Construction Quote_F.H. Paschen_Chapel Hill MS

AID 1483349 · View on Simbli

Agenda Item

ii. EZIQC Contract No. GA-ST01-040820-FHP for General Contractor Services for the Construction of a Soccer Mini-Pitch at Chapel Hill Middle School and Sequoyah Middle School (F.H. Paschen, S.N. Nielsen & Associates, LLC $283,755)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve the award of EZIQC Contract No GA-ST01-040820-FHP to F.H. Paschen, S.N. Nielsen & Associates, LLC. Work to be performed as per the Final Detailed Scope of Work attached and as per the terms and conditions of EZIQC Contract No GA-ST01-040820-FHP for the cost of materials, delivery, design and construction services for the construction of outdoor soccer mini-pitch at both Chapel Hill Middle School in an amount not to exceed $142,284 and Sequoyah Middle School in an amount not to exceed $141,471 for a total of $283,755.

Work to be performed as per the Final Detailed Scope of Work per the terms and conditions of EZIQC Contract No GA-ST01-040820-FHP.
Why: To approve the award of a lump sum construction contract for the cost of materials, delivery, design, and construction services for the construction of outdoor soccer mini-pitch at both Chapel Hill Middle School and Sequoyah Middle School.
Details: The Design and Construction Department is requesting approval for the construction services for the construction of outdoor soccer mini-pitch at both Chapel Hill Middle School and Sequoyah Middle School to be performed by F.H. Paschen, S.N. Nielsen & Associates, LLC.

The Design and Construction Department is requesting to utilize a Sourcewell (formerly known as National Joint Powers Alliance) cooperative contract. Sourcewell Solicitation Number: EZIQC Contract No GA-ST01-040820-FHP contract permits the general construction services for K-12 education uses. This contract is between Sourcewell, 202 12th Street Northeast, P.O. Box 219, Staples, MN 56479 (Sourcewell) and F.H. Paschen, S.N. Nielsen & Associates, LLC is located at 739 Trabert Avenue NW, Suite A, Atlanta, GA 30318 in the State of Georgia.

Use of Cooperative Agreements increases economies of scale, resulting in efficiencies regarding reduced unit costs as well as shipping costs, installation, and administrative oversight. This recommendation is based on the review and evaluation of the price quote provided by the Sourcewell contract regulations. The DeKalb County School District’s Standard Form of Fixed Price Construction Contract will be used. F.H. Paschen, S.N. Nielsen & Associates, LLC is located at 739 Trabert Avenue NW, Suite A, Atlanta, GA 30318.
Financial impact: The total contract amount of $283,755 for the Chapel Hill Middle School soccer mini-pitch in the amount of $142,284 and Sequoyah Middle School Soccer mini-pitch in the amount of $141,471 will be allocated from cost code 100.2600.543009.00011.7520.9990.8013.040.0000, MAINT-SYS-PARTS & MAJOR WORK.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676.1475
Mr. Richard H. Boyd, Director of Design and Construction, Division of Operations, 678.676.1483
Mr. Bobby Moncrief, Director of Facilities, Division of Operations, 678.676.1478
Effective: Upon Board Approval
Status: Approved by General Counsel
                                                                                                                                         2.00




Work Order Signature Document

                                           EZIQC Contract No.: GA-ST01-040820-FHP

                                X       New Work Order              Modify an Existing Work Order

 Work Order Number:         111931.00                         Work Order Date:        12/05/2022

 Work Order Title:     DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
 Owner Name:       DeKalb County School District              Contractor Name:        F.H. Paschen, S.N. Nielsen & Assoc., LLC
 Contact:          Lemuel Hawkins                             Contact:                Wayne Thompson
 Phone:            404-668-9960                               Phone:                  404-942-1307

                                                   Work to be Performed
 Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
 EZIQC Contract No GA-ST01-040820-FHP.
 Brief Work Order Description:
 DCSD - Chapel Hill Middle School Mini Pitch Soccer Field




 Time of Performance                See Schedule Section of the Detailed Scope of Work


Liquidated Damages                  Will apply:             Will not apply:       X


