                                                                                                                         Orginial Budget/Estimate
                                                                                                                                        Budget (SP5)    Current Budget     Revised Estimate at   Budget/Estimate   Estimated Construction     Estimated Project
            School/Facility                               Brief Description                            Funding Source    Date                                                                                                                                        Project Status                 Recommendation / Notes
                                                                                                                                       Estimate (SP6)    March 2024      Completion March FY24      Difference           Start Date         Substantial Completion
                                                                                                                                                                                                                                                                                       Estimate based on reccomendation to close project and
101. Sprinkler Installation A                                                                            E-SPLOST V     Nov-2016         $1,230,000       $8,676,915           $739,667            $7,937,248                 -                        -                 Active
                                                                                                                                                                                                                                                                                              move budget to Program Contingency
                                      Sprinkler installation at 7 schools:
                                      Allgood ES, Brockett ES, Evansdale ES, John Lewis ES
                                                                                                                                                                                                                                                                                       Estimate based on reccomendation to close project and
102. Sprinkler Installation B         (temporary/Druid Hills), Margaret Harris                           E-SPLOST V     Nov-2016         $1,250,000       $9,671,848           $859,939            $8,811,909                 -                        -                 Active
                                                                                                                                                                                                                                                                                              move budget to Program Contingency
                                      Comprehensive School, Stone Mill ES, Stone Mountain
                                      ES
                                      Sprinkler installation at 6 5 schools:
                                                                                                                                                                                                                                                                                       Estimate based on reccomendation to close project and
103. Sprinkler Installation C         Chesnut ES, Huntley Hills ES, Montgomery ES, Sequoyah              E-SPLOST V     Nov-2016         $1,420,000      $10,090,355           $708,725            $9,381,630                 -                        -                 Active
                                                                                                                                                                                                                                                                                              move budget to Program Contingency
                                      MS, Vanderlyn ES, and Woodward ES
                                      Installation of security vestibules at 10 schools: Bob
                                      Mathis ES, Cedar Grove ES, Columbia ES, International
                                                                                                                                                                                                                                                                                       Dates reflect McNair HS only. All Schools except McNair
115. Security Vestibules A            Student Center (Midway), McNair HS, Rainbow ES,                    E-SPLOST V     Nov-2016         $917,000         $2,910,902           $3,210,902           ($300,000)            Spring 24                 Aug 24               Active
                                                                                                                                                                                                                                                                                                            HS complete.
                                      Stephenson MS, Stone Mountain HS, Wadsworth
                                      Magnet (Knollwood), and Woodridge ES
                                                                                                                                                                                                                                                                                      Original Budget based on major scope change approved
                                      Installation of security vestibule and sprinkler
                                                                                                                                                                                                                                                                                       by Board in February 2020. Project closed due to being
201. Cross Keys HS                    installation and installation of synthetic turf field at           E-SPLOST V     Feb-2020         $3,080,000        $310,973            $310,973                $0                     -                        -               Canceled
                                                                                                                                                                                                                                                                                      made unnecessary by updated scope of Project 214: Cross
                                      practice field
                                                                                                                                                                                                                                                                                                      Keys HS modernization.
                                      Installation of synthetic turf at football practice field,
                                      installation of security vestibule, and accessibility                                                                                                                                                                                           Original Budget based on major scope change approved
213. Clarkston HS                                                                                        E-SPLOST V     Feb-2020         $1,650,000       $1,650,000           $3,200,000          ($1,550,000)          Summer 24                  Aug 25               Active
                                      improvements (elevator(s), lift for stage, and improved                                                                                                                                                                                                       by Board in February 2020.
                                      assisted toileting area
                                      Construction of Addition and Modernization (Extensive                                                                                                                                                                                           Original Budget based on major scope change approved
214. Cross Keys HS                                                                                       E-SPLOST V     Apr-2022        $81,250,000      $81,250,000          $147,466,000        ($66,216,000)          Summer 24                  Aug 26               Active
                                      Renovation) of Cross Keys HS                                                                                                                                                                                                                                     by Board in April 2022.
                                      Design of a New Sequoyah Middle School and a New                                                                                                                                                                                                    Project Created April 2022. Scope is design only.
217. Design New Sequoyah MS & HS                                                                         E-SPLOST V     Apr-2022        $10,000,000      $10,000,000          $14,000,000          ($4,000,000)               -                        -                 Active
                                      Sequoyah High School                                                                                                                                                                                                                                  Construction will be funded by E-SPLOST VI.
