Chronology_of Agenda Item

AID 1417773 · View on Simbli

Agenda Item

ii. Approval of the Fiscal Year 2024 Capital Outlay Application

Summary: Presented by: Mr. Richard Boyd, Interim Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve the Fiscal Year 2024 Capital Outlay Application to the Georgia Department of Education (Ga DOE), totaling $16,861,594.
Why: This will allow for the DeKalb County School District to collect reimbursement funds for these capital improvement projects in the amount of $16,861,594 as allowable under the State Capital Outlay program.
Details: The State of Georgia provides limited funding assistance for capital outlay projects in school districts as determined by state formula. These entitlement funds are awarded as projects are completed. This process is known as "reimbursable" funding, meaning the project (or phases of that project) must be completed first, and then the District applies for the allotted reimbursement.







Each year, districts must submit a Capital Outlay Application, listing the projects for which they will seek reimbursement. The District’s FY 2024 Capital Outlay Project Application requests reimbursement funds in the amount of $16,861,594 from the Georgia Department of Education to be appropriated by the 2023 Georgia General Assembly.







Projects applying for reimbursement funds in the FY 2023 Capital Outlay Project Application include modernization of Cross Keys HS, Modernization of Druid Hills HS, and cooler/freezer replacement at 25 District schools.
Financial impact: The total State Capital Outlay Reimbursement for these projects in the amount of $16,861,594 will be allocated to the capital program which funded the capital outlay: the E-SPLOST V program, the E-SPLOST VI program, or the Operations capital improvement portion of the general fund.
Contact: Mr. Richard Boyd, Interim Chief Operating Officer, Division of Operations, 678.676.1483



Mr. Hans Williams, Director, Planning & E-SPLOST Programming, Division of Operations, 678.676.1588
Effective: Upon board approval
Status: Approved by General Counsel.
Chronology of Recent State Capital Outlay Applications

In September of 2018, the Board approved the FY 2020 Capital Outlay Application, which qualified the
district to receive $2,542,752.

In October of 2019, the Board approved the FY 2021 Capital Outlay Application, which qualified the
district to receive $8,692,880.

In November of 2020, the Board approved the FY 2022 Capital Outlay Application, which qualified the
district to receive $8,635,420.

In October of 2021, the Board approved the FY 2023 Capital Outlay Application, which qualified the
district to receive $2,039,031.

If approved, the FY 2024 Capital Outlay Application will allow the District to receive $16,861,594 in
Capital Outlay Funds from the Georgia Department of Education.

Projects applying for reimbursement funds in the FY 2024 Capital Outlay Project Application include
modernization of Cross Keys HS, Modernization of Druid Hills HS, and cooler/freezer replacement at 25
District schools.




9/12/2016