNDATION SECTIONS AND DETAILS                                   10/30/2024
S3.04                                FOUNDATION SECTIONS AND DETAILS                                   10/30/2024
S3.10                                FOUNDATION SECTIONS AND DETAILS                                   10/30/2024
S4.01                                NEW NORTH BUILDING STEEL COLUMN SCHEDULE                          10/30/2024
S4.02                                NEW SOUTH BUILDING STEEL COLUMN SCHEDULE                          10/30/2024
S4.03                                NEW SOUTH BUILDING STEEL COLUMN SCHEDULE                          10/30/2024




                                                                                           7 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                          DESCRIPTION     DATED
S4.04                                AUDITORIUM AND MUSIC SUITES STEEL COLUMN SCHEDULE             10/30/2024
S4.05                                AUDITORIUM AND MUSIC SUITES STEEL COLUMN SCHEDULE             10/30/2024
S4.11                                BRACED FRAME TYPICAL DETAILS                                  10/30/2024
S4.12                                BRACED FRAME ELEVATIONS                                       10/30/2024
S5.01                                SECTIONS AND DETAILS                                          10/30/2024
S5.02                                SECTIONS AND DETAILS                                          10/30/2024
S5.03                                SECTIONS AND DETAILS                                          10/30/2024
S5.04                                SECTIONS AND DETAILS                                          10/30/2024
S5.10                                SECTIONS AND DETAILS                                          10/30/2024
S5.11                                SECTIONS AND DETAILS                                          10/30/2024
S5.12                                SECTIONS AND DETAILS                                          10/30/2024
S6.01                                NEW BUILDING CANOPIES                                         10/30/2024
S7.01                                JOIST LOADING DIAGRAMS                                        10/30/2024
S9.00                                FRP SECTIONS & DETAILS                                        10/30/2024
S9.01                                FRP SECTIONS & DETAILS                                        10/30/2024
S10.01                               SITE RETAINING WALLS                                          10/30/2024
S10.02                               BUS LOOP CANOPY FOUNDATION PLAN AND SECTIONS                  10/30/2024
                                     MECHANICAL
M0.01                                HVAC GENERAL NOTES & LEGEND                                   10/30/2024
M1.01                                HVAC DEMO WORK - LEVEL 1 - AREA A                             10/30/2024
M1.02                                HVAC DEMO WORK - LEVEL 1 - AREA B                             10/30/2024
M1.03                                HVAC DEMO WORK - LEVEL 1 - AREA C                             10/30/2024
M1.04                                HVAC DEMO WORK - LEVEL 1 - AREA D                             10/30/2024
M1.05                                HVAC DEMO WORK - LEVEL 1 - AREA E                             10/30/2024
M1.06                                HVAC DEMO WORK - LEVEL 1 - AREA F                             10/30/2024
M1.07                                HVAC DEMO WORK - LEVEL 1 - AREA G                             10/30/2024
M1.08                                HVAC DEMO WORK - LEVEL 1 - AREA H                             10/30/2024
M1.09                                HVAC DEMO WORK - LEVEL 1 - AREA J                             10/30/2024
M1.10                                HVAC DEMO WORK - MEZZANINE - AREA J                           10/30/2024
M1.11                                HVAC DEMO WORK - LEVEL 1 - AREA K                             10/30/2024
M1.12                                HVAC DEMO WORK - LEVEL 1 - AREA L                             10/30/2024
M1.13                                HVAC DEMO WORK - LEVEL 1 - AREA M                             10/30/2024
M1.14                                HVAC DEMO WORK - LOW ROOF - AREA A, B, & C                    10/30/2024
M1.15                                HVAC DEMO WORK - LOW ROOF - AREA D & E                        10/30/2024
M1.16                                HVAC DEMO WORK - LOW ROOF - AREA F, G, H                      10/30/2024
M1.17                                HVAC DEMO WORK - MID ROOF - AREA J, K, & L                    10/30/2024
M1.18                                PIPING DEMO WORK - LEVEL 1 - AREA A                           10/30/2024
M1.19                                PIPING DEMO WORK - LEVEL 1 - AREA B                           10/30/2024
M1.20                                PIPING DEMO WORK - LEVEL 1 - AREA C                           10/30/2024
M1.21                                PIPING DEMO WORK - LEVEL 1 - AREA D                           10/30/2024
M1.22                                PIPING DEMO WORK - LEVEL 1 - AREA E                           10/30/2024
M1.23                                PIPING DEMO WORK - LEVEL 1 - AREA F                           10/30/2024
M1.24                                PIPING DEMO WORK - LEVEL 1 - AREA G                           10/30/2024
M1.25                                PIPING DEMO WORK - LEVEL 1 - AREA H                           10/30/2024
M2.01                                HVAC NEW WORK - LEVEL 1 - AREA A                              10/30/2024
M2.02                                HVAC NEW WORK - LEVEL 1 - AREA B                              10/30/2024
M2.03                                HVAC NEW WORK - LEVEL 1 - AREA C                              10/30/2024
M2.04                                HVAC NEW WORK - LEVEL 1 - AREA D                              10/30/2024
M2.05                                HVAC NEW WORK - LEVEL 1 - AREA E                              10/30/2024
M2.06                                HVAC NEW WORK - LEVEL 1 - AREA F                              10/30/2024
M2.07                                HVAC NEW WORK - LEVEL 1 - AREA G                              10/30/2024
M2.08                                HVAC NEW WORK - LEVEL 1 - AREA H                              10/30/2024
M2.09                                HVAC NEW WORK - LEVEL 1 - AREA J                              10/30/2024
M2.10                                HVAC NEW WORK - MEZZANINE - AREA J                            10/30/2024
M2.11                                HVAC NEW WORK - LEVEL 1 - AREA K                              10/30/2024
M2.12                                HVAC NEW WORK - LEVEL 1 - AREA L                              10/30/2024
M2.13                                HVAC NEW WORK - LEVEL 1 - AREA M                              10/30/2024
M2.14                                HVAC NEW WORK - LEVEL 1 - AREA N                              10/30/2024
M2.15                                HVAC NEW WORK - LEVEL 2 - AREA A                              10/30/2024
M2.16                                HVAC NEW WORK - LEVEL 2 - AREA B                              10/30/2024
M2.17                                HVAC NEW WORK - LEVEL 2 - AREA C                              10/30/2024
M2.18                                HVAC NEW WORK - LEVEL 3 - AREA A                              10/30/2024
M2.19                                HVAC NEW WORK - LEVEL 3 - AREA B                              10/30/2024
M2.20                                HVAC NEW WORK - LEVEL 3 - AREA C                              10/30/2024
M2.21                                HVAC NEW WORK - HIGH ROOF - AREA A, B, & C                    10/30/2024
M2.22                                HVAC NEW WORK - LOW ROOF - AREA D & E                         10/30/2024
M2.23                                HVAC NEW WORK - LOW ROOF - AREA F, G, & H                     10/30/2024
M2.24                                HVAC NEW WORK - MID ROOF - AREA J, K, & L                     10/30/2024
M2.25                                HVAC NEW WORK - MID ROOF - AREA M & N                         10/30/2024
M3.01                                PIPING NEW WORK - LEVEL 1 - AREA A                            10/30/2024
M3.02                                PIPING NEW WORK - LEVEL 1 - AREA B                            10/30/2024
M3.03                                PIPING NEW WORK - LEVEL 1 - AREA C                            10/30/2024
M3.04                                PIPING NEW WORK - LEVEL 1 - AREA D                            10/30/2024
M3.05                                PIPING NEW WORK - LEVEL 1 - AREA E                            10/30/2024
M3.06                                PIPING NEW WORK - LEVEL 1 - AREA F                            10/30/2024
M3.07                                PIPING NEW WORK - LEVEL 1 - AREA G                            10/30/2024
M3.08                                PIPING NEW WORK - LEVEL 1 - AREA H                            10/30/2024
M3.09                                PIPING NEW WORK - LEVEL 1 - AREA J                            10/30/2024
M3.10                                PIPING NEW WORK - LEVEL 1 - AREA K                            10/30/2024
M3.11                                PIPING NEW WORK - LEVEL 1 - AREA L                            10/30/2024




                                                                                         8 of 11
List of Drawings, Specifications and Addendums


        INDEX OF DRAWINGS                                                                DESCRIPTION    DATED
M3.12                                PIPING NEW WORK - LEVEL 1 - AREA M                                10/30/2024
M3.13                                PIPING NEW WORK - LEVEL 1 - AREA N                                10/30/2024
M3.14                                PIPING NEW WORK - LEVEL 2 - AREA A                                10/30/2024
M3.15                                PIPING NEW WORK - LEVEL 2 - AREA B                                10/30/2024
M3.16                                PIPING NEW WORK - LEVEL 2 - AREA C                                10/30/2024
M3.17                                PIPING NEW WORK - LEVEL 3 - AREA A                                10/30/2024
M3.18                                PIPING NEW WORK - LEVEL 3 - AREA B                                10/30/2024
M3.19                                PIPING NEW WORK - LEVEL 3 - AREA C                                10/30/2024
M4.01                                HVAC SECTIONS                                                     10/30/2024
M4.02                                HVAC SECTIONS                                                     10/30/2024
M4.03                                HVAC SECTIONS                                                     10/30/2024
M4.04                                HVAC SECTIONS                                                     10/30/2024
M4.05                                HVAC LARGE SCALE PLANS                                            10/30/2024
M4.06                                HVAC ADDITIONAL VIEWS                                             10/30/2024
M5.01                                HVAC DETAILS                                                      10/30/2024
M5.02                                HVAC DETAILS                                                      10/30/2024
M5.03                                HVAC DETAILS                                                      10/30/2024
M5.04                                HVAC DETAILS                                                      10/30/2024
M6.01                                HVAC SCHEDULES                                                    10/30/2024
M6.02                                HVAC SCHEDULES                                                    10/30/2024
M6.03                                HVAC SCHEDULES                                                    10/30/2024
M7.01                                HVAC CONTROLS                                                     10/30/2024
M7.02                                HVAC CONTROLS                                                     10/30/2024
M7.03                                HVAC CONTROLS                                                     10/30/2024
M7.04                                HVAC CONTROLS                                                     10/30/2024
M7.05                                HVAC CONTROLS                                                     10/30/2024
M7.06                                HVAC CONTROLS                                                     10/30/2024
                                     PLUMBING
P0.01                                PLUMBING NOTES & SCHEDULES                                        10/30/2024
P0.02                                PLUMBING DETAILS                                                  10/30/2024
P0.03                                PLUMBING DETAILS                                                  10/30/2024
P0.04                                NATURAL GAS RISER - EXISTING/TEMPORARY                            10/30/2024
P0.05                                NATURAL GAS RISER - DEMOLITION                                    10/30/2024
P0.06                                NATURAL GAS RISER - NEW WORK                                      10/30/2024
P1.00                                PLUMBING OVERALL DEMOLITION PLAN - LEVEL 1                        10/30/2024
P1.01                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA A                       10/30/2024
P1.02                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA B                       10/30/2024
P1.03                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA C                       10/30/2024
P1.04                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA D                       10/30/2024
P1.05                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA E                       10/30/2024
P1.06                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA F & G                   10/30/2024
P1.07                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA H                       10/30/2024
P1.08                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA J                       10/30/2024
P1.09                                PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA K & L                   10/30/2024
P1.10                                PLUMBING DEMOLITION PLAN - ROOF - AREA A, B & C                   10/30/2024
P1.11                                PLUMBING DEMOLITION PLAN - ROOF - AREA D & E                      10/30/2024
P1.12                                PLUMBING DEMOLITION PLAN - ROOF - AREA F, G & H                   10/30/2024
P1.13                                PLUMBING DEMOLITION PLAN - ROOF - AREA J, K & L                   10/30/2024
P2.00                                PLUMIBNG OVERALL NEW WORK PLAN - LEVEL 1                          10/30/2024
P2.01                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA A                         10/30/2024
P2.02                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA B                         10/30/2024
P2.03                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA C                         10/30/2024
P2.04                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA D                         10/30/2024
P2.05                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA E                         10/30/2024
P2.06                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA F & G                     10/30/2024
P2.07                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA H                         10/30/2024
P2.08                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA J                         10/30/2024
P2.09                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA K & L                     10/30/2024
P2.10                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA M                         10/30/2024
P2.11                                PLUMBING NEW WORK PLAN - LEVEL 1 - AREA N                         10/30/2024
P2.12                                PLUMBING NEW WORK PLAN - LEVEL 2 - AREA A                         10/30/2024
P2.13                                PLUMBING NEW WORK PLAN - LEVEL 2 - AREA B                         10/30/2024
P2.14                                PLUMBING NEW WORK PLAN - LEVEL 2 - AREA C                         10/30/2024
P2.15                                PLUMBING NEW WORK PLAN - LEVEL 3 - AREA A                         10/30/2024
P2.16                                PLUMBING NEW WORK PLAN - LEVEL 3 - AREA B                         10/30/2024
P2.17                                PLUMBING NEW WORK PLAN - LEVEL 3 - AREA C                         10/30/2024
P2.18                                PLUMBING NEW WORK PLAN - ROOF - AREA A, B & C                     10/30/2024
P2.19                                PLUMBING NEW WORK PLAN - ROOF - AREA D & E                        10/30/2024
P2.20                                PLUMBING NEW WORK PLAN - ROOF - AREA F, G & H                     10/30/2024
P2.21                                PLUMBING NEW WORK PLAN - ROOF - AREA J, K & L                     10/30/2024
P2.22                                PLUMBING NEW WORK PLAN - ROOF - AREA M & N                        10/30/2024
P3.01                                PLUMBING PART PLANS - KITCHEN DRAINAGE                            10/30/2024
P3.02                                PLUMBING PART PLANS - KITCHEN SUPPLY                              10/30/2024
P3.03                                PLUMBING PART PLANS - AREA A RESTROOMS                            10/30/2024
P3.04                                PLUMBING PART PLANS - AREA B RESTROOMS                            10/30/2024
P3.05                                PLUMBING PART PLANS - LEVEL 2 & 3 - AREA A                        10/30/2024
P3.06                                PLUMBING PART PLANS - LEVEL 2 - AREA B                            10/30/2024
P3.07                                PLUMBING PART PLANS - LEVEL 3 - AREA B                            10/30/2024
P3.08                                PLUMBING PART PLANS - LEVEL 2 - AREA C - DRAINAGE                 10/30/2024
P3.09                                PLUMBING PART PLANS - LEVEL 3 - AREA C - DRAINAGE                 10/30/2024