                                                                                                                                                                                                                                                                                       Project created in February 2020. Estimate based on
224. New Dunwoody / Chamblee ES       New 950 seat prototype elementary school                           E-SPLOST V     Feb-2020        $35,000,000     $36,550,000.00         $6,949,829          $29,600,171                -                        -                 Active        reccomendation to close project and move budget to
                                                                                                                                                                                                                                                                                                       Program Contingency
                                      Restroom and plumbing fixture replacement, fire
322. Redan MS                         sprinkler installation, improved assisted toileting area,          E-SPLOST V     Nov-2016         $807,000         $7,487,984           $8,053,162           ($565,178)            Spring 24                Fall 2024             Active                HVAC added to scope in October 2022
                                      roof replacement and HVAC system replacement
                                      Accessibility improvements at 4 schools:
                                      Cedar Grove MS (accessibility improvements and
341. Accessibility improvements and   plumbing fixtures), Chapel Hill MS (accessibility
                                                                                                         E-SPLOST V     Nov-2016         $1,593,000        $155,153            $170,981             ($15,828)                 -                        -                 Defer                     Scope of project to E-SPLOST VI
plumbing fixtures at 4 schools        improvements and plumbing fixtures), Oakcliff Theme
                                      ES (accessibility improvements only), and Rainbow ES
                                      (accessibility improvements only)
                                      Security vestibule installation, plumbing fixture
                                      replacement, and accessibility improvements (new light
343. Druid Hills MS                                                                                      E-SPLOST V     Nov-2016         $855,000         $1,901,328           $1,907,328            ($6,000)            Summer 24                  Apr 25               Active
                                      duty elevator, new lifts, improved assisted toileting
                                      area)
                                      Accessibility improvements (light duty elevator in new
                                      exterior shaft, platform lift for stage, and improved
344. Midvale ES                                                                                          E-SPLOST V     Nov-2016         $516,000         $9,774,984           $9,774,984              $0                Summer 24                  Apr 26               Active
                                      assisted toileting area), installation of fire sprinklers, and
                                      HVAC Replacement
                                      Major building system replacement with emphasis on
351. Henderson Mill ES                                                                                   E-SPLOST V     Nov-2016         $7,020,000       $8,807,300           $8,807,300              $0                Summer 24                  Feb 25               Active
                                      Roof, Plumbing, HVAC Components
                                      Major building system replacement with emphasis on
352. Toney ES                                                                                            E-SPLOST V     Nov-2016         $6,790,000       $6,790,000           $7,290,000           ($500,000)           Summer 24                  Aug 24               Active
                                      HVAC
                                      Major building system replacement with emphasis on
353. Former Nancy Creek                                                                                  E-SPLOST V     Nov-2016         $6,045,000       $8,500,000          $13,871,073          ($5,371,073)          Summer 24                  Feb 25               Active
                                      HVAC and Fire sprinkler installation
                                      Major building system replacement with emphasis on,
354. E. L. Miller ES                                                                                     E-SPLOST V     Nov-2016         $4,243,000       $8,300,000           $8,500,000           ($200,000)             Fall 23                  Aug 24               Active
                                      HVAC, Fire Protection
                                      Major building system replacement with emphasis on
355. Stoneview ES                                                                                        E-SPLOST V     Nov-2016         $4,860,000       $4,860,000          $15,000,000         ($10,140,000)          Summer 24                  Aug 26               Active
                                      Roof, HVAC Components
                                      Major building system replacement with emphasis on
                                                                                                                                                                                                                                                                                      Project made unnecessary by New Sequoyah MS & New
356. Cary Reynolds ES                 Roof, HVAC Components and Installation of security                 E-SPLOST V     Nov-2016         $5,635,000        $12,040              $12,040                $0                     -                        -               Canceled
                                                                                                                                                                                                                                                                                                         Sequoyah HS
                                      vestibule
                                      Major building system replacement with emphasis on
357. Briar Vista ES                   Roof, Accessibility improvements between levels; and               E-SPLOST V     Nov-2016         $4,160,000       $4,715,100           $4,715,100              $0                  Fall 23                  Aug 24               Active
                                      Installation of security vestibule
                                      Major building system replacement with emphasis on
358. Champion Theme MS                HVAC Components and Fire sprinkler installation, Old               E-SPLOST V     Nov-2016         $6,063,000       $6,063,000          $30,000,000         ($23,937,000)          Summer 24                  Aug 25               Active
                                      Rock Gym Renovation
                                      Major building system replacement with emphasis on
359. Livsey ES                                                                                           E-SPLOST V     Nov-2016         $4,100,000       $6,000,000           $9,000,000          ($3,000,000)            Fall 24                  Aug 26               Active
                                      HVAC
                                      Major building system replacement with emphasis on
360. DeKalb HS of Technology-South                                                                       E-SPLOST V     Nov-2016         $3,860,000      $10,647,500          $10,647,500              $0                 Spring 24                 Aug 24               Active
                                      HVAC Components, Plumbing & Site improvements
                                      Major building system replacement with emphasis on
                                      Roofing and Site Improvements, Plumbing fixture
361. Fairington ES                                                                                       E-SPLOST V     Nov-2016         $2,439,000       $6,084,462           $6,294,787           ($210,325)             Fall 23                  Fall 24              Active
                                      replacement, HVAC upgrades as needed and fire
                                      sprinkler installation
                                                                                                                                                                                                                                                                                       Original Budget unchanged when major scope change
362. Dresden ES                       Design of New Dresden ES replacement facility                      E-SPLOST V     Nov-2016         $3,570,000       $2,343,140           $3,783,140          ($1,440,000)               -                        -                 Active        approved by Board in April 2022. Scope is design only.
                                                                                                                                                                                                                                                                                            Construction will be funded by E-SPLOST VI.

