Paryani Constrution Executed Extension

AID 1615178 · View on Simbli

Agenda Item

iii. GC Services for Stone Mountain High School Weight Room Floor Project (Paryani Construction (Not to exceed $239,800.06)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve the award of the General Contractor Services for the Stone Mountain High School Weight Room Floor Project to Paryani Construction, one of the awarded vendors under the State of Georgia Indefinite Quantity Construction Contract for a not to exceed the amount of $239,800.06, to repair and reinforce the floor under the weight room.
Why: The weight room and concession stand area have been closed and will remain closed until the repairs are completed because there is concern that the concrete pieces will continue to fall and could cause injury. Due to the immediate need to make the repairs, utilizing an approved contractor on the State of Georgia Indefinite Quantity Construction Contract would expedite the completion of the project.
Details: On February 24, 2020, the State of Georgia, in conjunction with Sourcewell issued an ITB to provide access to contractors to provide construction, repair and renovation services over an extended period of time. Paryani Construction was awarded a one (1) year agreement effective April 20, 2020 with three (3) bilateral options to extend the term for an additional term. On March 30, 2023, the contract was extended for the period of April 20, 2023 through April 19, 2024.
Financial impact: The total budget for this project is allocated from the cost code (100.2600.543009.011.7520.9990.8013.040.0000) under the Operations Division General Fund Budget in the fixed-price amount of $239,800.06.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676.1475

Mr. Richard Boyd, Director of Design and Construction, Division of Operations, 678.676.1483
Effective: Upon Board Approval
Status: Approved by General Counsel
          



                               CONTRACT AMENDMENT, MODIFICATION, AND EXERCISE OF OPTION
                                                made by and between

                                                       Paryani Real Estate LLC
                                                       961 W Highland Dr NW
                                                         Atlanta, GA 30318
                                                           (“Contractor”)

                                                                and

                                                             Sourcewell
                                                         202 12th Street NE
                                                             PO Box 219
                                                         Staples, MN 56479
                                               Phone: (218) 894-1930 or (888) 894-1930



             Contractor and Sourcewell have entered into an Indefinite Quantity Construction Contract, Contract
             Number: GA-A07-040820-PAR, with an effective date of April 20, 2020, an initial term of one year, and
             three (3) bilateral options to extend the term for an additional term.

             The parties agree that certain terms within Contract Number GA-A07-040820-PAR will be amended and
             modified, and that the option to extend for a one-year term will be exercised.

             IN CONSIDERATION OF the mutual covenants and agreements described in this Amendment,
             Modification, and Exercise of Option, the parties agree as follows:

             AMENDMENT: CORRECTION OF TYPOGRAPHICAL ERROR

             Section 4. A. of Contract Number: GA-A07-040820-PAR included a typographical error at the time of
             execution. The parties agree that Section 4. A. is amended by striking the word “two” in two locations
             (as indicated by red strikeout font), and inserting the word “four” (as indicated by the underlined font),
             to read as follows:

                     This Contract has an initial term of one (1) year and a bilateral option provision for three (3)
                     additional terms. The total term of the Contract cannot exceed two four (4) years. One
                     additional one-year renewal-extension may be offered by Sourcewell to Contractor beyond the
                     original two four-year term if Sourcewell deems such action to be in the best interests of
                     Sourcewell and its Members. The Contractor may withdraw from the Contract on each
                     anniversary of the award, provided that the Contractor gives 60 Days written notice of its intent
                     to withdraw. Sourcewell may, for any reason, terminate this Contract at any time.

