Agenda Item
ii. E-SPLOST V Project ~ Guaranteed Maximum Price, Budget Reallocation, and Amendment Request ~ #35235 ~Toney Elementary School HVAC Systems Replacement and Renovations ~ Ajax Building Company, LLC and Croft & Associates, Inc. ~ Final GMP Approval, Budget Reallocation, and Amendment No. 2 -A/E Fee Adjustment (Not to exceed ~ Collectively ~$9,284,971.50)
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School Board of Education (“the Board”) approve the below:
Approve the established Guaranteed Maximum Price (“GMP”) of $7,335,874 for the construction of the Toney Elementary School HVAC Systems Replacement and Renovations E-SPLOST V project per the terms set forth in the Construction Manager at Risk (“CM@Risk”) contract previously awarded to Ajax Building Company, LLC.
It is also requested to approve a Budget Reallocation of $1,784,124 from E-SPLOST V program contingency to fund this project.
It is further requested that the Board of Education approve Amendment No. 02 to Croft & Associates, Inc. in a Not -to-Exceed amount of $164,973.50 for added design services.
Approval of the Guaranteed Maximum Price (GMP), budget reallocation and Amendment No. 02 meets Strategic Goal Area 6: Organizational Excellence.
Why: Approval of the Guaranteed Maximum Price (GMP) of $7,335,874 and budget reallocation of $1,784,124 for the construction of the Toney Elementary School HVAC Systems Replacement and Renovations E-SPLOST V project project as per the CM@Risk contract approved by the Board, February 12, 2024, to Ajax Building Company, LLC, ensures the completion of this project supporting a safe and healthy teaching and learning environment for students and staff.
Approval of Amendment No. 2 to amend the agreement with Croft & Associates, Inc. in the amount of $164,973.50, will provide the necessary funds for the additional scope and construction administration services (“CA”) as outlined in the Fee Adjustment document (s).
Details: On February 12, 2024, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Ajax Building Company, LLC for the completion of the Toney ES HVAC Systems Replacement and Renovations and for Pre-Construction Services in the amount of $50,000.
On May 9, 2022, the Board approved the award of a Professional Architectural and Engineering (A/E) Services contract for the design of the Toney ES Major Building System Replacement to Croft & Associates, Inc. in the amount of $294,346.50.
Pursuant to that agreement, the Design Professional (CROFT), CM@R (Ajax), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan, and a GMP in the best interest of the DeKalb County School District.
This action establishes a Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached Toney ES GMP Amendment 10-16-24.
Financial impact: The total contract amount for the Toney Elementary School HVAC Systems Replacement and Renovations project in the amount of $7,335,874 will be allocated from the general contractor construction cost code SP5FACCON.35235.GENCONTR under the voter-approved E-SPLOST V program and will require a budget reallocation of $1,784,124 from E-SPLOST V program contingency to fund this project.
The total contract amount for the Toney Elementary School HVAC Systems Replacement and Renovations project in the amount of $498,020 will be allocated from the Architect cost code SP5FACCON.35235.ARCHITECT under the voter approved E-SPLOST V program.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
Board Agenda Item
MEETING DATE: December 9, 2024
AGENDA ITEM TITLE: E-SPLOST V Project – Guaranteed Maximum Price,
Budget Reallocation, and Amendment Request-#35235- Toney Elementary
School HVAC Systems Replacement and Renovations – Ajax Building
Company, LLC and Croft & Associates, Inc. - Final GMP Approval, Budget
Reallocation, and Amendment No. 2 -A/E Fee Adjustment – Not to Exceed –
Respectively -$7,335,874.00, 1,784,124, $164,973.50.
QUICK SUMMARY ABSTRACT:
Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Operations
Division
REQUESTED ACTION:
It is requested that the Dekalb County School Board of Education (“the Board”)
approve the below:
• Approve the established Guaranteed Maximum Price (“GMP”) of $7,335,874
for the construction of the Toney Elementary School HVAC Systems
Replacement and Renovations E-SPLOST V project per the terms set forth
in the Construction Manager at Risk (“CM@Risk”) contract previously awarded
to Ajax Building Company, LLC.