                                      Major building system replacement with emphasis on
363. Kingsley ES                                                                                         E-SPLOST V     Nov-2016         $2,610,000       $2,610,000           $3,610,000          ($1,000,000)          Summer 24                  Dec 25               Active
                                      HVAC Components and Fire sprinkler installation

                                      Major building system replacement with emphasis on
364. Hawthorne ES                                                                                        E-SPLOST V     Nov-2016         $4,510,000      $10,178,350          $10,178,350              $0                 Spring 24                 Aug 24               Active
                                      HVAC Components, Plumbing, and Roof Replacement
                                  Major building system replacement with emphasis on
365. Salem MS                                                                                 E-SPLOST V    Nov-2016    $4,530,000    $11,479,986     $12,013,551      ($533,565)     Spring 24    Fall 24     Active
                                  HVAC Components, and roof replacement as needed
                                  Major building system replacement with emphasis on
                                  HVAC, site improvements, lighting replacement, fire
366. Rock Chapel ES                                                                           E-SPLOST V    Nov-2016    $3,210,000     $5,530,000     $12,000,000     ($6,470,000)    Summer 24    Dec 25      Active
                                  alarm system replacement, new fire sprinkler system,
                                  and additional parking
                                  Major building system replacement with emphasis on
                                  HVAC and Windows, addition of a security vestibule, a
368. Laurel Ridge ES                                                                          E-SPLOST V    Jun-2020    $7,300,000    $10,260,000     $10,260,000         $0          Spring 24    Aug 24      Active                  Project created in June 2020.
                                  fire sprinkler system, replacement of light fixtures with
                                  LED fixture, ceiling replacement and roof replacement

                                  Major building system replacement with emphasis on
                                  HVAC, addition of a fire sprinkler system, replacement
369. Woodridge ES                                                                             E-SPLOST V    Jun-2020    $7,300,000    $10,060,000     $10,060,000         $0          Summer 24    Aug 24      Active                  Project created in June 2020.
                                  of light fixtures with LED fixtures, roofing improvements
                                  and ceiling replacement

                                  Major building system replacement with emphasis on
                                  HVAC, addition of a fire sprinkler system, roofing
370. Chesnut ES                                                                               E-SPLOST V    Jun-2020    $6,400,000     $9,080,000     $9,080,000          $0          Summer 24    Aug 24      Active                  Project created in June 2020.
                                  improvements, replace existing lighting with LED light
                                  fixtures and ceiling replacement
                                  Major building system replacement with emphasis on                                                                                                                                        Project created in June 2020. Project deemed not
373. Montgomery ES                                                                            E-SPLOST V    Jun-2020    $1,600,000         $0             $0              $0              -           -       Canceled
                                  Roofing                                                                                                                                                                                    necessary - Work completed under E-SPLOST IV
                                  Major building system replacement with emphasis on                                                                                                                                        Project created in June 2020. Project deemed not
376. Browns Mill ES                                                                           E-SPLOST V    Jun-2020    $1,900,000         $0             $0              $0              -           -       Canceled
                                  Roofing                                                                                                                                                                                    necessary - Work completed under E-SPLOST IV
                                  Ensure all DCSD school facilities meet minimum                                                                                                                                         Project created in April 2021. Scope of project moved to
379. Update HVAC Controls                                                                     E-SPLOST V    Jul-2021    $4,500,000         $0             $0              $0              -           -        Defer
                                  standard for HVAC Controls                                                                                                                                                                                    E-SPLOST VI
                                  Rennovation of Green Forrest Drive facility (former
                                  location of Wadsworth ES) at act as swing space to
380. Green Forrest Drive                                                                      E-SPLOST V    Apr-2021    $3,000,000    $6,000,000.00   $6,000,000          $0          Summer 24    Apr 25      Active                  Project created in April 2021.
                                  schools undergoing a major capital improvement
                                  project
                                  Add parking spaces at 10 schools and repave existing
                                  parking (number of new parking spaces shown): Canby
                                  Lane ES (31), Columbia ES (31), Flat Shoals ES (34),                                                                                                                                   Original budget did not include repaving existing parking,
381. Parking Addition                                                                         E-SPLOST V    Nov-2016    $1,579,000     $7,433,026     $7,433,026          $0          Summer 23    Aug 25      Active
                                  Hambrick ES (36), Jolly ES (29), Oakcliff Theme ES (32),                                                                                                                                                 scope added in 2020
                                  Rainbow ES (32), Snapfinger ES (34), Stone Mill ES (31),
                                  and Stone Mountain ES (29)
                                  Replace outdated musical
521. Music Instruments                                                                        E-SPLOST V    Nov-2016   $10,000,000    $10,000,000     $10,000,000         $0              -           -        Active                   Not a construction project
                                  instruments and equipment
602. Program Contingency          Set-aside for unforeseen conditions                         E-SPLOST V    Nov-2016    $3,041,434     $2,795,772         $0          $2,795,772          -           -        Active                   Not a construction project
                                  Miscellaneous expenses in support
604. General Services                                                                         E-SPLOST V    Nov-2016    $1,000,000     $1,000,000     $1,320,000       ($320,000)         -           -        Active                   Not a construction project
                                  of the E-SPLOST program
                                  Management of the E-SPLOST
605. Program Consultants          program by third party management as well as other          E-SPLOST V    Nov-2016   $13,000,000    $13,962,143     $13,962,143         $0              -           -        Active                   Not a construction project
                                  consultants, as required.