             MODIFICATION: FIRST RENEWAL OPTION PERIOD

             Pursuant to the Contract, a new Construction Task Catalog® will be furnished on the anniversary of the
             solicitation and will be in effect for the twelve (12) month period after the anniversary of the award
             date. The following is the Construction Task Catalog® for the next option period:

             April 2021: Sourcewell Georgia, Northern

             Pursuant to the agreement between the parties, the Adjustment Factors shall remain fixed for the
             duration of the contract and are as follows:
          




                            #GA-A07-040820-PAR                                    Adjustment Factor

                            Non Pre-priced                                        1.1351

                            Normal Working Hours – Non Secure Areas               1.2216

                            Normal Working Hours – Secure Areas                   1.2432

                            Other Than Normal Working Hours - Non Secure Areas 1.2432

                            Other Than Normal Working Hours - Secure Areas        1.2649


             EXERCISE OF OPTION: EXTENSION

             Contractor and Sourcewell hereby desire and agree to extend and renew the above defined contract,
             with the above identified amendment and modifications, for the period of April 20, 2021 through April
             19, 2022.



             Sourcewell


             By:____________________________________, Its: __________Chief Procurement Officer___________


             Name printed or typed: _____________Jeremy Schwartz____________________________

                                 
             Date: ________________________________


             Paryani Real Estate LLC - # GA-A07-040820-PAR


                                                            
             By:____________________________________, Its: _______________________________________________

                                      
             Name printed or typed: ________________________________________________________

                                 
             Date: ________________________________




             If you do not want to extend the contract, please sign below and return this agreement.
             Discontinue: We desire to discontinue the contract.


             Signature:___________________________________________ , Date:__________________________
            



                                         ANNUAL RENEWAL AND MODIFICATION OF CONTRACT

                                                     Paryani Construction (“Vendor”)
                                                        961 West Highland Dr NW
                                                         Atlanta, Georgia 30318

                                                                   and

                                                               Sourcewell
                                                           202 12th Street NE
                                                           Staples, MN 56479


             Whereas: Vendor and Sourcewell have entered into Contract GA-A07-040820-PAR with an effective date of
             April 20, 2020, a maturity date of April 19, 2024, and which is subject to annual renewal at the option of both
             parties.

             MODIFICATION: OPTION PERIOD 4/20/22 – 4/19/23

             Pursuant to the agreement between the parties, a Construction Task Catalog® (CTC) will be furnished on the
             anniversary of the solicitation and will be in effect for the twelve (12) month period after the anniversary of
             the award date. The following is the CTC for the option period April 20, 2022 through April 19, 2023:

                      April 2022 - Sourcewell, Georgia Northern Area

             Pursuant to the agreement between the parties, the Adjustment Factors remain fixed for the duration of the
             contract.

             Now Therefore:

             Vendor and Sourcewell hereby desire and agree to extend and renew the Contract and with the above
             identified modification for the period of April 20, 2022 through April 19, 2023.


                       Sourcewell                                        Paryani Construction




               By: __________________________                         By: __________________________
                                                                           
                    Jeremy Schwartz
               Title: Chief Procurement Officer                       Title: 

                        
               Date: ________________________                                  
                                                                      Date: ________________________
                                 AGREEMENT TO
                              MODIFY AND EXTEND
                     SOURCEWELL CONTRACT #GA-A07-040820-PAR


THIS AGREEMENT TO MODIFY AND EXTEND, Sourcewell Contract #GA-A07-040820-PAR, is effective
upon the date of the last signature below.

Sourcewell and Paryani Construction Contractor have entered into an Indefinite Quantity
Construction Contract, Contract Number GA-A07-040820-PAR, with an initial term ending April 19,
2021, and three bilateral options to extend for an additional one-year term            . The Contract
has previously been extended by the parties for the term ending April 19, 2023. The parties agree to
modify and extend the Contract as stated below.

CONTRACT MODIFICATION

The following is adopted as the new CTC for the Contract effective April 20, 2023:

Sourcewell, Northern Georgia - Area A


term and are unaffected by this modification.

EXERCISE OF OPTION: EXTENSION

Contractor and Sourcewell hereby desire and agree to extend the Contract, with the above modification,
for the period of April 20, 2023 through April 19, 2024.


 Sourcewell                                          Paryani Construction



 By: __________________________                      By: __________________________
      Jeremy Schwartz                                     Manish Paryani
 Title: Chief Procurement Officer                    Title: President

 Date:                                               Date: