RFQu 24-752-038 - AE Services for Allgood Elementary School

AID 1709942 · View on Simbli

Agenda Item

ii. E-SPLOST VI Project ~ Contract Award ~ RFQu No. 24-752-038 ~ Professional Architectural and Engineering Services ~ Goodwyn, Mills, Cawood, LLC. ~ Allgood Elementary School ~ HVAC Systems Replacement ~ (Not to exceed $1,200,000)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve the award of RFQu 24-752-038 for Architectural and Engineering Services for Allgood Elementary School HVAC Replacement and Renovations to Goodwyn, Mills, Cawood, LLC., for the lump sum amount of $1,200,000.
Why: To approve the award of a lump sum design contract for Professional Architectural and Engineering Services for Allgood Elementary School HVAC Replacement and Renovations project in accordance with the Dekalb County School District (“DCSD”) voter-approved E-SPLOST VI program, will provide a safe and healthy learning environment.

The approval of this contract award meets Strategic Goal Area 6: Organizational Excellence.
Details: The scope of work for this project includes Architectural Engineering Services for Allgood Elementary School HVAC Replacement and Renovations. Specific details and project information can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/.

The RFQu was issued on July 11, 2024, and sixteen (16) submittals were received on August 15, 2024. All sixteen (16) firms were deemed responsive and evaluated by a selection committee. Seven (7) firms were shortlisted and recommended by the selection committee to be interviewed. Interviews were conducted on September 17, 2024. This recommendation is based on the final scoring of the interview and presentation process.

Goodwyn, Mills, Cawood, LLC. was selected as the most responsive and responsible offeror and will be responsible for the architectural and engineering design work as set forth in the solicitation documents. The DeKalb County School District’s Standard Form of Contract for Architectural Services will be used for this project. Goodwyn, Mills, Cawood, LLC. is located at 6120 Powers Ferry Road NW, Suite 200, Atlanta, GA 30339.
Financial impact: The financial impact of the contract award for the Professional Architectural and Engineering Services for Allgood Elementary HVAC Replacement and Renovations project is $1,200,000 and will be allocated from cost code SP6CIP.20136.ARCHITECT.2050 under the voter-approved E-SPLOST VI program.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676.1447
Mr. Richard Boyd, Director of Design and Construction, Division of Operations, 678.676.1483
Effective: Upon Board Approval
Status: Approved by the Office of Legal Affairs
DeKalb County School District                                                           RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations               Project No. 201-36
July 11, 2024                                                                                   Page 1 of 24

  J                               DeKalb County Board of Education
                                  Operations Division
                                  Sam A. Moss Service Center
                                  1780 Montreal Road
                                  Tucker, GA 30084-6705

                     REQUEST FOR QUALIFICATIONS (RFQu) No. 24-752-038
                                             for
               PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES FOR
                 Allgood Elementary School HVAC Replacement and Renovations

Project:                   ALLGOOD ELEMENTARY SCHOOL HVAC REPLACEMENT AND RENOVATIONS

DCSD Project Nos.:         201-36

Owner:                     DeKalb County Board of Education (the “Board”)

Solicitation Timeline Summary (Subject to Change)
             EVENT                         DATE(S)            TIME                        LOCATION

  Solicitation Opens                     July 11, 2024                         http://dekalbschoolsga.ionwave.net
  Virtual Mandatory Pre-
                                         July 25, 2024      11:00 AM                      Via TEAMS
  Submittal Conference
                                                                                Allgood Elementary School
  Optional Site Visit                   Upon Request          TBA
                                                                        659 Allgood Rd., Stone Mountain GA 30083

  Final Questions Due                    July 31, 2024      2:00 PM         dcsd-op-bidquestion@dekalbschoolsga.org

  Final Addendum                        August 7, 2024      2:00 PM          http://www.dekalbschoolsga.ionwave.net
  Statement of Qualifications
                                       August 15, 2024      2:00 PM           http://dekalbschoolsga.ionwave.net
  Due Date & Time
                                                                               http://dekalbschoolsga.ionwave.net
  Public Acknowledgement                August 19, 2024     5:00 PM

  Selection Committee
                                      August 19-23, 2024
  Evaluation
  Shortlist Finalist Notified                                           Public Notice of Short List will be posted to the
                                             N/A
  (If Interviews are Conducted                                               DCSD website by close of business
  Anticipated Interviews
  Conducted                                  N/A
  (If Requested)
  Anticipated Board Review and
                                      November 11, 2024
  Approval

  Anticipated Notice of Award         November 18, 2024

  Anticipated Notice to Proceed        December 2, 2024
DeKalb County School District                                                           RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations               Project No. 201-36
July 11, 2024                                                                                   Page 2 of 22
                                       Request for Qualifications
               PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES FOR
            ALLGOOD ELEMENTARY SCHOOL HVAC REPLACEMENT AND RENOVATIONS

Qualifications will be received electronically on the DeKalb County School District website at
https://dekalbschoolsga.ionwave.net for ARCHITECTURAL AND ENGINEERING SERVICES FOR
ALLGOOD ELEMENTARY SCHOOL, until 2:00 p.m. EST, Thursday, August 15, 2024. Qualifications
received after the specified time will not be considered. All potential respondents must register as a vendor at
http://dekalbschoolsga.ionwave.net. NOTE: A virtual mandatory pre-submittal conference will be held on
Thursday July 25, 2024, 11:00 a.m., EST, via TEAMS. Attendees must provide the following information by
5:00 p.m., EST on Wednesday, July 24, 2024:

    1.   Individual Name and Title
    2.   Company Name
    3.   Telephone Number
    4.   Email Address

This information must be sent to dcsd-op-solicitation@dekalbschoolsga.org. A meeting link will be sent to all
registered attendees no later than 10:30 a.m., EST on Thursday, July 25, 2024.

This document shall serve to provide interested parties with specific information as to the Procedures for
Selection of Professional Architectural and Engineering Services for the DeKalb County School District.
DeKalb County School District                                                                                         RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                                             Project No. 201-36
July 11, 2024                                                                                                                 Page 3 of 22
 Table of Contents
 Section            Description                                                                                                         Page

                    Request for Qualifications:

 1.0                Project Description ............................................................................................... 6
 2.0                General Scope of Work........................................................................................ 7
 3.0                Requirements ...................................................................................................... 11
 4.0                Statement of Qualifications .................................................................................. 11
 5.0                Initial Screening Criteria ....................................................................................... 13
 6.0                Interview and Presentation................................................................................... 16
 7.0                Selection Process ................................................................................................ 18
 8.0                Schedule .............................................................................................................. 19
 9.0                General Instructions ............................................................................................. 19
 10.0               Terms and Conditions .......................................................................................... 20
 11.0               Protest Process ................................................................................................... 21
                    RFQu Advertisement ........................................................................................... 24

 Attachments (separate file from RFQu)
 Attachment A     A/E Checklist and Certification
 Attachment B1    Corporate Certificate
 Attachment B2    Partnership Certificate
 Attachment B3    Entity Certificate
 Attachment C     Design Fee Form – Allgood Elementary School
 Attachment D     Offeror’s and Individuals’ Affidavit of Non collusion
 Attachment E     Conflict of Interest Disclosure Affidavit
 Attachment F     Consent to Release Information
 Attachment G     Immigration and Security Certification
 Attachment H     No Submittal Response