                                                                                                                                                                                                                                  Project budgets are base on approved
101. New Sequoyah MS & Sequoyah   Construction of a New Sequoyah Middle School and a
                                                                                              E-SPLOST VI   Feb-2023   $170,000,000     $175,000      $235,000,000   ($234,825,000)   Summer 24   Fall 2027    Active      contracts/commitments only. All other values are
HS                                New Sequoyah High School (design in E-SPLOST V)
                                                                                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                                  Project budgets are base on approved
                                                                                                                                                                                                                           contracts/commitments only. All other values are
                                  Design and construction of a New Cross Keys MS,
102. New Cross Keys MS                                                                        E-SPLOST VI   Feb-2023   $90,000,000         $0             $0              $0              -           -        Active            estimates, including "Original Estimate".
                                  including purchase of land
                                                                                                                                                                                                                         Current estimate based on expectation that new MS will
                                                                                                                                                                                                                                   not be built/funded by E-SPLOST VI.
                                  HVAC Refresh, Update of Security Cameras, Update of                                                                                                                                             Project budgets are base on approved
201. Allgood ES                   Access Controls, Update of Intrusion Detection, New or      E-SPLOST VI   Feb-2023    $6,030,000         $0         $23,140,000    ($23,140,000)    Winter 25   Spring 26    Active      contracts/commitments only. All other values are
                                  Upgraded Security Vestibule                                                                                                                                                                    estimates, including "Original Estimate".
                                  HVAC Refresh, Update of Security Cameras, Update of                                                                                                                                             Project budgets are base on approved
202. Ashford Park ES              Access Controls, Update of Intrusion Detection, Update      E-SPLOST VI   Feb-2023    $5,459,000      $650,000      $12,289,000    ($11,639,000)     Fall 24    Spring 26    Active      contracts/commitments only. All other values are
                                  Fire Alarm                                                                                                                                                                                     estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
203. Austin ES                    Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $340,000           $0          $340,000        ($340,000)     Spring 25   Spring 26    Active      contracts/commitments only. All other values are
                                  Security Vestibule                                                                                                                                                                             estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
204. Avondale ES                  Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $854,000           $0          $854,000        ($854,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Security Vestibule, Update Fire Alarm                                                                                                                                                          estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
205. Barack Obama ES              Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $340,000           $0          $340,000        ($340,000)     Spring 25   Spring 26    Active      contracts/commitments only. All other values are
                                  Security Vestibule                                                                                                                                                                             estimates, including "Original Estimate".
                                                                                                                                                                                                                                  Project budgets are base on approved
                                  Update of Security Cameras, Update of Access Controls,
206. Bob Mathis ES                                                                            E-SPLOST VI   Feb-2023    $348,000           $0          $348,000        ($348,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                                  Project budgets are base on approved
                                  Update of Security Cameras, Update of Access Controls,
207. Briar Vista ES                                                                           E-SPLOST VI   Feb-2023    $323,000           $0          $323,000        ($323,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                                                 estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
208. Briarlake ES                 Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $818,000           $0          $818,000        ($818,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Security Vestibule, Update Fire Alarm                                                                                                                                                          estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
209. Brockett ES                  Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $640,000           $0          $640,000        ($640,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Security Vestibule                                                                                                                                                                             estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
210. Browns Mill ES               Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $868,000           $0          $868,000        ($868,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Security Vestibule, Update Fire Alarm                                                                                                                                                          estimates, including "Original Estimate".
                                  Update of Security Cameras, Update of Access Controls,                                                                                                                                          Project budgets are base on approved
211. Canby Lane ES                Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $850,000           $0          $850,000        ($850,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Security Vestibule, Update Fire Alarm                                                                                                                                                          estimates, including "Original Estimate".
                                                                                                                                                                                                                                  Project budgets are base on approved
                                  Update of Security Cameras, Update of Access Controls,
213. Cedar Grove ES                                                                           E-SPLOST VI   Feb-2023    $368,000           $0          $368,000        ($368,000)      Fall 24     Fall 25     Active      contracts/commitments only. All other values are
                                  Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                                                 estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
214. Chapel Hill ES        Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $844,000        $0         $844,000      ($844,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                                                                                                                                                                                                              Project budgets are base on approved
                           Update of Security Cameras, Update of Access Controls,
215. Chesnut ES                                                                      E-SPLOST VI   Feb-2023    $140,000        $0         $140,000      ($140,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Update of Intrusion Detection
                                                                                                                                                                                                             estimates, including "Original Estimate".
