RFP 23-752-023 Proposal Certification and Recomendation of Award

AID 1425951 · View on Simbli

Agenda Item

iv. E-SPLOST V Project: RFP No. 22-752-023 for GC Services E.L. Miller Elementary School Major Building System Replacement (Centennial Contractors Enterprises, Inc. (not to exceed $6,997,200)

Summary: Presented by: Mr. Richard H. Boyd, Interim Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve an E-SPLOST V budget reallocation in the amount of $1,100,000 from Program Contingency which will allow the proper funds to be allocated to the necessary project cost code for the construction of the major building system replacement at E.L. Miller Elementary School.

It is requested that the Board of Education approve the award of RFP No. 22-752-023 to Centennial Contractors Enterprises, Inc., the most responsive and responsible offeror whose proposal is the most advantageous to the Board based on the evaluation factors, for general contractor services for E.L. Miller Elementary School for the lump sum amount of $6,997,200.
Why: To approve the award of a lump sum construction contract for major building system replacement at E.L. Miller Elementary School.
Details: Specific details related to the scope of work for this Request for Proposal can be found on the DeKalb County School District’s solicitation website at https://dekalbschoolsga.ionwave.net/

The RFP was issued on April 28, 2022, and notification of the upcoming bid was sent via email to more than 150 vendors from the DCSD vendor list, 2,331 vendors through the State of Georgia Procurement Registry, and 327 vendors through Demandstar. The solicitation was advertised in the Champion and posted on the DCSD website. Eight (8) people attended the virtual mandatory pre-proposal meeting on May 12, 2022, representing five (5) general contractor firms. Three (3) proposals were received on July 12, 2022, for the E.L. Miller Elementary School Major Building System Replacement Project. All three proposals were deemed responsive and were evaluated by a selection committee.

Centennial Contractors Enterprises, Inc., will be responsible for the general contracting work as outlined in the proposal documents. The DeKalb County School District’s Standard Firm Fixed Price Contract will be used. The award of this contract will allow for the commencement of the construction of this project. Centennial Contractors Enterprises, Inc., is located at 3200 Cobb Galleria Parkway, Suite 210, Atlanta, Georgia 30339.
Financial impact: The total contract amount for the E.L. Miller Elementary School Major Building System Replacement project in the amount of $6,997,200 will be allocated from the construction cost code SP5FACCON.35435.GENCONTR under the voter-approved E-SPLOST V program. A budget reallocation of $1,100,000 from program contingency is required to fund this project.
Contact: Mr. Richard Boyd, Interim Chief Operating Officer, Division of Operations, 678.676.1483
Effective: Upon board approval.
Status: Approved by General Counsel.