Preliminary AE Report

AID 1436180 · View on Simbli

Agenda Item

i. E-SPLOST V Project: 364-35 Approval of Additional Scope of Work and Related Budget Adjustment for the Hawthorne Elementary School Major Building System Replacement (in the amount of $330,000)

Summary: Presented by: Mr. Richard Boyd, Interim Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve additional scope of work for E-SPLOST V Project 36435: Hawthorne ES to include replacing the roof.

It is also requested that the Board of Education approve a related budget adjustment in the amount of $330,000 to cover the cost of the additional scope of work.
Why: To provide the Hawthorne ES facility with further needed improvements related to safety, security, and health. The additional scope of work was recommended by the project’s design professionals and/or requested by DCSD Facilities to fulfill program wide initiatives. The requested budget addition is based on the opinions of probable costs provided by the project’s design professionals.
Details: On July 12, 2021, the Board approved the award of RFQu No. 21-752-032 for Professional Architectural and Engineering Services for Nancy Creek Facility, Dresden Elementary School, Kingsley Elementary School, and Hawthorne ES to SSOE.

The E-SPLOST V Project 36435: Hawthorne ES currently has a scope of work that includes “Major building system replacement with emphasis on HVAC components and plumbing”.

It is requested that the scope of work be expanded to include “...replacing the roof.”

It is also requested that the budget of E-SPLOST V Project 36435: Hawthorne ES be increased by $330,000 to cover the additional cost of the increased scope of work. This budget would be transferred from E-SPLOST V Project 60235: Program Contingency.
Financial impact: A budget transfer of $330,000. from E-SPLOST V Project 60235: Program Contingency (cost code: SP5MANG. 60235.PRGCONTIN) to E-SPLOST V Project 36435: Hawthorne ES (cost code: SP5FACCON. 36435.GENERALCONTRACTOR).
Contact: Mr. Richard Boyd, Interim Chief Operating Officer, Division of Operations, 678.676.1483
Mr. Hans Williams, Director of Planning and E-SPLOST Programming, Division of Operations, 678.676.1588
Effective: Upon board approval.
Status: Approved by General Counsel.
Preliminary Consultation

Hawthorne Elementary School
Major Building System Renovation




DCSD Project Number: 364-035
SSOE|S&W Project Number: 021-01172-03

September 07, 2021




Prepared by:
Dekalb County School District                       Hawthorne Elementary School
                                                Major Building System Renovation



Dekalb County School District
Hawthorne Elementary School – Major Building System Replacement


Dekalb County School District
1701 Mountain Industrial Boulevard
Stone Mountain, Georgia 30083
Ms. Cheryl Watson-Harris, Superintendent
https://www.dekalbschoolsga.org/



Dekalb County School District Facilities
Sam Moss Service Center
1780 Montreal Road
Tucker, GA 30084
Brian Albanese
Senior Project Manager
404.242.4582 (c)
C09271212@dekalbschoolsga.org




Hawthorne Elementary School
2535 Caladium Drive NE
Atlanta, Georgia 30345

http://www.hawthornees.dekalb.k12.ga.us/




                                             Preliminary Consultation | 09.07.21 | 1
 Dekalb County School District                                Hawthorne Elementary School
                                                          Major Building System Renovation

DESIGN TEAM
Architecture:
SSOE | Stevens & Wilkinson
100 Peachtree Street, NW
Suite 2500
Atlanta, Georgia 30303
https://ssoe-sw.com/

 Bill Polk, AIA, LEED BD+C                     Josef Fischer
 Principal-in-charge                           Project Manager
 404.521.6208 (d), 404.723.8287 (c)            404.521.6358
 bpolk@ssoe.com                                jfischer@ssoe.com

Engineering:
SSOE | Stevens & Wilkinson
100 Peachtree Street, NW
Suite 2500
Atlanta, Georgia 30303
https://ssoe-sw.com/

 Ken Daenecke                                  Grant Cherrington
 Engineering Principal-in-charge, Electrical   HVAC Project Manager
 Project Manager
 404.521.6332 (d)                              404.521.6342 (d)
 kdaenecke@ssoe.com                            gcherrington@ssoe.com

Cost Estimating:
ADE Construction Consultants, Inc
1298 Rockbridge Road
Suite A
Stone Mountain, Georgia 30087

 Dan Ergle
 770.921.2701
 danergle@adeconstructionconsultants.com

Civil Engineering
Eberly & Associates
2951 Flowers Road South
Suite 119
Atlanta, Georgia 30341

 Jeremiah Phillips, PE
 678.287.4727 (d)
 jphillips@eberly.net



                                                       Preliminary Consultation | 09.07.21 | 2
Dekalb County School District                                   Hawthorne Elementary School
                                                            Major Building System Renovation




TABLE OF CONTENTS
Table of Contents
Introduction
      Report Scope                                                       p.4
      Project Summary                                                    p.4
      Schedule Summary                                                   p.4
      Budget Summary                                                     p.4

Context / Existing Conditions
      Hawthorne Elementary School                                        p.5
      Design Criteria                                                    p.6
      Building Codes                                                     p.6

Strategy
      Hawthorne Elementary School HVAC Solutions                         p.8
      Hawthorne Elementary School Electrical Solutions                   p.13
      Hawthorne Elementary School Life Safety Solutions                  p.15
      Hawthorne Elementary School Plumbing Solutions                     p.16
      Hawthorne Elementary School Site Improvement Solutions             p.16
      Hawthorne Elementary School Architectural Solutions                p.17

Executive Summary                                                        p.20

Preliminary Cost Analysis                                                Appendix 1




                                                         Preliminary Consultation | 09.07.21 | 3
 Dekalb County School District                                     Hawthorne Elementary School
                                                               Major Building System Renovation

INTRODUCTION
Report Scope
This report will assess existing conditions at Hawthorne Elementary School and recommend
replacement options for major systems and related improvements.
Project Summary/Scope of Work
Dekalb County School System has defined a scope of work to replace heating, ventilation, and
air conditioning (HVAC) components at Hawthorne Elementary School. The scope of work
includes the following items from the original RFP #RFQu 21-752-032 for Hawthorne (364-35),
dated 03.25.21:

        •   Replacement of HVAC components throughout the building
The above is not intended to be an all-inclusive list of the scope of work. At the pre-proposal
meeting held on August 13, Brian Albanese reiterated the RFQ’s intent for SSOE | S&W to
make scope recommendations based on the existing conditions observed as part of our report.
SSOE | S&W recommends the following items to be added to the scope, to be elaborated in the
remaining sections of our report.

       •    Roof replacement
       •    Full HVAC system replacement
       •    Fire alarm replacement
       •    Intercom replacement
       •    Outdoor and classroom lighting replacement
       •    Emergency generator installation
       •    Fire sprinkler installation
       •    Ceiling replacement
       •    Modifications to room layout to allow for the creation of a dedicated electrical room
            separate from mechanical room 99.4, affecting rooms 99.4, 101, 101.1, 101.2 102,
            and 102.1.
       •    Plumbing fixture replacement one for one
       •    Main sewer line replacement – approximately 100’ of subgrade exterior
       •    Wheelchair lift for stage
Schedule Summary
The construction phase is tentatively scheduled to occur per the RFP from 07.01.22 through the
07.31.23. Design work is to be completed by mid-January 2022, with permitting and bidding
scheduled for early 2022, allowing time for a contractor to begin procuring equipment prior to
construction start.
Budget Summary
The construction budget for this project is $3,350,000. The preliminary cost review included in
this report is based on this narrative and will be used to reconcile the scope with the budget.
Our preliminary cost review has a proposed construction budget of $5,671,659. This initial cost
analysis shows an 69% increase in the stated cost limitation defined by the original RFQ.

