Midvale ES - Change Order No 3 & 4 - backup document

AID 1712024 · View on Simbli

Agenda Item

v. E-SPLOST V Project ~ Ratification ~ Evergreen Construction #344-35 for Midvale Elementary School Major Systems Replacement ~ Change Order No. 4 for Owner Requested Items and Unforeseen Conditions (Not to exceed $1,185,031) ~ Updated 11.11.2024

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County Board of Education (“the Board”) approve a Ratification / E-SPLOST V budget reallocation in the amount of $1,185,031 from Program Contingency to the Contractor cost code.

It is also requested that the DeKalb County Board of Education approve Change Order No. 4 to Evergreen Construction for the Midvale Elementary School Major Systems Replacement project in the amount of $1,185,031 which will be funded by the budget reallocation.
Why: Approval of the budget reallocation and Change Order No. 4 will provide additional funds for unforeseen conditions, and Owner (DeKalb County School District - DCSD) requested items as outlined in the Change Order No. 4 documents for the Midvale Elementary School Major Systems Replacement project.

Approval of Change Order No. 4 meets Strategic Goal Area 6: Organizational Excellence
Details: On September 11, 2023, the Board of Education approved the E-SPLOST V budget reallocation of $12,227,935 from Program Contingency to fund the award of RFP 23-752-022 for General Contractor Services to Evergreen Construction. The schools included in the budget reallocation are:


Midvale Elementary School - $5,440,435
Dekalb High School of Technology -South - $6,787,500


Change Order No. 04 for Midvale Elementary School Major Systems Replacement provides for the unforeseen conditions and an approved additional scope of work recommended by the project’s design and construction professionals and/or requested by DCSD Facilities to fulfill program wide initiatives.

Specific details related to the original scope of work for this project can be found on the DCSD solicitation website at https://dekalbschoolsga.ionwave.net/.
Financial impact: The financial impact of Change Order No. 4 for the total amount of $1,185,031, due to the unforeseen conditions and additional scope of the Midvale Elementary School Major Systems Replacement project is a budget reallocation of $1,185,031 from program contingency SP5MANG.60235.PRGCONTIN to the general contractor cost code SP5FACCON.34435.GENCONTR. under the voter-approved E-SPLOST V program.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1447
Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
                                                                                                         Midvale Elementary School
                                                                                                     Change Order No. 3 & 4 - Breakdown