                                                                                             9 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                               DESCRIPTION      DATED
P3.10                                PLUMBING PART PLANS - LEVEL 2 - AREA C - SUPPLY                     10/30/2024
P3.11                                PLUMBING PART PLANS - LEVEL 3 - AREA C - SUPPLY                     10/30/2024
P3.12                                PLUMBING PART PLANS                                                 10/30/2024
P3.13                                PLUMBING PART PLANS                                                 10/30/2024
P4.01                                PLUMBING RISERS - GREASE WASTE & VENT                               10/30/2024
P4.02                                PLUMBING RISERS - LAB WASTE & VENT                                  10/30/2024
P4.03                                PLUMBING RISERS - DRAINAGE                                          10/30/2024
P4.04                                PLUMBING RISERS - DRAINAGE                                          10/30/2024
                                     FIRE PROTECTION
FP0.01                               FIRE PROTECTION NOTES & DETAILS                                     10/30/2024
FP1.00                               FIRE PROTECTION OVERALL PLAN - LEVEL 1                              10/30/2024
FP1.01                               FIRE PROTECTION OVERALL PLAN - LEVEL 2 & 3                          10/30/2024
FP2.01                               FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA A, B, D & E          10/30/2024
FP2.02                               FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA J, K & L             10/30/2024
FP2.03                               FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA C, F, G & H          10/30/2024
FP2.04                               FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA M & N                10/30/2024
FP2.11                               FIRE PROTECTION NEW WORK PLAN - LEVEL 2 - AREA A, B & C             10/30/2024
FP2.12                               FIRE PROTECTION NEW WORK PLAN - LEVEL 3 - AREA A, B & C             10/30/2024
FP3.00                               FIRE PROTECTION STANDPIPE SECTIONS                                  10/30/2024
                                     ELECTRICAL
E1.00                                ELECTRICAL LEGEND, NOTES, SCHEDULES AND DETAILS                     10/30/2024
E2.01                                ELECTRICAL OVERALL SITE PLAN                                        10/30/2024
E2.02                                ELECTRICAL BUS CANOPY PLAN                                          10/30/2024
E3.11A                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA A                           10/30/2024
E3.11B                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA B                           10/30/2024
E3.11C                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA C                           10/30/2024
E3.11D                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA D                           10/30/2024
E3.11E                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA E                           10/30/2024
E3.11F                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA F & G                       10/30/2024
E3.11H                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA H                           10/30/2024
E3.11J                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA J                           10/30/2024
E3.11K                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA K & L                       10/30/2024
E3.11M                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA M                           10/30/2024
E3.11N                               ELECTRICAL LIGHTING PLAN LEVEL 1 – AREA N                           10/30/2024
E3.12A                               ELECTRICAL LIGHTING PLAN LEVEL 2 – AREA A                           10/30/2024
E3.12B                               ELECTRICAL LIGHTING PLAN LEVEL 2 – AREA B & C                       10/30/2024
E3.13A                               ELECTRICAL LIGHTING PLAN LEVEL 3 – AREA A                           10/30/2024
E3.13B                               ELECTRICAL LIGHTING PLAN LEVEL 3 – AREA B & C                       10/30/2024
E3.21                                ELECTRICAL ENLARGED LIGHTING PLANS                                  10/30/2024
E4.11A                               ELECTRICAL POWER PLAN LEVEL 1 – AREA A                              10/30/2024
E4.11B                               ELECTRICAL POWER PLAN LEVEL 1 – AREA B                              10/30/2024
E4.11C                               ELECTRICAL POWER PLAN LEVEL 1 – AREA C                              10/30/2024
E4.11D                               ELECTRICAL POWER PLAN LEVEL 1 – AREA D                              10/30/2024
E4.11E                               ELECTRICAL POWER PLAN LEVEL 1 – AREA E                              10/30/2024
E4.11F                               ELECTRICAL POWER PLAN LEVEL 1 – AREA F & G                          10/30/2024
E4.11H                               ELECTRICAL POWER PLAN LEVEL 1 – AREA H                              10/30/2024
E4.11J                               ELECTRICAL POWER PLAN LEVEL 1 – AREA J                              10/30/2024
E4.11K                               ELECTRICAL POWER PLAN LEVEL 1 – AREA K & L                          10/30/2024
E4.11M                               ELECTRICAL POWER PLAN LEVEL 1 – AREA M                              10/30/2024
E4.11N                               ELECTRICAL POWER PLAN LEVEL 1 – AREA N                              10/30/2024
E4.12A                               ELECTRICAL POWER PLAN LEVEL 2 – AREA A                              10/30/2024
E4.12B                               ELECTRICAL POWER PLAN LEVEL 2 – AREA B & C                          10/30/2024
E4.13A                               ELECTRICAL POWER PLAN LEVEL 3 – AREA A                              10/30/2024
E4.13B                               ELECTRICAL POWER PLAN LEVEL 3 – AREA B & C                          10/30/2024
E4.21                                ELECTRICAL ENLARGED POWER PLAN - KITCHEN (NORTH)                    10/30/2024
E4.22                                ELECTRICAL ENLARGED POWER PLAN - KITCHEN (SOUTH)                    10/30/2024
E4.23                                ELECTRICAL ENLARGED POWER PLAN - ROBOTICS                           10/30/2024
E4.24                                ELECTRICAL ENLARGED POWER PLAN - SCIENCE LABS                       10/30/2024
E4.25                                ELECTRICAL ENLARGED POWER PLAN - SCIENCE LABS                       10/30/2024
E4.26                                ELECTRICAL ENLARGED POWER PLAN - CULINARY ARTS                      10/30/2024
E4.31A                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA A                    10/30/2024
E4.31B                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA B                    10/30/2024
E4.31C                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA C                    10/30/2024
E4.31D                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA D                    10/30/2024
E4.31E                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA E                    10/30/2024
E4.31F                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA F & G                10/30/2024
E4.31H                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA H                    10/30/2024
E4.31J                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA J                    10/30/2024
E4.31K                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA K & L                10/30/2024
E4.31M                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA M                    10/30/2024
E4.31N                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 1 - AREA N                    10/30/2024
E4.32A                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 2 - AREA A                    10/30/2024
E4.32B                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 2 - AREA B & C                10/30/2024
E4.33A                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 3 - AREA A                    10/30/2024
E4.33B                               ELECTRICAL HVAC & PLUMBING PLAN LEVEL 3 - AREA B & C                10/30/2024
E4.34A                               ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA A                       10/30/2024
E4.34B                               ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA C                       10/30/2024
E4.34C                               ELECTRICAL HVAC & PLUMBING PLAN ROOF - AREA B                       10/30/2024
E4.35                                ELECTRICAL HVAC AND PLUMBING SCHEDULES                              10/30/2024
E5.11A                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA A                        10/30/2024




                                                                                              10 of 11
List of Drawings, Specifications and Addendums


         INDEX OF DRAWINGS                                                                 DESCRIPTION     DATED
E5.11B                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA B                         10/30/2024
E5.11C                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 – AREA C                         10/30/2024
E5.11D                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA D                         10/30/2024
E5.11E                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA E                         10/30/2024
E5.11F                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA F & G                     10/30/2024
E5.11H                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA H                         10/30/2024
E5.11J                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA J                         10/30/2024
E5.11K                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA K & L                     10/30/2024
E5.11M                               ELECTRCIAL LOW VOLTAGE PLAN LEVEL 1 - AREA M                         10/30/2024
E5.11N                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 1 - AREA N                         10/30/2024
E5.12A                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 2 - AREA A                         10/30/2024
E5.12B                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 2 - AREA B & C                     10/30/2024
E5.13A                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 3 - AREA A                         10/30/2024
E5.13B                               ELECTRICAL LOW VOLTAGE PLAN LEVEL 3 - AREA B & C                     10/30/2024
E6.01                                ELECTRICAL RISER DIAGRAM, NOTES, AND SCHEDULE                        10/30/2024
E6.02                                ELECTRICAL RISER DIAGRAM, NOTES, AND SCHEDULE                        10/30/2024
E6.11                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.12                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.13                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.14                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.15                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.16                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.17                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
E6.18                                ELECTRICAL PANEL SCHEDULES                                           10/30/2024
                                     AUDIOVISUAL
AV0.01                               AUDIOVISUAL LEGENDS                                                  10/30/2024
AV0.02                               AUDIOVISUAL GENERAL INFORMATION                                      10/30/2024
AV0.03                               AUDIOVISUAL DISPLAY SCHEDULES                                        10/30/2024
AV2.01                               AUDIOVISUAL OVERALL LEVEL 1 FLOOR PLAN                               10/30/2024
AV2.11A                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA A                              10/30/2024
AV2.11B                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA B                              10/30/2024
AV2.11C                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA C                              10/30/2024
AV2.11J                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA J                              10/30/2024
AV2.11M                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA M                              10/30/2024
AV2.11N                              AUDIOVISUAL LEVEL 1 FLOOR PLAN - AREA N                              10/30/2024
AV2.40A                              AUDIOVISUAL OVERALL LEVEL 1 REFLECTED CEILING PLAN                   10/30/2024
AV2.41A                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA A                  10/30/2024
AV2.41B                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA B                  10/30/2024
AV2.41C                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA C                  10/30/2024
AV2.41J                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA J                  10/30/2024
AV2.41M                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA M                  10/30/2024
AV2.41N                              AUDIOVISUAL LEVEL 1 REFLECTED CEILING PLAN - AREA N                  10/30/2024
AV4.01                               AUDIOVISUAL ELEVATIONS                                               10/30/2024
AV4.02                               AUDIOVISUAL ELEVATIONS                                               10/30/2024
AV4.03                               AUDIOVISUAL ELEVATIONS                                               10/30/2024
AV5.10                               AUDIOVISUAL WIRING DIAGRAMS - AUDITORIUM                             10/30/2024
AV5.11                               AUDIOVISUAL WIRING DIAGRAMS - AUDITORIUM                             10/30/2024
AV5.20                               AUDIOVISUAL WIRING DIAGRAMS - DINING                                 10/30/2024
AV5.30                               AUDIOVISUAL WIRING DIAGRAMS - MEDIA CENTER                           10/30/2024
AV5.40                               AUDIOVISUAL WIRING DIAGRAMS - GYM                                    10/30/2024
AV5.50                               AUDIOVISUAL WIRING DIAGRAMS - BLACK BOX                              10/30/2024
AV6.01                               AUDIOVISUAL DETAILS                                                  10/30/2024
AV6.02                               AUDIOVISUAL DETAILS                                                  10/30/2024
AV6.10                               AUDIOVISUAL PLATE DETAILS                                            10/30/2024
AV6.11                               AUDIOVISUAL PLATE DETAILS                                            10/30/2024
AV6.12                               AUDIOVISUAL PLATE DETAILS                                            10/30/2024
AV6.20                               AUDIOVISUAL RACK ELEVATIONS                                          10/30/2024
AV6.21                               AUDIOVISUAL RACK ELEVATIONS                                          10/30/2024
                                     THEATER
TLA-01                               LEVEL 1 PLAN - AREA N - AUDITORIUM                                   10/30/2024
TLA-02                               LEVEL 1 RCP - AREA N - AUDITORIUM                                    10/30/2024
TLA-03                               STAGE LIGHTING PLOT - AUDITORIUM                                     10/30/2024
TLA-04                               LEVEL 1 SECTION - AREA N - AUDITORIUM                                10/30/2024
TLA-05                               LEVEL 1 RISER - AREA N - AUDITORIUM                                  10/30/2024
TLA-06                               THEATRICAL SCHEDULES - AUDITORIUM                                    10/30/2024
TLA-07                               SCOPE MATRIX AUDITORIUM                                              10/30/2024
TLBB-01                              LEVEL 1 PLAN - AREA M - BLACK BOX                                    10/30/2024
TLBB-02                              SECTIONS - AREA M - BLACK BOX                                        10/30/2024
TLBB-03                              RISER - AREA M - BLACK BOX                                           10/30/2024
TLBB-04                              SCOPE MATRIX - BLACK BOX                                             10/30/2024
TLBB-05                              EQUIPMENT SCHEDULE - BLACK BOX                                       10/30/2024
TLBB-06                              LEVEL 1 PLAN - AREA M - BLACK BOX PLOT                               10/30/2024
TLBB-07                              FIXTURE SCHEDULE - BLACK BOX                                         10/30/2024