 Work Order Firm Fixed Price: $142,284.00

      Owner Purchase Order Number:


 Approvals




 Owner                                                    Date           Contractor                                               Date




Work Order Signature Document                                                                                                    Page 1 of 1
                                                     DeKalb County School District                                                12/5/2022
                                                                                                                               3.00




Detailed Scope of Work

To:   Wayne Thompson                                                   From:    Lemuel Hawkins
      F.H. Paschen, S.N. Nielsen & Assoc., LLC                                  DeKalb County School District
      739 Trabert Ave NW, Suite A                                               1780 Montreal Road
      Atlanta, Ga 30318                                                         Tucker, GA 30084
      404-942-1307                                                              404-668-9960

Date Printed:             December 05, 2022

Work Order Number:        111931.00

Work Order Title:         DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Brief Scope:              DCSD - Chapel Hill Middle School Mini Pitch Soccer Field


                Preliminary                              Revised                                     X    Final


The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.


Contractor to provide all necessary labor, material, and supervision for DCSD - Chapel Hill Middle School Mini Pitch
Soccer Field project as outlined in the attached Detailed Scope of Work .




Contractor                                                            Date




Owner                                                                 Date




Scope of Work                                                                                                          Page 1 of 1
                                                    DeKalb County School District                                       12/5/2022
                                                                                                            4.00




Contractor's Price Proposal - Summary
Date:                              December 05, 2022

IQC Master Contract #:             GA-ST01-040820-FHP
Work Order Number:                 111931.00
Owner PO #:
Work Order Title:                  DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Contractor:                        F.H. Paschen, S.N. Nielsen & Assoc., LLC
Proposal Name:                     DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Proposal Value:                    $142,284.00

Bond                                                                                                $1,936.00

Fencing Demolition                                                                                   $802.00

Synthetic Turf                                                                                    $139,546.00

Proposal Total                                                                                    $142,284.00

This total represents the correct total for the proposal. Any discrepancy between line totals,
sub-totals and the proposal total is due to rounding.

The Percentage of NPP on this Proposal:                               %




Contractor's Price Proposal - Summary                                                               Page 1 of 1
                                                                  DeKalb County School District      12/5/2022
                                                                                                                                                             5.00




Contractor's Price Proposal - Detail
Date:                             December 05, 2022

IQC Master Contract #:            GA-ST01-040820-FHP
Work Order Number:                111931.00
Owner PO #:
Work Order Title:                 DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Contractor:                       F.H. Paschen, S.N. Nielsen & Assoc., LLC
Proposal Name:                    DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Proposal Value:                   $142,284.00


         Sect.         Item       Modifer   UOM      Description                                                                                      Line Total
Labor      Equip.    Material   (Excluded if marked with an X)


Bond

   1     01 22 16 00 0002                   EA          Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible                $1,936.00
                                                        costs as directed by Owner. Insert the appropriate quantity to adjust the base
                                                        cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees,
                                                        list each one separately and add a comment in the "note" block to identify the
                                                        Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended
                                                        warranty, expedited shipping costs, etc.). A copy of each receipt shall be
                                                        submitted with the Price Proposal.
                                                                     Quantity                Unit Price                    Factor            Total
                                            Installation                           x                         x                     =     1,936.00
                                                                     1,760.00                       1.00                  1.1000
                                            Bond

Subtotal for Bond                                                                                                                                    $1,936.00

Fencing Demolition

   2     01 22 16 00 0002                   EA          Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible                   -$0.45
                                                        costs as directed by Owner. Insert the appropriate quantity to adjust the base
                                                        cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees,
                                                        list each one separately and add a comment in the "note" block to identify the
                                                        Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended
                                                        warranty, expedited shipping costs, etc.). A copy of each receipt shall be
                                                        submitted with the Price Proposal.
                                                                     Quantity                Unit Price                    Factor            Total
                                            Installation                           x                         x                     =        -0.45
                                                                        -0.45                       1.00                  1.0000
   3     32 31 13 13 0147                   LF          6' Galvanized Chain Link Fence, 9 Gauge Coiled Spring Mesh, Top And Bottom                     $802.45
                                                        Rails, 2-1/2" Line Post At 10' On Center, 3" Corner Post
                                                                     Quantity                 Unit Price              Factor                 Total
                                            Installation                            x                        x               =               0.00
                                                                         0.00                      36.17             1.0081
                                            Demolition              400.00      x                1.99      x            1.0081 =          802.45
                                            Demo Existing Fence