                                                            Preliminary Consultation | 09.07.21 | 4
 Dekalb County School District                                     Hawthorne Elementary School
                                                               Major Building System Renovation

CONTEXT / EXISTING CONDITIONS
Hawthorne Elementary School is a 53,418 square foot one-story elementary school building in
the Dekalb County School System. The original building (building 2010) is 32,060 square feet
and was constructed in 1961. A one-story 6,240 square foot addition (building 2011) was built in
1963, a 9,640 square foot one-story addition (building 2012) was built in 1966, and a 5,478
square foot gym (building 2020) was built in 2003.




                                                                                                  ^
^ Hawthorne Elementary School Aerial View

HVAC: The school has several types of HVAC systems.

    •   Building 2010, 2011, 2012: 2-pipe system water source heat pump (WSHP) with zone
        level WSHPs, and unit ventilators. The 2-pipe system distributes condenser water to the
        WSHPs.
    •   Building 2010: The administration area is partially separated from the main system and
        served by mini-split ductless units with condensers on grade outside.
    •   Building 2020: gymnasium has a 25 ton packaged air conditioning unit installed on grade
        on the north side of the building. The unit cools supply air by direct expansion (DX)
        refrigerant and heats utilizing natural gas. Supply and return duct work is installed on the
        building exterior.
    •   The existing boiler exploded recently and has not been replaced. The zone pumps are
        leaking throughout the building.
    •   Abandoned unit ventilator cabinets still exist along the exterior wall of all classrooms,
        and are open to unconditioned outside air.
    •   Existing 1960s ductwork is not insulated properly in select locations around the building.


                                                            Preliminary Consultation | 09.07.21 | 5
 Dekalb County School District                                       Hawthorne Elementary School
                                                                 Major Building System Renovation

   •   Piping systems are insulated with asbestos laden material identified with warning
       language labeled on the insulation. Replacement will require hazardous materials
       remediation.
Fire Protection: The facility is not currently served by a fire sprinkler system.
Plumbing: Restroom fixtures are not operational in many locations and beyond their useful life.
Partition doors are attached to demising walls built of glazed units and CMU. Doors are
consistently pulled out of broken glazed units. Water heater dates vary but are past their useful
life. The school sanitary system backs up frequently due to a problem downstream in the main
line. Scoping will be required to verify the issue.
Electrical: Electrical systems for each building appear to date to the original construction for
each building. Lighting has been replaced in the corridors, media center, and cafeteria with flat
panel LED fixtures. Classrooms, administrative offices, and back-of-house spaces are provided
with fluorescent fixtures.
Low Voltage: Fire alarm and sound system appear to date to the original construction for each
building.



Design Criteria

SSOE | S&W will follow the Dekalb County School District Design Guidelines for Facility
Construction, version 2018.04.04.

SSOE | S&W has also reviewed the School Assessment Reports for the school dated May 19,
2016 and April 15, 2021. Based on our review of these reports, the scope of work and our
recommendations for renovation / replacement will align with the recommendations of these
reports.


Building Codes

State Minimum Standard Codes
   • International Building Code (IBC), 2018 Edition w/ Georgia Amendments dated 2020
   • International Fire Code (IFC), 2018 Edition as amended by OICFSC Rules and
       Regulations 120-3-3
   • International Plumbing Code (IPC), 2018 Edition w/ Georgia Amendments dated 2020
   • International Mechanical Code (IMC) 2018 Edition w/ Georgia Amendments dated 2020
   • International Fuel Gas Code (IFGC) 2018 Edition w/ Georgia Amendments dated 2020
   • National Electrical Code, 2020 Edition w/ Georgia Amendments dated 2021
   • International Energy Conservation Code, 2015 Edition w/ Georgia Supplements and
       Amendments dated 2020.
   • NFPA 101 Life Safety Code, 2018 Edition as amended by OICFSC Rules and
       Regulations 120-3-3
   • Georgia Accessibility Code as adopted and amended by OICFSC Rules and
       Regulations 120-3-20

                                                              Preliminary Consultation | 09.07.21 | 6
 Dekalb County School District                                     Hawthorne Elementary School
                                                               Major Building System Renovation


Life Safety Code 2018 - Chapter 43.4
The project scale per LSC Chapter 43 Building Rehabilitations definition for Renovation will
apply for most of Hawthorne Elementary School. New work shall comply with the requirements
of Chapter 15 Existing Education and associated referenced sections. New interior finish
materials will need to meet the requirements for new construction. A proposed Modification per
Section 43.5 is provided as shown in Appendix 2 to resolve the existing mechanical and
electrical room 99.4 clearance issues. The new fire riser location is proposed in mechanical
room 99.4. The addition of sprinklers to Hawthorne Elementary School may require the work to
comply with Section 43.5 Modifications which requires the new work to comply with the
requirements of new construction, Chapter 14 Education, and associated referenced sections.

Means of Egress occupancy load and exit capacity will be confirmed based on current
Certificates of Occupancy or assumption of occupancy based on classroom occupants:
   • Hawthorne ES– Since no Certificate of Occupancy is available for this building, assume
        40 occupants per classroom (25 classrooms = 1,000 occupants) + the cafeteria
        occupancy at 15 SF per occupant in 4,426 SF = 296 occupants for a total max
        occupancy of 1,296, well within the calculated existing exit capacity of 2,240, utilizing 7
        double doors.


GA IBC 2020 Amendments – Section 3401
The Georgia Amendments to the 2018 IBC added Section 3401.7 ‘Existing System
conformance’ to clarify the extents of existing systems that will have to be modified to conform
to the requirements of the State Minimum Standard Codes. Item #1 will require new work to be
brought into conformance with the current codes if the new work is less than 50% of the
replacement cost of the existing system. Item #2 will require the entire system to be made to
conform to current codes if the new work is equal to or greater than 50% of the replacement
cost of the existing system. Most of the proposed project scope will fall under item #2 requiring
the entire system meet current code. Systems impacted will be existing mechanical, electrical,
plumbing, and life safety systems. Plumbing fixture replacement will be one for one and will not
include renovation of the toilet rooms.




                                                            Preliminary Consultation | 09.07.21 | 7
 Dekalb County School District                                 Hawthorne Elementary School
                                                           Major Building System Renovation

Hawthorne Elementary School
HVAC Solutions
DCSD scope for Hawthorne Elementary is listed as component replacement. Based on the age
of systems and site assessment SSOE | S&W is recommending that the scope be modified to
include a complete system replacement. The system replacement recommended is a water
source heat pump condenser water loop system, including all associated duct work.

Demolition:
At building 2010, 2011, and 2012, remove and discard the existing HVAC systems including:
   • Cooling tower
   • Natural gas fired boiler
   • Condenser water pumps
   • Packaged WSHPs
   • Exhaust fans
   • Split systems
   • Condenser water piping
   • Metal and non-metal duct work
   • Grilles, registers, and diffusers
   • Direct digital controls systems
   • All systems in the ceiling plenum that have been previously abandoned in place.
   • All systems and equipment on the roof that have been previously abandoned in place.

Existing systems to remain include:
  • Gymnasium (building 2020) is served by a brand-new packaged unit mounted on grade.
       No work shall be required in this building.
  • Process systems are not part of this scope of work and as such will not be replaced. This
       pertains primarily to all existing kitchen systems.