                                                                                                                                                                                                              Project budgets are base on approved
                           Update of Security Cameras, Update of Access Controls,
216. Columbia ES                                                                     E-SPLOST VI   Feb-2023    $367,000        $0         $367,000      ($367,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
217. Doraville United ES   Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                                                                                                                                                                                              Project budgets are base on approved
                           Construction of a new Dresden ES facility (design in E-
218. Dresden ES                                                                      E-SPLOST VI   Feb-2023   $42,000,000    $10,000     $76,000,000   ($75,990,000)   Spring 24   Spring 26   Active   contracts/commitments only. All other values are
                           SPLOST V)
                                                                                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
219. Dunaire ES            Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $825,000        $0         $825,000      ($825,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
220. Dunwoody ES           Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
221. E.L. Bouie ES         Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $915,000        $0         $915,000      ($915,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
222. E. L. Miller ES       Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $857,000        $0         $857,000      ($857,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
223. Evansdale ES          Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $802,000        $0         $802,000      ($802,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
224. Fairington ES         Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
225. Fernbank ES           Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
226. Flat Rock ES          Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $664,000        $0         $664,000      ($664,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
227. Flat Shoals ES        Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $831,000        $0         $831,000      ($831,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                                                                                                                                                                                                              Project budgets are base on approved
                           Update of Security Cameras, Update of Access Controls,
228. Hambrick ES                                                                     E-SPLOST VI   Feb-2023    $140,000        $0         $140,000      ($140,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Update of Intrusion Detection
                                                                                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
229. Hawthorne ES          Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
230. Henderson Mill ES     Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $808,000        $0         $808,000      ($808,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Roof Replacement, Update of Security Cameras, Update                                                                                                                               Project budgets are base on approved
231. Hightower ES          of Access Controls, Update of Intrusion Detection, New    E-SPLOST VI   Feb-2023   $2,343,000       $0        $2,803,000    ($2,803,000)     Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           or Upgraded Security Vestibule, Update Fire Alarm                                                                                                                                 estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
232. Huntley Hills ES      Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $802,000        $0         $802,000      ($802,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           HVAC Refresh, Update of Security Cameras, Update of                                                                                                                                Project budgets are base on approved
233. Idlewood ES           Access Controls, Update of Intrusion Detection, Update    E-SPLOST VI   Feb-2023   $5,968,000    $1,250,000   $23,358,000   ($22,108,000)    Fall 24    Summer 27   Active   contracts/commitments only. All other values are
                           Fire Alarm                                                                                                                                                                        estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
234. Indian Creek ES       Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
235. John Lewis ES         Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                           Roof Replacement, Update of Security Cameras, Update                                                                                                                               Project budgets are base on approved
236. Jolly ES              of Access Controls, Update of Intrusion Detection, New    E-SPLOST VI   Feb-2023   $2,946,000    $1,937,680   $2,956,000    ($1,018,320)     Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           or Upgraded Security Vestibule, Update Fire Alarm                                                                                                                                 estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
237. Kelley Lake ES        Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $808,000        $0         $808,000      ($808,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
238. Kingsley ES           Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $821,000        $0         $821,000      ($821,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Roof Replacement, HVAC Refresh, Update of Security
                           Cameras, Update of Access Controls, Update of                                                                                                                                      Project budgets are base on approved
239. Kittredge Magnet      Intrusion Detection, New or Upgraded Security             E-SPLOST VI   Feb-2023   $7,144,000    $1,520,000   $2,384,000     ($864,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                           Vestibule, Update Fire Alarm (Needs Addition or move,                                                                                                                             estimates, including "Original Estimate".
                           not HVAC)
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
240. Laurel Ridge ES       Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $815,000        $0         $815,000      ($815,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
241. Livsey ES             Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $761,000        $0         $761,000      ($761,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule, Update Fire Alarm                                                                                                                                             estimates, including "Original Estimate".
                           Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
242. Marbut Theme ES       Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                           Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                               Roof Replacement, Update of Security Cameras, Update                                                                                                                             Project budgets are base on approved
243. McLendon ES               of Access Controls, Update of Intrusion Detection, New   E-SPLOST VI   Feb-2023   $2,290,000   $1,674,000   $2,440,000     ($766,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               or Upgraded Security Vestibule                                                                                                                                                  estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
244. Midvale ES                Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
245. Montclair ES              Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $855,000        $0         $855,000      ($855,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
246. Montgomery ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 24    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               HVAC Refresh, Update of Security Cameras, Update of                                                                                                                              Project budgets are base on approved
247. Murphey Candler ES        Access Controls, Update of Intrusion Detection, New or   E-SPLOST VI   Feb-2023   $6,581,000   $830,000     $15,361,000   ($14,531,000)    Fall 24    Summer 27   Active   contracts/commitments only. All other values are
                               Upgraded Security Vestibule, Update Fire Alarm                                                                                                                                  estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
248. Nancy Creek (Former)      Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $811,000        $0         $811,000      ($811,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
249. Narvie Harris ES          Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $938,000        $0        $1,538,000    ($1,538,000)     Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                Project budgets are base on approved
                               Update of Security Cameras, Update of Access Controls,
250. Oak Grove ES                                                                       E-SPLOST VI   Feb-2023   $307,000        $0         $307,000      ($307,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                               estimates, including "Original Estimate".
