Champion Theme Phase 2 Exhibit M

AID 1949649 · View on Simbli

Agenda Item

iv. E-SPLOST V Project #35835 ~ Champion Theme Middle School ~ Balfour Beatty ~ Phase 2 Guaranteed Maximum Price (Not to Exceed $10,004,387.66)

Summary: Presented by: Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the DeKalb County School Board of Education approve the items below:
Establish a Phase 2 Guaranteed Maximum Price (“Phase 2 -GMP”) of $10,004,387.66 per the terms set forth in the Construction Manager at Risk (“CMAR”) contract previously awarded to Balfour Beatty via EXHIBIT M - GMP Amendment to Agreement.
Approve a Budget Reallocation from Program Contingency to the necessary project cost code (SP5FACCON. 35835.GENCONTR) for Phase 2 of the E-SPLOST V Project #35835 - Champion Theme Middle School Major Building System Replacement Project in the amount not to exceed $10,004,387.66.
Why: Approval of the amended agreement with Balfour-Beatty establishes a Phase 2 Guaranteed Maximum Price of $10,004,387.66 added with the previous approved work included in Phase 1 and Phase 1.5, resulting in a combined GMP total(s) $33,525,260.
Details: On December 11, 2023, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Balfour Beatty for Pre-Construction Services in the amount of $50,000.
On May 6th, 2024, the Board of Education established a Phase I Guaranteed Maximum Price of $22,779,266 for work included in Phase I of the E-SPLOST V Champion Theme MS project previously awarded to Balfour-Beatty.
On January 12th, 2026, the Board of Education established a Phase 1.5 Guaranteed Maximum Price of $691,605.34 for work completed Phase 1.5 Science Lab renovation raising the total GMP to $23,520,875.34.

This action establishes a Phase 2 Guaranteed Maximum Price for all the Work set forth in the attached Phase 2 GMP PCO Package.
Financial impact: This project will be funded from E-SPLOST V Project #35835 - Champion Theme Middle School Major Building Systems Replacement.

Original Contract Sum ... $50,000 (previously approved)
Phase I GMP ... $22,779,267 (previously approved)
Phase 1.5 GMP ... $691,605.34 (previously approved)
Phase 2 GMP ... $10,004,387.66
Total GMP ... $33,525,260

If approved, a budget reallocation of $10,004,387.66 from Program Contingency will be required into in the construction cost code (SP5FACCON. 35835.GENCONTR).
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-0168
Mr. Hans Williams, Director of Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Pending Approval by the Office of Legal Affairs
                                                           EXHIBIT M
           GMP AMENDMENT TO AGREEMENT BETWEEN OWNER AND
                     CONSTRUCTION CONTRACTOR

               AMENDMENT NO. 1 TO AGREEMENT BETWEEN OWNER AND
             CONSTRUCTION CONTRACTOR FOR Champion Theme School Major Building Systems Replacement and Renovations
                           AGREEMENT NO. SP5FACCON.35835.GENCONTR
        Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
 (“Agreement”), dated 1/18/2024     , between The School Board of DeKalb County, Georgia
 (“Owner”) and      Balfour Beatty

 (“Construction Contractor”), with respect to the construction of Owner’s
     Champion Theme School Major Building Systems Replacement and Renovations
                                                        (“Project”), Owner and Construction
 Contractor hereby agree to amend and modify the Agreement by this Amendment No. 1 and
 establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
 capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
 unless otherwise noted.

                                                             ARTICLE 1


                                                        SCOPE OF WORK
 The scope of the Work consists of the construction of a Major Building Systems Replacement
  and Renovation                                   , in accordance with the Agreement, this
 Amendment and the other Contract Documents listed as Attachments 1 through 7 below, which
 are hereby incorporated into and made a part of the Amendment by this reference:

Attachment No.                   Description                                    Pages                    Date

List of Drawings, Specifications and Addendums
1.                               Allowances                                      N/A_ through __
                                                                                ___            N/A__
2.                               Assumptions and Clarifications                 _ 6     through _ 19__   01/09/2026 (updated)

3.                               Completion Schedule                            _ 20 _ through __30      12/31/2025

4.                               Schedule of Values                             _ 31 _ through _ 31__    01/07/2026

5.                               List of Itemized General Conditions _ 32 through                 32     02/28/2024

6.                               List of Subcontractors and                        __ through _ N/A
                                                                                __N/A             __
                                 Major Suppliers
                                                                                                         3/8/2024
7.                               Alternates                                        33   through   33




                                                                        M-1
                                               ARTICLE 2


                                GUARANTEED MAXIMUM PRICE


           2.1      Construction Contractor’s Guaranteed Maximum Price (“GMP”) for the Work,
 including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
 Construction Management Fee as defined in Section 4 of the Agreement, is Thirty Three Million Five Hundred
Twenty Five Thousand Two Hundred Sixty  ($ $33,525,260.00 ).

         2.2     The Construction Management Fee for the entire Work anticipated on this Project
 is hereby established as a lump sum amount of One Million Five Hundred Ninety Six Thousand Four Hundred Forty One
 ($ 1,596,441.00 ), said lump sum amount is included within the above noted GMP.

         2.3     The general condition expenses for the entire Work anticipated on this Project are
 hereby established as a lump sum amount of Three Million Eight Hundred Forty One Thousand Three Hundred Eighty
 ($ 3,841,380.00 , said lump sum amount is included within the above noted GMP (“General
 Conditions Expenses”). The items included as General Condition Expenses are listed in the List
 of Itemized General Conditions attached hereto and incorporated herein as Attachment No. 5 .
 Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
 Change Order or Construction Change Directive, Construction Contractor acknowledges and
 agrees that Owner shall have no liability for any General Condition expenses beyond payment of
 the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
 to receive any additional compensation from Owner for the General Conditions beyond the above
 lump sum amount. There shall be no additional General Conditions Expenses payable to
 Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
 of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
 this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
 Change Directive Work). Further, there shall be no mark-up for a subcontractor’s General
 Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
 Change Order and Construction Change Directive Work to be performed by such subcontractor.

        2.4    Monthly installment payment of the Construction Management Fee and the General
 Condition Expenses shall be based upon the percent completion of the designated portion of the
 Work for each particular month.

         2.5     In order to efficiently and timely address any unknown or unanticipated conditions
 that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
 of the Work, but excluding all items that are to be reimbursed under the lump sum General
 Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
 contingency within the GMP in an amount not-to-exceed amount of                 Zero            and
  0 /100 Dollars ($      0.00                ) (“Owner’s Contingency”). Owner’s Contingency
 funds shall be used to cover costs that may result from incomplete design and unanticipated costs
 that arise during construction that are not identified by the construction documents. Construction

                                                        M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner’s Contingency without first obtaining Owner’s express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner’s Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor’s Work compensated within the
GMP and not chargeable against Owner’s Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner’s Contingency expenditures. Further, the work that
is the subject of any Owner’s Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner’s Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner’s Contingency.

                 2.6      In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above, the parties have agreed to
                                                                           One Million Six Hundred Four Thousand
establish a contingency within the GMP in an amount not-to-exceed One Hundred Seventy Eight.
Dollars ($1,604,178.00)(“Contractor’s Contingency”). Construction Contractor shall not proceed
with any portion of   ofthe Work which it intends to charge against the Contractor’s Contingency
without first obtaining Owner’s express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor’s
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor’s Work compensated within the GMP and not chargeable against
Contractor’s Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor’s Contingency expenditures. Further, the work that is the subject of any Owner’s
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor’s Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor’s Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of 5 % of
the Cost of the Work charged against the Contractor’s Contingency.

        2.7     The parties have agreed to establish an allowance within the GMP for
     N/A (GMP #002)           in the amount of zero (GMP #002)                   s ($ 0.00          ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance (“Allowance Work”) without first obtaining Owner’s express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments          through . Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenever costs are more
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.




                                                       M-3
                2.8     Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
     payment is made to Construction Contractor the total Cost of the Work has been increased by
     approved Change Orders in an amount causing the original GMP as set forth in this Amendment
     to be exceeded by more than five hundred thousand and      /100 Dollars ($ 500,000.00      ), then
     Construction Contractor shall be entitled to an increase in the Construction Management Fee in
     the amount of and /100 Dollars (                  5         %) of the amount exceeding the sum of
five hundred thousand and   /100 Dollars ($ 500,000.00 _) plus that original GMP amount.

          2.9     Construction Contractor recognizes that the Contract includes work for trench
  excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
  set forth by all federal, state and local requirements. Construction Contractor certifies that the
  required trench safety standards will be in effect during the period of construction of the Project
  and Construction Contractor agrees to comply with all such required trench safety standards.

                 2.10.1 The amount of                     zero                 and /100         Dollars
  ($    0.00        ) has been separately identified for the cost of compliance with the required trench
  safety standards; said amount is included within the GMP.

          2.10 At the completion of the Work, should the actual amount of “General
  Requirements” expenses be less than the amount included therefor in the Schedule of Values
  approved by Owner, the resulting “savings” shall accrue to the benefit of Owner and a deductive
  Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
  of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
  may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
  Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
  separate guaranteed maximum price for such expenses and any overruns in General Requirements
  expenses shall be borne by Construction Contractor without reimbursement from Owner.

          2.11 By executing this Amendment and furnishing Owner with a GMP based on a
  detailed Schedule of Values and a Master Project Schedule, Construction Contractor represents
  and warrants that the Contract Documents, including the Construction Documents, as well as other
  materials, and information furnished Construction Contractor as of the date of this Amendment
  have described the scope, construction requirements, and design intent of the Work in detail
  sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
  Project Schedule. To the extent that the Construction Documents are anticipated to require further
  development, Construction Contractor has provided in the GMP for such further development
  consistent with the Contract Documents and reasonably inferable therefrom.

          2.12 Savings will be computed as of the date of final completion of the Work and shall
  consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
  accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
  Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
  benefit of Owner.



                                                      M-4
                                          ARTICLE 3


                                      CONTRACT TIME
        3.1     The Construction Phase Commencement Date for the Work is 4/15/2024 . The
total period of time beginning with the Construction Phase Commencement Date through the date
required for Substantial Completion of the Work is      One Thousand Two Hundred Two ( 1202 )
days ("Contract Time"). THE SUBSTANTIAL COMPLETION DATE IS THEREFORE
ESTABLISHED AS              July 30, 2027              .

        3.2     Pursuant to the Agreement, the parties have established liquidated damage rates for
reasons stated therein, which the parties acknowledge and agree apply to this Amendment and
Construction Contractor’s responsibility to substantially complete the Work within the Contract
Time as stated herein and finally complete the Work within the time prescribed in the Contract.
Accordingly, the liquidated damage rates established in the Agreement shall be assessed against
Construction Contractor for each calendar day Construction Contractor fails to achieve Substantial
Completion of the Work within the Contract Time or final completion of the Work within the time
prescribed in the Contract.

                                          ARTICLE 4


                                      MISCELLANEOUS
4.1 Except as expressly modified herein, the terms and conditions of the Agreement remain
unchanged. All terms not specifically defined herein shall have the meaning ascribed to them in
the Agreement. In the event of a conflict between the terms of this Amendment and those of the
Agreement, Owner and Construction Contractor agree that the terms of this Amendment shall
prevail and control. This Amendment may be executed in counterparts, each of which shall be
deemed to be an original, but all of which shall constitute one and the same instrument.

Owner                                        Construction Contractor

By:                                                  By:

Its:                                                 Its:

Date:                                                Date:

Attest:                                              Attest:




                                                  M-5
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                           Revied GMP Estimate
  Stone Mountain, GA                                                     January 7, 2026



Assumptions & Clarifications-Phase 1

The following clarifications and assumptions, organized by CSI division, are included as part of the Agreement.

General Notes
   1. This GMP Estimate for Champion Theme Middle School is based upon the following documents, unless
       otherwise stated in Clarifications below:
             a. Project Manual Issued for Construction dated Jan.20,2022 by SSOE
             b. Plans Issued for Construction dated Jan.20,2022 by SSOE
             c.   Addendum #1 – Not provided
             d. Addendum #2 dated June.21, 2022 by SSOE
             e. RFI log#1 (see attached)


This estimate includes:
    1. Construction Manager will furnish and maintain General Liability Insurance through a GL/Excess BBC’s
        master insurance program. The General Liability Insurance will be billed at a fixed rate of 1.10% of the GMP
        with the first Payment Application. Direct bills from the master program are not available as the fixed rate is
        based on the entire portfolio of US projects and calculated as a fixed rate.
    2. Balfour Beatty P&P Bond will be provided at a fixed rate of 0.561% of the GMP. Bond costs will be billed
       100% with the first Payment Application.
    3. Builder’s Risk policy will be provided by Contractor and be billed at actual cost with the first Payment
       Application at a value equal to the cost of work. Owner shall maintain property insurance for facility.
    4. Construction Manager will furnish and maintain Subcontractor Default Insurance (SDI) through BBC’s master
       insurance program. SDI will be billed at a fixed rate of 1.52% of the cost of work. Direct bills from the master
       program are not available as the fixed rate is based on the entire portfolio of US projects and calculated as a
       fixed rate. Construction Manager will purchase, maintain, and enroll all eligible and prequalified
       subcontractors, suppliers, and vendors into a SDI program at a fixed amount which shall be billed in total at
       the outset of the project. Any subcontractors who do not meet SDI prequalification requirements who have
       subcontractors over $250,000 will be bonded at the contractor’s discretion.