Proposed HVAC System:
DCSD acceptable equipment manufacturers for select equipment:
  • Exhaust fans: Greenheck, Cook, Jennaire, Gaylord, Halton, and CaptiveAire
  • Cooling Towers: Evapco
  • Water treatment: Superior Water Services, Inc.
  • Boilers: Ajax, Rite, and Apac
  • Chillers (air cooled only): Carrier
  • Pumps: Bell & Gossett, Flo‐Fab, Patterson, Taco, Inc., and Armstrong
  • Dehumidification Units: Munters
  • Heat Exchangers: Sondex, Inc.
  • Flow Controls and Balancing Valves for Supply and Return Line Assemblies: Flow
     Design, Inc., Griswold, and Bell & Gossett




                                                        Preliminary Consultation | 09.07.21 | 8
 Dekalb County School District                                   Hawthorne Elementary School
                                                             Major Building System Renovation

   •   Automated Temperature Controls and Energy Management System: Direct digital
       control system sole source is STAEFA TALON. Submit listing of control points for
       approval by DeKalb County School District.
   •   Building automation system controls shall be Web Control by CCI only.


The following is a schematic summary of the new HVAC systems:
   1. Central Energy Systems
           a. Provide two (2) new natural gas fired condensing boilers totaling 4.25 MBTU/hr
               (one 2,000 MBTU/hr and one 1,000 MBTU/hr).
           b. Provide one (1) new 150 ton / 360 gallon per minute (gpm) cooling tower with
               water side economizer. Cooling tower shall be closed circuit type.
           c. Provide two (2) new 25 horse power (hp) condenser water pumps.
           d. Provide new chemical treatment system for hydronic loop.
           e. Cooling tower fan and condenser water pumps shall be variable frequency drive
               (VFD).
   2. Controls
           a. Provide all new direct digital controls (DDC).
   3. Ventilation Systems
           a. Provide two (2) new dedicated outdoor air systems (DOAS), one for each
               classroom wing. Each DOAS shall serve fourteen classrooms, each with 30
               students. Outdoor air flow shall be provided at 10 CFM per person and 0.12 CFM
               per ft2. Each classroom shall be provided with 400 CFM. Each DOAS shall
               provide 5,500 CFM.
           b. DOAS units shall ventilate core restrooms and classroom restrooms in each
               wing. Each core restroom shall require approximately 1,300 CFM of exhaust air.
               Each classroom restroom shall require approximately 100 CFM of exhaust air.
           c. DOAS units shall have powered exhaust accessory to relieve excess pressure.
           d. Janitor's closet shall have dedicated inline exhaust fan (EF) estimated to be 150
               CFM.
   4. Environmental Units
           a. Kitchen
                     i. Packaged roof top unit (RTU) with natural gas heating. Estimated size of
                        5 tons.
           b. Cafeteria
                     i. Packaged water source heat pump (WSHP). Estimated size of 25 tons.
           c. Media Center
                     i. Packaged water source heat pumps (WSHP). Three (3) units with
                        estimated size of 5 tons each.
                    ii. Office and work room and conference rooms shall be placed on
                        independently controlled, separate zones.
                   iii. Media Center shall be equipped with humidity sensors.
           d. Administration
                     i. Packaged RTU with natural gas heating. Estimated size of 7.5 tons.
           e. Classrooms
                     i. Packaged WSHP. Twenty-five (25) units with estimated size of 3 tons
                        each.

                                                          Preliminary Consultation | 09.07.21 | 9
Dekalb County School District                                       Hawthorne Elementary School
                                                                Major Building System Renovation

         f.   IT/Telecom Room: One (1) wall mounted ductless mini-split with estimated
              capacity of 1.5 tons.
          g. Mechanical rooms shall be ventilated using a roof mounted EF, and heated using
              wall mounted electric unit heaters.
          h. Vestibules and corridor areas adjacent to exterior doors shall have ceiling
              mounted electric unit heaters.
  5. Filtration
          a. Air filtration shall be a minimum MERV 13.
          b. Bipolar ionization shall be provided for all units recirculating indoor air. Ionization
              shall not be required for outdoor air systems.
  6. Air Distribution
          a. Duct work downstream of new RTUs shall be 4 inwc pressure class.
          b. Duct work downstream of new WSHPs shall be 2 inwc pressure class.
          c. Duct work downstream of new EFs shall be 2 inwc pressure class.
  7. Insulation
          a. Duct work: 2 inch fiberglass batt insulation, 75 lb/ft3 with foil jacket.
          b. Condenser piping: 2 inch cellular glass with jacketing.
          c. Condenser water piping with insulation installed outdoors, or in mechanical
              rooms shall be protected with metal jacketing.

 •   BUILDING 2010, 2011, AND 2012

     Description of Heating, Air Conditioning, and Ventilation Systems to be completely
     furnished and installed shall include, but not be limited to, the following:

     o        The heating and air conditioning of the new classrooms will be provided by water
              source heat pumps. This year‐round system will consist of horizontal above‐the‐
              ceiling heat pumps sized to handle the individual zones served. The system shall tie
              into a two‐pipe closed water loop maintained throughout the year in a temperature
              range of between 60 deg. F and 100 deg F. The temperature range shall be
              maintained by supplemental heating being injected into the water loop, and cooling
              shall be maintained by the rate of heat rejection capability of the cooling tower.
              Heating is introduced by gas‐fired boilers (or electric boilers, based on owner’s
              preference) located in the mechanical equipment room and cooling is supplied by
              cooling towers and plate and frame heat exchangers (type 304 Stainless Steel). One
              heat pump will serve each classroom.

     o        Water in the loop is distributed throughout the building to the heat pumps by variable
              speed circulating pumps located in the mechanical room.

     o        The cooling tower fan and associated condenser water pumps shall be VFD.

     o        Ventilation air shall be introduced into the classrooms by a constant volume, 100
              percent outside air units with heat reclaim via an exhaust air heat exchanger. Air
              shall be supplied into the building via horizontal ducts in the ceiling cavity following
              treatment of air by an air-to-air energy recovery unit. Each wing shall be provided
              with its own energy recovery unit.



                                                            Preliminary Consultation | 09.07.21 | 10
Dekalb County School District                                       Hawthorne Elementary School
                                                                Major Building System Renovation

     o        The internal surfaces of air units, heat pumps, plenums, supply and return ductwork,
              etc. shall be protected during construction from dirt, dust and debris. These items
              shall be clean when the systems are turned over to the Owner.

     o        The new water source heat pumps shall be equipped with a quick opening/slow
              closing two‐way solenoid water valve for variable speed pumping requirements.
              Water Source Heat Pumps shall be provided with hot-gas reheat for humidity control.

     o        Ionic generation by Global Plasma Solutions shall be used in the supply ductwork of the
              new heat pumps to improve air quality and help mitigate the proliferation of COVID-
              19. The whole building will have ionic generation.

     o        Provide the highest Minimum Efficiency Reporting Value (MERV) applicable for the
              HVAC units (WSHP and DOAS). MERV 13 is recommended minimum if equipment
              can accommodate pressure drop and MERV 14 is preferred.

     o        During a Pandemic event, the HVAC control system shall have the capability to
              disable any Demand Control Ventilation (DCV) and introduce the maximum possible
              outdoor air flow 24/7 until the event expires. During this event indoor environmental
              conditions may require limiting comfort setpoints.

     o        IDF rooms will be cooled utilizing a split system air conditioning unit with condensing
              unit mounted on roof.

     o        Electrical rooms will be cooled utilizing a split system air conditioning unit with
              condensing unit mounted on roof.

     o        Space air diffusers, registers and grilles shall be complimentary to the ceiling spaces
              utilized in the individual spaces.

      o       New packaged HVAC systems will be used for: the Administration Area, Media
              Center, Cafeteria/Stage, and Kitchen.

      o       All ductwork systems will be galvanized steel constructed per the latest SMACNA
              Standards. Duct work between the Energy Recovery Unit will be constructed to 2”
              pressure requirements.

      o       All duct work will be insulated with a FSK faced blanket insulation that has an
              installed R-value of 4.2 or greater. For exposed ductwork less than 8’ above the
              finished floor, provide rigid duct board insulation with aluminum jacketing. Provide
              glass-fab tape and low-VOC vapor barrier mastic. Foil tape is not acceptable even
              for patching tears.

      o    Split systems
          o Air-cooled split systems will be provided to cool IDF rooms to allow these spaces
            to be placed on backup power systems.
          o Wall mounted or ceiling cassette split system fan coil units with condensate pumps
            will be provided for each space. Wall mounted thermostats by the manufacturer
            will be provided.
          o Air-cooled outdoor units will be located on the roof or at grade.