Subtotal for Fencing Demolition                                                                                                                       $802.00

Synthetic Turf

   4     01 22 16 00 0002                   EA          Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible                   -$0.79
                                                        costs as directed by Owner. Insert the appropriate quantity to adjust the base
                                                        cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees,
                                                        list each one separately and add a comment in the "note" block to identify the
                                                        Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended
                                                        warranty, expedited shipping costs, etc.). A copy of each receipt shall be
                                                        submitted with the Price Proposal.
                                                                     Quantity                Unit Price                    Factor            Total
                                            Installation                           x                         x                     =        -0.79
                                                                        -0.79                       1.00                  1.0000




Contractor's Price Proposal - Detail                                                                                                                 Page 1 of 3
                                                                 DeKalb County School District                                                        12/5/2022
Contractor's Price Proposal - Detail Continues..


Work Order Number:              111931.00
Work Order Title:               DCSD - Chapel Hill Middle School Mini Pitch Soccer Field

Proposal Name:                    DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Proposal Value:                   $142,284.00


         Sect.         Item       Modifer   UOM        Description                                                                                    Line Total
Labor      Equip.    Material   (Excluded if marked with an X)


Synthetic Turf

   5     01 22 23 00 1023                   WK          10,000 LB Telescopic Boom, Hi-Reach, Rough Terrain Construction Forklift                      $3,914.92
                                                        With Full-Time Operator
                                                                     Quantity             Unit Price                  Factor                 Total
                                            Installation                        x                       x                     =          3,914.92
                                                                        1.00               3,883.46                  1.0081
                                            Material Lift
   6     01 22 23 00 1401                   WK          6 CY Rear Dump Truck With Full-Time Truck Driver                                              $3,891.96
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =       3,891.96
                                                                        1.00                   3,860.69                 1.0081
                                            Disposal
   7     07 22 16 00 0277                   SF          3.75" Average Thickness (20.63 Average R-Value), 1/8" Slope, Tapered                         $31,247.07
                                                        Extruded Polystyrene Board (XEPS), Cold Adhesive Applied
                                                                    Quantity               Unit Price                  Factor                Total
                                            Installation                         x                       x                    =         31,247.07
                                                                   5,400.00                      5.74                 1.0081
                                            Use for EPS Underlayerment
   8     31 23 16 36 0021                   CY          Compaction Of Fill Or Subbase For Building Foundations and Other Structures                    $317.45
                                                        by Vibratory Plate, Air Tamper, Etcetera
                                                                     Quantity                 Unit Price              Factor                 Total
                                            Installation                           x                     x                    =            317.45
                                                                       67.00                        4.70              1.0081
                                            Site Work
   9     31 23 16 36 0021         0024      MOD         For >50 To 250, Add                                                                            $126.98
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =         126.98
                                                                       67.00                       1.88                 1.0081
  10     31 23 16 36 0026                   SY          Finish Grading For Building Foundations And Other Structures by Hand                          $2,776.31
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =       2,776.31
                                                                      600.00                       4.59                 1.0081
                                            Site Work
  11     32 11 16 16 0005                   SY          2" Crushed Aggregate Base Course For Roadways And Parking Areas                               $1,983.94
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =       1,983.94
                                                                      600.00                       3.28                 1.0081
                                            Use for crushed granite stone base
  12     32 11 16 16 0005         0009      MOD         For >500 To 1,000, Add                                                                         $199.60
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =         199.60
                                                                      600.00                       0.33                 1.0081
  13     32 18 23 29 0098                   SF          2-1/2" Height, 53 Ounce, Tufted 3/8" Gauge Monofilament Synthetic Turf With                  $38,215.05
                                                        Thatch Layer And Ethylene Propylene Diene Monomer (EPDM) Infill (G9 Turf
                                                        Playmaker Turf)For football and multi-sport fields. Excludes preparation of
                                                        sub-base, grooming, sports lines and logos.
                                                                    Quantity                 Unit Price                   Factor             Total
                                            Installation                          x                           x                     =   38,215.05
                                                                    5,400.00                       7.02                   1.0081
                                            Turf Install
  14     32 18 23 29 0102                   EA          Soccer Inlays For G9 Synthetic Turf                                                          $24,918.76
                                                                     Quantity                 Unit Price                Factor               Total
                                            Installation                         x                         x                     =      24,918.76
                                                                        1.00                  24,718.54                 1.0081
                                            Soccer Inlays