Division 1                       General Requirements
This estimate includes:
    1. Digital Documents: All documents including closeouts will be transmitted digitally. No provisions for hard
       copies are included.
    2. Potential Trade Escalation: Should the award of certain Trade Contracts not allow for a fixed-price structure
       where the Trade Contractor would bear all or part of the responsibility for future inflation and/or cost
       escalation for the entire scope and value of the Trade Contract due to either (1) market conditions (supply
       chain, etc.) that won’t allow for firm fixed price commitments at time of Trade Contract award and/or (2) at the
       request of the Owner who wants to remove such Escalation Allowances or Escalation Contingencies for
       anticipated or potential future inflation and/or cost escalation from the initial Trade Contract amount and fully
       bear that future risk, the Expenditure Authorization Letter will capture such details and outline the mutually
       agreed-upon timeline and process for which the material escalation items will be measured and later




                                                    Page 6 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                           Revied GMP Estimate
  Stone Mountain, GA                                                     January 7, 2026



       reconciled. Upon reconciliation of any material escalation item from Trade Contracts, the GMP contract
       amount will be adjusted accordingly via Change Order. Should the Owner elect to deviate from the agreed-
       upon timeline for reconciling the escalation as outlined in the Expenditure Authorization Letter, any further
       cost or schedule impacts resulting from that change will cause the GMP to be adjusted via the Change Order
       process outlined in the Agreement.
   3. General Conditions: Are established as a lump sum that shall be paid in equal installments on a monthly basis
      over the course of the project.
   4. Construction Contingency: Our GMP Proposal contains 7 percent (7.00%) of Cost of the Work construction
      contingency (based on the 100% CD’s). The Construction Contingency will be used at the reasonable
      discretion of the Contractor to address unexpected circumstances and expenses incurred to: (a) pay for
      purchase of subcontracts, suppliers and vendors in excess of budgeted line item(s) within the GMP; (b) fill
      scope gaps between trade subcontractors; (c) repair un-assignable damaged work; and (d) settle minor
      disputes with trade subcontracts at the completion of the Project. In essence, these are expenses which are
      ordinary and customary that does not constitute a change in the Work as defined in the Agreement. The
      Construction Contingency can be used to offset cost overruns incurred by the Contractor for General
      Conditions or General Requirements. Conversely, any savings will flow into the Construction Contingency.
   5. Pandemic/ Supply Chain Issues: Any delays in deliveries, unavailability of materials or equipment, labor
      shortages and/or cost escalation attributable to epidemic, pandemic or public health emergencies as well as
      supply chain issues will constitute compensable delays or change events.
   6. An assumption that to the extent the specifications do not involve design elements performed by different trades
      and is otherwise a customary proprietary design or engineered component requiring a professional engineer’s
      stamp on shop drawings such as fire suppression systems, fire alarm systems and other similar activities,
      Construction Manager’s liability for design errors and omissions is limited to amounts we recover from the
      subcontractor or its insurance carriers.
   7. Installation, rental, and removal of three (3) eight-classroom modular classroom trailers to relocate students
      during construction. Rental included for 26 months (from 5/1/2024 through 07/01/2026). Classroom trailers
      include electrical, mechanical, plumbing, and fire protection installation. This scope includes an allowance for
      electrical and plumbing (water/sewer) final connections since the final tie-in locations are not known at this time.
      See Allowances.
This estimate excludes:
   8. Repairs to existing structure(s) other than as provided on the Contract Documents.
   9. Security guards, security cameras, or security services.
   10. Any code updating of existing facility not specifically shown or identified on the documents.
   11. Utility consumption fees, except temporary construction power due to this being occupied campus.
   12. Design responsibility inherent in performance specifications that involve assemblies or interfaces among
       design elements performed by different trades or are otherwise not customary proprietary specifications
       obtained from single manufacturers.
   13. Specifications that state the following or something substantively similar to the following 1) “delegated design:
       design assembly or interface, including comprehensive engineering analysis by a qualified professional
       engineer, using performance requirements and design criteria indicated”; 2) requirements for code
       compliance and design features “whether or not indicated on the drawings,” and 3) references to design “by
       others” on the drawings.
   14. All Testing




                                                    Page 7 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                             Revied GMP Estimate
  Stone Mountain, GA                                                       January 7, 2026



Division 2                       Demolition
This estimate includes:
    1. All Selective demolition as indicated on the contract documents.
    2. Allowance for Abatement. See Allowances.
    3. Allowance for removal of all Furniture, Fixtures & Equipment (FF&E) prior to commencement of construction
       work. See Allowances.


This estimate excludes:
    4. The demolition or modification of the existing raised cooling tower platform (note 1/A0.01)
    5. Grinding of existing floors for mastic removal, removal of adhesives and curing compounds from concrete
       slabs
    6. The extent of abatement excludes all items listed as unknown on the provided Ahera Asbestos Inspection
       Report and Management Plan (dated June 12,2023) and items that will not or should not be at all affected of
       disturbed as part of the overall Project Goal (stage curtains, fire doors, floor tile, fume hoods, in
       areas/classrooms not affected of the overall project scope).
    7. Air testing and final air clearance testing.
    8. Any bracing/shoring or engineering of such as required for demolition.
    9. Removal of all existing nails, brackets, plastic shield, hooks, clips, tape, screws etc. from walls, floors or
       ceilings.




Division 3                       Concrete
This estimate includes:
    1. Modifications to existing equipment pads as required.
This estimate excludes:
    2. Pedestal/footings for any equipment not specifically shown on the contract documents.


Division 4                       Masonry
This estimate includes:
    1. New masonry walls as indicated on the contract documents.


This estimate excludes:
    2. Patching pre-existing holes/penetrations on existing masonry walls
    3. Patching holes in masonry walls, made by the removal of any existing FF&E and any wall mounted
       accessories.
    4. Grouting of existing masonry walls




                                                      Page 8 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                           Revied GMP Estimate
  Stone Mountain, GA                                                     January 7, 2026




Division 5                       Metals
This estimate includes:
    1. All structural steel as indicated on the structural drawings.
    2. An allowance for Structural steel for any roof openings through the roof deck. See Allowances.




This estimate excludes:
    1. AISC certification.
    2. Recycled materials requirement
    3. New cooling tower steel platform or modifications to the existing cooling tower steel platform
    4. Reinforcing existing steel or concrete joists, deck, or any structure




Division 7                       Thermal and Moisture Protection
This estimate includes:
    1. Roofing warranty only for areas affected by this scope of work
    2. 500 lf of new walkway pads
    3. Blocking as required only for the areas of the roof affected by this scope of work
    4. An allowance for patching existing spray fireproofing. See Allowances.
This estimate excludes:
    5. Warranty for existing roof to remain
    6. Replacement of existing wood blocking and insulation at existing areas not affected by this scope of work
    7. Testing for roofing
    8. Repair/replacement of any edge metal, gutters or downspouts
    9. New roof hatch/ roof ladders


Division 8                       Doors and Windows
This estimate includes:
    1. All doors, frames and hardware as indicated on the door schedule in the contract documents.




This estimate excludes:




                                                    Page 9 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                            Revied GMP Estimate
  Stone Mountain, GA                                                      January 7, 2026



    1.   Replacement of any existing doors, frames, and hardware not specifically indicated on the contract
         documents.
    2.   Replacement of any existing glazing, windows, storefronts, or louvers not specifically indicated on the contract
         documents.


Division 9                       Finishes
This estimate includes:
    1. Painting only at new interior hollow metal frames.
    2. Painting only ‘corner to corner’ at existing walls where patching will occur for new construction activities
    3. Metal framing to structure at soffits and bulkheads as called out on A6.90 included with a proposed height of
       14’-0” per Detail 3/A3.01
    4. Flooring material allowances as follows:
         - VCT = $1.25/SF
         - 4” rubber base = $0.80/LF
         - CT1 = $5.51/SF
         - CT2 = $2.86/SF
         - Tile base = $1.75/piece
    5. Minor floor prep
    6. Manufacturer standard colors for all floor and wall tile and grout colors
    7. Manufacturer standard colors for VCT




This estimate excludes:
    1. R13 insulation
    2. Abuse-resistant gypsum wallboard
    3. Sound-Attenuation Blankets (Type 1)
    4. Scraping all peeling paint from existing walls and repainting
    5. Custom colors for any flooring products
    6. Moisture mitigation/remediation
    7. Excessive floor prepping for flooring installation
    8. Major levelling
    9. Seismic bracing
    10. Patching and painting pre-existing holes and penetrations on walls, floors or ceilings.
    11. Patching holes in the masonry walls, made by the removal of any existing FF&E and any wall mounted
        accessories and finishing/painting of the same.




                                                    Page 10 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                          Revied GMP Estimate
  Stone Mountain, GA                                                    January 7, 2026




Division 10                     Specialties
This estimate includes:
    1. Replacing existing toilet accessories as called for in the contract documents.


This estimate excludes:
    2. Removal or replacement of any work associated with toilet partitions.


Division 12                     Casework
This estimate includes:
    1. All science lab casework by TMI Systems, overlay laminate casework. Casework to include ¾” particleboard
       core drawers, doors and shelves (1” over 30” wide). VGS laminate on exterior faces & exposed ends. TFL
       white laminate for interiors and wall cabinet bottoms. 3 mm PVC edging on all four sides of doors and
       drawers. 1mm PVC edging on cabinet bodies and front edge of shelves. Units include 5-knuckle epoxy
       powder coated hinges, vendor stock pulls, dual pin poly shelf clips, magnetic door catches, bottom mounted
       drawer slides and disc tumbler locks where indicated.
    2. 1” plastic laminate tops with particleboard core, 3mm PVC edge band and applied backsplash. Laminates to
       be selected from Formica standard laminates.


This estimate excludes:
    3. Window Treatment
    4. Furniture




Division 21,22 & 23                     Mechanical Systems (Plumbing, Fire Protection, HVAC)
This estimate includes:
    1. This proposal assumes that existing plumbing rough-in and supports do not require modifications for new
       plumbing fixtures.
    2. This proposal includes HVAC equipment & systems as R-410A per the Contract Documents. This proposal
       does not include the forthcoming legal mandated changes to refrigerants. The proposal assumes that HVAC
       equipment will be included in early release and all submittals completed and approved in a timely fashion for
       all HVAC equipment to be ordered before July 1, 2024.
    3. HVAC life safety dampers as indicated on the Construction Drawings. This proposal assumed the Mechanical
       Designer has shown all dampers required by code.
This estimate excludes:
    4. This proposal assumes the existing gas service is sufficient and excludes any upgrades to the existing
       service.




                                                  Page 11 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                             Revied GMP Estimate
  Stone Mountain, GA                                                       January 7, 2026



    5. Temporary equipment for heating/cooling. This proposal only includes running permanent units for temp
       heat/cooling once installed.
    6. Fire Pumps. This proposal assumes the provided Flow Test analysis is sufficient.
    7. Delegated-design of hangers & supports.
    8. Seismic Bracing requirements.
    9. Any new roof drains or any new work associated with drainage
    10. Any repair of existing to remain pipe, insulation or equipment


Division 26                       Electrical Systems
This estimate includes:
    1.   Allowance for ERRCS testing and installation. See Allowances
    2.   New raceways installed below ceiling will be surface mounted.
    3.   Salvage and reinstallation of low voltage devices mounted to ceiling as noted on Contract Documents.
This estimate excludes:
    4.   Installation of new Tele/data/AV systems including Smartboards
    5.   Any repair or adjustment for existing to remain feeders or equipment




Division 31 & 32                          Sitework & Fencing
This estimate includes:
    1.   Fencing includes 8’ black 8-gauge chain link fence.
    2.   Sod for the area where classroom modular trailers are located.
    3.   Paving and striping only at areas disturbed by the new Fire Line installation.


This estimate excludes:
    10. New granite curbs.
    11. Re-surfacing or re-striping existing parking lot which is outside the limits of the scope of work
    12. Excavation, removal, and or replacement of unsuitable soils/ rock.




                                                    Page 12 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                          Revied GMP Estimate
  Stone Mountain, GA                                                    January 7, 2026



Alternates
Alternate amounts listed below are the direct cost amounts and do not include Contractor overhead, fees, insurances,
or indirect costs. Alternates may be incorporated by future Change Order. Alternate pricing is good for twenty (20)
days.

    1. N/A



Estimate / Owner Allowances (Included in Budget)
Allowance amounts listed below are the direct cost amounts and do not include Contractor overhead, fees,
insurances, or other indirect costs. Allowances are for the Owner and will be reconciled by change order. Contractor
assumes no cost exposure for the assigned value of the indicated Allowances.

    1. Allowance for the water/sewer/electrical connections for the classroom trailers = $50,000
    2. Allowance for patching existing spray fireproofing as required = $27,000

    3. Allowance for Abatement = $155,680
    4. Allowance for testing for an ERRCS = $40,661
    5. Allowance for installation and commissioning of an ERRCS = $203,303
    6. Allowance for electrical bid spread = $1,200,000
    7. Allowance for removal of all Furniture, Fixtures & Equipment (FF&E) prior to commencement of construction
       work = $100,000
    8. An allowance for Structural steel for any roof openings through the roof deck = $84,000




PLEASE REVIEW NEXT PAGE FOR PHASE 2 GMP CLARIFICATIONS




                                                  Page 13 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                           Revied GMP Estimate
  Stone Mountain, GA                                                     January 7, 2026



Assumptions & Clarifications – Phase 2 GMP

The following clarifications and assumptions, organized by CSI division, are included as part of the Agreement.

General Notes
   1. This GMP Estimate for Champion Theme Middle School is based upon the following documents, unless
       otherwise stated in Clarifications below:
             a. CHAMPION MS - PH 2_ARCHITECTURAL 80% CD_11.14.2025
             b. CHAMPION MS - PH2_CIVIL 80%CD_11.14.2025
             c.   CHAMPION MS - PH2_MECHANICAL 80% CD_11.14.2025
             d. CHAMPION MS -PH2_ELECTRICAL 80%CD_ 11.14.2025
             e. CHAMPION MS-PH2_PLUMBING 80% CD_ 11.14.2025
             f.   Email correspondence between BB & SSOE dated 12.10.2025
Division 1                       General Requirements
This estimate includes:
    1. Digital Documents: All documents including closeouts will be transmitted digitally. No provisions for hard
       copies are included.
    2. Potential Trade Escalation: Should the award of certain Trade Contracts not allow for a fixed-price structure
       where the Trade Contractor would bear all or part of the responsibility for future inflation and/or cost
       escalation for the entire scope and value of the Trade Contract due to either (1) market conditions (supply
       chain, etc.) that won’t allow for firm fixed price commitments at time of Trade Contract award and/or (2) at the
       request of the Owner who wants to remove such Escalation Allowances or Escalation Contingencies for
       anticipated or potential future inflation and/or cost escalation from the initial Trade Contract amount and fully
       bear that future risk, the Expenditure Authorization Letter will capture such details and outline the mutually
       agreed-upon timeline and process for which the material escalation items will be measured and later
       reconciled. Upon reconciliation of any material escalation item from Trade Contracts, the GMP contract
       amount will be adjusted accordingly via Change Order. Should the Owner elect to deviate from the agreed-
       upon timeline for reconciling the escalation as outlined in the Expenditure Authorization Letter, any further
       cost or schedule impacts resulting from that change will cause the GMP to be adjusted via the Change Order
       process outlined in the Agreement.
    3. General Conditions: Are established as a lump sum that shall be paid in equal installments on a monthly basis
       over the course of the project.
    4. Construction Contingency: Our GMP Proposal contains 5 percent (5.00%) of Cost of the Work construction
       contingency (based on the 100% CD’s). The Construction Contingency will be used at the reasonable
       discretion of the Contractor to address unexpected circumstances and expenses incurred to: (a) pay for
       purchase of subcontracts, suppliers and vendors in excess of budgeted line item(s) within the GMP; (b) fill
       scope gaps between trade subcontractors; (c) repair un-assignable damaged work; and (d) settle minor
       disputes with trade subcontracts at the completion of the Project. In essence, these are expenses which are
       ordinary and customary that does not constitute a change in the Work as defined in the Agreement. The
       Construction Contingency can be used to offset cost overruns incurred by the Contractor for General
       Conditions or General Requirements. Conversely, any savings will flow into the Construction Contingency.
       Our GMP #2 includes 5% Construction Contingency and 2% Design Contingency.