                                                           Preliminary Consultation | 09.07.21 | 11
Dekalb County School District                                    Hawthorne Elementary School
                                                             Major Building System Renovation



Additional Requirements
     o     DDC Controls:

              DDC controls will be utilized for all equipment. Individual microprocessor based
               digital equipment controllers with a standalone building management system
               that will report to a central local area network for building global
               communications from a central location. All major equipment controllers will
               have standalone capability with respect to the specific equipment in each
               system that is served from a dedicated control panel.

              The DDC system for this facility will consist of a central building controller
               connected to lower-level application specific equipment controllers through a
               local area network cable system. The central building controller in this facility
               will include the interface necessary for internet-based access. However, the
               DDC controllers will have stand-alone operational capability, with the
               respective equipment related to each system served from a dedicated control
               panel. The central building controller will be equipped to connect to a laptop
               computer for local set point adjustment.

              Individual room/zone temperature control will be provided through wall
               mounted temperature sensors with local timed override and user temperature
               set point adjustment within 2-degrees of set point at 1-degree intervals.

              Each classroom, media center, and other high occupancy area will include a
               humidity sensor to provide input so that systems can be manipulated to
               maintain space humidity below the set point. Classrooms shall have occupancy
               sensors to control HVAC setback.

              Each classroom will also include a CO2 sensor to indicate occupancy. The CO2
               sensor will be used to modulate the outside air level to maintain space the CO2
               differential set point.

              The DDC System will be capable of displaying status, entering and leaving
               conditions, etc. for all equipment. This system will be capable of trending
               simultaneous control points. This system will also be capable of individual user
               IDs & passwords with multiple levels of access to the DDC System. The DDC
               System will only be accessible to authorized users through a secure internet
               interface.


     o     TESTING, ADJUSTING AND BALANCING (TAB):

              All airside equipment will require a comprehensive testing and balancing
               process by an AABC or NEBB certified firm.



                                                         Preliminary Consultation | 09.07.21 | 12
Dekalb County School District                                     Hawthorne Elementary School
                                                              Major Building System Renovation

                The TAB contractor will be a third-party firm, and not a subcontractor of the
                 mechanical and/or plumbing contractor.

                All reports will be submitted on AABC or NEBB forms.


       o     COMMISSIONING:

                The owner will be responsible for obtaining the services of a qualified
                 commissioning agent capable of the level of commission (basic or enhanced
                 commissioning).

                The mechanical contractor, DDC contractor, and all of their sub-contractors will
                 provide all necessary support required to complete the commissioning process.

Hawthorne Elementary School
Electrical Solutions
Demolition
   •   Existing lighting fixtures throughout facility were replaced within the last 4-5 years with
       an assortment of 32W T8 fluorescent lamped linear lighting fixtures mostly 2’x4’
       volumetric center basket type and lensed troffers found in administrative areas,
       classrooms and cafeteria.
   •   Most of the original power distribution equipment was replaced within the last 4-5 years,
       except for computer dedicated panelboards and transformer, a few loadcenters, and
       gymnasium panel and transformer.

Power Distribution
   •   Existing surface raceways and devices (receptacles, teacher station outlets, data, etc.)
       should be replaced with an aluminum dual compartment type surface raceway with new
       devices to match existing and DCSD guidelines.
   •   Provide GFCI type receptacle outlets at HACR equipment and in utility spaces.
   •   Provide GFCI type receptacle outlets or GFCI type circuit breakers serving kitchen
       equipment per NEC.
   •   Main Mechanical room shall be reconfigured to improve on code required clearances
       and headroom above electrical equipment. Various water pipes are indiscriminately
       routed above and around existing electrical equipment. Water puddling is present
       around electrical equipment. Existing power distribution added 4-5 years ago found in
       good working conditions will be relocated to new Electrical Room. See architectural
       sketch.
   •   Provide new power distribution equipment to match existing Computer Dedicated panel
       boards (208V) and step down transformer in new Electrical Room. See architectural
       sketch.
   •   Replace Gymnasium panelboard, transformer and disconnect switch.
   •   Provide dedicated spaces for new power distribution equipment that will replace existing
       equipment currently located in Custodian Rooms and near water piping.


                                                          Preliminary Consultation | 09.07.21 | 13
Dekalb County School District                                     Hawthorne Elementary School
                                                              Major Building System Renovation

   •   Provide surge protective devices at Main Service, sources serving roof top mounted
       equipment and sensitive electronic loads.
   •   Provide a natural gas generator, est. 125KW, 480Y/277V, 3ph, 4w.
   •   Provide a generator docking station for maintenance, 100A, 480Y/277V, 3ph, 4w.
   •   Provide fault current study, arc flash hazard study and coordination study. The
       emergency system shall be selectively coordinated.

Lighting Fixtures and Controls
   •   Outdoor lighting fixtures mounted on walls and underside of soffits and canopies shall be
       replaced with LED lighting fixtures.
   •   Replace existing lighting throughout with new LED lighting fixtures.
   •   Provide new LED exit signs throughout.
   •   Provide occupancy and vacancy controls throughout. Corridors shall be time clock
       controlled.
   •   Lighting switches shall be lowered to ADA mounting heights.
   •   Provide elementary school level theatrical lighting batten and lighting instruments and
       dimming control console.

Low Voltage
   •   Remove abandoned equipment and low voltage cabling from above the ceilings and
       roof.
   •   Replace existing intercommunications and time clock system with new to include
       headend equipment, call stations, speakers, and cabling.
   •   Data cabling management above equipment racks shall be improved by securely
       fastening in place. Relocate patch panel, switch, data cabling and patch cables from
       shelf to a wall mounted cabinet. Provide new CAT6 cabling from patch panel to the
       workstation area outlet.

Fire Alarm
   •   Replace existing fire alarm control panel, power boosters, Digital Alarm Communicator
       Transmitter, initiation devices (smoke detectors, pull stations), notification appliances
       (strobes, strobe/horns, bells) and cabling with a new fully addressable and code
       compliant coverage throughout the facility. Provide voice evacuation control for
       assembly areas (cafeteria, gymnasium, Media Center).
   •   Provide testing for an Emergency Responders Radio Coverage System and include
       allowance for a new system.




                                                          Preliminary Consultation | 09.07.21 | 14
Dekalb County School District                                   Hawthorne Elementary School
                                                            Major Building System Renovation

Hawthorne Elementary School
Life Safety Solutions
   •   Provide complete wet system automatic sprinkler throughout the building in accordance
       with NFPA 13, & 24 latest edition, Georgia State Minimum Standard Fire Prevention
       Code (International Fire Code), 2018 Edition, State of Georgia Chapter 120‐3‐3 "Rules
       of Safety Fire Commissioner, Rules and Regulations. The system shall and consist of
       the following major elements:
   •   The building will have a post indicator valve, backflow preventer, and rough brass wall
       mounted fire department connection provided in accordance with NFPA 24, "Standard
       for the Installation of Private Fire Service Mains and their Appurtenances" as amended
       by 120‐3‐3.
   •   Provide fire department hose and test connections as and where required by the Fire
       Marshal.