Contractor's Price Proposal - Detail                                                                                                                 Page 2 of 3
                                                                 DeKalb County School District                                                        12/5/2022
Contractor's Price Proposal - Detail Continues..


Work Order Number:              111931.00
Work Order Title:               DCSD - Chapel Hill Middle School Mini Pitch Soccer Field

Proposal Name:                     DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Proposal Value:                    $142,284.00


         Sect.          Item       Modifer    UOM       Description                                                                                       Line Total
Labor      Equip.    Material    (Excluded if marked with an X)


Synthetic Turf

  15     32 18 23 29 0109                     SF         Styrene-Butadiene Rubber (SBR) Infill For G9 Synthetic Turf                                     $10,833.04
                                                                      Quantity                   Unit Price              Factor                Total
                                              Installation                          x                         x                   =       10,833.04
                                                                      5,400.00                        1.99               1.0081
                                               Use for Crumb Rubber infill
  16     32 18 23 29 0117                     SF          Drainage Layer For G9 Synthetic TurfUsed for drainage over asphalt or on roof                  $21,121.71
                                                          tops.
                                                                     Quantity                 Unit Price                 Factor                Total
                                              Installation                        x                         x                     =       21,121.71
                                                                     5,400.00                       3.88                1.0081
                                               Use for Drainage Layer

Subtotal for Synthetic Turf                                                                                                                            $139,546.00


Proposal Total                                                                                                                                         $142,284.00

This total represents the correct total for the proposal. Any discrepancy between line totals,
sub-totals and the proposal total is due to rounding.


The Percentage of NPP on this Proposal:                               %




Subcontractor Listing                                                                                                                                     Page 3 of 3
                                                                  DeKalb County School District                                                            12/5/2022
Client - DeKalb County School District

Detailed Scope of Work

Print Date:              December 05, 2022

Work Order Number:       111931.00
Work Order Title:        DCSD - Chapel Hill Middle School Mini Pitch Soccer Field
Contractor:              GA-ST01-040820-FHP - F.H. Paschen, S.N. Nielsen & Assoc., LLC
Brief Scope:             DCSD - Chapel Hill Middle School Mini Pitch Soccer Field

To:     Wayne Thompson                                                    From:     Lemuel Hawkins
        F.H. Paschen, S.N. Nielsen & Assoc., LLC                                    DeKalb County School District
        739 Trabert Ave NW, Suite A                                                 1780 Montreal Road
        Atlanta, Ga 30318                                                           Tucker, GA 30084
        404-942-1307                                                                404-668-9960
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.
Detailed Scope:

Contractor to provide all necessary labor, material, and supervision for DCSD - Chapel Hill Middle School Mini Pitch
Soccer Field project as outlined in the attached Detailed Scope of Work .




Owner                                                                    Date




Contractor                                                               Date




Detailed Scope of Work                                                                                                 Page 1 of 1
                                                                                                                        12/5/2022
                                                      DeKalb County School District
                                  SCOPE OF WORK
           DeKalb County School District – Chapel Hill Middle School Mini Pitch
                      3535 Dogwood Farm Rd, Decatur, GA 30034
                                  December 5th, 2022

Summary Scope
Installation of 60’ x 90’ synthetic turf to be used as a mini pitch soccer field.