                                                   Page 14 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                             Revied GMP Estimate
  Stone Mountain, GA                                                       January 7, 2026



    5. Pandemic/ Supply Chain Issues: Any delays in deliveries, unavailability of materials or equipment, labor
       shortages and/or cost escalation attributable to epidemic, pandemic or public health emergencies as well as
       supply chain issues will constitute compensable delays or change events.
    6. An assumption that to the extent the specifications do not involve design elements performed by different trades
       and is otherwise a customary proprietary design or engineered component requiring a professional engineer’s
       stamp on shop drawings such as fire suppression systems, fire alarm systems and other similar activities,
       Construction Manager’s liability for design errors and omissions is limited to amounts we recover from the
       subcontractor or its insurance carriers.
This estimate excludes:
    1. Repairs to existing structure(s) other than as provided on the Contract Documents.
    2. Security guards, security cameras, or security services.
    3. Any code updating of existing facility not specifically shown or identified on the documents.
    4. Utility consumption fees, except temporary construction power due to this being occupied campus.
    5. Design responsibility inherent in performance specifications that involve assemblies or interfaces among
       design elements performed by different trades or are otherwise not customary proprietary specifications
       obtained from single manufacturers.
    6. Specifications that state the following or something substantively similar to the following 1) “delegated design:
       design assembly or interface, including comprehensive engineering analysis by a qualified professional
       engineer, using performance requirements and design criteria indicated”; 2) requirements for code
       compliance and design features “whether or not indicated on the drawings,” and 3) references to design “by
       others” on the drawings.
    7. All Testing




Division 2                       Demolition
This estimate includes:
    1. Demolition of media center, restrooms, kitchen, security vestibule, windows/storefronts/doors, lockers as
       shown in the contract documents
    2. Demolition of marker boards, tackboards, flooring for Level 1


This estimate excludes:
    1. Grinding of existing floors for mastic removal, removal of adhesives and curing compounds from concrete
       slabs
    2. Demolition of door frames
    3. Air testing and final air clearance testing.
    4. Any bracing/shoring or engineering required for demolition.
    5. Removal of all existing nails, brackets, plastic shields, hooks, clips, tape, screws etc. from walls, floors or
       ceilings.




                                                      Page 15 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                           Revied GMP Estimate
  Stone Mountain, GA                                                     January 7, 2026



Division 3                       Concrete
This estimate includes:
    1. New structure build-out for security vestibule
    2. Patching 500 SF of concrete slabs for plumbing work
This estimate excludes:
    1. Pedestal/footings for any equipment not specifically shown on the contract documents.


Division 4                       Masonry
This estimate includes:
    1. New CMU wall and brick veneer at security vestibule


This estimate excludes:
    1. Patching pre-existing holes/penetrations on existing masonry walls
    2. Patching holes in masonry walls, made by the removal of any existing FF&E and any wall mounted
       accessories.
    3. Grouting of existing masonry walls and door frames


Division 6                       Millwork
This estimate includes:
    1. Media center furnishings by Media Technologies
    2. Science lab casework per PCO #014 dated 11/13/2025 by TMI Systems-overlay laminate casework.
       Casework to include ¾” particleboard core drawers, doors and shelves (1” over 30” wide). VGS laminate on
       exterior faces & exposed ends. TFL white laminate for interiors and wall cabinet bottoms. 3 mm PVC edging
       on all four sides of doors and drawers. 1mm PVC edging on cabinet bodies and front edge of shelves. Units
       include 5-knuckle epoxy powder coated hinges, vendor stock pulls, dual pin poly shelf clips, magnetic door
       catches, bottom mounted drawer slides and disc tumbler locks where indicated.
    3. 1” plastic laminate tops with particleboard core, 3mm PVC edge band and applied backsplash. Laminates to
       be selected from Formica standard laminates.


This estimate excludes:
    1. Media center seating
    2. Wood Base / Wood Panels


Division 8                       Openings
This estimate includes:
    1. YKK 2" x 4-1/2" system for interior and exterior storefront. Exterior glazing shall be 1" clear with SB90 #2
       temp and Interior Glazing shall be 1" Clear temp.




                                                   Page 16 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                             Revied GMP Estimate
  Stone Mountain, GA                                                       January 7, 2026



    2. Factory finished solid core wood doors, FRP doors, Hollow Metal Doors and door hardware
    3. Minor field prep for door frames to remain
    4. Safe haven SW660 at W-14 & W-15; 3M Ultra 800 for interior door kit glass and 3M S70X at exterior door kit
       glass.


This estimate excludes:
    1. Replacing door frames
    2. Card Readers
    3. Major field modifications to existing HM Frames
    4. Custom painted storefront frame
    5. Water testing




Division 9                      Finishes
This estimate includes:
    1. Infill of walls at locations where lockers have been removed
    2. Glassliner FRP Series 1600 (Ivory) in kitchen
    3. Painting on walls, ceilings, door frames on Level 1
    4. Material allowance of $30 per SY for carpet flooring and $3 per SF for Resilient Athletic Flooring
    5. Allowance of $25 per SF for furnish and installing epoxy flooring
    6. 2" squared edged fabric wrapped acoustic panels in gym area. Panels shall be wrapped using Guilford of
       Maine: FR-701 #2100
    7. 800 grit polished concrete


This estimate excludes:
    1. R13 insulation
    2. Abuse-resistant gypsum wallboard
    3. Sound-Attenuation Blankets (Type 1)
    4. Scraping all peeling paint from existing walls and repainting
    5. Custom colors for any flooring products
    6. Moisture mitigation/remediation
    7. Major levelling / Excessive floor preparation
    8. Seismic bracing




                                                    Page 17 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                                Revied GMP Estimate
  Stone Mountain, GA                                                          January 7, 2026



Division 10                        Specialties
This estimate includes:
    1. New toilet accessories and partitions in renovated restrooms
    2. Tack board, marker board, and teacher’s cabinet for Level 1 classrooms


Division 21,22, & 23               Mechanical Systems (Plumbing, Fire Protection, HVAC)
This estimate includes:
    1. Demo of Fume hood exhaust duct. Ducts shall be removed and capped in ceiling.
    2. Unit heat for security vestibule and UDS for kitchen.
    3. Allowance of $150,000 for replacement of outdated kitchen hood system.
This estimate excludes:
    4. This proposal assumes the existing gas service is sufficient and excludes any upgrades to the existing
       service.
    5. Flash and seal roof at exhaust curbs


Division 26                        Electrical Systems
This estimate includes:
    1.   Power to new UDS and Unit Heater
    2.   Modifications to Fire Alarm system
This estimate excludes:
    1.   Installation of new Tele/data/AV systems including Smartboards
    2.   Any repair or adjustment for existing to remaining feeders or equipment


Division 31 & 32                            Sitework & Exterior improvements
This estimate includes:
    1. Demolition
         •    Remove track pavement, curb & gutter, block walls, sidewalks, and water lines.
         •    Salvage barbed fence at track area.
         •    Disconnect and cap utilities to modular buildings.
    2. Excavation & Grading
         •    Clear and grub site, strip topsoil, haul out debris.
         •    Import fresh topsoil for track area, fine grading, and hand excavation near retaining walls.
    3. Utilities
         •    Install 4" DIP water line with meter vault and tie-in to building.




                                                       Page 18 of 33
  CLARIFICATIONS AND ASSUMPTIONS
  Champion Theme Middle School                                            Revied GMP Estimate
  Stone Mountain, GA                                                      January 7, 2026



        •   Install 12" DIP storm line and perforated drains at security vestibule and retaining walls.
        •   Secondary drainage at security vestibule and retaining walls
    4. Erosion Control
        •   Provide silt fence, concrete washouts, construction entrance, inlet sediment traps, and ongoing
            maintenance.
    5. Site Concrete
        •   Installation of 24" curb & gutter, ADA ramps, sidewalks, and block walls
        •   Construct 8" concrete retaining walls
        •   Reinstall barbed fence.
    6. Asphalt mill and repave from material laydown yard to cul-de-sac
    7. Striping and signage
    8. Athletic track with concrete curbs, 7” GAB, 2” Base course, 2” Finish course, ST55 track surface


This estimate excludes:
    1. Excavation, removal, and or replacement of unsuitable soils/ rock.
    2. Irrigation System
    3. Athletic Equipment




Estimate / Owner Allowances (Included in Budget)
Allowance amounts listed below are the direct cost amounts and do not include Contractor overhead, fees,
insurances, or other indirect costs. Allowances are for the Owner and will be reconciled by change order. Contractor
assumes no cost exposure for the assigned value of the indicated Allowances.

    1. Replace of kitchen hood                                                      $ 150,000
    2. Carpet Material Allowance                                                    $30 per SY
    3. RAF Material Allowance                                                       $3 per SF




                                  END OF ASSUMPTIONS AND CLARIFICATIONS




                                                    Page 19 of 33
Activity ID              Activity Name                                             OD    RD       % Start           Finish                    2024                                     2025                                  2026                                  2027                      2028
                                                                                                                                  J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
                                                                                   996   418          23-Jan-24 A   27-Aug-27                                                                                                                                                 Champion MS Update 32 2025-12-30
   Champion MS Update 32 2025-12-30
    Milestones                                                                     996   418          23-Jan-24 A   27-Aug-27                                                                                                                                                 Milestones

     M100                Executed Precon Agreement                                  0     0    100% 23-Jan-24 A                    Executed Precon Agreement
     M110                NTP - Preconstruction                                      0     0    100% 29-Jan-24 A                     NTP - Preconstruction
     M120                Project Kick-off Meeting DCSD/SSOE/BB                      0     0    100% 29-Jan-24 A                     Project Kick-off Meeting DCSD/SSOE/BB
     M130                NTP - Construction                                         0     0    100% 12-Jun-24 A                                  NTP - Construction
     M150                Start Modular Classrooms                                   0     0    100% 29-Aug-24 A                                             Start Modular Classrooms
     M250                Start 2024-2025 School Year Work                           0     0    100% 04-Dec-24 A                                                      Start 2024-2025 School Year Work
     M350                Start Summer 2025 Work                                     0     0    100% 02-Jun-25 A                                                                         Start Summer 2025 Work
     M450                Start 2025-2026 School Year Work                           0     0    100% 16-Jul-25 A                                                                               Start 2025-2026 School Year Work
     M300                2024-2025 School Year Substantial Completion               0     0    100%                 24-Jul-25 A                                                               2024-2025 School Year Substantial Completion
     M400                Summer 2025 Work Substantial Completion                    0     0    100%                 11-Aug-25 A                                                                 Summer 2025 Work Substantial Completion
     M1000               Board Approval of Phase 2 GMP (Estimated)                  0     0      0%                 09-Feb-26*                                                                                   Board Approval of Phase 2 GMP (Estimated)
     M500                2025-2026 School Year Work Substantial Completion          0     0      0%                 08-Apr-26*                                                                                          2025-2026 School Year Work Substantial Completion
     M550                Start Summer 2026 Work                                     0     0      0% 01-Jun-26                                                                                                                 Start Summer 2026 Work
     M600                Summer 2026 Work Construction Completion                   0     0      0%                 31-Jul-26*                                                                                                      Summer 2026 Work Construction Completion
     M900                Project Substantial Completion (Initial Contract)          0     0      0%                 31-Jul-26                                                                                                       Project Substantial Completion (Initial Contract)
     M910                Project Substantial Completion (Phase 2 Added Work)        0     0      0%                 30-Jul-27                                                                                                                                              Project Substantial Completion (Phase 2 Added Work)
     M950                Final Completion                                           0     0      0%                 27-Aug-27                                                                                                                                                 Final Completion
     Durations                                                                     563   148          12-Jun-24 A   31-Jul-26                                                                                                       Durations
      DUR60              Project Construction Duration (calendar days)             810   213   73.7% 12-Jun-24 A    31-Jul-26                                                                                                       Project Construction Duration (calendar days)
      DUR20              2024-2025 School Year Construction Duration               167    0    100% 04-Dec-24 A     24-Jul-25 A                                                               2024-2025 School Year Construction Duration
      DUR30              Summer 2025 Construction Duration                         59     0    100% 02-Jun-25 A     11-Aug-25 A                                                                 Summer 2025 Construction Duration
      DUR40              2025-2026 School Year Construction Duration               295   99 66.44% 16-Jul-25 A      08-Apr-26                                                                                           2025-2026 School Year Construction Duration
      DUR50              Summer 2026 Construction Duration                         44    44      0% 01-Jun-26       31-Jul-26                                                                                                       Summer 2026 Construction Duration

    School Calendar                                                                796   394          23-May-24 A 26-Jul-27                                                                                                                                                School Calendar