 Appendices (separate file from RFQu)
 Appendix A      2021 Facility Condition Assessment – Allgood Elementary School
 Appendix B      Design Review-Minimum Submittal Requirements (SCL >$2M)
 Appendix C      DCSD Elementary School Educational Specifications
 Appendix D      DCSD Design Guidelines for Facility Construction
 Appendix E      Aerial Image – Allgood Elementary School
 Appendix F      Floor Plan – Allgood Elementary School
 Appendix G      Owner’s Master Schedule
 Appendix H      Standard Form of Contract for Architectural Services
 Appendix I      Acknowledgement of Conflict-of-Interest Policy and Disclosures
 Appendix J      2023-2024 and 2024-2025 School Calendar

 Exhibits (separate file from RFQu)
 Exhibit A – Proposal Evaluation Form
DeKalb County School District                                                             RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                 Project No. 201-36
July 11, 2024                                                                                     Page 4 of 22
                                 REQUEST FOR QUALIFICATIONS
                   PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES FOR
                        ALLGOOD ES HVAC REPLACEMENT AND RENOVATIONS

BACKGROUND

As the third largest school district in Georgia, the DeKalb County School District (DCSD) has more than 14,000 full-time
employees and serves over 93,000 students throughout DeKalb County. DCSD has approximately 138 schools and centers,
including 77 elementary, 19 middle schools and 22 high schools; 8 start-up charter schools, 13 specialized centers, 6
administrative centers and 5 athletic stadiums. Most facilities were constructed in the 1950’s and 1960’s. Almost all facilities
have had some form of renovation, repair, or addition over the years.

Since 1997, the Owner has utilized Education SPLOST (Special Purpose Local Option Sales Tax) funds as the primary
funding source for its capital improvement programs (CIP). On November 22, 2021, the DeKalb County voters approved the
Owner’s sixth E-SPLOST program. It is anticipated that approximately $700 million will be available to fund the District’s 2022-
2027 Capital Improvement Program through the utilization of the approved SPLOST funds, in conjunction with the State of
Georgia’s Capital Outlay Program.

A copy of the CIP Summary and more detailed information regarding the CIP can be obtained on the District’s website at
www.dekalbschoolsga.org/e-splost/

PURPOSE

The purpose of this RFQu is to solicit proposals from qualified Architect/Engineer firms to provide professional design services.
This solicitation is specifically for the design of a major building system replacement at an elementary school. Final documents
will become the property of DCSD.

The scope of work for this RFQu includes the full professional architectural and engineering services for DCSD Project, 201-
36. The 2021 Comprehensive Facility Assessment Report (Appendix A) is attached as a guide in determining the priority
of needs for the improvements.

The anticipated construction delivery method for this project is CM at Risk. The selected Architect/Engineer shall provide
professional services for the project as described below in Section 2 of this RFQu.


The Stated Cost Limitation (SCL) and estimated construction budget for this project is $20,000,000 DCSD has determined
that the stipulated fee the Architect will receive for this project scope will be 6% of the Stated Cost Limitation for a maximum
fee of $1,200,000. This fee is all inclusive and incorporates all reimbursable expenses for this project and is subject to
adjustments based on the final guaranteed maximum price.

1.0     PROJECT DESCRIPTION

        The Allgood Elementary School campus is located on 10 acres at 659 Allgood Rd., Stone Mountain, GA 30083. The
        original campus construction was completed in 1955, with building additions in 1960, 1963, 1965, and 2000. A
        gymnasium building was constructed in 2000. The current size is approximately 63,989 SF. At a minimum the
        project should meet the DCSD Elementary School Educational Specifications (Appendix C), and the DCSD
        Design Guidelines for Facility Construction, (Appendix D).
DeKalb County School District                                                             RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                 Project No. 201-36
July 11, 2024                                                                                     Page 5 of 22


2.0    GENERAL SCOPE OF WORK
       The anticipated scope of this project is to include but is not limited to the design of the following:

             •   Replacement of HVAC system throughout the building.
             •   Replacement of doors and door hardware throughout the building.
             •   Electrical upgrades
             •   Replacement of ceilings
             •   Window Replacement
             •   Replace light fixtures with LED fixtures
             •   Security Vestibule
             •   Fire Sprinkler System
             •   Roof Replacement
             •   Replace Classroom Casework
             •   Remove Chalkboards
             •   Restroom Renovations
             •   Emergency Generator
             •   Replace Fire Alarm System
             •   Replace Intercom/Clock System
             •   Mechanical and Electrical Room Renovations
             •   Replace Kitchen Equipment
             •   Replace Freezer/Cooler
             •   Kitchen Renovation
             •   Improve Site Storm Drainage
             •   Improve Site Accessibility
             •   Miscellaneous flooring replacement and painting

       This is not intended to be an all‐inclusive list of the scope of work. The selected Architect/Engineer shall confirm and
       obtain DCSD approval of full scope of work prior to the start of design.

       A formal Notice to Proceed (NTP) shall be provided by the Owner or its designated representative prior to proceeding
       with each design milestone. The Architect/Engineer will be responsible for confirming the need for these elements
       and for making recommendations if an element is deemed unnecessary or if a more pressing element is discovered.

       For more details on what is expected of the Architect, see the General Services section below.

       2.1       General Services
                 The following generally highlights the services that the Architect and its subconsultants will be required to
                 perform:
             A. Design Services
                1. Prior to starting Schematic Design, the Architect will perform a preliminary consultation with the Owner
                   including, but not limited to, reviewing the Owner’s policies, concepts, objectives, design criteria,
                   schedule, budget, and operational needs for these projects. The Architect will submit within 10 days of
                   NTP, a written report with their proposed recommendations, solutions to problems, etc.
                 2. The Architect will prepare and submit a Design Schedule that fits within the parameters of Appendix G:
                    Owner’s Master Schedule.
DeKalb County School District                                                               RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                   Project No. 201-36
July 11, 2024                                                                                       Page 6 of 22
               3. The Architect will prepare and submit schematic design documents per the requirements of Appendix
                  B: Design Review- Minimum Submittal Requirements and the Architect’s Detailed Design Schedule.

               4. The Architect will prepare and submit a construction estimate based on the Schematic Design
                  documents. This estimate will be compared with the stated cost limitation (SCL) for this project. If the
                  estimate is more than 5% over the SCL, then the Architect will prepare new schematic design documents
                  and prepare a recovery schedule.

               5. The design scope shall be based upon a construction Stated Cost Limitation (SCL) of $20,000,000.

               6. The Architect will submit documents as outlined below for review by DCSD and the Program Manager.
               7. Once Schematic Design Documents are reviewed and approved and upon written direction to proceed,
                  the Architect will proceed with the 30% Construction Document phase per Appendix B: Design Review-
                  Minimum Submittal Requirements and the Architect’s Detailed Design Schedule.
               8. The process used for Schematic Design Phase as outlined in items #3 – 7 above will be performed for
                  the 80% and 100% CD Phases.
               9. The Architect will submit to DCSD and the Project Manager reports, drawings, specifications, and
                  estimates for review according to the chart below:

                                                         Reports      Drawings       Specifications      Estimates
             Preliminary Consultation                      ✓
             Schematic Design                             ✓             ✓                ✓                ✓
             Design Development Phase                     ✓             ✓                ✓                ✓
             Construction Documents – 30%                 ✓             ✓                ✓                ✓
             Construction Documents – 80%                 ✓             ✓                ✓                ✓
             Construction Documents – 100%                ✓             ✓                ✓                ✓
             Others as required                            ✓              ✓                 ✓                ✓

               This information will be submitted to the GaDOE for review, comment, and approval.