   •   Provide pressure reducing stations as required if main water pressure fluctuates and
       exceeds fire protection system working pressure.


   •   Fire Sprinkler Heads:
           o Suspended Ceiling Types: Semi‐recessed pendent type with matching push on
               two-piece escutcheon plate. Finish: Chrome. Escutcheon Plate Finish: Enamel,
               chrome.
           o Gypsum Board Ceiling Type: Concealed pendent type with cover plate. Sprinkler
               Finish: Brass. Cover Plate Finish: White.
           o Exposed Area Type: Standard upright type with guard when below 8'‐0" AFF.
               Finish: Brass.
           o Sidewall Type: Standard horizontal sidewall type with matching push on two-
               piece escutcheon plate. Finish: Chrome. Escutcheon Plate Finish: Enamel,
               chrome.
   •   The fire protection design will include a minimum of 10 psi safety factor to allow for
       future losses in the water service pressure characteristics
   •   Automatic sprinkler system materials:
           o Buried piping: ductile iron pipe, ansi‐21.51, 250 psi minimum working pressure
               with slip‐on joints, ansi‐a21.11.
           o Above Ground Piping: Black carbon steel pipe. 2‐inch and Smaller: ASTM‐A‐
               135, Grade A, schedule 40 with 175 lb. black threaded cast iron fittings. 2‐1/2‐
               inch thru 6‐inch: ASTM‐A‐135, ASTM‐A‐53, grade A, schedule 10 with malleable
               iron grooved pipe fittings.




                                                        Preliminary Consultation | 09.07.21 | 15
    Dekalb County School District                                   Hawthorne Elementary School
                                                                Major Building System Renovation

Hawthorne Elementary School
Plumbing Solutions
      •   All existing plumbing fixtures shall be replaced with new fixtures (one for one). Plumbing
          fixtures to be replaced included, but not limited to, the following:
               o Water Closets
               o Urinals
               o Lavatories
               o Sinks
               o Water Fountains
               o Janitor Sinks
               o Hand Sinks located in the Kitchen will be replaced as required. No other Kitchen
                  equipment is to be replaced.

      •   All plumbing fixtures shall be water efficient. The plumbing system will be designed with
          water efficiency goals.

      •   All existing water heaters and recirculating pumps will be replaced with new. Preferred
          manufacturers are Rheem, and Rudd.

      •   Specified materials and equipment will be standard products of manufacturers regularly
          engaged in the manufacture of such products.

             o   Toilet areas and plumbing fixtures will be handicapped accessible.
             o   All other control components and equipment requiring adjustment and/or
                 maintenance shall be readily accessible through the use of lay-in ceilings and/or
                 appropriately sized access doors.


Hawthorne Elementary School
Site Improvement Solutions
Based on visual site review, the following site modification items will be included in the scope of
work:

•     Provide a new fire line with double detector check valve assembly from Caladium Drive NE
      to a new vault outside the building. New line will go to existing mechanical room 99.4 and
      split into 2 risers.
•     A Reduce Pressure Zone (RPZ) will be added to the existing Domestic Water main for
      building service.
•     Approximately 100-feet of existing sanitary main will need to be replaced (blue). Existing
      line will need to be scoped in both directions from the manhole to confirm extents of the
      damage.
•     Playground and surrounding area (brown) is waterlogged. Existing yard drains appear
      adequate in number, but playground loose rubber will need to be removed to add drainage
      system, and replaced with rubber mulch and modular plastic curbs.




                                                            Preliminary Consultation | 09.07.21 | 16
 Dekalb County School District                                     Hawthorne Elementary School
                                                               Major Building System Renovation




^ Hawthorne Elementary School Utility Plan


Hawthorne Elementary School
Architectural Solutions
ROOFING:
Although the existing modified bitumen roof not included in the DCSD Scope of work, we
observed roof leaks in multiple locations and the roof system is nearing the end of its estimated
useful life. Due to the duration of ongoing roof leaks, the underlying insulation is most likely
waterlogged. Full replacement is recommended.
CEILINGS:
Although the existing ceilings are not included in the DCSD Scope of work, per our review of the
existing acoustical ceiling panels and grid systems, the ceilings appear to be in fair shape. With
the scope of work identified by the electrical, HVAC, and new fire sprinkler, it is our opinion that
the existing acoustical ceilings would not be salvageable or re-useable. We are recommending
replacement of all acoustical ceiling systems.
Demolition: All acoustical ceiling panel systems will be removed and discarded in association
with replacement of building lighting and HVAC systems, including acoustical panels, metal grid,
and hangars.
All existing devices to remain mounted to the existing ceiling will be identified, removed, bagged
and tagged and placed above ceiling, or otherwise protected during construction for re-
installation after construction. These devices include LED lighting, smoke detectors, cameras,
and wireless devices.
New 2x2 acoustical panel ceilings will replace demolished ceilings unless noted otherwise.
Ceiling tiles basis of design to be 24 x 24 format - Armstrong Ceilings Cortega 770. Ceiling grid


                                                           Preliminary Consultation | 09.07.21 | 17
 Dekalb County School District                                             Hawthorne Elementary School
                                                                       Major Building System Renovation

basis of design to be 15/16” exposed tee grids – Armstrong Prelude. Scrubbable ceiling tiles
will be provided in the kitchen and restroom areas.
Existing finishes to be repaired as needed for patching or repairing areas affected by HVAC and
electrical modifications. This should include repainting of all hard ceilings due to lighting
replacement.
STAGE WHEELCHAIR LIFT:
DCSD requested that we consider the feasibility of a permanent ADA accessible wheelchair lift
for the stage. Provided below is a sketch showing a possible location and minimum clearances
for the lift based on previous projects with similar scope.




^ Hawthorne Elementary School existing Stage and storage      ^Proposed new storage entry and wheelchair lift


MECHANICAL/ELECTRICAL ROOMS, CLASSROOM AND TEACHER WORKROOM:
The new electrical distribution main with separate dedicated emergency power will require
clearance and fire safety requirements that do not fit in the existing conditions located in the 400
square feet mechanical room 99.4.




^ Hawthorne Elementary School existing Electrical/Mechanical Layout




                                                                  Preliminary Consultation | 09.07.21 | 18
 Dekalb County School District                                            Hawthorne Elementary School
                                                                      Major Building System Renovation

We propose to carve out a new electrical room from the old classroom 102. The remaining old
classroom space will be re-purposed as a new teacher workroom with psych and special ed
offices 101, 101.1, and 101.2, respectively. The Teacher workroom will be smaller than existing
conditions. The old teacher workroom 101 will then be re-purposed as a new location for
classroom 102 by adding an ADA toilet room and exterior sink/cabinets as shown, demolishing
the old Sp ed/psych demising walls. Finishes, including VCT/ceramic tile flooring, paint,
cabinets, plumbing fixtures, ceilings, etc. will be new to match existing conditions.