SPECIFICATIONS
Project Manual prepared by Cooper Carry dated October 30, 2024




                                                                                               11 of 11
Cross Keys High School                                    1/23/2025
Attachment 1 - Allowances Log

                                                           Value
 1 Phase 1 Fire Marshal Egress Requirements           $    50,000.00
 2 Rock and Unsuitable Soils                          $ 1,000,000.00
 3 Temporary Utilities/Re-Routing                     $ 250,000.00
 5 Modular Access                                     $    50,000.00
 6 Courtyard Canopies                                 $ 175,000.00
 7 Roof Leaders                                       $    50,000.00
 8 Repair Existing Asphalt                            $ 100,000.00
 9 Monumental Sign                                    $    50,000.00
10 Caulking of Existing School                        $    25,000.00
11 Educational Casework, Millwork, and Running Trim   $ 1,750,000.00
12 Wood Paneling                                      $ 100,000.00
13 Wood Ceiling                                       $ 100,000.00
14 Wall Graphics                                      $ 100,000.00
15 Special Coatings                                   $    50,000.00
16 Exterior Mural                                     $    60,000.00
17 Corner Guards                                      $    15,000.00
18 Storage Shelving                                   $ 80,000.00
19 Wayfinding                                         $ 50,000.00
20 Exterior Signage                                   $ 50,000.00
21 Louvered Canopies                                  $ 547,200.00
22 Kiln                                               $ 15,000.00
23 Commercial Laundry Equipment (Gym)                 $ 30,000.00
24 Loading Dock Equipment                             $   1,000.00
25 Landscape Lighting                                 $ 100,000.00
26 Remove/Abandon Existing Utilities                  $ 50,000.00
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025

1.     GENERAL
       1.1   We have not included any costs for building permit fees, water meter and tap fees,
             impact fees, or road closure permits.
       1.2   We have not included any costs for materials testing, NPDES monitoring,
             commissioning, building envelope testing or commissioning, or special inspections.
       1.3   We have not included any in-ground dewatering. We have included rainwater control.
       1.4   A construction contingency of 5% is included.
       1.5   A design contingency of 4% is included.
       1.6   The following allowances are included in the base contract value:
             a)      Phase 1 Fire Marshal Egress Requirements - $50,000
             b)      Rock and Unsuitable Soils - $1,000,000
             c)      Temporary Utilities/Re-Routing - $250,000
             d)      Modular Access - $50,000
             e)      Courtyard Canopies - $175,000
             f)      Roof Leaders - $50,000
             g)      Repair Existing Asphalt - $100,000
             h)      Monumental Sign - $50,000
             i)      Caulking of Existing School - $25,000
             j)      Educational Casework, Millwork, and Running Trim - $1,750,000
             k)      Wood Paneling – $100,000
             l)      Wood Ceiling - $100,000
             m)      Wall Graphics - $100,000
             n)      Special Coatings - $50,000
             o)      Exterior Mural - $60,000
             p)      Corner Guards - $15,000
             q)      Storage Shelving - $80,000
             r)      Wayfinding - $50,000
             s)      Exterior Signage - $50,000
             t)      Louvered Canopies - $150/SF
             u)      Kiln - $15,000
             v)      Commercial Laundry Equipment (Gym) - $30,000
             w)      Loading Dock Equipment - $1,000
             x)      Landscape Lighting - $100,000
             y)      Remove/Abandon Existing Utilities - $50,000
       1.7   The 80% GMP Proposal is based on a combination of the following documents:
             a)      Cross Keys High School Renovation, Project Manual, Issued for Permit/GMP,
                     dated 10/30/2024
             b)      Cross Keys High School Drawings Vol. 1, Issued for Permit/GMP, Dated
                     10/30/2024
             c)      Cross Keys High School Drawings Vol. 2, Issued for Permit/GMP, Dated
                     10/30/2024
             d)      Cross Keys High School Phase 1 GMP Addendum 1, Dated 08/07/2024
             e)      Cross Keys High School Phase 1 LDP 2nd Re-submittal, Dated 08/07/2024
             f)      Cross Keys High School Temporary Classrooms Portables dated 10/28/2024
                                            Page 1 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025

               g)      Precon RFI Log (file 1.04 RFI Log)
       1.8     We have not included any hazardous materials abatement.
       1.9     We have included relocation of furniture within the existing school to be renovated.
       1.10    We have included removal, storage and re-installation of any computers, smartboards,
               projectors, etc. during Summer renovations.
       1.11    We have not included any monies for installation of Owner furnished items (furniture,
               TVs, Smart Boards, etc.).
       1.12    We have only included temporary power for the construction offices. We assume all
               power running through the existing transformer or new transformer will remain in
               Dekalb County School’s name.
       1.13    We have included Builder’s Risk for the value of the new work. We have not insured the
               value of the existing building for Builder’s Risk Insurance.
       1.14    We have included cleaning of the school and modular classrooms during the summer of
               2025, 2026, and 2027
       1.15    We have included dismantling, relocating, and re-installing the existing 5-wide modular
               classroom located on the North side of the site adjacent to North Cliff Valley Way.
       1.16    We have included rental of three each 10 classroom modular classrooms as indicated in
               the Cross Keys High School Temporary Classrooms Portables dated 10/28/2024.
       1.17    We have included 32 months of parking at Congregation Or VeShalom at a monthly
               rate of $7,000.

2.     SITE CONSTRUCTION
       2.1    We have included temporary irrigation for the new plantings
       2.2    We have included Subsoil Termite Treatment with a five year warranty only beneath the
              new slab on grades
       2.3    We have included ROTC 3-person pull up station, push up bar, and high dip bar
              attachment by Kompan Playground
       2.4    We have not included prime coat for the asphalt paving.
       2.5    We have included heavy duty asphalt paving for the parent drop-off as called out but
              not shown.
       2.6    We have included asphalt reclamation or complete removal and replacement of existing
              GAB, Asphalt, and Track and replace with all new paving and track surfacing.
       2.7    We have not included any parking lot lighting.
       2.8    We have included one manual double swing gate for the back drive into the track.
       2.9    We have included a fire line and new fire hydrant to the football field as required by the
              Fire Marshal.
       2.10 We have included demolition and discarding of all of the existing modular classrooms
              (except for the five wide classroom to be relocated to the football field).
       2.11 We have included grey modular block retaining walls.
       2.12 We have included the retaining wall to the east of the football field as modular block in
              lieu of cast-in-place concrete indicated.
       2.13 We have not included 12-months of landscape maintenance as specified.
       2.14 We have included sealcoating and re-striping of the parking spaces along Curtis Drive.

                                              Page 2 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025

       2.15    We have included sealcoating and re-striping of the existing parking lot to remain.
       2.16    We have included a John Deere gator, lacrosse goals, four each cross mats and a discuss
               net at the synthetic turf field.

3.     CONCRETE

4.     MASONRY
       4.1  We have included Brick #1 as Watsontown Flashed Red Wirecut
       4.2  We have included Brick #2 as Watsontown Light Grey Wirecut
       4.3  We have included Elberton Granite Split Face for the granite veneer on retaining walls
       4.4  We have not included patching any of the existing brick veneer
       4.5  We have not included repointing of the existing brick veneer

5.     METALS

6.     WOODS & PLASTICS

7.     THERMAL & MOISTURE PROTECTION
       7.1  We have included re-roofing of the existing school with a 60 mil PVC KEE System for the
            re-roofing.
       7.2  We have included aluminum soffits as 10mm Trespa Meteon in a Wood Decors color
            with a Satin Finish
       7.3  We have included 4mm metal wall panels in lieu of the 6mm specified as replacement
            panels for 6mm will not be available in the future as thickness is phased out by
            manufacturers
       7.4  Dampproofing is included as Sealmastic Type II, or equal bituminous dampproofing with
            associated drainage mat, which serves as drainage and protection
       7.5  We have included dampproofing at the exterior landscape CMU retaining walls. We
            have not included HRS at these locations

8.     DOORS AND WINDOWS
       8.1    We have included an approved wood door manufacturer that no longer participates in
              the AWI/QCP program. Wood Doors will be manufactured to the AWI standard but will
              not have QCP labels
       8.2    Double acting traffic doors are included as follows:
           a) Hollow Metal Frames – knockdown construction, pre-machined, standard factory
              primed
           b) Double Acting Doors – Eliason SCP8, solid core HPL, manufacturer’s standard colors, pre-
              fit, pre machined
       8.3    Specification section 08 1416 did not clarify what edge to use on the wood doors. We
              have included a Type A edge
       8.4    We have included door types “QQQ” and “RRR” as flush doors



                                             Page 3 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025

       8.5    We have included acoustical seals, door bottom, and thresholds at openings 910.6,
              910.7, and 920.2 per the door schedule comments. We have not included sound control
              / STC doors at these openings.
       8.6    Standard storefront and curtainwall framing is included at storefront and curtainwall.
              We have not included ballistic level aluminum framing.
       8.7    All exterior glazing is included with 3M Ultra 800 blast resistant film.
       8.8    G1 glass is included as Solarban 70.
       8.9    We have included standard storefront and non-rated glass at smoke rated interior
              frames. To accommodate the smoke ratings we have done the following:
           a) Smoke seals at the doors
           b) Caulking the perimeter of all smoke rated glazing on smoke rated side of the framing.
              We have not included caulking of both sides (interior and exterior).
           c) We have included sanding and refinishing of the existing wood doors to remain.

9.     FINISHES
       9.1    We have included an eleven-foot two color logo for the main gym
       9.2    We have included Robbins Bio Cushion Classic Sprung Floor System for both the Stage
              and Black Box
       9.3    We have included a sprung floor for both the Black Box and Stage
       9.4    We have included Robbins Bio Cushion Classic Floor System for the Mezzanine finish
       9.5    We have included Ecor Beast Rolls for Resilient Athletic Flooring RRF-01
       9.6    We have not included any polished concrete as this finish has been taken out of the
              project
       9.7    We have included Rulon Aluratone 760 wood panels in the Performing Arts Center in
              lieu of the 700 series panels indicated.
       9.8    We have included painting of the exterior of existing lockers. We have not included
              painting of the interior of lockers.

10.    SPECIALTIES
       10.1 We have included Platinum Visual Solutions in lieu of Everwhite as Everwhite does not
              produce glass markerboards
       10.2 We have not included any horizontal sliding whiteboards
       10.3 We have included the following toilet accessories not called out but shown on the
              drawings:
           a) We have included two 72”x36” Mirrors
           b) We have included three 18” ADA Grab Bars
           c) We have included ten Mop/Broom Holders with shelf
           d) We have included two towel bars
       10.4 We have included 4 knox boxes
       10.5 We have not included any fire hose valve cabinets as there were no locations shown
       10.6 We have included two fire blanket cabinets with fire blankets inside for the robotics lab
       10.7 We have included all fire extinguisher and fire blanket cabinets as fully recessed per
              notes on A2.11A-A2.13C
       10.8 We have only used sign type F for office spaces
                                             Page 4 of 5
Cross Keys High School Addition & Modernization
80% GMP
Attachment 2 – Assumptions and Clarifications
January 23, 2025


11.    EQUIPMENT

       11.1    We have included three KN-107 Dunnage Racks
       11.2    We have included one KN-112 Floor Trough
       11.3    We have included one KN-309 Floor Trough
       11.4    We have included pricing for the culinary lab based on the equipment schedule and
               drawings as there are no specifications for this area
       11.5    Per drawing L1.05 we have not included tennis court bleachers in our scope
       11.6    We have included Whirlpool equipment for the washer/dryers

12.    FURNISHINGS
       12.1 We have included Wenger AcoustiCabinets in Band and Orchestra rooms with wave grill
             doors and Wenger UltraStor Cabinets in storage areas with standard grill doors.
       12.2 Musical Instrument Casework is included with standard particleboard PLAM core. Fire-
             rated cores are not included
       12.3 We have included Science Casework as manufactured by ICI with a 3 year warranty
       12.4 We have not included loading dock equipment
       12.5 We have included operable window shades at the Media Center Clerestory and manual
             shades at all classroom and exterior windows.
       12.6 We have not included window shades at the Lobby Curtainwall or the Dining
             Curtainwall.

13.    SPECIAL CONSTRUCTION

14.    CONVEYING SYSTEMS

15.    MECHANICAL
       15.1 We have not included roof top equipment cages.
       15.2 We have not included cleaning of the existing ductwork.

16.    ELECTRICAL
       16.1 We have not included certifications of the sound system installer.
       16.2 We have included a Firelite Fire Alarm system for the new fire alarm system.
       16.3 We have included junction boxes and raceways only for Voice, Data, & Security Systems.
       16.4 We have included testing, design and installation of a new ERRCS system for the entire
              school.