Detailed Scope of Work
The Contractor shall furnish the materials, equipment, labor, and supervision to provide and
install the work as described below;


Synthetic Turf

      Furnish and Install EPS perimeter boarding
      Furnish and Install crushed stone sub-base
      Furnish and Install rubber infill
      Furnish and Install approximately 5400 SF of premium synthetic turf and secure to
       perimeter boarding
Fencing Demolition

      Remove and dispose of existing perimeter fence


Clarifications

      There is an existing fence on site that will need to be demolished
      Installation of new fencing after demolition is not included.
Details that Apply to All Work Areas:
   1. Contractor shall utilize the latest issue of the ezIQC Specifications for all work.
   2. All submittals are to be provided to the Owner as part of the submittal process prior to
       installation by the contractor.
   3. Maintain clean work areas at all times. Remove and dispose of all demolished materials
       and construction debris. Site must be cleaned every day at the completion of work.
   4. All measurements and quantities supplied in this scope of work are approximate in nature
       and are supplied as a convenience for the contractor. The contractor is responsible for
       field verification of all measurements and quantities.
   5. Contractor shall verify all new and existing conditions and dimensions at job site prior to
       the proposed process start of construction, and during construction.
   6. The Contractor shall perform all work, make all deliveries and have access to work areas
       between 7:30 A.M. and 5:00 P.M. Monday through Friday and, upon written permission
       of the Owner, may make deliveries and have access to work areas at any hour of any day,
       but shall bear without any contribution from the Owner, any extra expense and
       responsibility for doing so, including, without limitation, its own overtime expense.
       Contractor shall coordinate inspections as required.
   7. Parking will be made available for the Contractor by the Owner and the Contractor shall
       coordinate all parking with the Owner prior to beginning work.
   8. Contractor shall obtain approvals in advance for all lay down and storage areas.
   9. All salvageable materials remain the property of the Owner.
   10. Contractor shall coordinate inspections as required.
   11. Prior to any shut-down of any system (electrical, mechanical, etc.), Contractor shall
       supply, not less than five (5) working days’ notice to the Architect with a copy to the
       Owner. No shutdown of any system shall occur until the Contractor has received
       permission from the Owner in writing.
   12. Contractor is responsible for protection of all surfaces including those not in the scope of
       work from construction dust, debris or damage during construction up until final
       acceptance. The methods of protection including plastic, paper, sealing doors or
       windows, etc.
   13. Final clean up and disposal: Remove debris, rubbish, and waste material from the
       property of the Owner on a daily basis. Upon completion of work, all construction areas
       shall be left clean and free from debris. Clean all dust, dirt, stains, hand marks, paint
       spots, droppings, and other blemishes.
   14. Contractor shall not be required to pay Davis Bacon Wage Rates.
Exclusions:
   1. Any and all work associated with hazardous materials including asbestos, lead, and mold
       is excluded from this scope of work. If at any time hazardous materials are uncovered,
       work will stop until the appropriate method of abatement or removal is determined.
       Method of removal may initiate a contract modification.

Submittals:
   1. Contractor shall submit to Owner, cut sheets Submittals / Product Data

Permitting:
At the time of issuance of a Purchase Order for this Work, it is understood that permits are not
required for this Work. If this changes, the Contractor will be responsible for obtaining such
applicable permits and the Owner will be responsible for compensating the Contractor for permit
fees and any design necessary to obtain such permits or related approvals as described in the
EZIQC master contract documents (i.e. permit fees are dollar for dollar reimbursable and
professional design and engineering fees are paid for at hourly rates published in the
Construction Task Catalog).


Schedule:
   1. All work shall be completed during normal working hours (7:30am to 5pm) as directed
      by Owner.
   2. Project construction will be scheduled upon receipt of the PO.


Owner Responsibilities:
  1. Provide access to the worksite during normal working hours.
  2. Provide a staging area for project related materials.
  3. Owner shall be responsible for re-routing pedestrian traffic as necessary.

Contract Document Order of Precedence:
Contract documents shall govern in the order first listed below:
   1. This Detailed Scope of Work
   2. EZIQC master contract document
   3. Owner issued Contract Documents
           a. Specifications, Drawings, and Sketches.
           b. Other documents referenced immediately above.