           10. The Architect will visit each school site. All areas of the existing facility will be made available to the Architect,
               and it is expected that the Architect will study these areas to fully understand any and all accessible existing
               conditions. The Architect shall investigate and document any limitations to be resolved during the design
               process.

           11. Coordination with DCSD’s Technology Department is critical during the Design Phase. DCSD’s Technology
               Department will design the Technology components and the Architect/Engineer will incorporate this design
               into the contract documents. The DCSD Technology Department will be responsible for the installation of
               the IT equipment, cabling, and wiring. The General Contractor (GC) will be responsible for the supporting
               infrastructure (conduit, boxes, etc.).

           12. Provide complete construction contract documents with professional seals and signatures in accordance with
               the requirements of the Georgia Department of Education Facilities Services Unit.

           13. Assure that the construction contract documents are in conformance with generally accepted architectural
               and engineering practices and comply fully with all applicable DCSD and GaDOE criteria, along with all
               federal, state, and local codes and laws.
DeKalb County School District                                                           RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations               Project No. 201-36
July 11, 2024                                                                                   Page 7 of 22
           14. Provide full and complete specifications including Division 1- General Conditions, reflecting current DCSD
               and GaDOE requirements. Specify materials and equipment that are readily available, to avoid delivery
               concerns during construction.

           15. Provide phasing plans, as appropriate, for construction. Include submission to and approval by DCSD and
               the Fire Marshal for the phased exiting of the facility.

           16. Provide design for on-site swing space (modular) as appropriate for the improvement activities, i.e. phasing.

           17. Provide design drawings and specifications for demolition of areas, as appropriate.

           18. Provide design drawings and specifications for security system (cameras, alarm, card access, motion
               detectors, recording devices, etc.), and MIS conduit/raceways, as needed. Equipment and cabling design
               and installation will be provided by approved DCSD vendors, as appropriate.

           19. Coordinate entrance design with and obtain approval from the agencies having jurisdiction as appropriate.
               Provide renderings when exterior modifications to the building are made.

           20. Coordinate and design all utility connections (gas, electrical, plumbing, sewer) with local utility provider and
               obtain necessary approvals. Deposits will be paid for by the district. The Architect will coordinate this effort.

           21. Represent DeKalb County School District by presenting necessary oral and/or graphic presentations to state
               and county agencies, or any other group having interest in the projects per the direction of DCSD.

           22. Complete all forms and documents in formats required by GaDOE and any other state or county agency.

           23. Each design phase submittal must include a detailed cost estimate confirming that the cost of the design is
               below the construction SCL for the respective project. Design estimates will be reviewed by the program
               manager. If the estimate shows a cost more than 5% greater than the SCL, the Architect must
               redesign the project to be below the construction SCL at no additional cost to the owner. The
               Architect will also be required to develop a recovery schedule to complete the design in the original
               timeframe.

           24. DCSD has adopted and implemented Kahua’s Project Management Information System (PMIS) software as
               the District’s project management software. All Contractors with a project’s construction value exceeding a
               Stated Cost Limitation of $1 million will be required to use Kahua for that project, and the Architect of Record
               will have to be versed in Kahua in order to review and comment on the contractor’s schedule. For
               construction contracts with values under $1 million, the Architect will be responsible for posting all project
               documents from the GC into Kahua.

           25. The Architect shall also comply with all activities and terms as outlined in the Standard Form of Contract for
               Architectural Services (State Capital Outlay Projects) between the DeKalb County Board of Education and
               the Architect. (See Appendix H).

           26. Provide the selected GC with three (3) copies of the construction contract documents (specifications and
               drawings) at the Preconstruction Conference.

           27. The Architect will develop the list of required shop drawings, product data, samples, etc. and issue it to the
               selected GC. The selected GC will take the list and incorporate it into their project construction schedule.
DeKalb County School District                                                          RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations              Project No. 201-36
July 11, 2024                                                                                  Page 8 of 22
           28. The Architect is responsible for providing and submitting all permit packages to the proper authorities. The
               Architect is responsible for pursuing the issuance of the permits until the permit is ready to be issued to the
               contractor or until the contractor receives a Notice to Proceed (NTP). Once the NTP is received, the Architect
               will hold a formal meeting to transfer the permit responsibilities to the contractor. The Architect is still
               responsible for assisting the contractor and for responding to any questions or issues documented by the
               permitting authorities.

           29. The Architect will update DCSD’s state inventory plans at the end of construction.

           30. The Architect will perform Contact Administration for these projects.
           31. The Architect will provide FF&E services for this project as outlined in the Standard Form of Contract for
               Architectural Services.

       B. Kahua Project Management Information System Software
          DCSD has adopted and implemented Kahua’s Project Management Information System (PMIS) software as the
          District’s project management software. DCSD will issue one license to the successful Architect and expects the
          Architect to participate in the management of these projects within the Kahua guidelines. This management will
          be performed in conjunction with DCSD and the Program Manager. This includes but is not limited to:

           1. General
                 • All project documentation shall be made available to DCSD in a format compatible with industry
                      standards and able to be uploaded and stored electronically in the District’s PMIS software.
                 • All invoicing – architect’s, contractor’s, vendors’, etc. will be recorded in the District’s PMIS software

           2. Schematic Design Phases
                 • All drawings will be posted in Kahua as one package for each phase (one file for SD)
                 • The detailed estimate will be posted in Kahua for each phase
                 • All reports will be posted individually in Kahua
                 • All project documentation (meeting minutes, photographs, etc.) will be posted in Kahua

           3.   Construction Document Submittals (50%, 100%)
                  • All drawings for the 50% CD submittals will be posted in Kahua as one package
                  • The detailed estimate will be posted in Kahua for the 50% submittals
                  • All reports will be posted individually in Kahua
                  • All project documentation (meeting minutes, photographs, etc.) will be posted in Kahua
                  • A detailed estimate is not required at 100% drawings
                  • Each individual drawing will be posted to Kahua (as individual files) at the 100% drawing submittal

           4. Contract Administration
                 • RFIs, Submittals, and Shop Drawings will be documented in Kahua
                 • Samples (color boards, brick, etc.) will be processed outside of Kahua, but will be tracked by a
                      transmittal inside Kahua
                 • Invoices will be recorded in Kahua
DeKalb County School District                                                            RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                Project No. 201-36
July 11, 2024                                                                                    Page 9 of 22
 3.0     REQUIREMENTS

         3.1    Firms must meet the following requirements:
                3.1.1 Requirements of the Request for Qualifications (RFQu).

                3.1.2   It is preferable that the Firm has experience providing A / E services for K-12 public school
                        programs.

                3.1.3   Firm must be authorized to do business in the State of Georgia and must possess professional
                        service registrations in accordance with applicable statutes, regulations, and rules.