                                             Page 5 of 5
       Attachment 3 - Cross Keys High School Addition and Modernization Schedule



           Dec 9                       Jun 1
                   Phase 1 Sitework (UG Detention, North Parking, New Bus Loop)
                        Apr 1         Jun 1
                                New Modular Classrooms
                                Jun 1      Jul 1
                                        Remove Existing Modulars
                                           Jun 1
                                        Move-Out (Existing Modulars)
                                Jun 1              Aug 29
                                        Phase 2 Sitework (Preparation for 3-Story)
                                Jun 1          Jul 31
                                        Phase 2 Sitework (Preparation for PAC)
                                            Sep 1                                                        Nov 30
                                                    Phase 2 - 3-Story Classroom Building
                                                                                                Dec 1      Jan 1
                                                                                                         Move-In
                                        Aug 1                                                   Sep 25
                                                Phase 2 - Performing Arts Center
                                Jun 1         Jul 31
                                        Temporary Corridors (admin, media, café)                     Jan 3             Mar 31
                                                                                                             Demolition of Existing Admin, Media &
                                                                                                             Cafeteria
                                                                                                                Apr 1                                            Mar 31
                                                                            Jun 1        Jul 31                         Phase 3 3-Story Classroom (remainder)
                                                                                    Summer Renovations 2026                                    Jan 1      Jan 31
                                      Summer Renovations 2025                                                                                          Remove New Modular Classrooms
                                Jun 1      Jul 31                                                                                                 Feb 1                          Jul 31
                                                                            Jun 1          Jul 31                                                         Football field & track redevelopment
                                                                                    PAC Connectors


2024                  2025                                        2026                                       2027                                       2028
                    Today
 Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                                   1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                            Quantity UM                Unit $            Total $       $/SqFt

Phasing Considerations
             Phase 1 Fire Marshal Eggress Requirements                 1   ALLW   $     50,000.00    $     50,000.00    $       0.15
             Dust Partitions                                       7,140   SF     $         25.00    $    178,500.00    $       0.55
             Temporary Walks                                      10,800   SF     $          8.00    $     86,400.00    $       0.27
             Temporary Stairs and Ramps                                5   EA     $      5,000.00    $     25,000.00    $       0.08
             Temporary Egress Doors                                   12   EA     $      3,500.00    $     42,000.00    $       0.13
             Temporary Covered Walkways                            7,700   SF     $         35.00    $    269,500.00    $       0.83
             Temporary Utilities/Re-Routing                            1   ALLW   $    250,000.00    $    250,000.00    $       0.77
             Modular Access                                            1   ALLW   $     50,000.00    $     50,000.00    $       0.15
             Courtyard Canopies                                        1   ALLW   $    175,000.00    $    175,000.00    $       0.54

Grading & Utilities Phase 1                                           1    LS     $   4,971,017.00   $   4,971,017.00   $     15.27
             Grading & Utilities Phase 2                              1    LS     $   2,555,320.00   $   2,555,320.00   $      7.85
             LDP Resubmittal #2 (North Druid Hills Accel Lane)        1    LS     $      58,225.00   $      58,225.00   $      0.18
             Fire Hydrants at South Football Field Modulars           1    LS     $      57,000.00   $      57,000.00   $      0.18
Demolition                                                                                                   Included
             Curb & Gutter                                                                                   Included
             Asphalt Paving                                                                                  Included
             Sidewalks                                                                                       Included
             Utilities                                                                                       Included
             Retaining Walls                                                                                 Included
             Tennis Courts                                                                                   Included
             Fencing                                                                                         Included
             Modulars                                                 1 LS        $    180,325.00    $     180,325.00   $       0.55
             Miscellaneous                                                                                   Included
Grading                                                                                                      Included
             Erosion & Sedimentation Control                                                                 Included
             Clearing                                                                                        Included
             Sidewalks                                                                                       Included
             Mass Grading                                                                                    Included
             Strip Topsoil                                                                                   Included
             Export Excess                                                                                   Included
             Export Foundation Spoils                              2,300 CY       $         34.00    $      78,200.00   $       0.24
             Export Stone from Laydown & Trailers                  4,315 CY       $         34.00    $     146,721.59   $       0.45
             Cut Fill                                                                                        Included
             Fine Grade                                                                                      Included
             Respread Topsoil                                                                                Included
             Backfill Foundation Walls / Retaining Walls                                                     Included
             Import                                                                                          Included
             Storm Sewer                                                                                     Included
             Underground Detention System                                                                    Included
             Double Handle Spoils                                                                            Included
             Roof Leaders                                             1 ALLW      $     50,000.00    $      50,000.00   $       0.15
             Sanitary Sewer                                                                                  Included
             Water & Fire                                                                                    Included
             Trench Drains                                            1 LS        $    125,303.00    $     125,303.00   $       0.38
             Concrete Washout                                        50 EA        $        800.00    $      40,000.00   $       0.12
Temporary Stone
             Temporary Parking & Laydown                           1,968   Tons   $         57.00    $     112,182.84   $       0.34
             Crane Road (Phase 2)                                  1,254   Tons   $         57.00    $      71,478.00   $       0.22
             Geotextile Fabric                                     4,200   SY     $          4.00    $      16,800.00   $       0.05
             Between Phases 2 & 3                                  2,604   Tons   $         57.00    $     148,404.63   $       0.46
Water Meter                                                                                                 By Owner
Tap Fees                                                                                                    By Owner
Impact Fees                                                                                                 By Owner
NOI Fees                                                              1 LS        $         496.00   $         496.00   $       0.00
Rock & Unsuitable Soils                                               1 ALLW      $   1,000,000.00   $   1,000,000.00   $       3.07

NPDES Monitoring                                                                                            By Owner

Asphalt Paving Phase 1
             Light Duty                                               1 LS        $    315,812.00    $    315,812.00    $       0.97
             Heavy Duty                                                                                     Included
Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                                 1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                             Quantity UM             Unit $            Total $       $/SqFt
             Sealcoat Curtis Drive Parking                          1,159 SY    $           2.76   $       3,197.61   $       0.01
             Prime Coat                                                                                Not Included
Asphalt Paving Phase 2
             Light Duty                                                1 LS     $    374,470.00    $    374,470.00    $       1.15
             Heavy Duty                                                                                    Included
             Sealcoat Existing                                         1 LS     $       7,905.00   $       7,905.00   $       0.02
             Prime Coat                                                                                Not Included
             Repair Existing Asphalt                                   1 ALLW   $    100,000.00    $    100,000.00    $       0.31

Curb & Gutter Phase 1
             Curb & Gutter                                             1 LS     $     94,530.00    $     94,530.00    $       0.29
             Roll Curb                                                                                    Included
Curb & Gutter Phase 2
             Curb & Gutter                                             1 LS     $     80,560.00    $     80,560.00    $       0.25

Fences & Gates                                                         1 LS     $    228,419.00    $    228,419.00    $       0.70
             4' Retaining Wall Chain Link Fencing                                                         Included
             6' Chain Link Fencing                                                                        Included
             8' Chain Link Fencing with Privacy Slats                                                     Included
             10' Tennis Courts Chain Link Fencing & Windscreen                                            Included
             10' Chain Link Fencing                                                                       Included
             12' Interior Fencing                                                                         Included
             Dumpster Enclosure                                                                           Included
             Guardrail                                                                                    Included
             Gates                                                                                        Included

Hardscapes                                                             1 LS     $   2,013,094.00   $   2,013,094.00   $       6.18
             A-101 - Concrete Stairs                                                                       Included
             A-102 - Concrete Ramp                                                                         Included
             A-103 - Vehicular Steel Bollard with Concrete Fill                                            Included
             A-103B - Removable Vehicular Bollard                                                          Included
             P-101 - 4" Standard Sidewalk                                                                  Included
             P-101B - 4" Sidewalk with Retardant Finish                                                    Included
             P-102 - Heavy Duty Concrete                                                                   Included
             P102B - Heavy Duty Concrete with Retardant Finish                                             Included
             P-103 - Ipe Wood Deck with drainage system                                                    Included
             P-104 - Concrete Unit Paver                                                                   Included
             P-106 - Slate Trail Mix                                                                       Included
             P-109 - #57 Stone                                                                             Included
             P-110 - Detectable Warning Paver                                                              Included
             P-111 - Grass Pave 2                                                                          Included
             P-113 - 6" Concrete Header                                                                    Included
             P-114 - Landscape Step Stone                                                                  Included
             S-105 - Aluminum Edging                                                                       Included
             S-110 - Landscape Boulder                                                                     Included
             W-102 - 6" CIP Curb                                                                           Included
             W-103 - 8" CIP Retaining Wall                                                                 Included
             W-104 - Seat Wall with Wood Top                                                               Included
             W-104B - CIP Concrete Seat Wall                                                               Included
             HC Ramps                                                                                      Included
             HD Concrete Dumpster Pad                                196 SF     $         18.50    $       3,626.00   $       0.01
             JROTC Practice Pad                                                                            Included
                            JROTC Site Furnishings                     1 LS     $     44,201.00    $      44,201.00   $       0.14
Retaining Walls
             Modular Block Phase 1                                     1 LS     $    221,950.00    $    221,950.00    $       0.68
             Modular Block Phase 2                                     1 LS     $     46,090.00    $     46,090.00    $       0.14

Pavement Striping & Signage                                            1 LS     $     44,098.00    $     44,098.00    $       0.14

Landscape / Irrigation                                                 1 LS     $    602,331.00    $    602,331.00    $       1.85
              Sod                                                                                         Included
              Trees                                                                                       Included
              Shrubs                                                                                      Included
              Groundcover                                                                                 Included
              Temporary Irrigation                                                                        Included
Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                              1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                          Quantity UM             Unit $            Total $       $/SqFt
                12-month Maintenance                                                                Not Included

Monumental Sign                                                     1 ALLW   $     50,000.00    $     50,000.00    $       0.15

Flagpole                                                            1 EA     $       5,694.00   $       5,694.00   $       0.02

Tennis Courts                                                        1 LS    $    162,475.00    $    162,475.00    $       0.50
                Tennis Court Bleachers                                                              Not Included

Resurface Track & Field                                              1 LS    $    406,685.00    $    406,685.00    $       1.25

Synthetic Turf Football Field                                        1 LS    $   1,649,065.00   $   1,649,065.00   $       5.07
              Football Goalpost                                                                         Included
              Track & Field Equipment                                                                   Included
                             Long Jump Take-Off Board System                                            Included
                             Pole Vault Box                                                             Included
                             Shot Put Circle                                                            Included
                             Discus Circle                                                              Included
              Gator                                                                                     Included
              Lacrosse Goals                                                                            Included
              Cross Mats (4 EA)                                                                         Included
              Discuss Net                                                                               Included
              Soccer Goal                                            1 LS    $     13,180.00    $      13,180.00   $       0.04

Demolition                                                          1 LS     $    879,595.00    $    879,595.00    $       2.70

Subsoil Termite Treatment                                           1 LS     $     6,779.000    $       6,779.00   $       0.02

Concrete Foundations & SOG                                          1 LS     $   3,079,562.00   $   3,079,562.00   $       9.46
            Foundation Wall                                                                             Included
            Elevated SOD                                                                                Included
            Concrete Phase 1                                        1 LS     $    226,039.00    $     226,039.00   $       0.69

Masonry
                CMU Walls                                           1 LS     $   8,851,796.00   $   8,851,796.00   $     27.19
                Brick                                                                                   Included
                Stone Veneer                                        1 LS     $    299,117.00    $     299,117.00   $       0.92
                Replace Existing Veneer                                                             Not Included

Structural & Misc. Metals                                           1 LS     $   5,966,800.00   $   5,966,800.00   $     18.33
              Joist & Deck                                                                              Included
              Fly Loft                                                                              Not Included
              AESS                                                                                  Not Included
              Stairs & Rails                                                                            Included
              Lobby Stair Premium                                                                       Included
              Ornamental Rails                                                                          Included
              Wood Overhang Soffit                                                                      Included
              Roof Opening Frames in Existing                                                           Included

FRP Reinforcement of Existing Structure                             1 LS     $    688,500.00    $    688,500.00    $       2.11

Millwork                                                            1 ALLW   $   1,750,000.00   $   1,750,000.00   $       5.38

Waterproofing, Dampproofing, and Caulking
            Waterproofing
                          Elevator Pit                              1 EA     $      2,015.00    $      2,015.00    $       0.01
                          Foundation Wall                           1 LS     $    124,250.00    $    124,250.00    $       0.38
            Air Barrier                                             1 LS     $    491,150.00    $    491,150.00    $       1.51
            Air-Barrier on Temp Exterior Wall
            Caulking                                                1 LS     $    196,715.00    $    196,715.00    $       0.60
                          Sidewalks                                                                    Included
                          Sidewalks to Building                                                        Included
                          Exterior Openings                                                            Included
                          Dissimilar Materials                                                         Included
                          CMU Control Joints                                                           Included
  Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                           1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                       Quantity UM             Unit $            Total $       $/SqFt
                           Caulking (Existing)                   1 ALLW   $     25,000.00    $     25,000.00    $       0.08
               Firestopping                                      1 LS     $     58,955.00    $     58,955.00    $       0.18
               Dampproofing                                      1 LS     $      6,600.00    $      6,600.00    $       0.02