                               Roof Replacement, Update of Security Cameras, Update                                                                                                                             Project budgets are base on approved
251. Oak View ES               of Access Controls, Update of Intrusion Detection, New   E-SPLOST VI   Feb-2023   $3,310,000   $1,923,000   $2,440,000     ($517,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                               or Upgraded Security Vestibule                                                                                                                                                  estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
252. Oakcliff Theme ES         Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $857,000        $0         $857,000      ($857,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
253. Panola Way ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $899,000        $0         $899,000      ($899,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
254. Peachcrest ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
255. Pine Ridge ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $902,000        $0         $902,000      ($902,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
256. Pleasantdale ES           Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
257. Princeton ES              Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $646,000        $0         $646,000      ($646,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                Project budgets are base on approved
                               Update of Security Cameras, Update of Access Controls,
258. Rainbow ES                                                                         E-SPLOST VI   Feb-2023   $359,000        $0         $359,000      ($359,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                               estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
259. Redan ES                  Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $899,000        $0         $899,000      ($899,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
260. Robert Shaw ES            Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
261. Rock Chapel ES            Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $853,000        $0         $853,000      ($853,000)      Fall 24     Fall 24    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
262. Rockbridge ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
263. Ronald E. McNair DLA ES   Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
264. Rowland ES                Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $834,000        $0         $834,000      ($834,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
265. Sagamore Hills ES         Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $806,000        $0         $806,000      ($806,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
266. Shadow Rock ES            Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
267. Smoke Rise ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $340,000        $0         $340,000      ($340,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
268. Snapfinger ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $853,000        $0         $853,000      ($853,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
269. Stone Mill ES             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
270. Stone Mountain ES         Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
271. Stoneview ES              Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000        $0         $640,000      ($640,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule                                                                                                                                                              estimates, including "Original Estimate".
                               Update of Security Cameras, Update of Access Controls,                                                                                                                           Project budgets are base on approved
272. Toney ES                  Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $808,000        $0         $808,000      ($808,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                               Security Vestibule, Update Fire Alarm                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
273. Vanderlyn ES                                                                            E-SPLOST VI   Feb-2023   $140,000     $0   $140,000     ($140,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
274. Wadsworth Magnet                                                                        E-SPLOST VI   Feb-2023   $330,000     $0   $330,000     ($330,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
275. Woodridge ES                                                                            E-SPLOST VI   Feb-2023   $315,000     $0   $315,000     ($315,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
276. Woodward ES                    Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $640,000     $0   $640,000     ($640,000)      Fall 24    Spring 26   Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Gym HVAC, Update of Security Cameras, Update of                                                                                                                        Project budgets are base on approved
277. Wynbrooke ES                   Access Controls, Update of Intrusion Detection, New or   E-SPLOST VI   Feb-2023   $925,000     $0   $1,525,000   ($1,525,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Upgraded Security Vestibule, Update Fire Alarm                                                                                                                        estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
301. DeKalb ES of the Arts          Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $720,000     ($720,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
302. Cedar Grove MS                 Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $5,230,000   $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule (Roof replaced in SP4)                                                                                                                             estimates, including "Original Estimate".
                                    Roof Replacement, Update of Security Cameras, Update                                                                                                                   Project budgets are base on approved
303. Chamblee MS                    of Access Controls, Update of Intrusion Detection, New   E-SPLOST VI   Feb-2023   $4,350,000   $0   $3,370,000   ($3,370,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    or Upgraded Security Vestibule                                                                                                                                        estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
304. Champion Theme MS              Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $1,125,000   $0   $1,275,000   ($1,275,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule, Update Fire Alarm                                                                                                                                 estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
305. Chapel Hill MS                 Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
306. Columbia MS                    Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
307. Druid Hills MS                                                                          E-SPLOST VI   Feb-2023   $705,000     $0   $705,000     ($705,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
308. Freedom MS                                                                              E-SPLOST VI   Feb-2023   $220,000     $0   $220,000     ($220,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
309. Henderson MS                                                                            E-SPLOST VI   Feb-2023   $859,000     $0   $859,000     ($859,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection, Update Fire Alarm
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
310. Lithonia MS                    Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
311. Mary McLeod Bethune MS         Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
312. Miller Grove MS                Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
313. Peachtree MS                   Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
314. Redan MS                       Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
315. Ronald E. McNair MS            Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
316. Salem MS                       Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $1,135,000   $0   $1,285,000   ($1,285,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule, Update Fire Alarm                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
317. Stephenson MS                                                                           E-SPLOST VI   Feb-2023   $220,000     $0   $220,000     ($220,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
318. Stone Mountain MS              Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
319. Tucker MS                      Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $720,000     $0   $870,000     ($870,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
401. AIC Facility (EAHS and DECA)                                                            E-SPLOST VI   Feb-2023   $310,000     $0   $310,000     ($310,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
402. Arabia Mountain HS             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $510,000     $0   $810,000     ($810,000)     Spring 25   Spring 26   Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
403. Cedar Grove HS                 Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $810,000     $0   $1,210,000   ($1,210,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
404. Chamblee HS                    Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $810,000     $0   $1,210,000   ($1,210,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                                                                                                                                                                                           Project budgets are base on approved
                                    Update of Security Cameras, Update of Access Controls,
405. Clarkston HS                                                                            E-SPLOST VI   Feb-2023   $310,000     $0   $310,000     ($310,000)      Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Update of Intrusion Detection
                                                                                                                                                                                                          estimates, including "Original Estimate".