     HOL100              Teacher Last Day 2023-2024                                 1     0    100% 23-May-24 A 23-May-24 A                    Teacher Last Day 2023-2024
     HOL110              Teacher First Day 2024-2025                                1     0    100% 29-Jul-24 A     29-Jul-24 A                       Teacher First Day 2024-2025
     HOL120              Thanksgiving Break 2024                                    5     0    100% 25-Nov-24 A     29-Nov-24 A                                     Thanksgiving Break 2024
     HOL130              Winter Break 2024-2025                                     11    0    100% 23-Dec-24 A     02-Jan-25 A                                         Winter Break 2024-2025
     HOL140              February Break 2025                                        5     0    100% 17-Feb-25 A     21-Feb-25 A                                             February Break 2025
     HOL150              Spring Break 2025                                          5     0    100% 07-Apr-25 A     11-Apr-25 A                                                  Spring Break 2025
     HOL160              Teacher Last Day 2024-2025                                 1     0    100% 30-May-25 A 30-May-25 A                                                             Teacher Last Day 2024-2025
     HOL170              Teacher First Day 2025-2026                                1     0    100% 28-Jul-25 A     28-Jul-25 A                                                                Teacher First Day 2025-2026
     HOL180              Fall Break 2025                                            5     0    100% 13-Oct-25 A     17-Oct-25 A                                                                       Fall Break 2025
     HOL190              Thanksgiving Break 2025                                    5     0    100% 24-Nov-25 A     28-Nov-25 A                                                                           Thanksgiving Break 2025
     HOL200              Winter Break 2025-2026                                    12     3     75% 22-Dec-25 A     02-Jan-26                                                                                 Winter Break 2025-2026
     HOL210              February Break 2026                                        5     5      0% 16-Feb-26*      20-Feb-26                                                                                      February Break 2026
     HOL220              Spring Break 2026                                          5     5      0% 06-Apr-26*      10-Apr-26                                                                                           Spring Break 2026
     HOL230              Teacher Last Day 2025-2026                                 1     1      0% 29-May-26*      29-May-26                                                                                                Teacher Last Day 2025-2026
     HOL240              Teacher First Day 2026-2027                                1     1      0% 27-Jul-26*      27-Jul-26                                                                                                       Teacher First Day 2026-2027
     HOL250              Teacher Last Day 2026-2027 (Estimated)                     1     1      0% 28-May-27       28-May-27*                                                                                                                                      Teacher Last Day 2026-2027 (Estimated)
     HOL260              Teacher First Day 2027-2028 (Estimated)                    1     1      0% 26-Jul-27*      26-Jul-27                                                                                                                                              Teacher First Day 2027-2028 (Estimated)

    Procurement                                                                    534   83           28-Feb-24 A   19-Jun-26                                                                                                    Procurement


              Remaining Level of Effort              Milestone                                                                                                                                                                                                                    Page 1 of 11
              Actual Level of Effort
              Remaining Work
                                                     Summary                   Champion MS Update 32 2025-12-30                                                                                                                                                          Data Date: 31-Dec-25
                                                                                                                                                                                                                                                                         Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                        Full Schedule



                                                                                                                                    Page 20 of 33
Activity ID              Activity Name                                                      OD    RD      % Start          Finish                    2024                                      2025                                   2026                               2027                   2028
                                                                                                                                         J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
     Initial Contract                                                                       320    0         28-Feb-24 A   17-Sep-25 A                                                                       Initial Contract

      Electrical                                                                            281    0         12-Jun-24 A   29-May-25 A                                                          Electrical
       PROC2000          Prep Electrical Submittals                                         20     0   100% 12-Jun-24 A    01-Jul-24 A                      Prep Electrical Submittals
       PROC2010          BBC Review/Submit Electrical Submittals                             3     0   100% 02-Jul-24 A    02-Jul-24 A                      BBC Review/Submit Electrical Submittals
       PROC2020          Review/Approve Electrical Submittals (includes resubmittals)       10     0   100% 02-Jul-24 A    01-Oct-24 A                               Review/Approve Electrical Submittals (includes resubmittals)
       PROC2040          Fab/Del 4000A Switchgear and Remaining Panel Boards                178    0   100% 13-Sep-24 A    29-May-25 A                                                          Fab/Del 4000A Switchgear and Remaining Panel Boards
       PROC2030          Fab/Del Initial Panelboards (25 weeks)                             125    0   100% 01-Oct-24 A    03-Feb-25 A                                             Fab/Del Initial Panelboards (25 weeks)
      Mechanical                                                                            294    0         12-Jun-24 A   17-Sep-25 A                                                                       Mechanical
       PROC1000          Prep Mechanical Submittals                                         10     0   100% 12-Jun-24 A    18-Jun-24 A                     Prep Mechanical Submittals
       PROC1010          BBC Review/Submit Mechanical Submittals                             3     0   100% 01-Jul-24 A    03-Jul-24 A                      BBC Review/Submit Mechanical Submittals
       PROC1020          Review/Approve Mechanical Submittals                               10     0   100% 03-Jul-24 A    22-Jul-24 A                        Review/Approve Mechanical Submittals
       PROC1100          Design Revisions/New Submittal (DOAS)                              58     0   100% 23-Jul-24 A    23-Oct-24 A                                  Design Revisions/New Submittal (DOAS)
       PROC1030          Fab/Del Above Ceiling Mechanical Equipment (8 weeks)               40     0   100% 23-Jul-24 A    15-Nov-24 A                                      Fab/Del Above Ceiling Mechanical Equipment (8 weeks)
       PROC1070          Fab/Del RTU (18 weeks) (to subcontractor storage)                  90     0   100% 04-Sep-24 A    09-Jan-25 A                                           Fab/Del RTU (18 weeks) (to subcontractor storage)
       PROC1110          Review/Approve DOAS Resubmittal                                    10     0   100% 10-Dec-24 A    13-Jan-25 A                                           Review/Approve DOAS Resubmittal
       PROC1080          Fab/Del HRU (16 weeks, to Subcontractor Warehouse))                121    0   100% 10-Dec-24 A    30-May-25 A                                                          Fab/Del HRU (16 weeks, to Subcontractor Warehouse))
       PROC1090          Fab/Del DOAS (20 weeks)                                            118    0   100% 14-Jan-25 A    17-Sep-25 A                                                                       Fab/Del DOAS (20 weeks)
       PROC1050          Fab/Del Heat Exchangers (8 weeks)                                  40     0   100% 27-Jan-25 A    14-Mar-25 A                                                   Fab/Del Heat Exchangers (8 weeks)
       PROC1060          Fab/Del Cooling Towers (10 weeks)                                  82     0   100% 13-Feb-25 A    22-May-25 A                                                         Fab/Del Cooling Towers (10 weeks)
      Temporary Facilities                                                                  90     0         28-Feb-24 A   24-Oct-24 A                                  Temporary Facilities
       TEMP100           GA Power Coordination                                              60     0   100% 28-Feb-24 A    09-May-24 A              GA Power Coordination
       TEMP130           Fab/Del Transformer                                                30     0   100% 09-May-24 A 24-Oct-24 A                                     Fab/Del Transformer
       TEMP110           Permit Drawing Design/Prep                                         20     0   100% 03-Jun-24 A    14-Jun-24 A                     Permit Drawing Design/Prep
       TEMP120           BB Review/Submit for Approval                                       3     0   100% 14-Jun-24 A    17-Jun-24 A                     BB Review/Submit for Approval
       TEMP140           Permitting                                                         30     0   100% 11-Jul-24 A    05-Aug-24 A                         Permitting
       TEMP150           Contract Execution for Mobile Classrooms                           10     0   100% 16-Aug-24 A    22-Aug-24 A                           Contract Execution for Mobile Classrooms
     Added Phase 2 Items                                                                    83    83         24-Feb-26     19-Jun-26                                                                                                      Added Phase 2 Items

      Millwork                                                                              83    83         24-Feb-26     19-Jun-26                                                                                                      Millwork
       PROC2050          Prep Millwork Submittals                                           20    20     0% 24-Feb-26      23-Mar-26                                                                                             Prep Millwork Submittals
       PROC2060          BBC Review/Submit Millwork Submittals                               3     3     0% 24-Mar-26      26-Mar-26                                                                                             BBC Review/Submit Millwork Submittals
       PROC2070          Review/Approve Millwork Submittals                                 10    10     0% 27-Mar-26      09-Apr-26                                                                                               Review/Approve Millwork Submittals
       PROC2080          Fab/Del Millwork (10 Weeks)                                        50    50     0% 10-Apr-26      19-Jun-26                                                                                                      Fab/Del Millwork (10 Weeks)
      Kitchen Equipment                                                                     83    83         24-Feb-26     19-Jun-26                                                                                                      Kitchen Equipment
       PROC2090          Prep Kitchen Equipment Submittals                                  10    10     0% 24-Feb-26      09-Mar-26                                                                                            Prep Kitchen Equipment Submittals
       PROC2100          BBC Review/Submit Kitchen Equipment Submittals                      3     3     0% 10-Mar-26      12-Mar-26                                                                                            BBC Review/Submit Kitchen Equipment Submittals
       PROC2110          Review/Approve Kitchen Equipment Submittals                        10    10     0% 13-Mar-26      26-Mar-26                                                                                             Review/Approve Kitchen Equipment Submittals
       PROC2120          Fab/Del Kitchen Equipment (12 Weeks)                               60    60     0% 27-Mar-26      19-Jun-26                                                                                                      Fab/Del Kitchen Equipment (12 Weeks)
      Doors/Frames/Hardware                                                                 73    73         24-Feb-26     05-Jun-26                                                                                                    Doors/Frames/Hardware
       PROC2130          Prep Doors/Frames/Hardware Submittals                              10    10     0% 24-Feb-26      09-Mar-26                                                                                            Prep Doors/Frames/Hardware Submittals
       PROC2140          BBC Review/Submit Doors/Frames/Hardware Submittals                  3     3     0% 10-Mar-26      12-Mar-26                                                                                            BBC Review/Submit Doors/Frames/Hardware Submittals
       PROC2150          Review/Approve Doors/Frames/Hardware Submittals                    10    10     0% 13-Mar-26      26-Mar-26                                                                                             Review/Approve Doors/Frames/Hardware Submittals
       PROC2170          Fab/Del Door Frames (6 Weeks)                                      30    30     0% 27-Mar-26      07-May-26                                                                                                 Fab/Del Door Frames (6 Weeks)
       PROC2160          Fab/Del Doors/Hardware (10 Weeks)                                  50    50     0% 27-Mar-26      05-Jun-26                                                                                                    Fab/Del Doors/Hardware (10 Weeks)
      Storefront/Ballistic Film                                                             73    73         24-Feb-26     05-Jun-26                                                                                                    Storefront/Ballistic Film


              Remaining Level of Effort               Milestone                                                                                                                                                                                                                           Page 2 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary                           Champion MS Update 32 2025-12-30                                                                                                                                                         Data Date: 31-Dec-25
                                                                                                                                                                                                                                                                                 Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                                 Full Schedule



                                                                                                                                           Page 21 of 33
Activity ID              Activity Name                                                OD    RD       % Start          Finish                    2024                                 2025                                   2026                                  2027                      2028
                                                                                                                                    J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       PROC2180          Prep Storefront/Ballistic Film Submittals                    10    10      0% 24-Feb-26      09-Mar-26                                                                                      Prep Storefront/Ballistic Film Submittals
       PROC2190          BBC Review/Submit Storefront/Ballistic Film Submittals        3     3      0% 10-Mar-26      12-Mar-26                                                                                      BBC Review/Submit Storefront/Ballistic Film Submittals
       PROC2200          Review/Approve Storefront/Ballistic Film Submittals          10    10      0% 13-Mar-26      26-Mar-26                                                                                       Review/Approve Storefront/Ballistic Film Submittals
       PROC2210          Fab/Del Storefront/Ballistic Film (10 Weeks)                 50    50      0% 27-Mar-26      05-Jun-26                                                                                               Fab/Del Storefront/Ballistic Film (10 Weeks)
      Window Frames/Glass                                                             73    73          24-Feb-26     05-Jun-26                                                                                               Window Frames/Glass
       PROC2220          Prep Window Frames/Glass Submittals                          10    10      0% 24-Feb-26      09-Mar-26                                                                                      Prep Window Frames/Glass Submittals
       PROC2230          BBC Review/Submit Window Frames/Glass Submittals              3     3      0% 10-Mar-26      12-Mar-26                                                                                      BBC Review/Submit Window Frames/Glass Submittals
       PROC2240          Review/Approve Window Frames/Glass Submittals                10    10      0% 13-Mar-26      26-Mar-26                                                                                       Review/Approve Window Frames/Glass Submittals
       PROC2250          Fab/Del Window Frames/Glass (10 Weeks)                       50    50      0% 27-Mar-26      05-Jun-26                                                                                               Fab/Del Window Frames/Glass (10 Weeks)

    Issues                                                                            14     0          16-Oct-24 A   13-Nov-24 A                             Issues

     Additional Admin Trailer                                                         14     0          16-Oct-24 A   13-Nov-24 A                             Additional Admin Trailer
      AAT1010            Foundation Install                                            2     0    100% 16-Oct-24 A    17-Oct-24 A                           Foundation Install
      AAT1000            Permit Approved                                               1     0    100% 16-Oct-24 A    29-Oct-24 A                            Permit Approved
      AAT1020            Set and Connect Trailer                                       2     0    100% 17-Oct-24 A    18-Oct-24 A                           Set and Connect Trailer
      AAT1030            Trailer Trim Out                                              5     0    100% 21-Oct-24 A    13-Nov-24 A                             Trailer Trim Out

    Construction                                                                      704   398         29-Aug-24 A   30-Jul-27                                                                                                                                              Construction

     Temporary Facilities                                                             420   10          29-Aug-24 A   12-Jun-26                                                                                                Temporary Facilities
      TF100              Mobilize                                                      3     0    100% 29-Aug-24 A    29-Aug-24 A                      Mobilize
      TF110              Install Foundations                                          10     0    100% 29-Aug-24 A    05-Sep-24 A                      Install Foundations
      TF120              Install Modular Trailers                                     10     0    100% 04-Sep-24 A    12-Sep-24 A                       Install Modular Trailers
      TF160              Power Connection to Modular Trailers                         10     0    100% 18-Sep-24 A    01-Nov-24 A                            Power Connection to Modular Trailers
      TF130              Install Fire Protection in Modular Trailers                  10     0    100% 19-Sep-24 A    30-Oct-24 A                            Install Fire Protection in Modular Trailers
      TF140              Install Low Voltage Tie-In from School                       10     0    100% 14-Oct-24 A    08-Nov-24 A                             Install Low Voltage Tie-In from School
      TF150              GA Power Transformer Installation                             5     0    100% 21-Oct-24 A    05-Nov-24 A                             GA Power Transformer Installation
      TF190              80% Ceiling Cover Up Inspection                               2     0    100% 01-Nov-24 A    15-Nov-24 A                                 80% Ceiling Cover Up Inspection
      TF920              ADA Access Install                                            3     0    100% 07-Nov-24 A    07-Nov-24 A                             ADA Access Install
      TF170              Final Inspection                                              2     0    100% 22-Nov-24 A    25-Nov-24 A                                 Final Inspection
      TF180              Move into Modular Trailers                                    3     0    100% 22-Nov-24 A    27-Nov-24 A                                  Move into Modular Trailers
      TF900              Move From Temporary Trailers to Renovated Areas               5     5      0% 01-Jun-26      05-Jun-26                                                                                               Move From Temporary Trailers to Renovated Areas
      TF910              Demobilize Temporary Trailers                                 5     5      0% 08-Jun-26      12-Jun-26                                                                                                Demobilize Temporary Trailers
     School Year 2024/2025                                                            150    0          04-Dec-24 A   24-Jul-25 A                                                            School Year 2024/2025