Expansion Joints                                                 1 LS     $    164,565.00    $    164,565.00    $       0.51
             Exterior                                                                               Included
             Interior                                                                               Included

Fireproofing                                                     1 LS     $    543,875.00    $    543,875.00    $       1.67
               Intumescent Paint                                                                    Included

Roofing                                                          1 LS     $   1,799,464.00   $   1,799,464.00   $      5.53
Re-Roof Existing School                                           1 LS    $   3,684,656.00   $   3,684,656.00   $     11.32

Metal Wall Panels                                                1 LS     $   1,721,700.00   $   1,721,700.00   $       5.29

Perforated Metal Wall Panels                                   641 SF     $        165.00    $    105,765.00    $       0.32

Doors, Frames, & Finish Hardware                                 1 LS     $   1,352,625.00   $   1,352,625.00   $       4.16
            Replace Existing Doors & HW                                                          Not Included
            Refinish Existing Doors                              1 LS     $       8,330.00   $       8,330.00   $       0.03

Door and Finish Hardware - Install                               1 LS     $     78,615.00    $     78,615.00    $       0.24

Overhead Coiling Doors                                           1 LS     $    219,250.00    $    219,250.00    $       0.67
              Scene Shop                                                                            Included
              Concessions                                                                           Included
              Fire Doors                                         1 LS     $    127,300.00    $    127,300.00    $       0.39
Exterior Glass Sectional Door                                    1 LS     $    109,155.00    $    109,155.00    $       0.34

Glass & Glazing                                                  1 LS     $   2,410,110.00   $   2,410,110.00
              Curtainwall                                                                            Included
              Exterior Storefront                                                                    Included
              Aluminum Storefront Doors                                                              Included
                             Storefront Door HW                  1 LS     $    225,700.00    $     225,700.00   $       0.69
              Interior Curtainwall                                                                   Included
              Interior Storefront                                                                    Included
              Door Lites / Sidelights                                                                Included
              Weight Room Mirrors                                1 LS     $       8,260.00   $       8,260.00   $       0.03
              Privacy Band at Conference Rooms                   1 LS     $       1,000.00   $       1,000.00   $       0.00
              Blast Resistant Film                                                                   Included

Drywall & Acoustical                                             1 LS     $   3,073,650.00   $   3,073,650.00   $       9.44
             Gyp. Board Partitions & Top Outs                                                        Included
             Gyp. Ceilings & Soffits                                                                 Included
             ACT Ceilings                                                                            Included
             Ceiling Baffle at Dining                                                                Included
             Radiused Ceiling at Auditorium                                                          Included
             Ceiling Baffle at Auditorium Entrance                                                   Included
             Ceiling Baffle at Extended Learning                                                     Included
             Acoustic Ceiling Panels at Black Box Theatre                                            Included
             Acoustic Wall Panels at Auditorium                                                      Included
             Acoustic Wall Panels at Gym                                                             Included
             Acoustic Wall Panels at Extended Learning                                               Included
             Wood Paneling                                       1 ALLW   $    100,000.00    $     100,000.00   $       0.31
             Wood Ceiling                                        1 ALLW   $    100,000.00    $     100,000.00   $       0.31

Temporary Exterior Wall                                      14,330 SF    $         25.00    $    358,246.15    $       1.10

Porch Pavers                                                     1 LS     $    155,470.00    $    155,470.00    $       0.48
               Hot Rubberized Asphalt WP                         1 LS     $    109,835.00    $    109,835.00    $       0.34

Flooring
               Tile
                           Floor Tile                            1 LS     $    120,200.00    $    120,200.00    $       0.37
  Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                            1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                        Quantity UM             Unit $            Total $       $/SqFt
                            Wall Tile                                                                 Included
              Carpet & Resilient Flooring
                            Carpet                                1 LS     $    883,755.00    $    883,755.00    $       2.71
                            LVT                                                                       Included
                            Rubber Base                                                               Included
                            Rubber Flooring                                                           Included
                            Transitions                                                               Included
                            Rubber Stair Treads and Risers                                        Not Included

Wood Athletic Flooring                                            1 LS     $    464,202.00    $    464,202.00    $       1.43
Wood Flooring                                                                                        Included
Resilient Athletic Flooring                                                                          Included

Epoxy Flooring                                                    1 LS     $    294,530.00    $    294,530.00    $       0.90
             Epoxy Base                                                                              Included

Painting                                                          1 LS     $   1,002,776.00   $   1,002,776.00   $       3.08
              Walls                                                                                   Included
              Gyp. Ceilings & Soffits                                                                 Included
              Wall Graphics                                       1 ALLW   $    100,000.00    $     100,000.00   $       0.31
              Wall Covering                                                                           Included
              Sealed Concrete                                     1 LS     $    138,977.00    $     138,977.00   $       0.43
              Polished Concrete                                                                   Not Included
              Special Coatings                                    1 ALLW   $     50,000.00    $      50,000.00   $       0.15

Exterior Mural                                                    1 ALLW   $     60,000.00    $     60,000.00    $       0.18

Specialties
              Fire Extinguishers & Cabinets                       1 LS     $     20,178.00    $     20,178.00    $       0.06
              Toilet Partitions                                   1 LS     $    264,353.00    $    264,353.00    $       0.81
              Toilet Accessories                                                                     Included
              Corner Guards                                       1 ALLW   $     15,000.00    $     15,000.00    $       0.05

Storage Shelving                                                  1 ALLW   $     80,000.00    $     80,000.00    $       0.25
             36"X10"X36" Shelving                                                                     Included
             18" Wire Shelving                                                                    Not Included
             Storage Shelving with 7 Shelves                                                          Included

Athletic & Dressing Room Lockers                                  1 LS     $    199,000.00    $    199,000.00    $       0.61

Gym Equipment                                                     1 LS     $    164,000.00    $     164,000.00   $       0.50
            Basketball Equipment                                                                      Included
            Wrestling Equipment                                                                       Included
            Volleyball Nets                                                                           Included
                          Floor Sleeves                                                               Included
            Wall Pads                                                                                 Included
Combination Baseball/Softball Complex                              1 LS    $   8,127,922.71   $   8,127,922.71   $     24.97

Scoreboards
              Interior (2 Each)                                   1 LS     $     15,950.00    $     15,950.00    $       0.05
              Exterior (Football Field)                           1 LS     $     43,143.00    $     43,143.00    $       0.13

Telescoping Bleachers (Plastic)                                   1 LS     $    155,880.00    $    155,880.00    $       0.48

Interior Signage                                                  1 LS     $     63,551.00    $     63,551.00    $       0.20
Wayfinding                                                        1 ALLW   $     50,000.00    $     50,000.00    $       0.15
Exterior Signage                                                  1 ALLW   $     50,000.00    $     50,000.00    $       0.15

Visual Display Boards                                             1 LS     $     77,171.00    $     77,171.00    $       0.24
              Markerboard                                                                            Included
              Install                                             1 LS     $     17,910.00    $     17,910.00    $       0.06

Parent Drop Off Canopy                                                                               Included
Bus Loop Canopy Phase 1                                           1 LS     $     92,140.00    $     92,140.00    $       0.28
Bus Loop Canopy Phase 2                                           1 LS     $     57,265.00    $     57,265.00    $       0.18
  Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                             1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                               Quantity UM                  Unit $                 Total $       $/SqFt
Louvered Canopies Allowance                           3,648 ALLW/SF   $         150.00    $         547,200.00    $       1.68

Operable Partition                                       1 LS         $      80,150.00    $          80,150.00    $       0.25

Food Service Equipment                                   1 LS         $    2,587,184.00   $        2,587,184.00   $       7.95

Commercial Laundry Equipment (Gym)                       1 ALLW       $      30,000.00    $          30,000.00    $       0.09

Residential Appliances                                   1 LS         $      27,698.00    $          27,698.00    $       0.09

Kiln                                                     1 ALLW       $      15,000.00        $      15,000.00    $       0.05

Window Treatments                                        1 LS         $     221,725.00    $         221,725.00    $       0.68

Educational Casework
             Educational Casework                                                           Incl. in Millwork
             Science / Lab Casework                      1 LS         $    1,057,660.00   $    1,057,660.00       $       3.25
             Library Casework                                                                       By Owner
             Music Suite Casework                        1 LS         $     105,214.00    $       105,214.00      $       0.32

Stage Curtains & Equipment                                                                             Included
             Moveable Chairs                                                                          By Owner

Knox Box                                                 4 EA         $         989.00    $            3,956.00   $       0.01

Loading Dock Equipment                                   1 ALLW       $        1,000.00   $            1,000.00   $       0.00

Elevator                                                 1 LS         $     135,000.00    $         135,000.00    $       0.41

Final Cleaning                                      284,843   SF      $            0.65   $         185,147.95    $       0.57
              Summer 2025                           169,275   SF      $            0.50   $          84,637.50    $       0.26
               Waxing                               109,016   SF      $            1.05   $         114,466.80    $       0.35
              Summer 2026                            39,780   SF      $            0.50   $          19,890.00    $       0.06
              Summer 2027                           261,477   SF      $            0.50   $         130,738.50    $       0.40
              Modulars (Summers 2025, 2026, 2027)    25,287   SF      $            1.50   $          37,930.50    $       0.12
               Waxing (Summers 2025, 2026, 2027)     25,287   SF      $            3.15   $          79,654.05    $       0.24

Fire Protection                                          1 LS         $    1,005,000.00   $        1,005,000.00   $       3.09

Plumbing                                                 1 LS         $    5,713,570.00   $        5,713,570.00   $     17.55

HVAC                                                     1 LS         $   11,224,000.00   $       11,224,000.00   $     34.48
             Test & Balance                                                                            Included
             Controls                                                                                  Included

Electrical                                               1 LS         $   11,100,107.00   $       11,100,107.00   $     34.10
             Lighting                                                                                  Included
             Theatrical Lighting & Sound                                                               Included
             ERRCS                                       1 LS         $     153,100.00    $          153,100.00   $       0.47
             Fire Alarm                                                                                Included
             Landscape Lighting Allowance                1 ALLW       $     100,000.00    $          100,000.00   $       0.31

Department Changes                                                                                     Included

Modulars                                                 1 LS         $    4,520,350.00   $        4,520,350.00   $     13.89
             Setup                                                                                     Included
             Rental                                                                                    Included
             Ramps & Steps                                                                             Included
             Relocation of Existing Modular                                                            Included
             Design                                       1 LS        $      13,000.00    $           13,000.00   $       0.04
             Temporary Stone                          1,475 Tons      $          57.00    $           84,060.32   $       0.26
             Water Line                                                                                Included
             Fire Line                                                                                 Included
             Sanitary Sewer                                                                            Included
             Fire Protection                                                                           Included
 Attachment 4 - Schedule of Values




Dekalb County Schools                                                                                     1/22/2025
Cross Keys High School Addition & Modernization
80% GMP Estimate

Trade                                                Quantity UM             Unit $             Total $       $/SqFt
              Plumbing                                                                        Included
              Electrical                                                                      Included
              Remove/Abandon Existing Utilities           1 ALLW   $     50,000.00    $      50,000.00    $       0.15

Accepted Value Engineering                               (1) LS    $   1,191,429.00   $   (1,191,429.00) $       (3.66)

              Total                                                                   $    107,159,614    $    329.18

FAA Study & Permit                                                                    $          3,500    $       0.01
Preconstruction Expenses
               Survey - Land Engineering                   1 LS    $     35,500.00    $         35,500    $      0.11
               Traffic Study - A & R Engineering           1 LS    $     12,250.00    $         12,250    $      0.04
               Combination Plat - Land Engineering         1 LS    $      4,350.00    $          4,350    $      0.01
               Arborist - Arborguard                       1 LS    $      4,135.00    $          4,135    $      0.01
Erosion Control & Maintenance Bond                         1 LS    $        372.00    $            372    $      0.00
Synagogue Parking                                         32 MO    $      7,000.00    $        224,000    $      0.69
F.O.G. Permit                                              1 LS    $        125.00    $            125    $      0.00
Sitework - General Conditions                                                         $        300,458    $      0.92
Sitework - General Requirements                                                       $        190,597    $      0.59
3 Story - General Conditions                                                          $      7,156,660    $     21.98
3 Story - General Requirements                                                        $      1,011,455    $      3.11
Performing Arts - General Conditions                                                  $      2,018,936    $      6.20
Performing Arts - General Requirements                                                $        314,726    $      0.97
Classroom Renovation - General Conditions                                             $        282,494    $      0.87
Classroom Renovation - General Requirements                                           $        567,740    $      1.74
Athletics - General Conditions                                                        $        252,919    $      0.78
Athletics - General Requirements                                                      $        195,502    $      0.60
Gym Renovation - General Conditions                                                   $        290,838    $      0.89
Gym Renovation - General Requirements                                                 $        273,588    $      0.84
Builders Risk Insurance                                                               $        335,754    $      1.03
Liability Insurance                                                                   $        214,013    $      0.66
Subcontractor Default Insurance                                                       $      1,607,394    $      4.94
Payment & Performance Bonds                                                           $        877,947    $      2.70
Construction Manager's Fee                                                            $      6,093,982    $     18.72
Total                                                                                 $    129,428,850    $    397.59
Contingency
               Design (4%)                                                            $      5,177,154    $     15.90
               Construction (5%)                                                      $      6,471,442    $     19.88
Subtotal                                                                              $    141,077,446    $    433.37
Sitework - Escalation (0%)                                                            $            -      $       -
3 Story - Escalation (2%)                                                             $      1,120,963    $      3.44
Performing Arts - Escalation (1%)                                                     $        177,139    $      0.54
Gym Renovation - Escalation (5%)                                                      $        333,568    $      1.02
Athletics - Escalation (5%)                                                           $         96,901    $      0.30
Classroom Reno - Escalation (5%)                                                      $        507,351    $      1.56
CTAE Reno - Escalation (5%)                                                           $        171,166    $      0.53
Modulars - Escalation (0%)                                                            $            -      $       -
               Total                                                                  $    143,484,535    $    440.76