^ Hawthorne Elementary School proposed Electrical/Mechanical Layout




                                                                 Preliminary Consultation | 09.07.21 | 19
 Dekalb County School District                                        Hawthorne Elementary School
                                                                  Major Building System Renovation

Hawthorne Elementary School
Executive Summary
Hawthorne Elementary School will undergo a building systems-focused renovation due to the
age and current condition of the systems. SSOE | S&W recommends the following scope of
work:
The HVAC systems will be replaced with new equipment to provide a 2 pipe water source heat
pump system for classrooms and new packaged units for administration, media center,
gymnasium, and kitchen/cafeteria.
The electrical power distribution system will be replaced along with selected panel boards.
Existing lighting and power distribution equipment will remain. A new generator will be provided.
Plumbing fixtures will be replaced one for one.
Fire alarm, intercom, and clock systems will be replaced.
The facility will be provided with a fire sprinkler system.
All acoustical ceiling tile systems will be replaced.
Modification of the existing mechanical room and adjacent classroom and teacher work room is
proposed to accommodate a new electrical room.
A lift system will be installed to provide access to the stage.
Site improvement will replace a section of sanitary sewer line to correct sewage back-up issues.
A playground are will be re-graded for proper drainage.
Existing roofing will be removed and replaced with a modified bitumen built-up roof.
Architectural finishes will be patched and finished where required due to other renovation work.
Architectural modifications will be required for the new electrical room and wheelchair stage lift.
Our cost analysis indicates a potential cost for this project of $5,671,659. This is approximately
an 69% increase over the stated budget of $3,350,000, with considerable scope added for this
report. The cost analysis detail document is included at the end of this report.




                                                              Preliminary Consultation | 09.07.21 | 20
                                         APPENDIX 01
                         PRELIMINARY ASSESSMENT ANALYSIS
                                                   For The

      HAWTHORNE ES MAJOR BLDG SYSTEM REPLACEMENT
                                               Atlanta, Georgia

Prepared: September 9, 2021                                                                              Revised:

 CODE                 DESCRIPTION                                    QTY         UNIT       COST        TOTAL



RENOVATION SUMMARY
SCOPE ITEMS                                                     Project Costs               Cost/SF

A. REPLACE HVAC SYSTEMS                                              1,223,275                  22.90


B. REPLACE ELECTRICAL SYSTEMS                                        1,451,744                  27.18


C. REPLACE PLUMBING FIXTURES                                          276,549                    5.18


D. REPLACE FIRE ALARM, COMM, & CLOCK SYSTEMS                          554,505                   10.38


E. PROVIDE FIRE SPRINKLER SYSTEM                                      328,958                    6.16


F. REPLACE ACOUSTICAL CEILING TILE SYSTEM                             288,843                    5.41


G. MODIFY ROOM LAYOUT FOR NEW ELEC RM                                  67,325                    1.26


H. PROVIDE LIFT SYSTEM AT STAGE                                        50,039                    0.94


I. SITE IMPROVEMENTS TO SS & PLAYGROUND                                68,451                    1.28


J. REPLACE ROOFING SYSTEM                                            1,361,969                  25.50




BUILDING CONSTRUCTION COSTS                                     $    5,671,659          $      106.18

                                                      53,418    SF

PROPOSED SCL CONSTRUCTION BUDGET                                $    3,350,000          $       62.71

           (OVER IN RED/UNDER IN BLACK)                         $ (2,321,659)




Hawthorthe ES Major Bldg Systems Replacement                                     ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                   Page 1 of 9                                            9/10/2021
 CODE                 DESCRIPTION                               QTY         UNIT      COST            TOTAL



RENOVATION DETAIL
A. REPLACE HVAC SYSTEMS

 A1010     Demo HVAC Systems                                      47,707     SF            1.50         71,561
 A1011     New HVAC Sytems                                        47,707     SF           17.50        834,873

                                               Replace HVAC Subtotal                                   906,433

           GENERAL REQUIREMENTS/CONDITIONS                                   7.0%                       63,450
           FEE                                                               5.0%                       48,494
           PERMITS, INSURANCES, AND BONDS                                    4.0%                       40,735
           DESIGN CONTINGENCY                                               10.0%                      105,911
           ESCALATION (5% Per Year)                                          5.0%                       58,251

                                               REPLACE HVAC TOTAL                                 $ 1,223,275

                                               COST/SF            53,418 SF                       $      22.90



B. REPLACE ELECTRICAL SYSTEM

 B1010     Demo Power Distribution Systems                        47,707     SF            3.00        143,121
 B1011     New Power Distriibution Sytems                         47,707     SF           15.00        715,605
 B1064     Emergency System:
 B1065      150KW Generator                                             1    LS      107,500.00        107,500
 B1066      Emergency Panels                                            1    LS       40,000.00         40,000
 B1067      Emergency Feeder Circuits                                   1    LS       65,000.00         65,000
 B1068      Chain Link Security Fencing                                60    LF           75.00          4,500

                                               Replace Elec Subtotal                                  1,075,726

           GENERAL REQUIREMENTS/CONDITIONS                                   7.0%                       75,301
           FEE                                                               5.0%                       57,551
           PERMITS, INSURANCES, AND BONDS                                    4.0%                       48,343
           DESIGN CONTINGENCY                                               10.0%                      125,692
           ESCALATION (5% Per Year)                                          5.0%                       69,131

                                               REPLACE ELEC TOTAL                                 $ 1,451,744

                                               COST/SF            53,418 SF                       $      27.18




Hawthorthe ES Major Bldg Systems Replacement                                ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                 Page 2 of 9                                         9/10/2021
 CODE                 DESCRIPTION                                 QTY         UNIT      COST            TOTAL


C. REPLACE PLUMBING FIXTURES

 C1010     Protect Existing Finishes - Allowance                        370    SF            1.00            370
 C1011     Demo Plumbing Fixtures                                        96    EA          150.00         14,400
 C1012     Demo Water Heaters                                             2    EA          500.00          1,000
 C1013     Demo Recirculating Pumps                                       2    EA          250.00            500
 C1014     New Water Closets                                             40    EA        1,400.00         56,000
 C1015     New Urinals                                                   15    EA        1,500.00         22,500
 C1016     New Sinks/Lavatories                                          30    EA        1,350.00         40,500
 C1017     New Mop Sinks                                                  5    EA        1,800.00          9,000
 C1018     New Drink Fountains                                           12    EA        2,150.00         25,800
 C1019     Gas Water Heater - 80 Gal                                      2    EA       10,500.00         21,000
 C1020     DHW System Recirculating Pumps                                 2    EA        1,050.00          2,100
 C1021     Patch/Repair Ceramic Tile - Allowance                          1    LS        1,250.00          1,250
 C1021     Dom Water - Reduced Pressure Zone - Allowance                  1    EA       10,500.00         10,500

                                                 Replace Plumbing Subtotal                               204,920

           GENERAL REQUIREMENTS/CONDITIONS                                     7.0%                       14,344
           FEE                                                                 5.0%                       10,963
           PERMITS, INSURANCES, AND BONDS                                      4.0%                        9,209
           DESIGN CONTINGENCY                                                 10.0%                       23,944
           ESCALATION (5% Per Year)                                            5.0%                       13,169


                                                 REPLACE PLUMBING TOTAL                             $    276,549

                                                 COST/SF            53,418 SF                       $       5.18




Hawthorthe ES Major Bldg Systems Replacement                                  ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                   Page 3 of 9                                         9/10/2021
 CODE                 DESCRIPTION                                 QTY        UNIT      COST           TOTAL


D. REPLACE FIRE ALARM, COMM, & CLOCK SYSTEMS

 D1010     Demo Existing Fire Alarm System                          53,514    SF           0.50         26,757
 D1011     New Fire Alarm System                                    53,514    SF           3.50        187,299
 D1012     Demo Existing Intercom System                            53,514    SF           0.25         13,379
 D1013     New Intercom System                                      53,514    SF           1.75         93,650
 D1014     Demo Existing Clock System                               53,514    SF           0.15          8,027
 D1015     New Clock System                                         53,514    SF           1.50         80,271
 D1016     Patch/Repair CMU Walls - Allowance                            1    LF         750.00            750
 D1016     Touch-up Paint CMU Walls - Allowance                          1    LF         750.00            750

                                                  FA, Comm, Clock Subtotal                             410,882

           GENERAL REQUIREMENTS/CONDITIONS                                    7.0%                      28,762
           FEE                                                                5.0%                      21,982
           PERMITS, INSURANCES, AND BONDS                                     4.0%                      18,465
           DESIGN CONTINGENCY                                                10.0%                      48,009
           ESCALATION (5% Per Year)                                           5.0%                      26,405