      Level 2 Classrooms                                                              126    0          04-Dec-24 A   11-Jul-25 A                                                           Level 2 Classrooms
       B1010             Install Protection and Selective Demo                        10     0    100% 04-Dec-24 A    15-Jan-25 A                                      Install Protection and Selective Demo
       B1000             Abatement (Phase 1)                                           7     0    100% 10-Dec-24 A    18-Dec-24 A                                    Abatement (Phase 1)
       B1020             MEP Overhead Rough                                           30     0    100% 13-Jan-25 A    24-Mar-25 A                                              MEP Overhead Rough
       B1040             Set/Connect Above Ceiling Mechanical Equipment               15     0    100% 28-Jan-25 A    25-Mar-25 A                                              Set/Connect Above Ceiling Mechanical Equipment
       B1210             Patch Above Ceilings/Stencil Walls                            8     0    100% 24-Feb-25 A    11-Mar-25 A                                            Patch Above Ceilings/Stencil Walls
       B1160             Set/Connect Initial Panelboards                              10     0    100% 03-Mar-25 A    17-Mar-25 A                                             Set/Connect Initial Panelboards
       B1060             Frame Hard Ceilings                                           5     0    100% 10-Mar-25 A    17-Mar-25 A                                             Frame Hard Ceilings
       B1070             Install Ceiling Grid                                          7     0    100% 10-Mar-25 A    09-Apr-25 A                                                Install Ceiling Grid
       B1100             MEP Drops into Grid                                          15     0    100% 12-Mar-25 A    14-Apr-25 A                                                MEP Drops into Grid
       B1080             MEP Drops into Hard Ceilings                                  3     0    100% 18-Mar-25 A    20-Mar-25 A                                             MEP Drops into Hard Ceilings
       B1090             MEP Cover-up Inspections - Hard Ceilings                      2     0    100% 21-Mar-25 A    21-Mar-25 A                                             MEP Cover-up Inspections - Hard Ceilings
       B1120             Hang/Tape/Finish Drywall - Hard Ceilings                      7     0    100% 25-Mar-25 A    08-Apr-25 A                                                Hang/Tape/Finish Drywall - Hard Ceilings

              Remaining Level of Effort               Milestone                                                                                                                                                                                                                 Page 3 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary                     Champion MS Update 32 2025-12-30                                                                                                                                                     Data Date: 31-Dec-25
                                                                                                                                                                                                                                                                       Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                           Full Schedule



                                                                                                                                      Page 22 of 33
Activity ID              Activity Name                                                OD    RD      % Start          Finish                    2024                    2025                                          2026            2027              2028
                                                                                                                                   J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       B1030             Wall Prep for Paint                                          10     0   100% 31-Mar-25 A    16-Apr-25 A                                   Wall Prep for Paint
       B1150             MEP Trim-out                                                  8     0   100% 02-Apr-25 A    30-Apr-25 A                                     MEP Trim-out
       B1130             Prime/1st Coat Paint - Hard Ceilings                          5     0   100% 03-Apr-25 A    16-Apr-25 A                                   Prime/1st Coat Paint - Hard Ceilings
       B1050             Prime/1st Coat Paint - Walls                                 10     0   100% 16-Apr-25 A    25-Apr-25 A                                     Prime/1st Coat Paint - Walls
       B1220             Fire Alarm Installation/Panel Programming                     5     0   100% 12-May-25 A 13-Jun-25 A                                             Fire Alarm Installation/Panel Programming
       B1180             Final Coat Paint - Walls                                      5     0   100% 12-May-25 A 11-Jul-25 A                                                   Final Coat Paint - Walls
       B1230             Fire Alarm Panel Back Box Procurement                        10     0   100% 30-May-25 A 12-Jun-25 A                                             Fire Alarm Panel Back Box Procurement
       B1110             MEP Cover-up Inspections - Grid Ceilings                      2     0   100% 17-Jun-25 A    17-Jun-25 A                                           MEP Cover-up Inspections - Grid Ceilings
      Roof                                                                            112    0         17-Feb-25 A   24-Jul-25 A                                                 Roof
       B2020             Set Roof Curbs                                                5     0   100% 17-Feb-25 A    24-Feb-25 A                               Set Roof Curbs
       B2040             Cut Deck                                                      5     0   100% 18-Feb-25 A    25-Feb-25 A                               Cut Deck
       B2030             Install Steel                                                 5     0   100% 04-Mar-25 A    14-Mar-25 A                                Install Steel
       B2010             Set/Connect Mechanical Equipment - RTUs                      10     0   100% 07-Apr-25 A    11-Apr-25 A                                   Set/Connect Mechanical Equipment - RTUs
       B3080             Set/Connect Mechanical Equipment - HRUs                      10     0   100% 16-Jun-25 A    27-Jun-25 A                                            Set/Connect Mechanical Equipment - HRUs
       B2000             MEP Rough-in (Gas Piping)                                     7     0   100% 09-Jul-25 A    24-Jul-25 A                                                 MEP Rough-in (Gas Piping)
     Summer 2025                                                                      165    2         03-May-25 A 05-Jan-26                                                                           Summer 2025

      Mechanical/Electrical Rooms                                                     165    2         03-May-25 A 05-Jan-26                                                                           Mechanical/Electrical Rooms
       A4040             Safeoff                                                       1     0   100% 03-May-25 A 03-May-25 A                                        Safeoff
       A4020             Abatement                                                     7     0   100% 05-May-25 A 13-May-25 A                                          Abatement
       A4090             Saw Cut/Demo Slab                                             2     0   100% 07-May-25 A 09-May-25 A                                         Saw Cut/Demo Slab
       A4050             Demo Existing Boilers                                         3     0   100% 13-May-25 A 14-May-25 A                                          Demo Existing Boilers
       A4110             Repour Footing in Slab and Pads                               2     0   100% 19-May-25 A 21-May-25 A                                           Repour Footing in Slab and Pads
       A4080             Install New Masonry Walls                                     3     0   100% 22-May-25 A 23-May-25 A                                           Install New Masonry Walls
       A4120             Electrical Room Build Out                                    10     0   100% 27-May-25 A 13-Jun-25 A                                             Electrical Room Build Out
       A4200             Safeoff/Demo Existing Switch Gear                             3     0   100% 02-Jun-25 A    02-Jun-25 A                                          Safeoff/Demo Existing Switch Gear
       A4130             Demo Existing Cooling Tower/Chillers/Associated Piping        5     0   100% 02-Jun-25 A    05-Jun-25 A                                          Demo Existing Cooling Tower/Chillers/Associated Piping
       A4210             Planned Power Outage                                          6     0   100% 02-Jun-25 A    09-Jun-25 A                                          Planned Power Outage
       A4100             Mechanical Rough Piping                                      18     0   100% 02-Jun-25 A    27-Jun-25 A                                            Mechanical Rough Piping
       A4230             Set/Connect New Switch Gear                                   7     0   100% 03-Jun-25 A    13-Jun-25 A                                          Set/Connect New Switch Gear
       A4060             Set New Boilers                                               2     0   100% 05-Jun-25 A    06-Jun-25 A                                          Set New Boilers
       A4190             Connect New Boilers                                           3     0   100% 09-Jun-25 A    11-Jun-25 A                                          Connect New Boilers
       A4310             Demo/Install Steel Supports for Cooling Tower                 3     0   100% 10-Jun-25 A    10-Jun-25 A                                          Demo/Install Steel Supports for Cooling Tower
       A4170             MEP UG Rough                                                  5     0   100% 11-Jun-25 A    16-Jun-25 A                                           MEP UG Rough
       A4160             Install New Cooling Tower                                     2     0   100% 16-Jun-25 A    16-Jun-25 A                                           Install New Cooling Tower
       A4030             Connect New Cooling Tower                                     5     0   100% 16-Jun-25 A    27-Jun-25 A                                            Connect New Cooling Tower
       A4240             Build Out Fire Riser                                          5     0   100% 09-Jul-25 A    22-Jul-25 A                                                 Build Out Fire Riser
       A4180             Install Temp DOAS                                             5     0   100% 15-Jul-25 A    18-Jul-25 A                                                Install Temp DOAS
       A4140             Install DOAS                                                  5     0   100% 13-Oct-25 A    17-Oct-25 A                                                           Install DOAS
       A4070             Boiler Inspection                                             2     2     0% 02-Jan-26*     05-Jan-26                                                                         Boiler Inspection
      Level 2 Classrooms                                                              43     0         19-May-25 A 11-Aug-25 A                                                     Level 2 Classrooms
       B1190             BBC Punch and Clean                                           5     0   100% 27-Jun-25 A    21-Jul-25 A                                                 BBC Punch and Clean
       B1140             Install Ceiling Tile                                          5     0   100% 12-Jul-25 A    17-Jul-25 A                                                Install Ceiling Tile
       B1200             Owner Punch                                                   5     0   100% 22-Jul-25 A    11-Aug-25 A                                                   Owner Punch
       Added Scope                                                                    40     0         19-May-25 A 15-Jul-25 A                                                  Added Scope
        ADD1000          Flooring Demo/Install (Areas 1, 2A, & 3)                     20     0   100% 19-May-25 A 12-Jul-25 A                                                   Flooring Demo/Install (Areas 1, 2A, & 3)

              Remaining Level of Effort              Milestone                                                                                                                                                                                   Page 4 of 11
              Actual Level of Effort
              Remaining Work
                                                     Summary                      Champion MS Update 32 2025-12-30                                                                                                                      Data Date: 31-Dec-25
                                                                                                                                                                                                                                        Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                           Full Schedule



                                                                                                                                     Page 23 of 33
Activity ID              Activity Name                                               OD   RD      % Start         Finish                    2024                 2025                                    2026                    2027              2028
                                                                                                                                J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
        ADD1010          Marker/Tack Boards Install                                   5    0   100% 09-Jul-25 A   14-Jul-25 A                                           Marker/Tack Boards Install
        ADD1020          Teacher Cabinet Install                                      5    0   100% 11-Jul-25 A   15-Jul-25 A                                           Teacher Cabinet Install
      Gym (Level 3)                                                                  40    0         30-May-25 A 11-Aug-25 A                                               Gym (Level 3)
       A1010             Move Out/Install Protection/Selective Demo                   6    0   100% 30-May-25 A 01-Jun-25 A                                       Move Out/Install Protection/Selective Demo
       A1000             Abatement (Phase 2)                                          5    0   100% 09-Jun-25 A   17-Jun-25 A                                      Abatement (Phase 2)
       A1020             MEP Overhead Rough                                          15    0   100% 09-Jun-25 A   11-Jul-25 A                                           MEP Overhead Rough
       A1050             Wall Prep & Prime Paint - Walls and Frames                   6    0   100% 25-Jun-25 A   11-Jul-25 A                                           Wall Prep & Prime Paint - Walls and Frames
       A1220             Wall Prep and Above Ceiling Patch & Rate                     5    0   100% 26-Jun-25 A   10-Jul-25 A                                           Wall Prep and Above Ceiling Patch & Rate
       A1210             Rebuild Masonry Chase Walls                                  3    0   100% 27-Jun-25 A   01-Jul-25 A                                        Rebuild Masonry Chase Walls
       A1030             Frame Hard Ceilings                                          4    0   100% 30-Jun-25 A   01-Jul-25 A                                        Frame Hard Ceilings
       A1110             Install Ceiling Grid                                         4    0   100% 30-Jun-25 A   11-Jul-25 A                                           Install Ceiling Grid
       A1060             MEP Drops into Hard Ceiling                                  3    0   100% 30-Jun-25 A   18-Jul-25 A                                            MEP Drops into Hard Ceiling
       A1090             Prime/1st Coat Paint - Walls                                 5    0   100% 07-Jul-25 A   10-Jul-25 A                                           Prime/1st Coat Paint - Walls
       A1180             MEP Trim-out                                                 3    0   100% 07-Jul-25 A   23-Jul-25 A                                            MEP Trim-out
       A1070             MEP Cover-up Inspections - Hard Ceilings                     1    0   100% 08-Jul-25 A   08-Jul-25 A                                           MEP Cover-up Inspections - Hard Ceilings
       A1130             Hang/Tape/Finish Drywall - Hard Ceilings                     5    0   100% 08-Jul-25 A   15-Jul-25 A                                           Hang/Tape/Finish Drywall - Hard Ceilings
       A1100             MEP Drops into Grid                                          5    0   100% 09-Jul-25 A   18-Jul-25 A                                            MEP Drops into Grid
       A1120             MEP Cover-up Inspections - Grid Ceilings                     2    0   100% 11-Jul-25 A   11-Jul-25 A                                           MEP Cover-up Inspections - Grid Ceilings
       A1040             Dryfall Paint - Exposed Structure and Perimeter Walls        5    0   100% 11-Jul-25 A   17-Jul-25 A                                            Dryfall Paint - Exposed Structure and Perimeter Walls
       A1190             BBC Punch and Clean                                          7    0   100% 17-Jul-25 A   25-Jul-25 A                                            BBC Punch and Clean
       A1140             Prime/1st Coat Paint - Hard Ceilings                         3    0   100% 18-Jul-25 A   22-Jul-25 A                                            Prime/1st Coat Paint - Hard Ceilings
       A1150             Install Ceiling Tile                                         5    0   100% 22-Jul-25 A   28-Jul-25 A                                             Install Ceiling Tile
       A1170             Final Coat Paint - Walls and Ceilings                        3    0   100% 23-Jul-25 A   25-Jul-25 A                                            Final Coat Paint - Walls and Ceilings
       A1200             Owner Punch                                                  6    0   100% 28-Jul-25 A   11-Aug-25 A                                              Owner Punch
      Gym Basement (Level 2)                                                         40    0         30-May-25 A 11-Aug-25 A                                               Gym Basement (Level 2)
       A2010             Move Out/Install Protection/Selective Demo                   6    0   100% 30-May-25 A 01-Jun-25 A                                       Move Out/Install Protection/Selective Demo
       A2020             MEP Overhead Rough                                          15    0   100% 04-Jun-25 A   25-Jun-25 A                                       MEP Overhead Rough
       A2200             Conduit Raceways for Emergency Panels                       10    0   100% 04-Jun-25 A   30-Jun-25 A                                        Conduit Raceways for Emergency Panels
       A2000             Abatement                                                    5    0   100% 09-Jun-25 A   17-Jun-25 A                                      Abatement
       A2080             Set/Connect Above Ceiling Mechanical Equipment               3    0   100% 13-Jun-25 A   16-Jun-25 A                                      Set/Connect Above Ceiling Mechanical Equipment
       A2030             Wall Prep and Above Ceiling Patch & Rate                     5    0   100% 16-Jun-25 A   24-Jun-25 A                                       Wall Prep and Above Ceiling Patch & Rate
       A2150             Install Plumbing Fixtures                                    3    0   100% 24-Jun-25 A   25-Jun-25 A                                       Install Plumbing Fixtures
       A4150             Rebuild Masonry Chase Walls                                  3    0   100% 24-Jun-25 A   26-Jun-25 A                                       Rebuild Masonry Chase Walls
       A2210             Prep and Prime Walls/Frames                                  6    0   100% 24-Jun-25 A   03-Jul-25 A                                        Prep and Prime Walls/Frames
       A2050             Frame Hard Ceilings                                          4    0   100% 25-Jun-25 A   28-Jun-25 A                                       Frame Hard Ceilings
       A2100             Install Ceiling Grid                                         4    0   100% 26-Jun-25 A   30-Jun-25 A                                        Install Ceiling Grid
       A2040             MEP Drops into Hard Ceilings                                 3    0   100% 27-Jun-25 A   02-Jul-25 A                                        MEP Drops into Hard Ceilings
       A2090             MEP Drops into Grid                                          4    0   100% 01-Jul-25 A   06-Jul-25 A                                           MEP Drops into Grid
       A2060             MEP Cover-Up Inspections - Hard Ceilings                     2    0   100% 07-Jul-25 A   07-Jul-25 A                                           MEP Cover-Up Inspections - Hard Ceilings
       A2120             Hang/Tape/Finish Drywall - Hard Ceilings                     4    0   100% 08-Jul-25 A   15-Jul-25 A                                           Hang/Tape/Finish Drywall - Hard Ceilings
       A2130             Install Ceiling Tile                                         5    0   100% 10-Jul-25 A   14-Jul-25 A                                           Install Ceiling Tile
       A2110             MEP Cover-up Inspections - Grid Ceilings                     2    0   100% 11-Jul-25 A   11-Jul-25 A                                           MEP Cover-up Inspections - Grid Ceilings
       A2070             1st/2nd Coat Paint - Walls & Ceilings                        3    0   100% 15-Jul-25 A   17-Jul-25 A                                            1st/2nd Coat Paint - Walls & Ceilings
       A2170             MEP Trim-out                                                 4    0   100% 15-Jul-25 A   21-Jul-25 A                                            MEP Trim-out
       A2180             BBC Punch and Clean                                          5    0   100% 17-Jul-25 A   23-Jul-25 A                                            BBC Punch and Clean