Alternates
Theatrical lighting add alternates                                                    $     185,200.00
 Attachment 4 - Schedule of Values




Cross Keys High School Addition and Modernization                                                                                                          1/23/2025
80% GMP Value Options
                                                                                                                                                         Accepted

       2-1 Remove the trees withing the courtyards                                                                                                        (28,883)
       2-1 Remove automation from the southeast parking lot gates                                                                                         (36,352)
       2-3 Painted steel bollards in lieu of stainless steel bollards                                                                                     (18,636)
       2-4 Remove the geotextile fabric and stone base beneath all sidewalks                                                                             (107,694)
       2-5 Remove the IPE wood deck and replace with sidewalks.                                                                                          (103,748)
      2-6b Concrete Paving P-102 in lieu of Pavers at the roundabout circle                                                                               (36,675)
      2-7b Concrete Paving P-102 in lieu of Pavers at the half moon behind auditorium                                                                     (18,132)
       2-8 Concrete Paving P-102 in lieu of P-102B concrete paving behind auditorium                                                                       (9,183)
       2-9 Standard sidewalks in lieu of sidewalks with retardant finish                                                                                  (17,460)
      2-10 Remove the wood top from the W-104 concrete seat walls.                                                                                        (29,161)
       4-1 Utilize brick in lieu of stone at site retaining walls                                                                                         (51,147)
       4-2 Drywall top outs in lieu of CMU top outs. CMU to one course of above highest adjacent ceiling.                                                (324,995)
       6-1 Remove 50% of the perforated screen walls from inside the building.                                                                            (52,883)
       7-1 60 mil PVC KEE roofing in lieu of 80 mil PVC KEE                                                                                               (57,280)
       9-7 Delete the Acoustical Ceiling Baffle at Extended Learning (AP-01)                                                                              (33,200)
      9-11 Delete the Acoustical Ceiling Baffles at Learning Huddle                                                                                        (3,900)
      15-2 Utilize schedule 40 PVC for all below slab storm, sanitary waste and vent piping in lieu of cast iron.                                        (106,000)
     15-11 Remove single zone VAV supply fans as shown in the schedule. The drawings and specifications contradict each other.                            (15,400)
           The specs call for single zone VAV on ALL RTUs but the schedule only calls for it on some of them. We carried SZVAV on
           all units on bid day to ensure we were covered so this deduct removes single zone VAV supply fans on the units that call
           for “single zone CV” on the schedule.
     15-12 Switch RTUs 5 tons and under to standard efficiency. Schedule calls for all units to have minimum 2-stages of cooling.                         (11,200)
           This is standard on all RTUs 6 tons and over but bumps us to the high efficiency units on the smaller tonnages (5 tons
           and under). This deduct is to switch the smaller units to standard efficiency (single stage units).

      16-1 Utilize 2x4 light fixtures in the classrooms in lieu of spec'd lights                                                                          (38,000)
      16-5 Utilize 4wall theatrical lighting package in lieu of Barbizon                                                                                  (91,500)

                                                                                                                                              TOTALS    ($1,191,429)

            *Design team review may be required to ensure code compliance, coordination, and building envelope integrity for some items listed above.
            Evergreen is not responsible for such review and has not included any additional cost for such review.
            TBD - To be determined
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                        1/23/2025
Sitework
General Conditions Estimate
                                             Qty           Unit       Labor        Labor Burden         Material          Equipment         Sub           Total
Project Team                                          1 LS        $      147,305 $         54,358                                                    $            201,663
  Assistant Project Manager (100%)                   30 Weeks                                                                                        $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Coordinator (100%)                         12 Weeks                                                                                        $                -
  Assistant Superintendent (100%)                   18 Weeks                                                                                         $                -
  Assistant Superintendent (100%)                   13 Weeks                                                                                         $                -
  Purchasing Agent (100%)                             5 Weeks     $        1,920 $           709                                                     $             13,143
  Project Secretary (100%)                           12 Weeks     $          720 $           266                                                     $             11,828
  Project Accountant (100%)                          12 Weeks     $        1,750 $           646                                                     $             28,749
  Travel & Entertainment                           -    Months                                      $           270                                  $                -
  Supervision Vehicles                             -    Months                                      $         1,790                                  $                -
  Superintendent Vehicle Fuel & Repair             -    Months                                      $         4,600                                  $                -
  Superintendent Vehicle Insurance                 -    Months                                                        $        562.50                $                -

  Safety Program & Inspections                       1 LS                                         $          10,000                                  $             10,000
  Safety Signage                                   -   LS         $        5,000 $          1,845 $          15,000                                  $                -
  Drug Testing                                       1 LS                                         $           1,080                                  $              1,080
  Hard Hats & Safety Vests                           1 LS                                         $           6,000                                  $              6,000
  Raingear & Boots                                   1 LS                                         $           1,500                                  $              1,500
  Eye & Ear Protection                               1 LS                                         $           1,500                                  $              1,500
  Safety Harnesses and Lifelines                   -   LS                                         $           1,735                                  $                -
  First Aid Supplies                               -   Months                                     $             108                                  $                -

  Office Trailer Rental                            -   Months                                       $         4,620                                  $                -
  Tool Trailer Rental                              -   Months                                       $           500                                  $                -
  Office Equipment                                 -   LS                                           $           650                                  $                -
  Computer Equipment                               -   LS                                           $        15,000                                  $                -
  Project Software - Procore                       -   Months                                       $       299,986                                  $                -
  Office Supplies & Postage                        -   Months                                       $           300                                  $                -
  Office Furniture                                 -   LS                                           $        15,000                                  $                -

  Drawings & Printing                              -   LS                                           $        10,000                                   $               -
  CAD Files                                        -   LS                                           $         5,000                                   $               -
  Web Cam - OxBlue                                 -   Months                                                                           $    1,500.00 $               -
  Daily Photos - Cupix                             -   Months                                       $           755                                   $               -
  Aerial Photograghy                               -   Months                                       $           500                                   $               -
  Closeout Documents & As-Builts                   -   LS                                           $         9,200                                   $               -




                                                                            1 of 2
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                             1/23/2025
Sitework
General Conditions Estimate
                                             Qty            Unit       Labor                 Labor Burden         Material       Equipment       Sub           Total
  Traffic Control/Flagman                          -     Weeks     $           2,220     $              819                                               $                -
  Setup & Remove Field Office                      -     LS        $           4,183     $            1,544   $        14,202                             $                -
  Setup & Remove Tool Trailer                      -     LS        $             750     $              277   $         1,703                             $                -
  Project Signs                                    -     LS        $           2,500     $              923   $         4,860                             $                -
  Radios                                           -     LS                              $              -     $         6,500                             $                -

  Temp/Permanent Power & Gas                       -     Months                                               $              -                             $               -
  Temporary Power                                  -     Months                                                                              $    1,620.00 $               -
  Temporary Power Setup (Georgia Power)            -     LS                                                   $        25,000                              $               -
  Temporary Heat                                   -     Months                                               $        15,000                              $               -
  Temporary Water                                  -     Months                                               $           -                                $               -
  Holding Tank                                     -     Months                                               $           378                              $               -
  Temporary Toilets                                -     Months                                               $         2,000                              $               -
  Sanitary Supplies                                -     Months                                               $           159                              $               -
  Ice, Cups, and Water                             -     Months                                               $           159                              $               -
  Telecom System & Installation (Internet)         -     LS                                                   $           650                              $               -
  Telecom Service (Internet & Cell Phones)         -     Months                                                                              $       1,104 $               -
                                                   -
  Barricades                                           1 LS                                                   $        24,995                             $             24,995

  Ceremonies                                           1 LS                                                   $              -                            $                -

TOTAL                                                                                                                                                     $            300,458




                                                                                2 of 2
Attachment 5 - List of Itemized General Conditions



Cross Keys Hish School                                                                                                                                      1/23/2025
Sitework
General Requirements Estimate
                                 Qty             Unit       Labor                Labor Burden       Material          Equipment         Sub              Total
  Fire Extinguishers                -      EA                                                   $          100                                       $               -
  Temporary Fence                 5,067    LF           $           5        $              2   $         15.64                                      $           113,932
  Continuous Cleanup                  26   Weeks        $       1,862        $            687                                                        $            66,277
  Dump Fees                           18   Pulls                                                                                    $         577    $            10,388
  Street Sweeper                    -      Months                                                                 $         1,610                    $               -
  Skid Steer                        -      Months                                                                 $         2,862                    $               -
  Equipment Rental                  -      Months                                                                 $         2,100                    $               -
  Fuel & Lubricant                  -      Months                                                                 $           250                    $               -
  Small Tools                       -      Months                                                                 $         1,000                    $               -
                                           SF                                                                                       $         0.35   $               -

TOTAL                                                                                                                                                $           190,597




                                                                    1 of 1
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                    1/23/2025
3 Story Addition
General Conditions Estimate
                                             Qty          Unit       Labor        Labor Burden        Material          Equipment         Sub          Total
Project Team                                         1 LS        $    3,662,336 $     1,351,461                                                    $       5,013,797
  Senior Project Manager (100%)                    110 Weeks                                                                                       $             -
  Project Manager (100%)                           165 Weeks                                                                                       $             -
  Assistant Project Manager (100%)                 165 Weeks                                                                                       $             -
  Assistant Project Manager (100%)                 165 Weeks                                                                                       $             -
  Project Engineer (100%)                           65 Weeks                                                                                       $             -
  Project Coordinator (100%)                        65 Weeks                                                                                       $             -
  Project Coordinator (100%)                        66 Weeks                                                                                       $             -
  General Superintendent (25%)                     110 Weeks                                                                                       $             -
  Project Superintendent (100%)                    165 Weeks                                                                                       $             -
  Assistant Superintendent (100%)                  165 Weeks                                                                                       $             -
  Assistant Superintendent (100%)                  165 Weeks                                                                                       $             -
  Surveyor (100%)                                    1 LS                                                                             $     49,996 $          49,996
  Engineering Equipment                              1 LS                       $         2,500                                                    $           2,500
  Engineering Supplies                               1 LS                       $         2,500                                                    $           2,500
  Purchasing Agent (100%)                           26 Weeks               1920 $           709                                                    $          68,341
  Project Secretary (100%)                          65 Weeks                720 $           266                                                    $          64,070
  Project Accountant (100%)                         65 Weeks               1750 $           646                                                    $         155,726
  Travel & Entertainment                            38 Months                                     $           270                                  $          10,260
  Supervision Vehicles                              46 Months                       $       -     $         2,051                                  $          94,342
  Superintendent Vehicle Fuel & Repair              46 Months                       $       -     $         4,600                                  $         211,600
  Superintendent Vehicle Insurance                  46 Months                       $       -                       $        562.50                $          25,875

  Safety Program & Inspections                        1 LS                                      $           6,200                                  $          6,200
  Safety Signage                                      1 LS       $       5,000 $          1,845 $          15,000                                  $         21,845
  Drug Testing                                     -    LS                                      $           1,080                                  $            -
  Hard Hats & Safety Vests                         -    LS                                      $           6,000                                  $            -
  Raingear & Boots                                 -    LS                                      $           1,500                                  $            -
  Eye & Ear Protection                             -    LS                                      $           1,500                                  $            -
  Safety Harnesses and Lifelines                      1 LS                                      $           1,735                                  $          1,735
  First Aid Supplies                                 38 Months                                  $             108                                  $          4,104

  Office Trailer Rental                            38 Months                                      $         4,620                                  $        175,560
  Tool Trailer Rental                              38 Months                                      $           500                                  $         19,000
  Office Equipment                                  1 LS                                          $           650                                  $            650
  Computer Equipment                                1 LS                                          $        20,000                                  $         20,000
  Project Software - Procore                        1 LS                                          $       299,986                                  $        299,986
  Office Supplies & Postage                        38 Months                                      $           300                                  $         11,400
  Office Furniture                                  1 LS                                          $        15,000                                  $         15,000



                                                                           1 of 2
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                              1/23/2025
3 Story Addition
General Conditions Estimate
                                             Qty               Unit       Labor                 Labor Burden        Material      Equipment       Sub           Total

  Drawings & Printing                                   1 LS                                                    $        15,000                             $            15,000
  CAD Files                                             1 LS                                                    $         5,000                             $             5,000
  Web Cam - OxBlue                                     38 Months                                                                              $         -   $               -
  Daily Photos - Cupix                                 38 Months                                                $            25                             $               950
  Aerial Photograghy                                    1 LS                                                    $         4,004                             $             4,004
  Closeout Documents & As-Builts                        1 LS                                                    $         9,200                             $             9,200
  Weather Station/Service                               1 LS                                                    $         2,500                             $             2,500