                3.1.4   Firms must be knowledgeable of the requirements of Georgia Code.

                3.1.5   Firms must be able to demonstrate financial strength appropriate to the scale of Project to be
                        managed.

                3.1.6   Statements of Qualifications must be submitted electronically to the School District on or before the
                        time and date indicated in the RFQu.

                3.1.7   Statements of Qualifications should be limited to not more than 30 electronic pages. Submissions
                        in excess of 30 electronic pages will not be disqualified; however, clarity, conciseness, and brevity
                        of this document will be part of the evaluation criteria.

                3.1.8   Statements of Qualification which have not been received by the DeKalb County School
                        District on or before the scheduled receipt time as set forth in the RFQu will not be considered.

                3.1.9   The selected firm and its sub consultants will be required to meet the insurance
                        requirements of DCSD.

                3.1.10 Costs of participating in the selection process, including presentations to the Selection
                        Committee, are solely those of the firm; DCSD will assume no responsibility for any costs.

                3.1.11 DCSD reserves the right to waive informalities and to terminate the selection process.

       4.0     STATEMENT OF QUALIFICATIONS
               Required Information and Format

                Statements of Qualifications must provide the required information in the following order and format:

         4.1    Letter of introduction and interest signed by an officer or partner of the responding firm. Letter shall include
                specific reason(s) why firm would be the best choice for the project listed. Letter shall include name of
                entity submitting, contact name, phone number, e-mail address, fax number and address of firm submitting.
         4.2    Table of Contents
         4.3    Compliance Information
                This is a compliance section and carries no evaluation points. Firms must meet minimum criteria as
                specified to receive further consideration. Submittals shall include the following:
                4.3.1   The Firm must be properly certified by the Georgia Secretary of State to do business in Georgia
                        at the time of submission.

                        4.3.1.1 State the legal name of the entity submitting and if Firm submitting is a corporation, joint
DeKalb County School District                                                           RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations               Project No. 201-36
July 11, 2024                                                                                  Page 10 of 22
                                venture, or partnership. Note: It is understood that if selected for this project the stated
                                entity name will be used in all legal contracting documents derived from this selection.

                        4.3.1.2 Provide a copy of certification for proper incorporation or registration from Georgia
                                Secretary of State. In the alternative, joint ventures and partnerships should provide a
                                copy of their joint venture or partnership agreement and certification from the Georgia
                                Secretary of State establishing that each joint venture partner or partner is authorized to
                                do business in Georgia.
                4.3.2   The Firm must be properly registered, licensed, and certified at the time of submission:
                        4.3.2.1 Firms and sub consultants must be property licensed. Provide copy of current Georgia
                                Professional Registration for Architect/Engineer.
                        4.3.2.2 If Firm is a joint venture, provide copy of the joint venture agreement and either:

                                     a. Copy of current Georgia Professional Registration of the joint venture; or

                                     b. A copy of the current Georgia Professional Registration of one of the joint
                                        venture partners.

                4.3.3   The Firm must have been in continuous business for a minimum of five years. Note: If Firm
                        is a joint venture, at least one of the companies comprising the joint venture or partnership
                        must have been in continuous business for a minimum of five years.

                        4.3.3.1 State number of years in business. If the Firm is a joint venture, state both the number
                                of years that the joint venture has been in business, as well as the number of
                                years that each joint venture partners has been in business.

                        4.3.3.2 State the location, address, and telephone number of Firm’s offices. If the
                                Firm is a joint venture or partnership, identify the location, address, and
                                telephone number of the principal place of business of the joint venture or
                                partnership designated with the Georgia Division of Corporations.

                        4.3.3.3 Submit the names of owners, officers or principals in charge.

                4.3.4   The Firm must identify any existing or potential conflicts of interest and disclose any
                        representation of parties or other relationships that might be considered a conflict of interest with
                        regard to this selection. "Conflict" or "conflict of interest" means a situation in which regard for a
                        private interest tends to lead to disregard of a public duty or interest.

                        4.3.4.1 If any conflicts of interest issues are identified, provide a detailed plan of action on how
                                any existing or potential conflicts of interest will be mitigated in the case your firm is
                                recommended for this project. DCSD at its sole discretion shall determine the adequacy
                                of the plan and whether the conflict will disqualify the firm from consideration for the
                                RFQu. If DCSD determines that the firm will be disqualified due to the conflict, the firm’s
                                proposal will not be evaluated or considered by the Selection Committee.

                4.3.5   The Firm must demonstrate they have the necessary financial resources to complete the
                        project and show their history of working proactively to avoid litigation with Owners.

                        4.3.5.1 Financial Statement: The Firm’s financial capability is to be expressed in the financial
                                statement (audited financial current within the past twelve months, such as a balance
                                sheet and statement of operations) and should indicate the resources and the necessary
DeKalb County School District                                                            RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                Project No. 201-36
July 11, 2024                                                                                   Page 11 of 22
                                 working capital to assure financial stability through the completion of the project. A
                                 certified audit is preferred; however, the Firm’s most recent tax return and balance sheet
                                 will be accepted. If the Firm is a joint venture or partnership all firms comprising the
                                 submitting entity will be required to submit the previously requested documentation.

                         4.3.5.2 Insurance Capacity: Firms must provide evidence that they have all insurance
                                 coverage’s as specified in A/E contract included with this RFQu (See Appendix H).

                         4.3.5.3 Litigation: Submit all litigation of any kind involving firm, its officers, or directors with a
                                 project owner where the total amount in controversy exceeds $100,000.00 within the last
                                 five years. If the firm is a joint venture or partnership submit litigation involving all firms
                                 comprising the submitting entity. State the court and location of the litigation.

                         4.3.5.4 Insurance Claims: Submit all Errors & Omissions and/or Professional Liability claims
                                 filed against the firms’ policy in the last two years for the proposal submittal date. The
                                 information should include amount and nature of the claim(s).

      5.0       INITIAL SCREENING CRITERIA

        5.1     Individual Review: Proposal Evaluation Committee (“PEC”) members shall use the Proposal Evaluation
                Form (Exhibit A) for the RFQu to document their review and evaluation of each Proposal in accordance
                with the criteria listed below, within their respective areas of experience and knowledge.

                5.1.1    Successful Related Architectural Experience (30 points):
                               Major consideration will be given to the successful completion of previous projects
                               comparable in design, scope, and complexity. This will include e valuating the firm’s
                               performance and quality of work on previous projects.

                         5.1.1.1 List the projects which best illustrate the experience of the firm which utilized the current
                                  staff which is being assigned to this Project. (List no more than 10 projects and do not list
                                  projects which were not completed by your firm or completed more than ten years
                                  ago). Include the following for each project:

                                          a. Name and location of the project.
                                          b. The nature of the firm's responsibility on the project.
                                          c. Project owner's representative name, address, telephone, and
                                               facsimile number.
                                          d. Project user's representative name, address and
                                               telephone number.
                                          e.   Date project construction was completed.
                                          f.   Size of project (construction gross square feet).
                                          g.   Cost of project (construction cost).
                                          h.   Work for which firm's staff was responsible.
                                          i.   Present status of the project.
                                          j.   Firm's key professionals involved on the project and who of that staff
                                               would be assigned to the Project covered by this RFQu.