• It is also requested to approve a Budget Reallocation of $1,784,124 from E-
SPLOST V program contingency to fund this project.
• It is further requested that the Board of Education approve Amendment No.
02 to Croft & Associates, Inc. in a Not -to-Exceed amount of $164,973.50
for added design services.
Approval of the Guaranteed Maximum Price (GMP), budget reallocation and
Amendment No. 02 meets Strategic Goal Area 6: Organizational Excellence
RATIONALE:
Approval of the Guaranteed Maximum Price (GMP) of $7,335,874 and budget
reallocation of $1,784,124 for the construction of the Toney Elementary School
HVAC Systems Replacement and Renovations E-SPLOST V project project as
per the CM@Risk contract approved by the Board, February 12, 2024, to Ajax
Building Company, LLC, ensures the completion of this project supporting a safe
and healthy teaching and learning environment for students and staff.
Approval of Amendment No. 2 to amend the agreement with Croft & Associates,
Inc. in the amount of $164,973.50, will provide the necessary funds for the
additional scope and construction administration services (“CA”) as outlined in the
Fee Adjustment document (s).
REVISED 09.2020
Board Agenda Item
DETAILS:
On February 12, 2024, the Board of Education approved the award of a Construction
Management at Risk (CM@R) contract to Ajax Building Company, LLC for the
completion of the Toney ES HVAC Systems Replacement and Renovations and for
Pre-Construction Services in the amount of $50,000.00.
On May 9, 2022, the Board approved the award of a Professional Architectural and
Engineering (A/E) Services contract for the design of the Toney ES Major Building
System Replacement to Croft & Associates, Inc. in the amount of $294,346.50.
Pursuant to that agreement the Design Professional (CROFT), CM@R (Ajax),
Program Manager (ACERM), multiple DCSD Departments and DCSD
Operations have collaborated to generate a design, a safe construction
phasing plan, and a GMP in the best interest of the DeKalb County School
District.
This action establishes a Guaranteed Maximum Price and Contract Time for all the
Work set forth in the attached Toney ES GMP Amendment 10-16-24.
SUMMARY:
The Guaranteed Maximum Price and Amendment No. 2 approvals become
effective upon Board approval and fully executed contract documents.
Specific details related to the establishment of the Guaranteed Maximum Price of
the project requested can viewed in Exhibit M of the CM@Risk Contract for Ajax
Building Company, LLC.
Specific details related to the additional scope and fee increase of the
Architectural & Engineering Services can be reviewed in the Fee Reconciliation
document submitted by Croft & Associates.
The approval of the Guaranteed Maximum Price (GMP), Budget Reallocation, and
Amendment No. 02 meets COGNIA Standard 5: Using Results for Continuous
Improvement.
FINANCIAL IMPACT:
The total contract amount for the Toney Elementary School HVAC Systems
Replacement and Renovations project in the amount of $7,335,874.00 will be
allocated from the general contractor construction cost code
SP5FACCON.35235.GENCONTR under the voter-approved E-SPLOST V program
and will require a budget reallocation of $1,784,124.00 from E-SPLOST V program
contingency to fund this project.
The total contract amount for the Toney Elementary School HVAC Systems
Replacement and Renovations project in the amount of $498,020.00 will be
allocated from the Architect cost code SP5FACCON.35235.ARCHITECT under the
voter approved E-SPLOST V program.
REVISED 09.2020
Board Agenda Item
CONTACTS:
Mr. Erick Hofstetter, Chief Operating Officer, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, 678-676-1588
SUPPORTING DOCUMENTS:
1. Toney ES GMP Amendment – 10-16-24
2. Chronology of the Agenda Item
GOALS:
Strategic Goal Area 6. Organizational
Excellence
COGNIA STANDARDS:
Standard 5: Using Results for Continuous Improvement
STATUS:
• Approved by the Office of Legal Affairs
IMPLEMENTATION DATE:
Upon Board Approval and a fully executed contract
REVISED 09.2020