                                    Update of Security Cameras, Update of Access Controls,                                                                                                                 Project budgets are base on approved
406. Columbia HS                    Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023   $810,000     $0   $1,210,000   ($1,210,000)    Fall 24     Fall 25    Active   contracts/commitments only. All other values are
                                    Security Vestibule                                                                                                                                                    estimates, including "Original Estimate".
                                                                                                                                                                                                                   No current scope of work. (Improvements funded under E-
407. Cross Keys HS                      None                                                      E-SPLOST VI   Feb-2023       $0           $0            $0             $0          Fall 24    Fall 25   Active
                                                                                                                                                                                                                                      SPLOST V Project)
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
408. DeKalb School of the Arts          Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
409. Druid Hills HS                     Modernization of the Druid Hills HS Facility              E-SPLOST VI   Feb-2023   $50,000,000   $350,000     $50,000,000   ($49,650,000)   Spring 25   Fall 26   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
410. Dunwoody HS                        Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
411. Lakeside HS                        Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                        Roof Replacement, Update of Security Cameras, Update                                                                                                                                Project budgets are base on approved
412. Lithonia HS                        of Access Controls, Update of Intrusion Detection, New    E-SPLOST VI   Feb-2023   $7,740,000    $3,480,530   $5,010,000    ($1,529,470)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        or Upgraded Security Vestibule                                                                                                                                                     estimates, including "Original Estimate".
                                        Roof Replacement (original building) Update of Security
                                                                                                                                                                                                                            Project budgets are base on approved
                                        Cameras, Update of Access Controls, Update of
413. Martin Luther King Jr. HS                                                                    E-SPLOST VI   Feb-2023   $5,980,000    $2,756,140   $4,210,000    ($1,453,860)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Intrusion Detection, New or Upgraded Security
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                        Vestibule
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
414. Miller Grove HS                    Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023   $1,569,000       $0        $1,969,000    ($1,969,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule, Update Fire Alarm                                                                                                                                              estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
415. Redan HS                           Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
                                        Roof Replacement, Update of Security Cameras, Update
416. Ronald E. McNair High                                                                        E-SPLOST VI   Feb-2023   $5,480,000    $4,942,000   $5,710,000     ($768,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        of Access Controls, Update of Intrusion Detection
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
417. Southwest DeKalb HS                Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
418. Stephenson HS                      Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
                                        Update of Security Cameras, Update of Access Controls,
419. Stone Mountain HS                                                                            E-SPLOST VI   Feb-2023    $310,000        $0         $310,000      ($310,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Update of Intrusion Detection
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
420. Towers HS                           Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $810,000        $0        $1,210,000    ($1,210,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
421. Tucker HS                           Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $510,000        $0         $810,000      ($810,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
501. Coralwood Education                 Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $680,000        $0         $680,000      ($680,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
502. DeKalb High of Technology South
                                         Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $680,000        $0         $680,000      ($680,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
Campus
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
503. Eagle Woods Academy                 Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $680,000        $0         $680,000      ($680,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
504. Early Learning Center at Terry Mill Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $380,000        $0         $380,000      ($380,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
505. East Campus I/DeKalb Alternative Update of Intrusion Detection, New or Upgraded              E-SPLOST VI   Feb-2023    $380,000        $0         $380,000      ($380,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                         Update of Security Cameras, Update of Access Controls,                                                                                                                             Project budgets are base on approved
506. Fernbank Science Center             Update of Intrusion Detection, New or Upgraded           E-SPLOST VI   Feb-2023    $680,000        $0         $680,000      ($680,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                         Security Vestibule                                                                                                                                                                estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
                                        HVAC Refresh, Update of Security Cameras, Update of
507. International Student Center                                                                 E-SPLOST VI   Feb-2023   $6,060,000    $950,000     $17,180,000   ($16,230,000)    Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Access Controls, Update of Intrusion Detection
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                        Roof Replacement, Update of Security Cameras, Update                                                                                                                                Project budgets are base on approved
508. Margaret Harris Comprehensive      of Access Controls, Update of Intrusion Detection, New    E-SPLOST VI   Feb-2023   $1,890,000       $0        $2,180,000    ($2,180,000)     Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        or Upgraded Security Vestibule                                                                                                                                                     estimates, including "Original Estimate".