                5.1.2    Proposed Project Staff and their Functions (30 points):
                        The quality, experience and quantity of staff and their functions will be evaluated by the
                        Committee. The Committee will also evaluate the firm’s capabilities to provide service.

                         5.1.2.1 Organization Chart: Develop an organization chart as it relates to the Project indicating
                                 key personnel, their relationship, and all consultants to be used on this project.
DeKalb County School District                                                            RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                Project No. 201-36
July 11, 2024                                                                                   Page 12 of 22

                         5.1.2.2 The firm shall name the actual staff to be assigned to this Project, describe their ability,
                                 and experience, and indicate the function of each within their organization and their
                                 proposed role on this Project. It is the intent that the proposed staff shall be
                                 assigned to this Project unless otherwise approved by Owner. The staff shall be
                                 present at the time of interview.

                         5.1.2.3 Give brief resumes of key persons to be assigned to the Project including, but not
                                 limited to, the following:
                                           a. Name and title.
                                           b. Job assignment for other projects.
                                           c. How many years with this firm. For sub-consultants, list prior projects your
                                               firm has worked with sub-consultant.
                                           d. How many years with other firms.
                                           e. Experience including types of projects, size of projects (dollar value and
                                               square footage of project), and specific project involvement.
                                           f. Education.
                                           g. Active registrations (if any).
                                           h. If submitting as a joint venture or partnership, include the assigned staff for
                                               the joint venture or partnership and indicate which of the joint ventures or
                                               partners employs the staff member.

                5.1.3 Workload (15 points):
                As part of the evaluation criteria, the Committee will review the firms and their sub-consultants current
                workload. If the submitting firm is a joint venture, the Committee will review the current workload of each of
                the firms comprising the submitting entity. A maximum of ten points will be awarded based on an
                evaluation of the firm’s total workload and capacity to perform the work.

                         5.1.3.1 Firms and their sub-consultant(s) shall provide a list of outstanding projects, client
                                 names, status of completion, anticipated completion date, and dollars committed on
                                 open project workload. Furthermore, if the submitting firm is a joint venture, they shall
                                 also include projects for each firm comprising the joint venture.


                                 Definition of sub-consultant as it relates to this selection process: An individual and/or
                                 firm contracted or to be contracted by the submitting entity to provide services related to
                                 or part of those which this will be required as part of this selection process.

                5.1.4     Equitable Distribution (10 points):
                        In an effort to consider the equitable distribution of work, the Committee shall evaluate data showing
                        dollar amounts of contracts and projects awarded by DCSD to the submitting firm(s). In the case of
                        submittals received by joint ventures the contracts and projects awarded to each of the firms
                        comprising the joint venture will be included in the calculation of the projects currently under contract
                        and those awarded by DCSD. Furthermore, this calculation will include all contracts and projects
                        awarded to the submitting firm either as a joint venture or as a separate entity, whereby the
                        submitting firm(s) was one of the entities included in the award and contract. The chart below will be
                        used to award a maximum of 10 points based on the combined dollar amount of projects currently
                        under contract, as well as those awarded by DCSD, but not yet under contract. For those projects
                        already under contract, the contract amount will reflect the dollar amount of the contract value, not
                        including amendments. The projects taken into account in the calculation will be those awarded by
                        the Owner within two (2) years prior to this solicitation opening. For projects recommended but not
                        yet awarded, the contract value will reflect the estimated fee based on the budget listed within the
                        RFQu for which the firm was selected. This single score will be allocated to each firm by the
                        Selection Process Facilitator and added to the cumulative score the committee members.
DeKalb County School District                                                            RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                Project No. 201-36
July 11, 2024                                                                                   Page 13 of 22

                                           Contract Value Awarded/ Recommended by DCSD                  Point Value
                                                             Up to $100,000                              10 points
                                                          $100,001 to $500,000                            8 points
                                                         $500,001 to $1,000,000                           6 points
                                                        $1,000,000 to $2,000,000                          4 points
                                                        Greater than $2,000,000                           0 points


                5.1.5 DESIGN FEE (O POINTS):
                      Design fee is NOT included in the Selection Criteria.

                         5.1.5.1 Indicate your proposed Design Fee for the Services and Work as required by the Proposal
                                 Documents and the Owner’s Agreement. Use Owner’s Design Fee Form (Attachment C)
                                 included in this Request for Qualifications.

                         5.1.5.2 Indicate any breakdown of the proposed Design Fee as required by the attached form.

                         5.1.5.3 Acknowledge receipt of addendum, if any.

                         5.1.5.4 All blanks shall be filled in and shall be filled in by typewriter or manually and legibly, in
                                 ink. Interlineations, alterations, and erasures must be initialed by the signer of the
                                 Proposal.

                5.1.6    References (15 points):
                        The Firm must demonstrate a positive relationship with prior clients on similar projects.

                         5.1.6.1 The firm shall submit a minimum of three (3) written recommendations from previous
                                 owners and discuss their strategy to provide a positive working relationship with
                                 DCSD. This strategy must include actual examples of how the firm has demonstrated
                                 their cooperation with other Owners. DCSD reserves the option of contacting any of
                                 the references provided to confirm information provided.

                         5.1.6.2 DCSD staff will provide input on a firm’s past work performance, this information
                                 includes but is not limited to the number of warranty requests and responsiveness,
                                 contract and process compliance, and information from the DCSD contractor evaluation
                                 process if available.

        5.2     Group Review. The PEC members shall meet and discuss the Proposals. The goal of this review is to
                allow each PEC member the opportunity to fully discuss the Proposals and to identify any information
                in the proposals deemed by the PEC member to be significant to the evaluation. At the conclusion
                of this meeting, each PEC member shall render his or her final scores for each proposal and submit his
                or her Proposal Evaluation Form to the Selection Process Facilitator.

                5.2.1    The Selection Process Facilitator shall combine the evaluation scores submitted by all PEC
                         members and shall determine the five (5) highest scoring firms (unless otherwise determined)
                         based on the total evaluation scores received. In the event of a tied score for fifth place, all such
                         tied firms shall be included in the short list.

                5.2.2    Short List Recommendation. The Selection Process Facilitator shall forward the PEC’s short list
                         recommendation to the Chief Operating Officer (“the COO”). The COO, in his or her sole
                         discretion, can either accept the short list recommendation or reject the short list recommendation.
                         If the COO accepts the recommendation, the selection process proceeds as noted below. If the
                         COO rejects the short list recommendation, he or she, in his or her sole discretion, can proceed
DeKalb County School District                                                             RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                 Project No. 201-36
July 11, 2024                                                                                    Page 14 of 22
                        in any of the following methods: directing the Selection Process Facilitator to recommence the
                        selection process at whatever stage the COO deems appropriate (including the Individual
                        Review stage or the Group Review stage); pursuing the project by any other alternative method
                        permitted under Georgia law; or abandoning the project all together. If the COO elects to pursue
                        the project by an alternative method or abandon the project, DCSD shall provide public notice of
                        this decision.

                5.2.3   Notice of Short List. Once the PEC’s short list recommendation has been accepted by the COO, the
                        Selection Process Facilitator will notify all submitting firms of whether or not they appear on the short
                        list and shall provide public notice of the short-listed firms.

