Chronology of the Agenda Item International Student Center - REVISED

AID 1753740 · View on Simbli

Agenda Item

iv. E-SPLOST VI Project: Final Guaranteed Maximum Price (GMP) and Amendment Request ~ #50736 ~ International Student Center HVAC Replacement and Renovations Project ~ The Winter Construction Company and Corgan Associates ~ Final GMP Approval and Amendment No. 2 (Not to exceed $26,317,664.52 Collectively) ~ Updated 3.3.2025

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School District Board of Education (“the Board”) approve the below:


Approve the established Final Guaranteed Maximum Price (“GMP”) of $25,677,042, for the construction of the International Student Center HVAC Replacement and Renovations per the terms set forth in the Construction Manager at Risk (“CM@Risk”) contract previously awarded to The Winter Construction Company (General Contractor - “GC”).
Additionally, it is requested that the Board approve Amendment No. 2 to Corgan Associates (Architectural & Engineering - “A/E”) in a Not -to-Exceed amount of $640,622.52, for added design services.
Why: Approval of the Guaranteed Maximum Price (GMP) of $25,677,042 for the construction of the International Student Center HVAC Replacement and Renovations as per the CM@Risk contract approved by the Board February 12, 2024, to The Winter Construction Company ensures the completion of this project supporting a safe and healthy teaching and learning environment for students and staff.

Approval of Amendment No. 2 to amend the agreement with Corgan Associates for the amount of $640,622.52 for the International Student Center HVAC Replacement and Renovations Project will provide the necessary funds for the expanded scope of work and additional design and engineering fees outlined in the Proposal for Additional Services documents.

Approval of the Final Guaranteed Maximum Price (GMP) and Amendment No. 08 meets Strategic Goal Area 6: Organizational Excellence
Details: On February 12, 2024, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Winter Construction Company for the completion of the International Student Center HVAC Replacement and Renovations Project and for Pre-Construction Services in the amount of $50,000.00.

On February 12, 2024, the Board of Education approved the award of a Professional Architectural and Engineering Services contract for the design of the International Student Center to Corgan Associates in the amount of $900,000 based on an estimated construction budget of $15,000,000.

Pursuant to that agreement the Design Professional (Corgan), CM@R (Winter), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan, and a GMP in the best interest of the DeKalb County School District.

This action establishes a Final Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached International Student Center - Exhibit M - GMP Amendment document
Financial impact: The total budget of $25,677,042 for the Final GMP for the International Student Center HVAC Replacement and Renovations Project and reimbursable expenses associated with the contract agreement for International Student Center will be allocated from the general construction cost code SP6CIP.50736.GENCONTR.3050 under the voter-approved E-SPLOST VI program.

The total budget of $640,622.52 for Amendment No. 2 GMP for the International Student Center HVAC Replacement and Renovations Project will be allocated from the Architect cost code SP6CIP.50736.ARCHITECT.3050 under the voter-approved E-SPLOST VI program.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations 678-676-1588
Effective: Upon Board Approval and Fully Executed Documents
Status: Approved by the Office of Legal Affairs
                      CHRONOLOGY OF THE AGENDA ITEM
             Final Guaranteed Maximum and Amendment Request
       International Student Center HVAC Replacement and Renovations
           The Winter Construction Company and Corgan Associates
            Final GMP and Amendment No. 2 – A/E Fee Adjustment


Scope:
Approval of the Guaranteed Maximum Price (GMP) for the previously awarded
Construction Management at Risk (CM@Risk) contract to The Winter
Construction Company.

Additionally, approval of the Amendment No. 2, Architectural & Engineering (A/E)
fee increase to Corgan Associates for additional scope and added design services.

Specific details regarding the scope supporting the above approvals can be found in
the following documents:

   •   International Student Center - Exhibit M – GMP Amendment document
       to The Winter Construction Company
   •   ISC Corgan Amendment 02 Submittal

Background
After the December 22, 2021, approval of the 2022-2027 E-SPLOST VI referendum
by DeKalb voters, the Dekalb County School District Board (“the Board”) approved
an initial E-SPLOST VI list of projects on February 1, 2023, that included the
replacement of major building systems at various schools throughout Dekalb
County School District.

A formal Request for Qualifications (“RFQu”) was issued on October 5, 2023, for a
CM@Risk contract for the International Student Center HVAC Replacement
and Renovations. On February 12, 2024, the Board approved the award of a
Construction Management at Risk (CM@R) contract to Winter Construction
Company for the completion of the International Student Center HVAC Replacement
and Renovations and for Pre-Construction Services in the amount of $50,000.00.

This agenda item seeks the establishment and approval of the Guaranteed Maximum
Price. The approval serves to provide adequate funding allowing Winter Construction
Company to perform the general contracting work and completion of the project as
outlined by the proposal documents.

A formal Request for Qualifications (“RFQu”) was issued on October 5, 2023, for a
lump sum design contract for Professional Architectural and Engineering
Services contract for the design of the International Student Center HVAC
Replacement and Renovations. Project. On February 12, 2024, the Board
approved the award of a Professional Architectural and Engineering Services
contract for the design of the Ashford Park ES HVAC Replacement and Renovations
Project to Corgan Associates in the amount of $900,000 based on an estimated
construction budget of $15,000,000. This fee was based on 6% of the stated cost
limitation (SCL) of $15,000,000.

The fee adjustment is to allow Corgan Associates, to address additional scope and
added design services during the construction phase as outlined by the proposal
documents.

The approval of Amendment No. 2 is for a fee increase in line with the increased
project cost and increased project duration due to construction phasing of the
International Student Center.

These approvals will allow completion of the International Student Center HVAC
Replacement and Renovations Project and provide the staff and students a safe
and ideal environment for teaching and learning.