  Traffic Control/Flagman                          165 Weeks          $           2,220     $             819                                               $           501,471
  Setup & Remove Field Office                        1 LS             $           4,183     $           1,544   $        14,202                             $            19,929
  Setup & Remove Tool Trailer                        1 LS             $             750     $             277   $         1,703                             $             2,730
  Temporary Ladders                                  4 EA             $             200     $              74   $           535                             $             3,235
  Project Signs                                      1 LS             $           1,500     $             554   $         3,000                             $             5,054
  Radios                                             1 LS                                                       $         6,500                             $             6,500

  Temp/Permanent Power & Gas                        6 Months                                                                                                $               -
  Temporary Power                                  38 Months                                                                                  $    1,620.00 $            61,560
  Temporary Power Setup (Georgia Power)             1 LS                                                        $        25,000                             $            25,000
  Temporary Heat                                    4 Months                                                    $        15,000                             $            60,000
  Temporary Water                                  38 Months                                                                                                $               -
  Holding Tank                                     38 Months                                                    $           378                             $            14,364
  Temporary Toilets                                38 Months                                                    $         2,000                             $            76,000
  Sanitary Supplies                                38 Months                                                    $           159                             $             6,042
  Ice, Cups, and Water                             38 Months                                                    $           159                             $             6,042
  Telecom System & Installation (Internet)          1 LS                                                        $           650                             $               650
  Telecom Service (Internet & Cell Phones)         38 Months                                                                                  $       1,104 $            41,943

  Barricades                                       -      LS                                                    $        25,000                             $               -

  Ceremonies                                           1 LS                                                     $        15,000                             $            15,000

TOTAL                                                                                                                                                       $       7,156,660




                                                                                   2 of 2
Attachment 5 - List of Itemized General Conditions



Cross Keys High School                                                                                                                                    1/23/2025
3 Story Addition
General Requirements Estimate
                                Qty            Unit       Labor                Labor Burden       Material          Equipment          Sub             Total
  Fire Extinguishers                25   EA                                                   $          100                                       $             2,463
  Temporary Fence                1,636   LF           $           5        $              2   $         15.64                                      $            36,792
  Continuous Cleanup               165   Weeks        $       1,862        $            687                                                        $           420,603
  Dump Fees                        160   Pulls                                                                                     $         577   $            92,094
  Lull                              12   Months                                                                 $       4,957.00                   $            59,484
  Street Sweeper                    35   Months                                                                 $          1,610                   $            56,350
  Skid Steer                        35   Months                                                                 $          2,862                   $           100,170
  Equipment Rental                  35   Months                                                                 $          2,100                   $            73,500
  Fuel & Lubricant                  35   Months                                                                 $          2,000                   $            70,000
  Small Tools                       35   Months                                                                 $          1,000                   $            35,000
  Cupix                              1   LS                                                                                        $   15,000.00   $            15,000
  Protect New Work                   1   LS                                                   $        50,000                                      $            50,000

TOTAL                                                                                                                                              $      1,011,455




                                                                  1 of 1
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                      1/23/2025
Performing Arts Center
General Conditions Estimate
                                            Qty           Unit       Labor        Labor Burden         Material          Equipment         Sub           Total
Project Team                                         1 LS        $    1,209,231 $        446,226                                                    $        1,655,457
  Senior Project Manager (100%)                     55 Weeks
  Project Manager (100%)                            70 Weeks
  Assistant Project Manager (100%)                  70 Weeks
  Project Engineer (100%)                          52 Weeks
  Project Engineer (100%)                          52 Weeks
  Project Coordinator (100%)                        52 Weeks
  General Superintendent (25%)                      55 Weeks
  Project Superintendent (100%)                    70 Weeks
  Assistant Superintendent (100%)                  70 Weeks
  Surveyor (100%)                                    1 LS                                                                              $     49,999 $          49,999
  Purchasing Agent (100%)                          20 Weeks                1920 $           709                                                     $          52,570
  Project Secretary (100%)                          52 Weeks                720 $           266                                                     $          51,256
  Project Accountant (100%)                         52 Weeks               1750 $           646                                                     $         124,580
  Travel & Entertainment                          -    Months                                      $           270
  Supervision Vehicles                            -    Months                                      $         1,790                                  $             -
  Superintendent Vehicle Fuel & Repair            -    Months                                      $         4,600                                  $             -
  Superintendent Vehicle Insurance                -    Months                                                        $        562.50                $             -

  Safety Program & Inspections                    -   LS                                         $          16,200                                  $             -
  Safety Signage                                    1 LS         $        5,000 $          1,845 $          15,000                                  $          21,845
  Drug Testing                                    -   LS                                         $           1,080                                  $             -
  Hard Hats & Safety Vests                        -   LS                                         $           6,000                                  $             -
  Raingear & Boots                                -   LS                                         $           1,500                                  $             -
  Eye & Ear Protection                            -   LS                                         $           1,500                                  $             -
  Safety Harnesses and Lifelines                  -   LS                                         $           1,735                                  $             -
  First Aid Supplies                              -   Months                                     $             108                                  $             -

  Office Trailer Rental                           -   Months                                       $         4,620                                  $             -
  Tool Trailer Rental                             -   Months                                       $           500                                  $             -
  Office Equipment                                -   LS                                           $           650                                  $             -
  Computer Equipment                              -   LS                                           $        15,000                                  $             -
  Project Software - Procore                      -   Months                                       $       299,986                                  $             -
  Office Supplies & Postage                       -   Months                                       $           300                                  $             -
  Office Furniture                                -   LS                                           $        15,000                                  $             -

  Drawings & Printing                             -   LS                                           $        10,000                                   $            -
  CAD Files                                       -   LS                                           $         5,000                                   $            -
  Web Cam - OxBlue                                -   Months                                                                           $    1,500.00 $            -



                                                                           1 of 2
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                          1/23/2025
Performing Arts Center
General Conditions Estimate
                                             Qty          Unit       Labor                 Labor Burden        Material       Equipment       Sub           Total
  Daily Photos - Cupix                             -   Months                                              $           755                             $               -
  Aerial Photograghy                               -   Months                                              $           500                             $               -
  Closeout Documents & As-Builts                   -   LS                                                  $         9,200                             $               -

  Traffic Control/Flagman                          -   Weeks     $           2,220     $             819                                               $               -
  Setup & Remove Field Office                      -   LS        $           4,183     $           1,544   $        14,202                             $               -
  Setup & Remove Tool Trailer                      -   LS        $             750     $             277   $         1,703                             $               -
  Temporary Ladders                                -   EA        $             200     $              74   $           535                             $               -
  Project Signs                                      1 LS        $           1,000     $             369   $         1,860                             $             3,229
  Radios                                           -   LS                                                  $         6,500                             $               -

  Temp/Permanent Power & Gas                         4 Months                                                                                           $              -
  Temporary Power                                  -   Months                                                                             $    1,620.00 $              -
  Temporary Power Setup (Georgia Power)            -   LS                                                  $        25,000                              $              -
  Temporary Heat                                     4 Months                                              $        15,000                              $           60,000
  Temporary Water                                  -   Months                                                                                           $              -
  Holding Tank                                     -   Months                                              $           378                              $              -
  Temporary Toilets                                -   Months                                              $         2,000                              $              -
  Sanitary Supplies                                -   Months                                              $           159                              $              -
  Ice, Cups, and Water                             -   Months                                              $           159                              $              -
  Telecom System & Installation (Internet)         -   LS                                                  $           650                              $              -
  Telecom Service (Internet & Cell Phones)         -   Months                                                                             $       1,104 $              -

  Barricades                                       -   LS                                                  $        25,000                             $               -

  Ceremonies                                       -   LS                                                  $              -                            $               -

TOTAL                                                                                                                                                  $        2,018,936




                                                                              2 of 2
 Attachment 5 - List of Itemized General Conditions



Cross Keys High School                                                                                                                                    1/23/2025
Performing Arts
General Requirements Estimate
                                Qty             Unit       Labor                Labor Burden       Material          Equipment         Sub             Total
  Fire Extinguishers                  7   EA                                                   $          100                                      $               656
  Temporary Fence                 1,006   LF           $           5        $              2   $         15.64                                     $            22,621
  Continuous Cleanup                 70   Weeks        $       1,862        $            687                                                       $           178,438
  Dump Fees                          43   Pulls                                                                                    $         577   $            24,545
  Street Sweeper                      3   Months                                                                 $         1,610                   $             4,830
  Skid Steer                          3   Months                                                                 $         2,862                   $             8,586
  Equipment Rental                    3   Months                                                                 $         2,100                   $             6,300
  Fuel & Lubricant                    3   Months                                                                 $           250                   $               750
  Small Tools                         3   Months                                                                 $         1,000                   $             3,000
  Cupix                               1   LS                                                                                       $   15,000.00   $            15,000
  Protect New Work                    1   LS                                                   $        50,000                                     $            50,000

TOTAL                                                                                                                                              $           314,726




                                                                   1 of 1
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                        1/23/2025
Classroom Renovation
General Conditions Estimate
                                             Qty           Unit       Labor        Labor Burden         Material          Equipment         Sub           Total
Project Team                                          1 LS        $      157,508 $         58,123                                                    $            215,631
  Assistant Project Manager (100%)                   26 Weeks                                                                                        $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Coordinator (100%)                         12 Weeks                                                                                        $                -
  Assistant Superintendent (100%)                   26 Weeks                                                                                         $                -
  Field Engineer (100%)                             24 Weeks                                                                                         $                -
  Purchasing Agent (100%)                           10 Weeks      $        1,920 $           709                                                     $             26,285
  Project Secretary (100%)                           12 Weeks     $          720 $           266                                                     $             11,828
  Project Accountant (100%)                          12 Weeks     $        1,750 $           646                                                     $             28,749
  Travel & Entertainment                           -    Months                                      $           270
  Supervision Vehicles                             -    Months                                      $         1,790                                  $                -
  Superintendent Vehicle Fuel & Repair             -    Months                                      $         4,600                                  $                -
  Superintendent Vehicle Insurance                 -    Months                                                        $        562.50                $                -

  Safety Program & Inspections                     -   LS                                         $          16,200                                  $                -
  Safety Signage                                   -   LS         $        5,000 $          1,845 $          15,000                                  $                -
  Drug Testing                                     -   LS                                         $           1,080                                  $                -
  Hard Hats & Safety Vests                         -   LS                                         $           6,000                                  $                -
  Raingear & Boots                                 -   LS                                         $           1,500                                  $                -
  Eye & Ear Protection                             -   LS                                         $           1,500                                  $                -
  Safety Harnesses and Lifelines                   -   LS                                         $           1,735                                  $                -
  First Aid Supplies                               -   Months                                     $             108                                  $                -

  Office Trailer Rental                            -   Months                                       $         4,620                                  $                -
  Tool Trailer Rental                              -   Months                                       $           500                                  $                -
  Office Equipment                                 -   LS                                           $           650                                  $                -
  Computer Equipment                               -   LS                                           $        15,000                                  $                -
  Project Software - Procore                       -   Months                                       $       299,986                                  $                -
  Office Supplies & Postage                        -   Months                                       $           300                                  $                -
  Office Furniture                                 -   LS                                           $        15,000                                  $                -

  Drawings & Printing                              -   LS                                           $        10,000                                   $               -
  CAD Files                                        -   LS                                           $         5,000                                   $               -
  Web Cam - OxBlue                                 -   Months                                                                           $    1,500.00 $               -
  Daily Photos - Cupix                             -   Months                                       $           755                                   $               -
  Aerial Photograghy                               -   Months                                       $           500                                   $               -
  Closeout Documents & As-Builts                   -   LS                                           $         9,200                                   $               -




                                                                            1 of 2
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                           1/23/2025
Classroom Renovation
General Conditions Estimate
                                             Qty          Unit       Labor                 Labor Burden         Material       Equipment       Sub           Total
  Traffic Control/Flagman                          -   Weeks     $           2,220     $              819                                               $                -
  Setup & Remove Field Office                      -   LS        $           4,183     $            1,544   $        14,202                             $                -
  Setup & Remove Tool Trailer                      -   LS        $             750     $              277   $         1,703                             $                -
  Temporary Ladders                                -   EA        $             200     $               74   $           535                             $                -
  Project Signs                                    -   LS        $           2,500     $              923   $         4,860                             $                -
  Radios                                           -   LS                                                   $         6,500                             $                -

  Temp/Permanent Power & Gas                       -   Months                                                                                            $               -
  Temporary Power                                  -   Months                                                                              $    1,620.00 $               -
  Temporary Power Setup (Georgia Power)            -   LS                                                   $        25,000                              $               -
  Temporary Heat                                   -   Months                                               $        15,000                              $               -
  Temporary Water                                  -   Months                                                                                            $               -
  Holding Tank                                     -   Months                                               $           378                              $               -
  Temporary Toilets                                -   Months                                               $         2,000                              $               -
  Sanitary Supplies                                -   Months                                               $           159                              $               -
  Ice, Cups, and Water                             -   Months                                               $           159                              $               -
  Telecom System & Installation (Internet)         -   LS                                                   $           650                              $               -
  Telecom Service (Internet & Cell Phones)         -   Months                                                                              $       1,104 $               -