              Remaining Level of Effort               Milestone                                                                                                                                                                              Page 5 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary                    Champion MS Update 32 2025-12-30                                                                                                                   Data Date: 31-Dec-25
                                                                                                                                                                                                                                    Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                          Full Schedule



                                                                                                                                  Page 24 of 33
Activity ID              Activity Name                                        OD    RD       % Start          Finish                    2024                 2025                                        2026                           2027              2028
                                                                                                                            J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       A2160             Final Coat Paint - Walls & Ceilings                   2     0    100% 18-Jul-25 A    21-Jul-25 A                                            Final Coat Paint - Walls & Ceilings
       A2190             Owner Punch                                           6     0    100% 23-Jul-25 A    11-Aug-25 A                                               Owner Punch
       Added Scope                                                             5     0          10-Jul-25 A   25-Jul-25 A                                             Added Scope
        ADD1050          Marker/Tack Board Install                             2     0    100% 10-Jul-25 A    10-Jul-25 A                                           Marker/Tack Board Install
        ADD1030          Flooring Install (Area 2B)                            5     0    100% 15-Jul-25 A    23-Jul-25 A                                             Flooring Install (Area 2B)
        ADD1080          Furniture Move In                                     2     0    100% 23-Jul-25 A    25-Jul-25 A                                             Furniture Move In
      Gym Main Entrance                                                       42     0          30-May-25 A 11-Aug-25 A                                                 Gym Main Entrance
       A3010             Move Out/Install Protection/Selective Demo            6     0    100% 30-May-25 A 01-Jun-25 A                                        Move Out/Install Protection/Selective Demo
       A3000             Abatement                                             5     0    100% 09-Jun-25 A    17-Jun-25 A                                       Abatement
       A3020             MEP Overhead Rough                                   15     0    100% 09-Jun-25 A    28-Jun-25 A                                        MEP Overhead Rough
       A3030             Wall Prep for Paint                                   6     0    100% 26-Jun-25 A    30-Jun-25 A                                         Wall Prep for Paint
       A3070             Frame Hard Ceilings                                   4     0    100% 26-Jun-25 A    01-Jul-25 A                                         Frame Hard Ceilings
       A3040             Prime/1st Coat Paint - Walls                          5     0    100% 30-Jun-25 A    01-Jul-25 A                                         Prime/1st Coat Paint - Walls
       A3100             MEP Drops into Hard Ceilings                          2     0    100% 30-Jun-25 A    06-Jul-25 A                                           MEP Drops into Hard Ceilings
       A3190             1st/2nd Coat Paint - Walls & Ceilings                 3     0    100% 01-Jul-25 A    03-Jul-25 A                                         1st/2nd Coat Paint - Walls & Ceilings
       A3090             Install Ceiling Grid                                  4     0    100% 01-Jul-25 A    06-Jul-25 A                                           Install Ceiling Grid
       A3120             MEP Cover-up Inspections - Hard Ceilings              2     0    100% 07-Jul-25 A    07-Jul-25 A                                           MEP Cover-up Inspections - Hard Ceilings
       A3080             MEP Drops into Grid                                   3     0    100% 07-Jul-25 A    10-Jul-25 A                                           MEP Drops into Grid
       A3110             MEP Cover-up Inspections - Grid Ceilings              2     0    100% 11-Jul-25 A    11-Jul-25 A                                           MEP Cover-up Inspections - Grid Ceilings
       A3140             Hang/Tape/Finish Drywall - Hard Ceilings              4     0    100% 14-Jul-25 A    16-Jul-25 A                                            Hang/Tape/Finish Drywall - Hard Ceilings
       A3130             Install Ceiling Tile                                  5     0    100% 15-Jul-25 A    16-Jul-25 A                                            Install Ceiling Tile
       A3160             MEP Trim-out                                          3     0    100% 15-Jul-25 A    18-Jul-25 A                                            MEP Trim-out
       A3170             BBC Punch and Clean                                   5     0    100% 17-Jul-25 A    23-Jul-25 A                                             BBC Punch and Clean
       A3150             Final Coat Paint - Walls and Ceilings                 2     0    100% 18-Jul-25 A    21-Jul-25 A                                            Final Coat Paint - Walls and Ceilings
       A3180             Owner Punch/Acceptance                                6     0    100% 28-Jul-25 A    11-Aug-25 A                                               Owner Punch/Acceptance
       Added Scope                                                             5     0          18-Jul-25 A   25-Jul-25 A                                             Added Scope
        ADD1040          Install Flooring (Gym Main Entrance)                  2     0    100% 18-Jul-25 A    23-Jul-25 A                                            Install Flooring (Gym Main Entrance)
        ADD1070          Furniture Move In                                     2     0    100% 23-Jul-25 A    25-Jul-25 A                                             Furniture Move In
      Exterior                                                                 5     0          12-May-25 A 16-May-25 A                                      Exterior
       C3000             MEP Rough-in (Gas Piping)                             5     0    100% 12-May-25 A 16-May-25 A                                       MEP Rough-in (Gas Piping)
     School Year 2025/2026                                                    263   148         16-Jul-25 A   31-Jul-26                                                                                         School Year 2025/2026

      Level 1 Classrooms                                                      263   148         16-Jul-25 A   31-Jul-26                                                                                         Level 1 Classrooms
       D1010             Install Protection                                    5     0    100% 16-Jul-25 A    22-Jul-25 A                                            Install Protection
       D1220             Selective Demo                                        5     0    100% 21-Jul-25 A    15-Aug-25 A                                               Selective Demo
       D1000             Abatement (Phase 3)                                   5     0    100% 29-Jul-25 A    05-Aug-25 A                                               Abatement (Phase 3)
       D1230             Electrical Overhead Rough                            25     0    100% 13-Aug-25 A    30-Oct-25 A                                                         Electrical Overhead Rough
       D1030             Set/Connect Above Ceiling Mechanical Equipment       15     0    100% 22-Sep-25 A    30-Oct-25 A                                                         Set/Connect Above Ceiling Mechanical Equipment
       D1020             Mechanical/Plumbing Overhead Rough                   25     0    100% 22-Sep-25 A    14-Nov-25 A                                                          Mechanical/Plumbing Overhead Rough
       D1300             Rated Wall Top Out                                   10     0    100% 29-Oct-25 A    26-Nov-25 A                                                            Rated Wall Top Out
       D1250             Abatement/Air Testing                                 5     0    100% 03-Nov-25 A    07-Nov-25 A                                                          Abatement/Air Testing
       D1240             Demo Slab - Existing Bathrooms                        1     0    100% 17-Nov-25 A    18-Nov-25 A                                                           Demo Slab - Existing Bathrooms
       D1260             UG Plumbing                                           3     0    100% 20-Nov-25 A    24-Nov-25 A                                                            UG Plumbing
       D1270             UG inspections                                        1     0    100% 25-Nov-25 A    25-Nov-25 A                                                            UG inspections
       D1310             Backfill UG Rough                                     1     0    100% 26-Nov-25 A    26-Nov-25 A                                                            Backfill UG Rough
       D1280             Slab Pour Back/Cure Time                              3     0    100% 03-Dec-25 A    05-Dec-25 A                                                             Slab Pour Back/Cure Time

              Remaining Level of Effort               Milestone                                                                                                                                                                                     Page 6 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary             Champion MS Update 32 2025-12-30                                                                                                                                 Data Date: 31-Dec-25
                                                                                                                                                                                                                                           Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                   Full Schedule



                                                                                                                              Page 25 of 33
Activity ID              Activity Name                                  OD    RD       % Start          Finish                    2024                 2025                             2026                               2027              2028
                                                                                                                      J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       D1040             Frame Hard Ceilings                            10     0    100% 08-Dec-25 A    12-Dec-25 A                                                   Frame Hard Ceilings
       D1290             Build Out Masonry Walls                         3     0    100% 08-Dec-25 A    12-Dec-25 A                                                   Build Out Masonry Walls
       D1070             MEP Drops into Hard Ceilings                    5     0    100% 15-Dec-25 A    19-Dec-25 A                                                   MEP Drops into Hard Ceilings
       D1090             Install Ceiling Grid                           10     5     50% 15-Dec-25 A    08-Jan-26                                                       Install Ceiling Grid
       D1120             MEP Drops into Grid                            10     7     30% 22-Dec-25 A    12-Jan-26                                                        MEP Drops into Grid
       D1080             MEP Cover-up Inspections - Hard Ceilings        3     3      0% 02-Jan-26      06-Jan-26                                                       MEP Cover-up Inspections - Hard Ceilings
       D1100             Hang/Tape/Finish Drywall - Hard Ceilings        5     5      0% 07-Jan-26      13-Jan-26                                                        Hang/Tape/Finish Drywall - Hard Ceilings
       D1130             MEP Cover-up Inspections - Grid Ceilings        3     3      0% 13-Jan-26      15-Jan-26                                                        MEP Cover-up Inspections - Grid Ceilings
       D1050             Wall Prep for Paint (As Needed)                 5     5      0% 14-Jan-26      21-Jan-26                                                         Wall Prep for Paint (As Needed)
       D1110             Prime/1st Coat Paint - Hard Ceilings           10    10      0% 14-Jan-26      28-Jan-26                                                         Prime/1st Coat Paint - Hard Ceilings
       D1060             Prime/1st Coat Paint - Walls (As Needed)        5     5      0% 22-Jan-26      28-Jan-26                                                         Prime/1st Coat Paint - Walls (As Needed)
       D1150             Install Ceiling Tile                           10    10      0% 29-Jan-26      11-Feb-26                                                           Install Ceiling Tile
       D1160             MEP Trim-out                                    5     5      0% 12-Feb-26      18-Feb-26                                                           MEP Trim-out
       D1170             Install Plumbing Fixtures                       5     5      0% 19-Feb-26      25-Feb-26                                                            Install Plumbing Fixtures
       D1180             Final Coat Paint - Walls                       10    10      0% 26-Feb-26      11-Mar-26                                                                Final Coat Paint - Walls
       D1190             BBC Punch and Clean                            10    10      0% 12-Mar-26      25-Mar-26                                                                 BBC Punch and Clean
       D1200             Owner Punch/Acceptance                         10    10      0% 26-Mar-26      08-Apr-26                                                                  Owner Punch/Acceptance
       Added Phase 2 Work                                               118   118         16-Feb-26     31-Jul-26                                                                                  Added Phase 2 Work
        P2ADD0030 Abatement                                             10    10      0% 16-Feb-26      27-Feb-26                                                               Abatement
        P2ADD0290 Remove/Replace Exterior Doors                          3     3      0% 02-Mar-26      04-Mar-26                                                               Remove/Replace Exterior Doors
        P2ADD0040 Selective Demo (Includes Slab Cuts)                   10    10      0% 02-Mar-26      13-Mar-26                                                                Selective Demo (Includes Slab Cuts)
        P2ADD0200 UG MEP Rough In                                        8     8      0% 12-Mar-26      23-Mar-26                                                                 UG MEP Rough In
        P2ADD0060 MEP Rough In                                          20    20      0% 16-Mar-26      10-Apr-26                                                                   MEP Rough In
        P2ADD0210 UG MEP Inspections                                     3     3      0% 24-Mar-26      26-Mar-26                                                                 UG MEP Inspections
        P2ADD0220 Slab Pour Back/Cure Time                               5     5      0% 27-Mar-26      02-Apr-26                                                                  Slab Pour Back/Cure Time
        P2ADD0070 MEP Cover Up Inspections                               3     3      0% 13-Apr-26      15-Apr-26                                                                   MEP Cover Up Inspections
        P2ADD0190 Install Door Frames                                    5     5      0% 08-May-26      14-May-26                                                                      Install Door Frames
        P2ADD0080 Prime/1st Coat Paint                                  10    10      0% 15-May-26      29-May-26                                                                        Prime/1st Coat Paint
        P2ADD0100 Install Marker/Tack Boards                             5     5      0% 01-Jun-26      05-Jun-26                                                                         Install Marker/Tack Boards
        P2ADD0050 Remove/Replace Windows                                20    20      0% 08-Jun-26      06-Jul-26                                                                              Remove/Replace Windows
        P2ADD0110 Install Flooring                                      15    15      0% 09-Jun-26      29-Jun-26                                                                              Install Flooring
        P2ADD0120 MEP Trim Out                                           5     5      0% 16-Jun-26      22-Jun-26                                                                           MEP Trim Out
        P2ADD0090 Install Millwork/Cabinets                              5     5      0% 22-Jun-26      26-Jun-26                                                                           Install Millwork/Cabinets
        P2ADD0130 Install Misc. Accessories                              3     3      0% 30-Jun-26      02-Jul-26                                                                              Install Misc. Accessories
        P2ADD0140 Install Doors/Hardware                                 8     8      0% 30-Jun-26      10-Jul-26                                                                               Install Doors/Hardware
        P2ADD0150 Final Paint                                            5     5      0% 13-Jul-26      17-Jul-26                                                                                Final Paint
        P2ADD0160 BBC Punch and Clean                                    5     5      0% 20-Jul-26      24-Jul-26                                                                                  BBC Punch and Clean
        P2ADD0260 Install ACT Tiles                                      5     5      0% 20-Jul-26      24-Jul-26                                                                                  Install ACT Tiles
        P2ADD0170 Owner Punch                                            5     5      0% 27-Jul-26      31-Jul-26                                                                                  Owner Punch
        P2ADD0180 FF&E Install                                           3     3      0% 29-Jul-26      31-Jul-26                                                                                  FF&E Install
     Summer 2026                                                        444   148         15-Oct-24 A   31-Jul-26                                                                                  Summer 2026
      A4320              BIM Scanning                                    5     0    100% 16-Oct-25 A    17-Oct-25 A                                              BIM Scanning
      A4370              BIM Modeling                                   40     1    97.5% 20-Oct-25 A   02-Jan-26                                                       BIM Modeling
      A4330              Coordinate Model                               20    20      0% 05-Jan-26      02-Feb-26                                                          Coordinate Model
      A4340              Shop Drawing Creation/Submission               15    15      0% 03-Feb-26      23-Feb-26                                                            Shop Drawing Creation/Submission