                5.2.4   The short-listed firms shall then be invited for interviews before the PEC, which will be scheduled
                        within three (3) business days of notification.

      6.0       INTERVIEWS AND PRESENTATION

        6.1     At the time of its scheduled interview, each short-listed firm shall provide additional information about
                its firm and operations as may be required by DCSD. This additional information shall include, but is not
                limited to, the following:
                6.1.2   Overall Approach, Methodology, & Knowledge of the Site (30 points):
                        6.1.2.1 The firm shall provide information regarding its knowledge of local codes and
                                ordinances, as an indication of its ability to deliver quality workmanship in an effective
                                and timely manner.

                        6.1.2.2 The firm shall demonstrate verbally and graphically its plan for performing the
                                Architectural/Engineering Services, documenting the services to be provided and showing
                                the interrelationship of all parties.

                        6.1.2.3 The firm shall present their quality assurance program. The program shall illustrate how
                                they will assure professional quality, technical accuracy, and coordination of all services
                                require under their contract.

                6.1.3   Project Team (25 points):
                                The firm shall express the general and specific project related experience and
                                capability of in-house staff and sub consultants and
                                their functions as it relates to this project.

                        6.1.3.1 Organization Chart: Develop an organization chart as it relates to the Project
                                indicating key personnel and their relationship. It shall be understood that it is the
                                intent of the District to insist that those key personnel indicated as the project
                                team in this RFQu response actually executes the Project.

                        6.1.3.2 If a joint venture, or prime subcontractor arrangement of two (or more) firms, indicate how
                                the work shall be distributed between the associated firms. Describe how the
                                organizational structure will ensure orderly communications, distribution of information,
                                effective coordination of activities and accountability.
                6.1.4   Cost Control (25 points):
                        6.1.4.1 Describe how you develop cost estimates, and how they are updated, providing specific
                                examples of successful recommendations implemented and cost containment strategies
                                utilized to maintain project budgets without sacrificing quality. Describe and explain the
                                benefits to the Owner.
DeKalb County School District                                                         RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations             Project No. 201-36
July 11, 2024                                                                                Page 15 of 22

                6.1.5   Project Scheduling (20 points):

                        6.1.5.1 As part of the project approach, the firm shall propose a process for scheduling
                                multiple projects and effectively managing and executing the work in the optimum
                                time. Provide a sample schedule and describe any major milestones for achieving
                                the schedule and any other recommendations that may directly impact the schedule.

                        6.1.5.2 The firm shall describe any representative current projects and the projected versus the
                                actual schedule for each.
        6.2     Interview

                6.2.1   The short-listed firms shall be invited for interviews before the PEC. At the time of its scheduled
                        interview, each short-listed firm shall provide additional information about its firm and operations
                        as may be required by DCSD. This additional information shall be identified in the RFQu.

                6.2.2   The PEC shall schedule a separate interview for each short-listed firm. As part of its interview,
                        and at the Selection Process Facilitator’s discretion, each firm shall make a short oral
                        presentation.

                6.2.3   After the PEC has interviewed all the short-listed firms, the PEC shall reconvene for the PEC
                        members to discuss the interviews and review each presentation. At the end of this
                        discussion, PEC members shall use the Presentation Evaluation Forms to record their
                        evaluation of each short-listed firm, and then submit the Presentation Evaluation Forms to
                        the Selection Process Facilitator.

                6.2.4   The Selection Process Facilitator shall combine the evaluation scores submitted by all PEC
                        members and determine the PEC’s ranking of the short-listed firms based upon the total
                        scores assigned to each firm for the presentation stage. If the ranking results in a tied score
                        for the number one or number two ranked firms, additional information shall be requested from
                        the tied firms and presented to the committee. The committee will score the firms based on the
                        responses to the additional information.

        6.3     Submittal of recommended highest ranked firm. The Selection Process Facilitator shall submit the
                highest ranked firm recommended by the PEC to the COO for approval. The COO, in his or her sole
                discretion, shall either accept the results of the PEC’s ranking recommendation and forward it to the Board
                of Education for approval or reject the results of the ranking recommendation. If the COO accepts the
                ranking recommendation, the approval process continues as noted below. If the COO rejects the results
                of the ranking recommendation, he or she, in his or her sole discretion, shall proceed with any of the
                following methods: directing the PEC Selection Process Facilitator to recommence the selection and
                ranking process at whatever stage the COO deems appropriate (including the Individual Review
                stage, the Group Review stage, or the Interview process); pursuing the project by any other alternative
                method permitted under Georgia law; or abandoning the project all together. If the COO elects to pursue
                the project through an alternative method or abandon the project all together, DCSD shall provide public
                notice of that decision.

        .       Upon the COO’s approval of the PEC’s recommendation, an agenda item shall be prepared and put on
                the next available agenda for the Board of Education review and approval.
DeKalb County School District                                                              RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                  Project No. 201-36
July 11, 2024                                                                                     Page 16 of 22
       7.0        SELECTION PROCESS:

         7.1      The Proposal Evaluation Committee (“PEC”) shall be established by the COO. The COO, or his
                  designee, shall approve the members of the PEC, to include the following:

                  7.1.1    At least three (3) DCSD staff persons with expertise in facilities design, construction, operation,
                           and/or maintenance, property, surveying and environmental, as recommended by the Chief
                           Operating Officer from their respective divisions, for the purpose of evaluating and scoring only
                           those elements of the responses that relate to facilities design, construction, operation, and
                           maintenance proposals, and on an as needed basis, those that include property, surveying and
                           environmental.

                  7.1.2    At least one (1) member of the SPLOST CIP staff with expertise in facilities design, construction,
                           operation, and/or maintenance, property, surveying and environmental, as recommended by the
                           Chief Operating Officer, for the purpose of evaluating and scoring only those elements of the
                           responses that relate to facilities design, construction, operation, and maintenance proposals.

                  7.1.3    Such other staff person(s) as deemed appropriate by the COO, or his designee, in order to
                           ensure that the PEC includes persons with experience and knowledge in the contractual services
                           being sought, for the purpose of evaluating and scoring only those elements of the responses
                           that relate to the person(s)’ area of experience and knowledge.

                  7.1.4    Membership of the PEC may include representation from other public or private entities or
                           others deemed appropriate as recommended by the Chief Operating Officer. The
                           recommendation may be based on project complexity, project cost and staff capacity.

                  7.1.5    All voting members of the PEC are required to comply with the provisions of Board Policy DJE
                           and the provisions of the Code of Ethics for Public Officers and Employees. No member shall
                           solicit or knowingly accept any gift, gratuity, loan, special discount, entertainment, transportation,
                           lodging, meals, favor or promise of future employment, based upon any understanding that the
                           vote, official action, or judgment of the member would be influenced thereby.

   7.2       The Chief Operating Officer, or his designee, shall select a Procurement representative who shall serve as
             the Selection Process Facilitator to monitor the selection process, ensure compliance with all applicable
             procedural requirements, limiting discussion which facilitates the procurement process, the facts of the
             procurement and documentation on file, and will always maintain objectivity.

   7.3       The Selection Process Facilitator shall be responsible for ensuring that each member is provided information on
             the project, directs discussion as necessary and determines when the committee may need to vote on any
             compliance related issues.