  Barricades                                       -   LS                                                   $        25,000                             $                -

  Ceremonies                                       -   LS                                                   $              -                            $                -

TOTAL                                                                                                                                                   $            282,494




                                                                              2 of 2
Attachment 5 - List of Itemized General Conditions



Cross Keys High School                                                                                                                                     1/23/2025
Classroom Renovation
General Requirements Estimate
                                 Qty            Unit       Labor                Labor Burden        Material          Equipment         Sub             Total
  Fire Extinguishers                   12 EA                                                    $          100                                      $             1,240
  Temporary Fence                    -    LF           $           5        $               2   $          6.24                                     $               -
  Continuous Cleanup                   24 Weeks        $       3,724        $           1,374                                                       $           122,357
  Dump Fees                            80 Pulls                                                                                     $         577   $            46,413
  Street Sweeper                     -    Months                                                                  $         1,610                   $               -
  Skid Steer                         -    Months                                                                  $         2,862                   $               -
  Equipment Rental                   -    Months                                                                  $         2,100                   $               -
  Fuel & Lubricant                   -    Months                                                                  $           250                   $               -
  Small Tools                        -    Months                                                                  $         1,000                   $               -
  Cupix                                 1 LS                                                                                        $   15,000.00   $            15,000
  Relocate Existing Furniture    100,035 SF                                                                                         $        1.00   $           100,035
  Relocate Existing Technology   100,035 SF                                                                                         $        1.00   $           100,035
  Protect New Work                      1 LS                                                   $      49,948.00                                     $            49,948
  Protect Existing Facility      100,035 SF                        0.56                   0.21 $           0.56                                     $           132,711
TOTAL                                                                                                                                               $           567,740




                                                                   1 of 1
  Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                         1/23/2025
Athletics
General Conditions Estimate
                                              Qty           Unit       Labor        Labor Burden         Material          Equipment         Sub           Total
Project Team                                           1 LS        $      145,505 $         53,694                                                    $            199,199
  Assistant Project Manager (100%)                    30 Weeks                                                                                        $                -
  Project Engineer (100%)                            12 Weeks                                                                                         $                -
  Project Engineer (100%)                            12 Weeks                                                                                         $                -
  Project Coordinator (100%)                          12 Weeks                                                                                        $                -
  Assistant Superintendent (100%)                    17 Weeks                                                                                         $                -
  Assistant Superintendent (100%)                    13 Weeks                                                                                         $                -
  Purchasing Agent (100%)                              5 Weeks     $        1,920 $           709                                                     $             13,143
  Project Secretary (100%)                            12 Weeks     $          720 $           266                                                     $             11,828
  Project Accountant (100%)                           12 Weeks     $        1,750 $           646                                                     $             28,749
  Travel & Entertainment                            -    Months                                      $           270
  Supervision Vehicles                              -    Months                                      $         1,790                                  $                -
  Superintendent Vehicle Fuel & Repair              -    Months                                      $         4,600                                  $                -
  Superintendent Vehicle Insurance                  -    Months                                                        $        562.50                $                -

  Safety Program & Inspections                      -   LS                                         $          16,200                                  $                -
  Safety Signage                                    -   LS         $        5,000 $          1,845 $          15,000                                  $                -
  Drug Testing                                      -   LS                                         $           1,080                                  $                -
  Hard Hats & Safety Vests                          -   LS                                         $           6,000                                  $                -
  Raingear & Boots                                  -   LS                                         $           1,500                                  $                -
  Eye & Ear Protection                              -   LS                                         $           1,500                                  $                -
  Safety Harnesses and Lifelines                    -   LS                                         $           1,735                                  $                -
  First Aid Supplies                                -   Months                                     $             108                                  $                -

  Office Trailer Rental                             -   Months                                       $         4,620                                  $                -
  Tool Trailer Rental                               -   Months                                       $           500                                  $                -
  Office Equipment                                  -   LS                                           $           650                                  $                -
  Computer Equipment                                -   LS                                           $        15,000                                  $                -
  Project Software - Procore                        -   Months                                       $       299,986                                  $                -
  Office Supplies & Postage                         -   Months                                       $           300                                  $                -
  Office Furniture                                  -   LS                                           $        15,000                                  $                -

  Drawings & Printing                               -   LS                                           $        10,000                                   $               -
  CAD Files                                         -   LS                                           $         5,000                                   $               -
  Web Cam - OxBlue                                  -   Months                                                                           $    1,500.00 $               -
  Daily Photos - Cupix                              -   Months                                       $           755                                   $               -
  Aerial Photograghy                                -   Months                                       $           500                                   $               -
  Closeout Documents & As-Builts                    -   LS                                           $         9,200                                   $               -




                                                                             1 of 2
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                           1/23/2025
Athletics
General Conditions Estimate
                                             Qty            Unit       Labor                 Labor Burden       Material       Equipment       Sub           Total
  Traffic Control/Flagman                          -     Weeks     $           2,220     $              819                                             $                -
  Setup & Remove Field Office                      -     LS        $           4,183     $            1,544 $        14,202                             $                -
  Setup & Remove Tool Trailer                      -     LS        $             750     $              277 $         1,703                             $                -
  Project Signs                                    -     LS        $           2,500     $              923 $         4,860                             $                -
  Radios                                           -     LS                                                 $         6,500                             $                -

  Temp/Permanent Power & Gas                       -     Months                                                                                          $               -
  Temporary Power                                  -     Months                                                                            $    1,620.00 $               -
  Temporary Power Setup (Georgia Power)            -     LS                                                $         25,000                              $               -
  Temporary Heat                                   -     Months                                            $         15,000                              $               -
  Temporary Water                                  -     Months                                                                                          $               -
  Holding Tank                                     -     Months                                            $            378                              $               -
  Temporary Toilets                                -     Months                                            $          2,000                              $               -
  Sanitary Supplies                                -     Months                                            $            159                              $               -
  Ice, Cups, and Water                             -     Months                                            $            159                              $               -
  Telecom System & Installation (Internet)         -     LS                                                $            650                              $               -
  Telecom Service (Internet & Cell Phones)         -     Months                                                                            $       1,104 $               -
                                                   -
  Barricades                                       -     LS                                                $         25,000                             $                -

  Ceremonies                                           1 LS                                                $               -                            $                -

TOTAL                                                                                                                                                   $            252,919




                                                                                2 of 2
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                     1/23/2025
Athletics
General Requirements Estimate
                                Qty              Unit       Labor                Labor Burden       Material          Equipment         Sub             Total
  Temporary Fence                 3,114    LF           $           5        $              2   $         15.64                                     $            70,022
  Continuous Cleanup                  26   Weeks        $       1,862        $            687                                                       $            66,277
  Dump Fees                           91   Pulls                                                                                    $         577   $            52,507
  Street Sweeper                    -      Months                                                                 $         1,610                   $               -
  Skid Steer                        -      Months                                                                 $         2,862                   $               -
  Equipment Rental                     2   Months                                                                 $         2,100                   $             4,200
  Fuel & Lubricant                     2   Months                                                                 $           248                   $               496
  Small Tools                          2   Months                                                                 $         1,000                   $             2,000

TOTAL                                                                                                                                               $           195,502




                                                                    1 of 1
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                        1/23/2025
Gym Renovation
General Conditions Estimate
                                             Qty           Unit       Labor        Labor Burden         Material          Equipment         Sub           Total
Project Team                                          1 LS        $      163,603 $         60,372                                                    $            223,975
  Assistant Project Manager (100%)                   26 Weeks                                                                                        $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Engineer (100%)                           12 Weeks                                                                                         $                -
  Project Coordinator (100%)                         12 Weeks                                                                                        $                -
  Assistant Superintendent (100%)                   26 Weeks                                                                                         $                -
  Field Engineer (100%)                             24 Weeks                                                                                         $                -
  Purchasing Agent (100%)                           10 Weeks      $        1,920 $           709                                                     $             26,285
  Project Secretary (100%)                           12 Weeks     $          720 $           266                                                     $             11,828
  Project Accountant (100%)                          12 Weeks     $        1,750 $           646                                                     $             28,749
  Travel & Entertainment                           -    Months                                      $           270
  Supervision Vehicles                             -    Months                                      $         1,790                                  $                -
  Superintendent Vehicle Fuel & Repair             -    Months                                      $         4,600                                  $                -
  Superintendent Vehicle Insurance                 -    Months                                                        $        562.50                $                -

  Safety Program & Inspections                     -   LS                                         $          16,200                                  $                -
  Safety Signage                                   -   LS         $        5,000 $          1,845 $          15,000                                  $                -
  Drug Testing                                     -   LS                                         $           1,080                                  $                -
  Hard Hats & Safety Vests                         -   LS                                         $           6,000                                  $                -
  Raingear & Boots                                 -   LS                                         $           1,500                                  $                -
  Eye & Ear Protection                             -   LS                                         $           1,500                                  $                -
  Safety Harnesses and Lifelines                   -   LS                                         $           1,735                                  $                -
  First Aid Supplies                               -   Months                                     $             108                                  $                -

  Office Trailer Rental                            -   Months                                       $         4,620                                  $                -
  Tool Trailer Rental                              -   Months                                       $           500                                  $                -
  Office Equipment                                 -   LS                                           $           650                                  $                -
  Computer Equipment                               -   LS                                           $        15,000                                  $                -
  Project Software - Procore                       -   Months                                       $       299,986                                  $                -
  Office Supplies & Postage                        -   Months                                       $           300                                  $                -
  Office Furniture                                 -   LS                                           $        15,000                                  $                -

  Drawings & Printing                              -   LS                                           $        10,000                                   $               -
  CAD Files                                        -   LS                                           $         5,000                                   $               -
  Web Cam - OxBlue                                 -   Months                                                                           $    1,500.00 $               -
  Daily Photos - Cupix                             -   Months                                       $           755                                   $               -
  Aerial Photograghy                               -   Months                                       $           500                                   $               -
  Closeout Documents & As-Builts                   -   LS                                           $         9,200                                   $               -




                                                                            1 of 2
Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                           1/23/2025
Gym Renovation
General Conditions Estimate
                                             Qty          Unit       Labor                 Labor Burden         Material       Equipment       Sub           Total
  Traffic Control/Flagman                          -   Weeks     $           2,220     $              819                                               $                -
  Setup & Remove Field Office                      -   LS        $           4,183     $            1,544   $        14,202                             $                -
  Setup & Remove Tool Trailer                      -   LS        $             750     $              277   $         1,703                             $                -
  Temporary Ladders                                -   EA        $             200     $               74   $           535                             $                -
  Project Signs                                    -   LS        $           2,500     $              923   $         4,860                             $                -
  Radios                                           -   LS                                                   $         6,500                             $                -

  Temp/Permanent Power & Gas                       -   Months                                                                                            $               -
  Temporary Power                                  -   Months                                                                              $    1,620.00 $               -
  Temporary Power Setup (Georgia Power)            -   LS                                                   $        25,000                              $               -
  Temporary Heat                                   -   Months                                               $        15,000                              $               -
  Temporary Water                                  -   Months                                                                                            $               -
  Holding Tank                                     -   Months                                               $           378                              $               -
  Temporary Toilets                                -   Months                                               $         2,000                              $               -
  Sanitary Supplies                                -   Months                                               $           159                              $               -
  Ice, Cups, and Water                             -   Months                                               $           159                              $               -
  Telecom System & Installation (Internet)         -   LS                                                   $           650                              $               -
  Telecom Service (Internet & Cell Phones)         -   Months                                                                              $       1,104 $               -

  Barricades                                       -   LS                                                   $        25,000                             $                -

  Ceremonies                                       -   LS                                                   $              -                            $                -

TOTAL                                                                                                                                                   $            290,838




                                                                              2 of 2
 Attachment 5 - List of Itemized General Conditions




Cross Keys High School                                                                                                                                   1/23/2025
Gym Renovation
General Requirements Estimate
                                 Qty           Unit       Labor                Labor Burden       Material          Equipment         Sub             Total
  Fire Extinguishers                   8 EA                                                   $          100                                      $               839
  Temporary Fence                   -    LF           $           5        $              2   $          6.24                                     $               -
  Continuous Cleanup                  26 Weeks        $       1,862        $            687                                                       $            66,294
  Dump Fees                           54 Pulls                                                                                    $         577   $            31,365
  Street Sweeper                    -    Months                                                                 $         1,610                   $               -
  Skid Steer                        -    Months                                                                 $         2,862                   $               -
  Equipment Rental                  -    Months                                                                 $         2,100                   $               -
  Fuel & Lubricant                  -    Months                                                                 $           250                   $               -
  Small Tools                       -    Months                                                                 $         1,000                   $               -
  Cupix                                1 LS                                                                                       $   15,000.00   $            15,000
  Relocate Existing Furniture    43,621 SF                                                                                        $           1   $            43,621
  Relocate Existing Technology   43,621 SF                                                                                        $           1   $            43,621
  Protect New Work                     1 LS                                                   $     14,978.00                                     $            14,978
  Protect Existing Facility      43,621 SF                        0.56                   0.21 $          0.56                                     $            57,870
TOTAL                                                                                                                                             $           273,588




                                                                  1 of 1