iv. E-SPLOST V Project ~ Modification and Budget Reallocation Request~ Mobile Modular Management Corporation ~ Modular Classroom Lease Extension at Fairington Elementary ~ October 2023 Board Agenda Item Modification and Budget Reallocation (Not to exceed $138,529) ~ Updated 12.3.2024
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School Board of Education (“the Board”) approve the below:
Approve the Modification of the October 2023 Agenda Item to include a total amount for the month-to-month lease of the portable classroom units at Fairington Elementary School.
Approve a Budget Reallocation from Program Contingency to the necessary project cost code (SP5FACCON.36135.PRECONST) for Fairington Elementary School Major Building System Replacement in the amount not- to- exceed $138,529.
Approval of the Modification and Budget reallocation from Program Contingency meets Strategic Goal Area 6: Organizational Excellence
Why: Approval of the modification of the October 2023 Agenda Item and a budget reallocation from Program Contingency provides the necessary funds for removal of the portable classroom units and the payment of the monthly lease extension payments.
Details: The modular buildings accommodate temporary classroom needs at Fairington Elementary during the E-SPLOST V Major Building System Replacement project. The reallocated funds will cover the expenses for monthly lease payments and removing the modular units.
Mobile Modular Costs
Monthly Lease for 5 Months $130,480
Cleaning and Removal Fee $ 8,049
Total Budget for Mobile Modular $138,529
Financial impact: The total budget reallocation of $138,529 from E-SPLOST V Program Contingency will be transferred to the pre-construction cost code (SP5FACCON.36135.PRECONST) under the voter-approved E-SPLOST V program for the Fairington Elementary School Major Building System Replacement project.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Richard Boyd, Director of Design and Construction, Division of Operations, 678-676-1483
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
BOARD AGENDA ITEM
MEETING DATE: December 9, 2024
AGENDA ITEM TITLE: E-SPLOST V Project -Modification and Budget
Reallocation Request- Mobile Modular Management Corporation-
Modular Classroom Lease Extension at Fairington Elementary
School- October 2023 Board Agenda Item Modification and Budget
Reallocation - Not to Exceed - $138,529.00
QUICK SUMMARY ABSTRACT:
Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Operations
Division
REQUESTED ACTION:
It is requested that the Dekalb County School Board of Education (“the Board”)
approve the below:
• Approve the Modification of the October 2023 Agenda Item to include a total
amount for the month-to-month lease of the portable classroom units at
Fairington Elementary School.
• Approve a Budget Reallocation from Program Contingency to the necessary
project cost code (SP5FACCON.36135.PRECONST) for Fairington
Elementary School Major Building System Replacement in the amount
not- to- exceed $138,529.00
Approval of the Modification and Budget reallocation from Program Contingency
meets Strategic Goal Area 6: Organizational Excellence
RATIONALE:
Approval of the modification of the October 2023 Agenda Item and a budget
reallocation from Program Contingency provides the necessary funds for removal of
the portable classroom units and the payment of the monthly lease extension
payments.
DETAILS:
The modular buildings accommodate temporary classroom needs at Fairington
Elementary during the E-SPLOST V Major Building System Replacement project. The
reallocated funds will cover the expenses for monthly lease payments and removing
the modular units.
Mobile Modular Costs
Monthly Lease for 5 Months $130,480.00
Cleaning and Removal Fee $ 8,049.00
Total Budget for Mobile Modular $138,529.00
SUMMARY:
The approval of the Modification to the previously approved October 2023 Board
Agenda Item and Budget Reallocation for the modular classroom buildings at
REVISED 07.2019
BOARD AGENDA ITEM
Fairington Elementary School becomes effective upon board approval and fully
executed contract documents.
Specific details related to the Modification of the original lease amount can be viewed
in the Lease Extension Addendum document.
The approval of the Modification to the October 2023 Board Agenda Item and
Budget Reallocation to support completion of the Fairington Elementary School
project meets COGNIA Standard 4: Resources and Support Systems
FINANCIAL IMPACT:
The total budget reallocation of $138,529.00 from E-SPLOST V Program
Contingency will be transferred to the pre-construction cost code
(SP5FACCON.36135.PRECONST) under the voter-approved E-SPLOST V program
for the Fairington Elementary School Major Building System Replacement
project.
CONTACTS:
Mr. Erick Hofstetter, Chief Operating Officer, 678-676-1447
Mr. Richard Boyd, Director of Design and Construction, 678-676-1483
SUPPORTING DOCUMENTS:
1. Mobile Modular Management Member Specific Agreement
2. Mobile Modular Lease Extension Addendum
3. Lease Terms and Conditions
4. Change Order Log
5. Budget Reallocation Worksheet
6. Review and Approval Form
7. Chronology of the Agenda Item
GOALS:
Strategic Goal Area 6. Organizational Excellence
COGNIA STANDARDS:
Standard 4: Resources and Support Systems
STATUS:
• Approved by the Office of Legal Affairs
IMPLEMENTATION DATE:
Upon Board Approval and fully executed contract documents.