                                                  FA, COMM, CLOCK TOTAL                           $    554,505

                                                  COST/SF           53,418 SF                     $      10.38




Hawthorthe ES Major Bldg Systems Replacement                                 ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                    Page 4 of 9                                       9/10/2021
 CODE                 DESCRIPTION                                 QTY          UNIT      COST            TOTAL

E. PROVIDE FIRE SPRINKLER SYSTEM

  E1010    New Fire Sprinkler System                                  53,418   SF             3.00        160,254
  E1011    Demo Lanscaping/Sod/Fixtures - Allowance                        1   LS         1,500.00          1,500
  E1013    Fire Line - Remove Street For Tie-In                          580    SF           15.00          8,700
  E1014    Fire Line - 8" DIP Fire Line To Building                      434    LF           75.00         32,550
  E1015    Fire Line -Tap Into Existing Water Line                         1    EA        2,000.00          2,000
  E1016    Fire Line - New Post Indicator Valve                            1    EA        2,250.00          2,250
  E1017    Fire Line - New Double Detector Check System                    1    EA       17,500.00         17,500
  E1018    Fire Line - New Wall Mtd Fire Dept Connector                    1    EA        2,500.00          2,500
  E1019    Fire Line - Repair Street                                     580    SF           25.00         14,500
  E1020    Replace Lanscaping/Sod/Fixtures - Allowance                     1   LS         2,000.00          2,000

                                                 Sprinkler Subtotal                                       243,754

           GENERAL REQUIREMENTS/CONDITIONS                                      7.0%                       17,063
           FEE                                                                  5.0%                       13,041
           PERMITS, INSURANCES, AND BONDS                                       4.0%                       10,954
           DESIGN CONTINGENCY                                                  10.0%                       28,481
           ESCALATION (5% Per Year)                                             5.0%                       15,665

                                                 SPRINKLER TOTAL                                     $    328,958

                                                 COST/SF              53,418 SF                      $       6.16



F. REPLACE ACOUSTICAL CEILING TILE SYSTEM

  F1010    Demo/Remove Existing ACT Ceiling System                    43,516    SF            1.00         43,516
  F1011    Demo/Remove Plaster Ceilings At Kitchen                     1,470    SF            2.00          2,940
  F1012    Bag & Tag Extg Lighting/Smk Det/Cameras - Allowance        44,985    SF            0.18          7,872
  F1013    New 2x2 ACT Ceiling System/W/ Grid                         43,516    SF            3.50        152,306
  F1014    New 2x2 ACT Ceiling System/W/ Grid - Scrubbable             1,470    SF            3.50          5,145
  F1015    Patch 8" CMU Wall - Allowance                                   1    LS          750.00            750
  F1016    Touch-up Paint At Int Walls - Allowance                         1    LS        1,500.00          1,500

                                                 ACT System Subtotal                                      214,029

           GENERAL REQUIREMENTS/CONDITIONS                                      7.0%                       14,982
           FEE                                                                  5.0%                       11,451
           PERMITS, INSURANCES, AND BONDS                                       4.0%                        9,618
           DESIGN CONTINGENCY                                                  10.0%                       25,008
           ESCALATION (5% Per Year)                                             5.0%                       13,754

                                                 ACT SYSTEM TOTAL                                    $    288,843

                                                 COST/SF              53,418 SF                      $       5.41




Hawthorthe ES Major Bldg Systems Replacement                                   ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                    Page 5 of 9                                         9/10/2021
 CODE                 DESCRIPTION                              QTY           UNIT      COST          TOTAL


G. MODIFY ROOM LAYOUT FOR NEW ELEC RM

 G1010     Remove/Replace Furniture - By Owner                       -       LS          NIC           NIC
 G1011     Remove/Store Classroom Fixtures - Allowance                   1    LS           500.00            500
 G1012     Demo ACT Ceiling At Extg CR #102                        -          SF     incl above     incl above
 G1013     Demo ACT Ceiling At Extg T-Work #101                    -          SF     incl above     incl above
 G1014     Demo Extg VCT Flooring/Base At #102                     755        SF             1.50          1,133
 G1015     Demo Extg VCT Flooring/Base At #101                     731        SF             1.50          1,097
 G1016     Sawcut CMU/Concrete At Demo - Allowance                   1        LS           750.00            750
 G1017     Demo/Remove Doors And Frames - Single                     2        EA            50.00            100
 G1018     Demo/Remove Int CMU PartitionWalls                      378        SF             2.00            756
 G1019     Demo/Remove SOG At Now Plumbing - Allowance              40        SF            15.00            600
 G1020     SS Line Fom Ne RR To Extg Group RR - Allowance            1        LF        1,250.00           1,250
 G1021     Concrete Slab Fill-in At New RR Plumbing                 25        SF            35.00            875
 G1022     Patch/Prep Extg Int Concrete SOG At Demo              1,486        EA             0.10            149
 G1023     Repair Extg CMU Partitions At Wall Demo                  60        SF            15.00            900
 G1024     Patch/Prep Extg CMU Partitions To Remain              1,970        SF             0.25            493
 G1025     New 8" CMU Interior Partitions                          622        SF            15.00          9,330
 G1026     Grout Fill At 8" CMU Ext Wall (50%)                     311        SF             3.50          1,089
 G1027     HM Frm/SC Wood Door - 3-0 x 7-0 - Single                  3        EA        1,150.00           3,450
 G1028     HM Frm/SC Wood Door - 3-0 x 7-0 - Pair                    1        EA        2,250.00           2,250
 G1029     Interior Finish Hardware - Per Leaf                       5        EA           550.00          2,750
 G1030     Ceramic Floor Tile In RRs                                90        SF            11.00            990
 G1031     Ceramic Tile Base In RRs                                 35        SF            11.50            403
 G1032     Floor Finish - VCT                                    1,128        SF             4.50          5,076
 G1033     Floor Finish - Sealed Concrete At New Elect Rm          300        SF             4.50          1,350
 G1034     Paint Existing CMU Partitions                         1,970        SF             2.00          3,940
 G1035     Paint New CMU Partitions                              1,037        SF             2.00          2,074
 G1036     Paint Interior Doors/Frames                               8        EA            50.00            400
 G1037     New ACT Ceiling At New Classrooms                       -          SF     incl above     incl above
 G1038     New ACT Ceiling At New Teacher Work #101                -          SF     incl above     incl above
 G1039     New PL Base Cabinets W/ PL Countertop                     6        LF           225.00          1,350
 G1040     New Sink Fixture - Complete                               1        LS        2,800.00           2,800
 G1041     New Toilet Fixture - Complete                             1        LS        2,600.00           2,600
 G1042     Handicap Grab Bars                                        2        EA            75.00            150
 G1043     Toilet Tissue Holder - Double Roll                        1        EA            65.00             65
 G1044     Toilet Seat Cover Dispenser                               1        EA            85.00             85
 G1045     Sanitary Napkin Disposal                                  1        EA           110.00            110
 G1046     Coat/Towel Hooks                                          1        EA            35.00             35
 G1047     Framed Mirror - 2'-0W x 3'-6"H                            1        EA           135.00            135
 G1048     Hand Soap Dispenser                                       1        EA            55.00             55
 G1049     Paper Towel Disp/Waste Receptacle                         1        EA           300.00            300




Hawthorthe ES Major Bldg Systems Replacement                                 ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                  Page 6 of 9                                         9/10/2021
 CODE                 DESCRIPTION                                    QTY           UNIT      COST             TOTAL