   7.4       The final rankings as approved by the Board of Education will rank all proposers from highest to lowest
             scores based on the selection criteria described in the RFQu.

 8.0     SCHEDULE
   8.1       Virtual Pre-submittal conference attendance (mandatory). It is the firm’s responsibility to become fully
             informed as to the nature and extent of the services required. The virtual pre-submittal conference will be
             held at 11:00 A.M., EST Thursday, July 25, 2024, via TEAMS. The RFQu will be reviewed, and questions
             will be addressed.
   8.2       Statements of Qualifications must be received electronically at the DeKalb County School District website
             https://dekalbschoolsga.ionwave.net not later than date and time set forth in the “Advertisement for RFQu for
             Professional Architectural and Engineering Services for Allgood Elementary School”. Based on evaluations of
DeKalb County School District                                                         RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations             Project No. 201-36
July 11, 2024                                                                                Page 17 of 22
           Statements of Qualifications, a maximum of five firms may be interviewed, at times and location to be determined
           at a later time. The order of presentation will be determined at DCSD’s sole discretion, and the firms so
           notified.
   8.3     The dates and times identified in this RFQu are subject to change. All changes will be posted to the
           DeKalb County School District solicitation website via addendum as it becomes available for all phases of this
           project.

 9.0     GENERAL INSTRUCTIONS

         9.1        Firms are required to register as a supplier using the IONWAVE portal and obtain a username and
                    password.
         9.2        The response shall contain manual signature of an authorized representative of the responding firm.
         9.3        Responses received after the receipt time noted in the RFQu will not be accepted.

         9.4        Firms responding to the RFQu shall be available for presentations and interviews to the DCSD PEC
                    Selection Committee.

         9.5        The contents of the proposal of a successful firm may become part of its contractual obligations.

         9.6        Excluding items 5.1.4 and 5.2, Proposals shall respond to each item noted in sections 4.0 and 5.0 in the
                    order noted. Identify responses with the same paragraph notation as contained in this RFQu.

         9.7        Submittals shall be typed. All corrections made by the proposer prior to the opening shall be initialed
                    and dated by the proposer. No changes or corrections will be allowed after proposals have been
                    unsealed.
         9.8        Questions: Any questions concerning the RFQu should be submitted electronically via email to the
                    Senior Procurement Manager at dcsd-op-bidquestion@dekalbschoolsga.org. Questions submitted
                    to any other email address will not be considered. The deadline for receipt of vendor questions is
                    Wednesday, July 31, 2024 at 2:00 p.m. EST. Questions received after the deadline time will not be
                    considered. Questions received by the deadline time will be answered in writing and posted to the
                    DCSD solicitation website http://dekalbschoolsga.ionwave.net no later than Wednesday, August 7,
                    2024 by 2:00 p.m. EST. No response other than written by the Senior Procurement Manager, will
                    be binding upon DCSD. All supplemental instructions will be in the form of written Addenda to the
                    RFQu.

         9.9        Selection committee members, school board members and school board personnel are not to
                    be contacted prior to the Board of Education’s decision to approve or reject the final
                    recommendation presented to it by the Chief Operating Officer. At the discretion of DCSD,
                    failure to comply with this requirement will be grounds for disqualification.

         9.10       Specifically, this NO-CONTACT PERIOD shall commence on the initial date of the advertisement for
                    Request for Qualifications and continue through and include the date the DeKalb County Board of
                    Education makes its determination to approve or reject the final recommendations.
         9.11       The assigned contact persons for this RFQu are Belinda Quillet, Senior Procurement Manager and
                    Tijauna Naylor-Smith, Procurement Manager. Mrs. Quillet can be reached at (678) 676-1373 or by
                    email at dcsd-op-bidquestion@dekalbschoolsga.org. Dr. Naylor-Smith can be reached at (678) 676-
                    1313 or by email at tijauna_naylor_smith@dekalbschoolsga.org. Prospective Respondents must
                    limit their contact regarding this RFQu to the assigned contact persons.

         9.12       Failure to meet any of these requirements may disqualify your firm from consideration.
DeKalb County School District                                                           RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations               Project No. 201-36
July 11, 2024                                                                                  Page 18 of 22

 10.0   TERMS AND CONDITIONS:

        10.1.        DCSD reserves the right to accept or reject any or all proposals in the best interest of DCSD.
                     DeKalb County School District reserves the right to waive any formalities in the selection process.

        10.2         It is mutually understood and agreed that the nature, amount, and frequency of the Services shall be
                     determined solely by Owner and that Owner does not represent or guarantee unto firm that any
                     specific amount of services will be requested or required of firm pursuant to this RFQu.

        10.3        Proposals which do not comply with these instructions or that do not include the requested data may
                    not be considered.

        10.4        The successful firm shall not discriminate against any person in accordance with Federal, State or
                    Local law.

        10.5        It is the sole responsibility of the submitting firm to ensure proposals are received on or before
                    the time and date required, and in the format stated.
        10.6        By submission of a response to this RFQu, the Respondent certifies that he/she and his/her employees
                    shall not engage in the unlawful manufacture, sale, distribution, dispensation, possession, or use of
                    controlled substance or drugs during the performance of the contract.
        10.7        By submission of a response to this RFQu, the Respondent certifies that he/she and his/her employees
                    shall not use tobacco products on DCSD property at any time during the performance of this contract.
        10.8        Respondents shall fully certify that they, as individuals or as officials of a business entity, have not
                    entered into any agreement, participated in collusion, or otherwise taken any action in restraint of free
                    and competitive responses to this RFQu. Further, Respondents guarantee that their response is not
                    made in conjunction with or on behalf of another party and that they have not been directly or indirectly
                    induced in any manner or taken any action to result in a restriction of trade or in an unfair advantage.

        10.9        By responding to this RFQu, the offeror certifies that the proposing company and/or its principals have
                    not been suspended, excluded, disqualified, debarred, proposed for debarment, declared ineligible or
                    voluntarily excluded from participation in any transaction by any Federal or State department or agency
                    and that the bidder complies with all applicable orders, rules and regulations related thereto. Further,
                    by responding to this RFQu, the offeror certifies that all lower tier participating individuals and/or
                    company(s) and all respective principals of lower tier participants have not been suspended, excluded,
                    disqualified, debarred, proposed for debarment, declared ineligible or voluntarily excluded from
                    participation in any transaction by any Federal or State department or agency and that the bidder
                    complies with all applicable orders, rules and regulations related thereto.

        10.10       DeKalb County School District, Georgia, does not discriminate in admission or access to, or
                    treatment or employment in its programs and activities, on the basis of race, color, religion, age,
                    sex, national origin, marital status, disability, genetic information, sexual orientation, gender identity
                    or expression, or any other reason prohibited by law.
        10.11       By making a submission, it is understood and agreed that the submitting entity consents to DCSD
                    contacting any parties referenced in the entities response including, but not limited to, all project
                    owners and references herein.
        10.12       Submitters acknowledge and agree that the contracting entity will be the Firm name identified in the
                    response to 4.3.1.1.

