v. E-SPLOST V Project ~ Final Guaranteed Maximum Price (GMP), Budget Reallocation, and Amendment Request ~ #21435 ~ Cross Keys High School New Addition and Modernization ~ Evergreen Construction Company and Cooper Carry, Inc. ~ Final GMP Approval, Budget Reallocation, and Amendment No. 8-A/E Fee Adjustment (Not to exceed –$148,421,607) ~ Updated 3.3.2025

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School District Board of Education (“the Board”) approve the below:


Approve the established Guaranteed Maximum Price (“GMP”) of $143,484,535 for the construction of the Cross Keys High School New Addition and Modernization E-SPLOST V project per the terms set forth in the Construction Manager at Risk (“CM@Risk”) contract previously awarded to Evergreen Construction Company (General Contractor- “GC”).
It is also requested to approve a Budget Reallocation of $99,065,458 from E-SPLOST V program contingency to fund this project.
It is further requested that the Board approve Amendment No. 08 to Cooper Carry, Inc. (Architectural & Engineering - “A/E”) in a Not -to-Exceed amount of $4,937,072 for added design services.
Why: Approval of the Guaranteed Maximum Price (GMP) of $143,484,535 and budget reallocation of $99,065,458 for the construction of the Cross Keys High School New Addition and Modernization E-SPLOST V project as per the CM@Risk contract approved by the Board, May 6, 2024, to Evergreen Construction Company ensures the completion of this project supporting a safe and healthy teaching and learning environment for students and staff.

Approval of Amendment No. 8 to amend the agreement with Cooper Carry, Inc. in the amount of $4,937,072 for the Addition and Modernization of Cross Keys High School project will provide the necessary funds for the revised scope of work and additional design and engineering fee outlined in the Proposal for Additional Services documents.

Approval of the Final Guaranteed Maximum Price (GMP), budget reallocation, and Amendment No. 08 meets Strategic Goal Area 6: Organizational Excellence
Details: On November 5, 2018, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Evergreen Construction Company for the completion of the Addition and Modernization of Cross Keys High School project and for Pre-Construction Services in the amount of $90,000.00.

On May 6, 2024, the Board approved the Component Guaranteed Maximum Price #01 Early Release Package of $44,419,077 for enabling work associated with the construction of the Addition and Modernization of Cross Keys High School SPLOST V project.

Pursuant to that agreement, the Design Professional (Cooper Carry), CM@R (Evergreen), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and a Final GMP in the best interest of the DeKalb County School District (“DCSD”).

This action establishes a Final Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached -Cross Keys HS Exhibit M - GMP Amendment document.
Financial impact: Amendment No. 8 for Cooper Carry, Inc will be funded by the Architect cost code of Project 21435 - SPFACCON.21435.ARCHITECT

The total contract amount for the Final GMP -Addition and Modernization of Cross Keys High School project in the amount of $143,484,535 will be allocated as follows:


$44,419,077.00 - previously funded - Initial GMP approved by the Board (5/6/2024)



$24,490,923.00 - Existing budget in E-SPLOST V Project 21435 cost code (SP5FACCON.21435.GENCONTR)



$39,000,000.00 - New budget added to E-SPLOST V program for E-SPLOST V Project 21435 cost code (SP5FACCON.21435.GENCONTR)



$35,574,535.00 - New budget added to E-SPLOST VI program for E-SPLOST VI Project 40736 cost code (SP5FACCON.21435.GENCONTR)


under the voter-approved E-SPLOST V program. The Final GMP will require a budget reallocation of $99,065,458.00 from E-SPLOST V program contingency to fund this project.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval and Fully Executed Documents
21435. Cross     Construction of Addition and Modernization (Extensive Renovation)   Final GMP Proposal
                                                                                                           $143,583,051.00
Keys HS          of Cross Keys HS                                                       January 2025
                   Brief Description of Phase                                                             New Value Pending                      Estimated Date of
     Phase                                               Funding Source               Approved Value                          Final GMP Amount
                            Package                                                                           Approval                            Board Approval

     Pre-
                   Pre-Construction Services                E-SPLOST V                  $90,000.00
 Construction

                  Site work, foundations, bus
                       loop, stormwater
 Early Release                                              E-SPLOST V                $44,419,077.00
                    management, long lead
                       items/equipment


                    CR Addition, Building
     Final        Modernization, Auditorium,             E-SPLOST V/TBD                                    $99,065,458.00     $143,484,535.00       3/10/2025
                     Athletics Upgrade
        Notes

    Approved at
November 2018 Board
     Meeting

Approved at May 2024
   Board Meeting

    80% CD Pricing.
    Allowances for
   baseball/softball
   complex and re-
  roofing of existing
   classroom wings.