              Remaining Level of Effort              Milestone                                                                                                                                                                         Page 7 of 11
              Actual Level of Effort
              Remaining Work
                                                     Summary        Champion MS Update 32 2025-12-30                                                                                                                          Data Date: 31-Dec-25
                                                                                                                                                                                                                              Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                             Full Schedule



                                                                                                                        Page 26 of 33
Activity ID              Activity Name                                                  OD    RD      % Start          Finish                    2024                          2025              2026                                   2027                  2028
                                                                                                                                     J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
      A4350              Review/Approve Shop Drawings                                   15    15     0% 24-Feb-26      16-Mar-26                                                            Review/Approve Shop Drawings
      A4360              Material Procurement                                           20    20     0% 17-Mar-26      13-Apr-26                                                              Material Procurement
      Sitework Improvements - Fire Line                                                 415   15         15-Oct-24 A   19-Jun-26                                                                    Sitework Improvements - Fire Line
       B3000             Install Erosion Controls                                        5     0   100% 15-Oct-24 A    16-Oct-24 A                      Install Erosion Controls
       B3010             Install Fire Line Extension                                    10     0   100% 16-Oct-24 A    20-Nov-24 A                         Install Fire Line Extension
       B3020             FRP Curb and Gutter/Sidewalk                                    5     0   100% 25-Nov-24 A    26-Nov-24 A                          FRP Curb and Gutter/Sidewalk
       B3030             Asphalt Pavement and Striping                                   5     0   100% 25-Nov-24 A    26-Nov-24 A                          Asphalt Pavement and Striping
       B3050             FRP Concrete Sidewalk                                           5     0   100% 25-Nov-24 A    26-Nov-24 A                          FRP Concrete Sidewalk
       B3040             Replace Fencing around Mechahanical Equipment Enclosures        5     5     0% 01-Jun-26      05-Jun-26                                                                   Replace Fencing around Mechahanical Equipment Enclosures
       B3060             BBC Punch and Clean                                             5     5     0% 08-Jun-26      12-Jun-26                                                                   BBC Punch and Clean
       B3070             Owner Punch/Acceptance                                          5     5     0% 15-Jun-26      19-Jun-26                                                                    Owner Punch/Acceptance
      Kitchen/Cafeteria                                                                 44    44         01-Jun-26     31-Jul-26                                                                           Kitchen/Cafeteria
       C1010             Move Out/Install Protection/Selective Demo                      6     6     0% 01-Jun-26      08-Jun-26                                                                   Move Out/Install Protection/Selective Demo
       C1000             Abatement (Phase 4)                                             5     5     0% 09-Jun-26      15-Jun-26                                                                    Abatement (Phase 4)
       C1030             MEP Overhead Rough                                             12    12     0% 16-Jun-26      01-Jul-26                                                                     MEP Overhead Rough
       C1050             Install Ceiling Grid                                            8     8     0% 24-Jun-26      06-Jul-26                                                                        Install Ceiling Grid
       C1020             Set/Connect Above Ceiling Mechanical Equipment                  5     5     0% 25-Jun-26      01-Jul-26                                                                     Set/Connect Above Ceiling Mechanical Equipment
       C1040             MEP Drops into Grid                                             5     5     0% 29-Jun-26      06-Jul-26                                                                        MEP Drops into Grid
       C1060             Wall Prep for Paint                                             5     5     0% 30-Jun-26      07-Jul-26                                                                        Wall Prep for Paint
       C1070             MEP Cover-up Inspections                                        2     2     0% 07-Jul-26      08-Jul-26                                                                        MEP Cover-up Inspections
       C1090             Install Plumbing Fixtures                                       5     5     0% 07-Jul-26      13-Jul-26                                                                        Install Plumbing Fixtures
       C1110             MEP Trim-out                                                    5     5     0% 07-Jul-26      13-Jul-26                                                                        MEP Trim-out
       C1080             Prime/1st Coat Paint - Walls                                    3     3     0% 08-Jul-26      10-Jul-26                                                                        Prime/1st Coat Paint - Walls
       C1120             Install Ceiling Tile                                            3     3     0% 09-Jul-26      13-Jul-26                                                                        Install Ceiling Tile
       C1150             Install Plumbing Fixtures                                       3     3     0% 09-Jul-26      13-Jul-26                                                                        Install Plumbing Fixtures
       C1100             Final Coat Paint - Walls                                        3     3     0% 15-Jul-26      17-Jul-26                                                                         Final Coat Paint - Walls
       C1130             BBC Punch and Clean                                             5     5     0% 16-Jul-26      22-Jul-26                                                                         BBC Punch and Clean
       C1160             Final/Health Inspections                                        5     5     0% 23-Jul-26      29-Jul-26                                                                          Final/Health Inspections
       C1140             Owner Punch/Acceptance                                          5     5     0% 27-Jul-26      31-Jul-26                                                                           Owner Punch/Acceptance
       Added Phase 2 Work                                                               26    26         16-Jun-26     22-Jul-26                                                                         Added Phase 2 Work
        P2ADD700         Install Door Frames                                             3     3     0% 16-Jun-26      18-Jun-26                                                                    Install Door Frames
        P2ADD730         Remove/Replace Exterior Doors                                   3     3     0% 16-Jun-26      18-Jun-26                                                                    Remove/Replace Exterior Doors
        P2ADD750         Install Flooring - Kitchen                                      8     8     0% 16-Jun-26      25-Jun-26                                                                     Install Flooring - Kitchen
        P2ADD640         Remove/Replace Windows                                         10    10     0% 16-Jun-26      29-Jun-26                                                                     Remove/Replace Windows
        P2ADD650         Install Flooring - Cafeteria                                    8     8     0% 06-Jul-26      15-Jul-26                                                                         Install Flooring - Cafeteria
        P2ADD660         Install Kitchen Equipment                                       5     5     0% 07-Jul-26      13-Jul-26                                                                        Install Kitchen Equipment
        P2ADD720         Install Doors/Hardware                                          2     2     0% 13-Jul-26      14-Jul-26                                                                        Install Doors/Hardware
        P2ADD690         Install Misc. Accessories                                       2     2     0% 14-Jul-26      15-Jul-26                                                                         Install Misc. Accessories
        P2ADD670         Install/Connect UDS system                                      5     5     0% 14-Jul-26      20-Jul-26                                                                         Install/Connect UDS system
        P2ADD680         Install Millwork/Counters                                       5     5     0% 16-Jul-26      22-Jul-26                                                                         Install Millwork/Counters
      Media Center/Admin                                                                44    44         01-Jun-26     31-Jul-26                                                                           Media Center/Admin
       C2010             Move Out/Install Protection/Selective Demo                      6     6     0% 01-Jun-26      08-Jun-26                                                                   Move Out/Install Protection/Selective Demo
       C2000             Abatement                                                       5     5     0% 09-Jun-26      15-Jun-26                                                                    Abatement
       C2030             MEP Overhead/In Wall Rough                                     12    12     0% 16-Jun-26      01-Jul-26                                                                     MEP Overhead/In Wall Rough
       C2020             Set/Connect Above Ceiling Mechanical Equipment                  5     5     0% 25-Jun-26      01-Jul-26                                                                     Set/Connect Above Ceiling Mechanical Equipment


              Remaining Level of Effort                 Milestone                                                                                                                                                                                   Page 8 of 11
              Actual Level of Effort
              Remaining Work
                                                        Summary                     Champion MS Update 32 2025-12-30                                                                                                                       Data Date: 31-Dec-25
                                                                                                                                                                                                                                           Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                             Full Schedule



                                                                                                                                       Page 27 of 33
Activity ID              Activity Name                                                OD   RD    % Start        Finish                  2024                 2025                    2026                                   2027                2028
                                                                                                                            J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       C2040             Wall Prep for Paint                                           5    5   0% 30-Jun-26    07-Jul-26                                                                   Wall Prep for Paint
       C2150             MEP Rough In Inspections                                      2    2   0% 02-Jul-26    06-Jul-26                                                                   MEP Rough In Inspections
       C2060             Install Ceiling Grid                                          8    8   0% 07-Jul-26    16-Jul-26                                                                   Install Ceiling Grid
       C2080             Prime/1st Coat Paint - Walls                                  3    3   0% 08-Jul-26    10-Jul-26                                                                   Prime/1st Coat Paint - Walls
       C2050             MEP Drops into Grid                                           5    5   0% 10-Jul-26    16-Jul-26                                                                   MEP Drops into Grid
       C2070             MEP Cover-up Inspections                                      2    2   0% 17-Jul-26    20-Jul-26                                                                    MEP Cover-up Inspections
       C2110             MEP Trim-out                                                  5    5   0% 17-Jul-26    23-Jul-26                                                                    MEP Trim-out
       C2090             Install Plumbing Fixtures                                     3    3   0% 21-Jul-26    23-Jul-26                                                                    Install Plumbing Fixtures
       C2120             Install Ceiling Tile                                          3    3   0% 21-Jul-26    23-Jul-26                                                                    Install Ceiling Tile
       C2130             BBC Punch and Clean                                           5    5   0% 22-Jul-26    28-Jul-26                                                                     BBC Punch and Clean
       C2100             Final Coat Paint - Walls                                      3    3   0% 24-Jul-26    28-Jul-26                                                                     Final Coat Paint - Walls
       C2140             Owner Punch/Acceptance                                        5    5   0% 27-Jul-26    31-Jul-26                                                                     Owner Punch/Acceptance
       Added Phase 2 Work                                                             32   32       16-Jun-26   30-Jul-26                                                                     Added Phase 2 Work
        P2ADD1030 Replace Exterior Doors                                               5    5   0% 16-Jun-26    22-Jun-26                                                               Replace Exterior Doors
        P2ADD1040 Install Door Frames                                                  5    5   0% 16-Jun-26    22-Jun-26                                                               Install Door Frames
        P2ADD1020 Remove/Replace Windows                                              10   10   0% 16-Jun-26    29-Jun-26                                                                Remove/Replace Windows
        P2ADD1090 Install Flooring                                                    10   10   0% 23-Jun-26    07-Jul-26                                                                   Install Flooring
        P2ADD1080 Install Misc. Accessories                                            3    3   0% 08-Jul-26    10-Jul-26                                                                   Install Misc. Accessories
        P2ADD1100 Install Doors/Hardware                                               5    5   0% 08-Jul-26    14-Jul-26                                                                   Install Doors/Hardware
        P2ADD1070 Install Millwork/Cabinets                                            5    5   0% 24-Jul-26    30-Jul-26                                                                     Install Millwork/Cabinets
      Sitework Improvements - ADA Parking                                             34   34       08-Jun-26   24-Jul-26                                                                    Sitework Improvements - ADA Parking
       E1000             Install Erosion Controls                                      8    8   0% 08-Jun-26    17-Jun-26                                                              Install Erosion Controls
       E1010             Seed and Straw as Necessary for Temporary Trailer Area        5    5   0% 15-Jun-26    19-Jun-26                                                              Seed and Straw as Necessary for Temporary Trailer Area
       E1020             FRP Curb and Gutter                                           6    6   0% 18-Jun-26    25-Jun-26                                                               FRP Curb and Gutter
       E1030             Asphalt Pavement and Striping                                 5    5   0% 26-Jun-26    02-Jul-26                                                                Asphalt Pavement and Striping
       E1040             FRP Concrete Sidewalk                                         5    5   0% 06-Jul-26    10-Jul-26                                                                   FRP Concrete Sidewalk
       E1050             BBC Punch and Clean                                           5    5   0% 13-Jul-26    17-Jul-26                                                                    BBC Punch and Clean
       E1060             Owner Punch/Acceptance                                        5    5   0% 20-Jul-26    24-Jul-26                                                                    Owner Punch/Acceptance
      Commissioning                                                                   20   20       08-Jun-26   06-Jul-26                                                                   Commissioning
       E2000             Test and Balance                                             10   10   0% 08-Jun-26    19-Jun-26                                                              Test and Balance
       E2010             Re-Certify Fire Protection System                             5    5   0% 22-Jun-26    26-Jun-26                                                               Re-Certify Fire Protection System
       E2020             Commissioning for MEP Systems                                10   10   0% 22-Jun-26    06-Jul-26                                                                   Commissioning for MEP Systems
      Phase 2 Added Work - Security Vestibule                                         43   43       01-Jun-26   30-Jul-26                                                                     Phase 2 Added Work - Security Vestibule
       P2ADD740          MEP Safeoff                                                   2    2   0% 01-Jun-26    02-Jun-26                                                             MEP Safeoff
       P2ADD810          Install CMU/Exterior Brick                                   10   10   0% 03-Jun-26    16-Jun-26                                                              Install CMU/Exterior Brick
       P2ADD970          Install Door Frames                                           2    2   0% 10-Jun-26    11-Jun-26                                                              Install Door Frames
       P2ADD950          Install Doors/Hardware                                        2    2   0% 12-Jun-26    15-Jun-26                                                              Install Doors/Hardware
       P2ADD850          Storefront Frames/Glass                                       5    5   0% 17-Jun-26    23-Jun-26                                                               Storefront Frames/Glass
       P2ADD860          MEP Rough In (OH and In Wall)                                 8    8   0% 17-Jun-26    26-Jun-26                                                               MEP Rough In (OH and In Wall)
       P2ADD890          Prime/1st Coat Paint (Interior and Exterior)                  3    3   0% 24-Jun-26    26-Jun-26                                                               Prime/1st Coat Paint (Interior and Exterior)
       P2ADD870          MEP Inspections                                               2    2   0% 29-Jun-26    30-Jun-26                                                                MEP Inspections
       P2ADD880          Install Flooring                                              3    3   0% 29-Jun-26    01-Jul-26                                                                Install Flooring
       P2ADD900          Install Ceiling Grid                                          3    3   0% 02-Jul-26    07-Jul-26                                                                   Install Ceiling Grid
       P2ADD910          MEP Drops in Grid                                             3    3   0% 07-Jul-26    09-Jul-26                                                                   MEP Drops in Grid
       P2ADD920          MEP Coverup Inspections                                       2    2   0% 10-Jul-26    13-Jul-26                                                                   MEP Coverup Inspections