        10.13       Appendix H is the most current version of the DCSD Standard Form of Contract for Architectural
DeKalb County School District                                                            RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                Project No. 201-36
July 11, 2024                                                                                   Page 19 of 22
                    Services. By submitting a response to this RFQu, submitters acknowledge and agree that they have
                    reviewed the contract and have no objection to it. All responders should thoroughly review the
                    documents prior to submitting a proposal. Any proposed revisions to the terms or language of these
                    documents must be submitted in writing during the question-and-answer period of the solicitation. All
                    requests must be submitted in writing prior to the close of the final questions. Requests for revisions
                    will be reviewed and approved or rejected by legal and legal rulings are final. If submitted or proposed
                    thereafter, such proposed revisions to the terms or language of these documents shall not be
                    considered by the Owner and the Architect/Engineer submittal shall be rejected. No alterations can
                    be made in the contract after award by DCSD.

11.0   PROTEST PROCESS:

       Any person who is adversely affected by a decision of the DeKalb County School District concerning this
       procurement, shall adhere to the following Protest Procedures:

        11.1        Protests. A bidder may file a written protest challenging DCSD’s compliance with applicable
                     procurement procedures subject to the bidder’s compliance with the provisions outlined below. Any
                     such written protest will be resolved in accordance with these provisions.

        11.2          Types of Challenges. Any bidder interested in and capable of responding to a competitive solicitation
                      may file a protest with respect to the competitive solicitation process including, but not limited to, a
                      challenge to specifications or any events or facts arising during the solicitation process. Any bidder
                      submitting a timely bid/proposal in response to a competitive solicitation may file a protest with respect
                      to DCSD’s intended or actual contract award including, but not limited to, events or facts arising during
                      the evaluation and/or negotiation process.
        11.3          Form of Protest. At a minimum, the written protest must include the following:
                         a. the name and address of the protestor;
                         b. appropriate identification of the solicitation;
                         c. a statement of reasons for the protest;
                         d. supporting exhibits, evidence, or documents to substantiate any claims unless not
                              available within the filing time (in which case the offeror must proceed to file the protest
                              during the filing period identified below but state the expected availability of the material);
                              and
                         e. the desired remedy.
               DCSD, at its discretion, may deem issues not raised in the initial protest as waived with prejudice
               by the protesting offeror.

        11.4          Filing Protests. A protest is considered to be properly filed when it is in writing, signed by a company
                      officer authorized to sign contracts on behalf of the offeror, and is received by the Design and
                      Construction Department. The protest may be sent by any of the following means:
                               MAIL: Attention: Mr. Erick Hofstetter
                                                Chief Operating Officer
                                                DeKalb County School District
                                                Sam A. Moss Service Center
                                                1780 Montreal Road
                                                Tucker, Georgia 30084
                               Email:           erick_hofstetter@dekalbschoolsga.org

        11.5          Type of Protests. A challenge to the competitive solicitation process must be filed within two (2)
                      business days prior to the closing date and time of the solicitation as identified on the RFQu.
DeKalb County School District                                                              RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations                  Project No. 201-36
July 11, 2024                                                                                     Page 20 of 22
                       A challenge to an intended or actual contract award must be filed within ten (10) calendar days of
                       the date the Notice of Intent to Award (NOIA) is posted by DCSD. In the event DCSD does not post
                       a NOIA, the protest must be filed within ten (10 calendar days of the date the Notice of Award (NOA)
                       is posted.

                       If a protest is not filed by the applicable deadline, such failure shall be deemed as a waiver
                       with prejudice of any grounds the bidder may have for protest.

        11.6           Stay of Procurement During Protest Review. When a protest challenging the competitive
                       solicitation process has been timely filed at least two (2) business days prior to the closing date and
                       time, the solicitation shall not close until a final decision resolving the protest has been issued, unless
                       the Facilities Management Department makes a written determination that the closing of the
                       solicitation without delay is necessary to protect the interests of DCSD.

                       When a protest challenging an intended contract award has been timely filed, DCSD shall not
                       proceed to actual contract award unless the Design and Construction Department makes a written
                       determination that the issuance of a contract or performance of the contract without delay is
                       necessary to protect the interests of DCSD. If it is determined that it is necessary to proceed with
                       contract performance without delay, the bidder/offeror with this contingent contract may proceed with
                       performance and receive payment for work performed in strict accordance with the terms of the
                       contract. The provisions of this paragraph are not applicable to a protest pertaining to events or facts
                       arising during the solicitation process.

        11.7           Protest Resolution. The Facilities Management Department shall review and issue a written
                       decision on the protest within seven (7) business days. This decision shall be deemed final.
                       Available remedies for sustained protests are as follows:

                   •    If a protest is sustained prior to the closing date and time of the solicitation, available remedies may
                        include, but are not limited to, the following: modification of the solicitation document including, but
                        not limited to, specifications and terms and conditions; extension of the solicitation closing date and
                        time (as appropriate); and cancellation of the solicitation.

                   •    If a protest of the intended/actual contract award is sustained available remedies may include but
                        are not limited to, the following: revision or cancellation of the NOIA/NOA, re-evaluation and re-
                        award, or re-solicitation with appropriate changes to the new solicitation.

        11.8           Costs. In no event shall a bidder be entitled to recover any costs incurred in connection with the
                       solicitation or protest process, including, but not limited to, the costs of preparing a bid/proposal,
                       the costs of participating in the protest process, or any attorney fees.
DeKalb County School District                                                          RFQu No. 24-752-038
A/E Services for Allgood Elementary School HVAC Replacement and Renovations              Project No. 201-36
July 11, 2024                                                                                 Page 21 of 22

                                               NOTICE
                       FOR PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES
                                   FOR ALLGOOD ELEMENTARY SCHOOL

DeKalb County Board of Education announces that Professional Architectural and Engineering Services are required for the
project listed below.

PROJECT AND NUMBER:                             Allgood Elementary School at 201-36
                                                RFQu No. 24-752-038

SERVICES TO BE PROVIDED:                        Professional Architectural and Engineering Design Services for Allgood
                                                Elementary School

 VIRTUAL PRE-SUBMITTAL MEETING:                 July 25, 2024, 11:00 a.m. EST, via TEAMS
                                                Attendees must provide the following information by Wednesday,
                                                July 24, 2024, 5:00 p.m. EST:
                                                1. Individual Name and Title
                                                2. Company Name
                                                3. Telephone Number
                                                4. Email Address
                                                Information must be sent to dcsd-op-solicitation@dekalbschoolsga.org
                                                A meeting link will be sent to all registered attendees.
                                                Attendance is mandatory.

 DCSD CONTACT:                                    Belinda Quillet, Senior Procurement Manager
                                                  Tijauna Naylor-Smith, Procurement Manager

 SUBMIT QUALIFICATIONS TO:                        http://dekalbschoolsga.ionwave.net

 QUALIFICATIONS DUE DATE AND TIME:               August 15, 2024, 2:00 p.m. EST


 Requirements: Interested firms are required to comply with all requirements of the Request for Qualification (RFQu). A
 copy of the RFQu and all clarifications issued shall be obtained from the DeKalb County School District web site
 http://dekalbschoolsga.ionwave.net. Furthermore, all Notices concerning this solicitation and award shall be posted to
 the aforementioned web site. These Notices shall include but are not limited to short list meeting dates and times,
 presentation meeting dates and times, intended decision and decision information.


                                 End of RFQu Document Consisting of 22 Pages