PCO #    Description                                                                                     Cost          Unforeseen Condition     AHJ Revisions Design Revisions Owner Request   Allowance     Change Order #3 Change Order #4
3R1      Issued for Construction Documents, Received on 11/8/23                                          $ 88,678                                                               $    88,678                                     $      88,678
6        Abatement Unit Rates Associated with ACM Reports Provided by DCSD                               $     -              $0.00                                                                          $           -
8        RFI #015 - Enlarged Toilet Plans                                                                $     983                                            $           983                                $           983
9        RFI #016 - P3, P4, P5, & P6 Motor Configuration                                                 $   4,462                                            $         4,462                                $         4,462
10R1     ASI #01, dated 3 15 24, Elevator Shaft and Clinic Revisions                                     $ 48,617                                             $        48,617                                                   $      48,617
11       RFI #18 - Toilet Accessories: Paper Towel Dispensers                                            $  (1,609)                                                             $    (1,609)                 $        (1,609)
12A      RFI #25 - Flooring: Stair Tread Selection                                                       $   3,241                                            $         3,241                                $         3,241
13       Submittal 08-71 00-03 - Door Hardware - New Hardware in lieu to Existing to Remain              $ 32,093                                                               $    32,093                                     $      32,093
14       Furnish and Install New Kiln                                                                    $   5,331                                                              $     5,331                                     $       5,331
15       ICN Low Voltage (WAPS, Access Controls, & Security Systems) Safe-Off as Requested by DCSD       $ 15,368                                                               $    15,368                                     $      15,368
16       Reconciliation of Relocation & Cleaning Allowance                                               $    (219)                                                                            $199,781.00 $            (219)
17       Reconciliation of Permit Review Comments and Fire, Life Safety Allowance                        $  (1,834)                                                                             $48,166.00 $          (1,834)
18       Schedule Impacts Associated with Early Access                                                   $ 536,705 $                  536,705                                                                                   $    536,705
19       Abatement of Asbestos Containing Materials                                                      $ 179,674 $                  179,674                                                                                   $    179,674
20       RFI #034 - Fencing Wind Screen                                                                  $     999                                                              $       999                  $           999
21       RFI #013 - New Penetration for Relief Duct                                                      $ 16,224 $                    16,224                                                                                   $      16,224
22       RFI #035 - Existing Sewer Line Conflict with Elevator Pit                                       $   9,081 $                    9,081                                                                                   $       9,081
23R1     Replace Roof Drains Conflicting with HVAC and Insulate for Code Compliance                      $   8,138 $                    8,138                                                                $         8,138
25       Adjustment to Wheelchair Lift Placement and Heights due to Existing Conditions                  $   9,417 $                    9,417                                                                $         9,417
026      Foundation for CMU Wall In Lower Level Stairwell                                                $   5,214 $                    5,214                                                                $         5,214
29       Raise Existing RTU Curbs to Accommodate New Roof Insulation Thickness                           $ 76,936 $                    76,936                                                                                   $      76,936
30       Service Existing RTU's to Ensure Proper Functionality                                           $   9,081                                                              $     9,081                  $         9,081
31       Clinic Countertop and Sink Revisions as Requsted by DCSD on 7/10/24                             $   8,530                                                              $     8,530                  $         8,530
33       Low Voltage, Security and Access Control Cabling to Gym                                         $ 20,548 $                    20,548                                                                                   $      20,548
34       Replace Kitchen ACT Tile with Wipeable Tile (see punchlist)                                     $   7,132                                            $         7,132                                $         7,132
35       FAID Elevator Access Cage for Code Compliance                                                   $   1,060                              $     1,060                                                  $         1,060
36       Fire Alarm Revisions due to Existing Conditions                                                 $ 42,411 $                    42,411                                                                                   $      42,411
37       Additional Floor Tile In Room 133.6                                                             $   2,469 $                    2,469                                                                $         2,469
38       New Doors and Frames at Special Ed Classrooms and Klin Room                                     $ 23,390 $                    23,390                                                                                   $      23,390
39       RFI #038 Kiln Electrical Requirements Clarification                                             $ 25,140                                                               $    25,140                                     $      25,140
40       New Sidewalk for Safe Means of Egress for Students Per FM Request on 7/18/24                    $   7,529                              $     7,529                                                                     $       7,529
42       Repair Existing Plumbing Fixtures in Principals RR                                              $   1,513                                                                                           $         1,513
43       Relocate GFI's in Special Ed Classrooms                                                         $   1,865 $                    1,865                                                                $         1,865
44       Relocate Power for Trash Compactor                                                              $   1,748 $                    1,748                                                                $         1,748
45       Replace Water Closets in Pre-K Classrooms with Kiddie Size                                      $   5,243                                                              $     5,243                  $         5,243
46.1     Teacher Lounge Countertops, Sinks, & Outlet Revisions as Requested by DCSD                      $ 24,019                                                               $    24,019                                     $      24,019
47       Furnish and Install Quarry Tile in Existing Kitchen Locker and Kiln Room 124.1                  $   8,116                                            $         8,116                                                   $       8,116
48       RFI #029 - Wheelchair Lift Power Requirements                                                   $   1,340 $                    1,340                                                                $         1,340
49       AHJ Life Safety Requirements for Boiler and Hot Water Heaters                                   $   3,741                              $     3,741                                                  $           -   $          3,741
50       Unforeseen Chase and Toilet Demolition                                                          $   4,855 $                    4,855                                                                $         4,855
51       Repair Existing Ductwork in Room 112                                                            $   1,752 $                    1,752                                                                                $          1,752
53       Wheelchair Lift Guardrail Structural Revisions                                                  $   1,216 $                    1,216                                                                $         1,216
54       Revisions to Clinic Door Swings                                                                 $   5,289                                                              $     5,289                                  $          5,289
55       Add CMU Chase for HVAC Piping in Boys Restroom 113.1                                            $   2,684                                                              $     2,684                                  $          2,684
56       Cleaning of Existing RTU Grilles                                                                $   6,711 $                    6,711                                                                                $          6,711
58       Lower Level Classroom Door Lite Installation                                                    $   4,994                                                $4,994.00                                                  $          4,994
61       Provide Permanent Power to Monument Sign                                                        $   1,499 $                    1,499                                                                $         1,499 .




Totals                                                                                                   $ 1,261,374       $951,193.00           $12,330.00       $77,545.00    $220,846.00    $247,947.00       $76,343.00     $1,185,031.00   $1,261,374.00   $0.00

NOTES