                                        Update of Security Cameras, Update of Access Controls,                                                                                                                              Project budgets are base on approved
509. Warren Technical                   Update of Intrusion Detection, New or Upgraded            E-SPLOST VI   Feb-2023    $670,000        $0         $670,000      ($670,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                        Security Vestibule                                                                                                                                                                 estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
601. Doraville Bus & Administrative     Update of Security Cameras                                E-SPLOST VI   Feb-2023    $25,000         $0         $85,000        ($85,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
602. East Campus II - Transportation    Update of Security Cameras                                E-SPLOST VI   Feb-2023    $25,000         $0         $85,000        ($85,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                   No current scope of work. (Improvements funded under E-
603. Green Forest Drive                 None                                                      E-SPLOST VI   Feb-2023       $0           $0            $0             $0          Fall 24    Fall 25   Active
                                                                                                                                                                                                                                      SPLOST V Project)
                                                                                                                                                                                                                            Project budgets are base on approved
604. Hatton Drive Warehouse             Update of Security Cameras                                E-SPLOST VI   Feb-2023    $25,000         $0         $85,000        ($85,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
605. Panthersville Bu s& Administrative Update of Security Cameras                                E-SPLOST VI   Feb-2023    $25,000         $0         $85,000        ($85,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
606. Sam A. Moss Service Center         Update of Security Cameras                                E-SPLOST VI   Feb-2023    $50,000         $0         $110,000      ($110,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                            Project budgets are base on approved
607. William Bradley Bryant
                                        Update of Security Cameras                                E-SPLOST VI   Feb-2023    $45,000         $0         $105,000      ($105,000)      Fall 24    Fall 25   Active      contracts/commitments only. All other values are
Technology Center
                                                                                                                                                                                                                           estimates, including "Original Estimate".
                                                                                                                                                                                                                                             No current scope of work. (Improvements funded under E-
608. Old Rock Gym                       None                                                       E-SPLOST VI    Feb-2023          $0               $0                     $0                      $0             -         -      Active
                                                                                                                                                                                                                                                         SPLOST V Champion MS Project)
                                                                                                                                                                                                                                                      Project budgets are base on approved
609. Adams Stadium                      Update of Security Cameras                                 E-SPLOST VI    Feb-2023        $25,000            $0                   $85,000                ($85,000)      Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
610. Avondale Stadium                   Update of Security Cameras                                 E-SPLOST VI    Feb-2023        $25,000            $0                   $85,000                ($85,000)      Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
611. Hallford, James R. Stadium         Update of Security Cameras                                 E-SPLOST VI    Feb-2023        $25,000            $0                   $85,000                ($85,000)      Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
612. North DeKalb Stadium               Update of Security Cameras                                 E-SPLOST VI    Feb-2023        $25,000            $0                   $85,000                ($85,000)      Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
613. William Buck Godfrey Stadium       Update of Security Cameras                                 E-SPLOST VI    Feb-2023        $25,000            $0                   $85,000                ($85,000)      Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
801. Bus & Vehicle Purchase             Purchase of Busses and other vehicles as needed.           E-SPLOST VI    Feb-2023      $35,500,000          $0                 $35,500,000            ($35,500,000)    Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
802. Device refresh                     Replace and purchase computer equipment as needed.         E-SPLOST VI    Feb-2023      $45,000,000          $0                 $45,000,000            ($45,000,000)    Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
                                        Update IT infrastructure as needed to support
803. Infrastructure refresh & Support                                                              E-SPLOST VI    Feb-2023      $45,000,000      $17,000,000            $45,000,000            ($28,000,000)    Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                        continued District operations.
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
804. Update Disaster Recovery Systems Update disaster recovery systems at DCSD facilities          E-SPLOST VI    Feb-2023      $1,500,000           $0                 $1,500,000              ($1,500,000)    Fall 24   Fall 25   Active      contracts/commitments only. All other values are
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                                                                                                                                                                                                                                      Project budgets are base on approved
805. Update Communication
                                        Update communication infrastructure as needed              E-SPLOST VI    Feb-2023      $3,500,000           $0                 $3,500,000              ($3,500,000)    Fall 24   Fall 26   Active      contracts/commitments only. All other values are
Infrastructure
                                                                                                                                                                                                                                                     estimates, including "Original Estimate".
                                        Management of the E-SPLOST program by third party
902. Program Management                                                                            E-SPLOST VI    Feb-2023      $18,000,000      $18,000,000            $10,000,000             $8,000,000         -         -      Active                 Not a construction project
                                        management as well as other consultants, as required.
                                        Salary for District employees in support of the E-SPLOST
901. DCSD Staff                                                                                    E-SPLOST VI    Feb-2023      $10,000,000      $10,000,000            $18,000,000             ($8,000,000)       -         -      Active                 Not a construction project
                                        program
999. Program Contingency                                                                           E-SPLOST VI    Feb-2023      $42,000,000          $0                     $0                      $0             -         -                             Not a construction project.

                                                                                                                                Budget (SP5)    Current Budget      Revised Estimate at      Budget/Estimate
                                                                                                                               Estimate (SP6)    March 2024       Completion March FY24         Difference
                                                                                                                 E-SPLOST V
                                                                                                                               $273,833,434     $353,942,261          $421,190,500            ($67,248,239)
                                                                                                                  Remaining
                                                                                                                 E-SPLOST VI   $700,000,000     $67,448,350           $722,560,000           ($655,111,650)

                                                                                                                                                  Estimated      Total Program Estimate at   Revenue/Estimate
                                                                                                                                                   Revenue        Completion March FY24         Difference

                                                                                                                               E-SPLOST V       $649,300,000          $697,126,610            ($47,826,610)
                                                                                                                               E-SPLOST VI      $780,000,000          $722,560,000             $57,440,000