SPLOST V - DHMS & RHS Baseball Fields - Budget Reallocation

AID 1425998 · View on Simbli

Agenda Item

xii. E-SPLOST V Project: Design/Build Services for Druid Hills Middle School and Redan High School Baseball Facilities Improvements – Change Order No. 1 to Gilbane Building Company (for a not-to-exceed amount of $584,622)

Summary: Presented by: Mr. Richard H. Boyd, Interim Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve an E-SPLOST V budget reallocation in the amount of $584,622 from Program Contingency which will allow the proper funds to be allocated to the necessary project cost codes for the baseball facilities improvements at Druid Hills Middle School and Redan High School.

It is also requested that the Board of Education approve the Gilbane Building Company Change Order No. 1 for the additional scope associated with the Druid Hills Middle School dugouts, press box, and bleachers; and an ADA walkway, press box and field irrigation at Redan HS for $584,622.
Why: Approval of Change Order No. 1 for the additional scope associated with the Druid Hills Middle School will provide the student/athletes from Druid Hills HS with the proper facilities needed due to the situation whereby the Druid Hills HS Baseball Team practices and plays its sanctioned home games at Druid Hills MS. Typically, a baseball team utilizes the locker room and related facilities at their resident high school, but due to the need for the Druid HS baseball team to travel from Druid Hills HS to Druid Hills MS, those facilities are still needed at Druid Hills MS. Approval of Change Order No. 1 for the additional scope associated with Redan HS will provide improved access to the baseball field in accordance with ADA requirements and repair the inoperable field irrigation system.
Details: Specific details related to the scope of work for this project can be found on the District’s solicitation website at https://dekalbschoolsga.ionwave.net/.

On October 27, 2021, the Board of Education approved the award of RFP No. 21-752-046 for Design/Build Services for Druid Hills Middle School and Redan High School to Gilbane Building Company. The scope of work for this project includes improvements to the baseball facilities at Druid Hills Middle School and Redan High School in response to specific urgent needs for the student/athletes in these 2 clusters.
Financial impact: The total amount of $584,622 for Gilbane Building Company Change Order No.1 will be allocated from the cost code SP5FACCON.30435.GENCONTR under the voter-approved E-SPLOST V program, after the budget reallocation requested herein is completed.
Contact: Mr. Richard H. Boyd, Interim Chief Operating Officer, Division of Operations, 678.676.1483
Effective: Upon board approval
Status: Approved by General Counsel
                                                    SPLOST V Capital Improvement Plan - Fund 423
                                                               Budget Reallocation
                                                         Board Meeting September 12, 2022

                Cost Code                           Code Description               Code Type       Current Budget          Change           Revised Budget
SP5MANG.60235.PRGCONTIN.                                               Program Contingency     $      20,386,842.99   $   (11,880,241.37) $      8,506,601.62

SP5NEWFAC.32235.GENCONTR.             Redan MS                         General Contractor      $       2,640,874.00   $    2,356,281.00   $      4,997,155.00

SP5NEWFAC.36135.GENCONTR.             Fairington ES                    General Contractor      $       1,963,395.00   $    2,240,466.37   $      4,203,861.37

SP5NEWFAC.36535.GENCONTR.             Salem MS                         General Contractor      $       3,737,250.00   $    5,166,440.00   $      8,903,690.00

SP5NEWFAC.35435.GENCONTR.             E.L. Miller                      General Contractor      $       5,940,000.00   $    1,100,000.00   $      7,040,000.00

SP5NEWFAC.30435.GENCONTR.             DHMS/RHS Baseball                General Contractor      $       1,600,000.00   $      584,622.00   $      2,184,622.00

SP5FACCON. 36135.ARCHITECT            Fairington ES                    Architect               $         146,340.00   $      115,321.00   $       261,661.00

SP5FACCON .36535.ARCHITECT            Salem MS                         Architect               $         250,000.00   $      317,111.00   $       567,111.00

SP5SAFSEC. 10935.MGTADMINDC           Life Safety Set Aside            MGT/ADMIN               $       3,530,000.00   $    (2,570,000.00) $       960,000.00

SP5FACCON.37035.GENERALCONTRACTOR     Chesnut ES                       General Contractor      $       5,120,000.00   $      630,000.00   $      5,750,000.00

SP5FACCON.36835.GENERALCONTRACTOR     Laurel Ridge ES                  General Contractor      $       6,640,000.00   $    1,030,000.00   $      7,670,000.00

SP5FACCON.36935.GENERALCONTRACTOR).   Woodridge ES                     General Contractor      $       5,840,000.00   $      910,000.00   $      6,750,000.00

Total                                                                                          $      57,794,701.99   $            (0.00) $    57,794,701.99




                                                                        Page 1 of 1