 G1050     Replace Existing Classroom Fixtures - Allowance                     1    LS          500.00            500

                                                   Modify Rooms Subtotal                                        49,887

           GENERAL REQUIREMENTS/CONDITIONS                                          7.0%                         3,492
           FEE                                                                      5.0%                         2,669
           PERMITS, INSURANCES, AND BONDS                                           4.0%                         2,242
           DESIGN CONTINGENCY                                                      10.0%                         5,829
           ESCALATION (5% Per Year)                                                 5.0%                         3,206

                                                   MODIFY ROOMS TOTAL                                     $     67,325

                                                   COST/SF                 53,418 SF                      $       1.26



H. PROVIDE LIFT SYSTEM AT STAGE

 H1010     Remove/Replace Furniture - By Owner                               -     LS          NIC           NIC
 H1011     Demo ACT Ceiling At Cafeteria                                     -      SF     incl above     incl above
 H1012     Demo Extg VCT Flooring/Base Stor Rm                                54    SF             1.50             81
 H1013     Sawcut CMU/Concrete At Demo - Allowance                             1    LS           750.00            750
 H1014     Demo/Remove Doors And Frames - Single                               1    SF            50.00             50
 H1015     Demo/Remove Int GWB Partition Walls At Stor Rm                    216    SF             2.50            540
 H1016     Demo/Reomve CMU Wall At Stage                                      81    SF             7.50            608
 H1017     Patch/Prep Extg Int Concrete SOG At Demo                           54    SF             4.00            216
 H1018     Patch/Prep Extg CMU Partitions To Remain                          377    SF             1.00            377
 H1019     Modify/Tooth New CMU to Extg                                       41    SF            15.00            615
 H1020     New 8" CMU Interior Partitions                                    216    SF            17.50          3,780
 H1021     Grout Fill At 8" CMU Ext Wall (50%)                               108    SF             3.50            378
 H1022     New GWB Interior Partitions                                        42    SF            15.00            630
 H1023     New GWB Bulkhead                                                   35    SF             8.50            298
 H1024     HM Frm/SC Wood Door - 3-0 x 7-0 - Single                            1    EA        1,150.00           1,150
 H1025     Interior Finish Hardware - Per Leaf                                 1    EA           550.00            550
 H1026     Floor Finish - VCT                                                 45    SF             4.50            203
 H1027     Floor Finish - Sealed Concrete                                     24    SF             5.00            120
 H1028     Paint Existing CMU Partitions                                     377    SF             2.50            943
 H1029     Paint New CMU Partitions                                          448    SF             2.50          1,120
 H1030     Paint GWB Interior Partitions                                      42    SF             2.00             84
 H1031     Paint GWB Bulkhead                                                 15    SF             4.00             60
 H1032     Paint Interior Doors/Frames                                         1    EA            50.00             50
 H1033     New ACT Ceiling At New Classrooms                                  36    SF             4.50            162
 H1027     HDCP Lift At Corridor                                               1    EA           22,500         22,500
 H1028     Wheelchair Lift Power Circuit - Complete                            1    LS        1,815.00        1,815.00

                                                   Provide Lift Subtotal                                        37,078

           GENERAL REQUIREMENTS/CONDITIONS                                         7.0%                          2,595
           FEE                                                                     5.0%                          1,984




Hawthorthe ES Major Bldg Systems Replacement                                       ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                     Page 7 of 9                                            9/10/2021
 CODE                 DESCRIPTION                               QTY         UNIT      COST            TOTAL

           PERMITS, INSURANCES, AND BONDS                                    4.0%                        1,666
           DESIGN CONTINGENCY                                               10.0%                        4,332
           ESCALATION (5% Per Year)                                          5.0%                        2,383

                                               PROVIDE LIFT TOTAL                                 $     50,039

                                               COST/SF            53,418 SF                       $       0.94



I. SITE IMPROVEMENTS TO SANITARY SEWER & PLAYGROUND
          Sanitary Sewer Main
   I1010  Demo Lanscaping/Sod/Fixtures - Allowance                  1        LS          500.00            500
   I1011  Remove Street For Tie-In                                 32        SF          100.00          3,200
   I1012  Demo/Remove 10" Sanitary Sewer Line                     104        LF           20.00          2,080
   I1013  New 10" Sanitary Sewer Line                             104        EA           65.00          6,760
   I1014  Clean Out Exisiting SS Manhole - Allowance                2        EA        1,000.00          2,000
   I1015  Scope Extg SS Sewer Line To Bldg - Allowance              1        EA        5,000.00          5,000
   I1016  Repair Street Paving                                     32        SF           75.00          2,400
   I1017  Replace Lanscaping/Sod/Fixtures - Allowance               1        LS        1,500.00          1,500
   I1018  Miscellaneous/Unforseen Demo And/Or Replace               1        LS        2,500.00          2,500
                                                  Subtotal : $ 25,940
          Playground Drainage                                                                              -
   I1020  Demo/Remove Existing Playgound Rubber Mulch           1,870        SF            0.50            935
   I1021  Demo/Remove Existing Sod/Topsoil                      2,250        SF            0.75          1,688
   I1022  Clean Existing Yard Drains - Allowance                    1        LS          750.00            750
   I1023  Add Yard Drains At Playground - Allowance                 2        EA        2,500.00          5,000
   I1024  Tie-in To Extg Storm Drains                               2        EA        1,500.00          3,000
   I1025  Re-grade Playground At New Drains - Allowance         4,120        SF            0.25          1,030
   I1026  New Modular Plastic Curbing At Playground               172        LF            7.50          1,290
   I1027  Rubber Mulch                                             23        CY          300.00          6,900
   I1028  Landscping - Sod                                      2,252        SF            0.75          1,689
   I1029  Miscellaneous/Unforseen Demo And/Or Replace               1        SF        2,500.00          2,500
                                                  Subtotal : $ 23,847

                                               Site Improvements Subtotal                               50,722

           GENERAL REQUIREMENTS/CONDITIONS                                   7.0%                        3,551
           FEE                                                               5.0%                        2,714
           PERMITS, INSURANCES, AND BONDS                                    4.0%                        2,279
           DESIGN CONTINGENCY                                               10.0%                        5,927
           ESCALATION (5% Per Year)                                          5.0%                        3,260

                                               SITE IMPROVEMENTS TOTAL                            $     68,451

                                               COST/SF            53,418 SF                       $       1.28




Hawthorthe ES Major Bldg Systems Replacement                                ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                 Page 8 of 9                                         9/10/2021
 CODE                 DESCRIPTION                               QTY        UNIT      COST            TOTAL


J. REPLACE ROOFING SYSTEM

  J1010    Demo/Remove Modified Bitumous Roofing System           47,705    SF            2.50        119,263
  J1011    Demo/Remove Metal Parapet Coping                        2,296    LF            1.50          3,444
  J1012    New Modified Bitumen Roof System (Gym NIC)             47,705    SF           17.50        834,838
  J1013    New Metal Parapet Coping                                2,296    SF           22.50         51,660

                                               Roof System Subtotal                                  1,009,204

           GENERAL REQUIREMENTS/CONDITIONS                                  7.0%                       70,644
           FEE                                                              5.0%                       53,992
           PERMITS, INSURANCES, AND BONDS                                   4.0%                       45,354
           DESIGN CONTINGENCY                                              10.0%                      117,919
           ESCALATION (5% Per Year)                                         5.0%                       64,856

                                               ROOF SYSTEM TOTAL                                 $ 1,361,969

                                               COST/SF            53,418 SF                      $      25.50




Hawthorthe ES Major Bldg Systems Replacement                               ADE Construction Consultants, Inc.
Preliminary Assessment Analysis                 Page 9 of 9                                        9/10/2021