              Remaining Level of Effort               Milestone                                                                                                                                                                          Page 9 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary                     Champion MS Update 32 2025-12-30                                                                                                              Data Date: 31-Dec-25
                                                                                                                                                                                                                                Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                                           Full Schedule



                                                                                                                              Page 28 of 33
Activity ID              Activity Name                                    OD    RD     % Start        Finish                  2024                 2025                    2026                                      2027                          2028
                                                                                                                  J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       P2ADD930          Install ACT Tiles                                 3     3    0% 14-Jul-26    16-Jul-26                                                                   Install ACT Tiles
       P2ADD940          MEP Trim Out                                      3     3    0% 14-Jul-26    16-Jul-26                                                                   MEP Trim Out
       P2ADD960          Final Paint (Interior and Exterior)               3     3    0% 17-Jul-26    21-Jul-26                                                                   Final Paint (Interior and Exterior)
       P2ADD980          BBC Punch and Clean                               5     5    0% 17-Jul-26    23-Jul-26                                                                   BBC Punch and Clean
       P2ADD1000         Final Inspections                                 5     5    0% 24-Jul-26    30-Jul-26                                                                    Final Inspections
       P2ADD990          Owner Punch                                       5     5    0% 24-Jul-26    30-Jul-26                                                                    Owner Punch
     Phase 2 Added Work                                                   284   284       15-Jun-26   30-Jul-27                                                                                                                Phase 2 Added Work

      Exterior                                                            140   140       15-Jun-26   06-Jan-27                                                                                        Exterior
       P2ADD1110         MEP Safeoff                                       5     5    0% 15-Jun-26    19-Jun-26                                                              MEP Safeoff
       P2ADD1120         Selective Demo                                   15    15    0% 22-Jun-26    13-Jul-26                                                                   Selective Demo
       P2ADD1200         Install Retaining Wall                           10    10    0% 14-Jul-26    27-Jul-26                                                                    Install Retaining Wall
       P2ADD1210         Field Measure for Retaining Wall Handrails        2     2    0% 28-Jul-26    29-Jul-26                                                                    Field Measure for Retaining Wall Handrails
       P2ADD1130         Remove/Replace Water Line                        20    20    0% 28-Jul-26    24-Aug-26                                                                       Remove/Replace Water Line
       P2ADD1220         Fab/Del Retaining Wall Handrails                 30    30    0% 30-Jul-26    10-Sep-26                                                                         Fab/Del Retaining Wall Handrails
       P2ADD1140         Fine Grading                                     15    15    0% 25-Aug-26    15-Sep-26                                                                         Fine Grading
       P2ADD1230         Install Handrails                                 5     5    0% 11-Sep-26    17-Sep-26                                                                          Install Handrails
       P2ADD1150         Install Track                                    15    15    0% 16-Sep-26    06-Oct-26                                                                            Install Track
       P2ADD1180         Landscaping/Stabilization                        10    10    0% 07-Oct-26    20-Oct-26                                                                             Landscaping/Stabilization
       P2ADD1190         Install Hardscapes/Sidewalks                     10    10    0% 21-Oct-26    03-Nov-26                                                                               Install Hardscapes/Sidewalks
       P2ADD1160         Parking Lot Repair                               15    15    0% 04-Nov-26    24-Nov-26                                                                                 Parking Lot Repair
       P2ADD1170         Parking Lot Striping/Signage                     10    10    0% 25-Nov-26    10-Dec-26                                                                                    Parking Lot Striping/Signage
       P2ADD1240         BBC Punch and Clean                               5     5    0% 11-Dec-26    17-Dec-26                                                                                       BBC Punch and Clean
       P2ADD1250         Final Inspections                                 5     5    0% 18-Dec-26    28-Dec-26                                                                                        Final Inspections
       P2ADD1260         Owner Punch                                       5     5    0% 29-Dec-26    06-Jan-27                                                                                        Owner Punch
      Classrooms/Corridors/Restrooms - Level 2                            43    43        01-Jun-27   30-Jul-27                                                                                                                Classrooms/Corridors/Restrooms - Level 2
       P2ADD220          Remove Furniture and Return to Owner              2     2    0% 01-Jun-27    02-Jun-27                                                                                                         Remove Furniture and Return to Owner
       P2ADD230          MEP Safeoff                                       2     2    0% 01-Jun-27    02-Jun-27                                                                                                         MEP Safeoff
       P2ADD240          Abatement                                        10    10    0% 03-Jun-27    16-Jun-27                                                                                                            Abatement
       P2ADD250          Selective Demo                                    5     5    0% 17-Jun-27    23-Jun-27                                                                                                            Selective Demo
       P2ADD270          Remove/Replace Windows                           10    10    0% 17-Jun-27    30-Jun-27                                                                                                             Remove/Replace Windows
       P2ADD280          MEP Rough In                                      5     5    0% 24-Jun-27    30-Jun-27                                                                                                             MEP Rough In
       P2ADD320          Install Door Frames                               5     5    0% 24-Jun-27    30-Jun-27                                                                                                             Install Door Frames
       P2ADD330          Prime/1st Coat Paint                              5     5    0% 28-Jun-27    02-Jul-27                                                                                                             Prime/1st Coat Paint
       P2ADD350          Install Millwork/Cabinets                         3     3    0% 30-Jun-27    02-Jul-27                                                                                                             Install Millwork/Cabinets
       P2ADD310          MEP Cover Up Inspections                          2     2    0% 01-Jul-27    02-Jul-27                                                                                                             MEP Cover Up Inspections
       P2ADD440          Install ACT Tiles                                 4     4    0% 06-Jul-27    09-Jul-27                                                                                                             Install ACT Tiles
       P2ADD370          MEP Trim Out                                      5     5    0% 08-Jul-27    14-Jul-27                                                                                                              MEP Trim Out
       P2ADD390          Install Doors/Hardware                            5     5    0% 09-Jul-27    15-Jul-27                                                                                                              Install Doors/Hardware
       P2ADD400          Final Paint                                       5     5    0% 14-Jul-27    20-Jul-27                                                                                                               Final Paint
       P2ADD380          Install Misc. Accessories                         3     3    0% 15-Jul-27    19-Jul-27                                                                                                              Install Misc. Accessories
       P2ADD410          BBC Punch and Clean                               5     5    0% 19-Jul-27    23-Jul-27                                                                                                               BBC Punch and Clean
       P2ADD420          Owner Punch                                       5     5    0% 26-Jul-27    30-Jul-27                                                                                                                Owner Punch
       P2ADD430          FF&E Install                                      3     3    0% 28-Jul-27    30-Jul-27                                                                                                                FF&E Install
      Gym/Level 3                                                         42    42        01-Jun-27   29-Jul-27                                                                                                                Gym/Level 3
       P2ADD450          Remove Furniture and Return to Owner              2     2    0% 01-Jun-27    02-Jun-27                                                                                                         Remove Furniture and Return to Owner

              Remaining Level of Effort               Milestone                                                                                                                                                                    Page 10 of 11
              Actual Level of Effort
              Remaining Work
                                                      Summary         Champion MS Update 32 2025-12-30                                                                                                                      Data Date: 31-Dec-25
                                                                                                                                                                                                                            Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                               Full Schedule



                                                                                                                    Page 29 of 33
Activity ID              Activity Name                                  OD   RD    % Start       Finish                  2024                 2025                    2026                    2027                       2028
                                                                                                             J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
       P2ADD460          MEP Safeoff                                     2    2   0% 01-Jun-27   02-Jun-27                                                                                     MEP Safeoff
       P2ADD470          Abatement                                      10   10   0% 03-Jun-27   16-Jun-27                                                                                      Abatement
       P2ADD480          Selective Demo                                  5    5   0% 17-Jun-27   23-Jun-27                                                                                       Selective Demo
       P2ADD490          Remove/Replace Windows                         10   10   0% 17-Jun-27   30-Jun-27                                                                                       Remove/Replace Windows
       P2ADD500          MEP Rough In                                    5    5   0% 24-Jun-27   30-Jun-27                                                                                       MEP Rough In
       P2ADD510          Install Door Frames                             5    5   0% 24-Jun-27   30-Jun-27                                                                                       Install Door Frames
       P2ADD520          Prime/1st Coat Paint                            5    5   0% 28-Jun-27   02-Jul-27                                                                                       Prime/1st Coat Paint
       P2ADD540          MEP Cover Up Inspections                        2    2   0% 01-Jul-27   02-Jul-27                                                                                       MEP Cover Up Inspections
       P2ADD530          Install Flooring                                3    3   0% 06-Jul-27   08-Jul-27                                                                                           Install Flooring
       P2ADD550          Install ACT Tiles                               4    4   0% 06-Jul-27   09-Jul-27                                                                                           Install ACT Tiles
       P2ADD570          Install Doors/Hardware                          5    5   0% 09-Jul-27   15-Jul-27                                                                                           Install Doors/Hardware
       P2ADD560          MEP Trim Out                                    5    5   0% 13-Jul-27   19-Jul-27                                                                                            MEP Trim Out
       P2ADD580          Final Paint                                     5    5   0% 13-Jul-27   19-Jul-27                                                                                            Final Paint
       P2ADD600          BBC Punch and Clean                             5    5   0% 16-Jul-27   22-Jul-27                                                                                            BBC Punch and Clean
       P2ADD590          Install Misc. Accessories                       3    3   0% 20-Jul-27   22-Jul-27                                                                                            Install Misc. Accessories
       P2ADD610          Owner Punch                                     5    5   0% 23-Jul-27   29-Jul-27                                                                                             Owner Punch
       P2ADD620          FF&E Install                                    3    3   0% 27-Jul-27   29-Jul-27                                                                                             FF&E Install
       P2ADD630          Health Inspection (Concession Area Only)        3    3   0% 27-Jul-27   29-Jul-27                                                                                             Health Inspection (Concession Area Only)




              Remaining Level of Effort              Milestone                                                                                                                                           Page 11 of 11
              Actual Level of Effort
              Remaining Work
                                                     Summary        Champion MS Update 32 2025-12-30                                                                                              Data Date: 31-Dec-25
                                                                                                                                                                                                  Print Date: 30-Dec-25
              Actual Work
              Critical Remaining
                                                                             Full Schedule



                                                                                                               Page 30 of 33
                                                                                   Champion Theme Middle School
                                                                                                                        Stone Mountain, GA
REVISED FINAL GMP ESTIMATE SUMMARY 2026.01.07                                                                               January 7, 2026




                                                     GMP #1 - Phase 1              GMP #2 - Phase 1+2             Revised Final GMP
                      Item of Work
                                                        Total [A]                      Total [B]                  Grand Total [A+B]

01D Relocation Logistics                         $                 2,678,263   $                        -     $                 2,678,263
01E Phase 1 GMP 2 Science Classrooms (#PCO 14)   $                       -     $                    691,605   $                   691,605
01G General Requirements                         $                   473,582   $                    226,163   $                   699,745
01R Science Lab Renovation                       $                   167,953   $                        -     $                   167,953
02A Demolition                                   $                   549,942   $                    418,920   $                   968,862
03I Concrete Place & Finish                      $                       -     $                     48,406   $                    48,406
04A Masonry                                      $                    49,751   $                     75,179   $                   124,930
05A Structural & Miscellaneous Steel (Turnkey)   $                   197,780   $                        -     $                   197,780
06F Architectural Millwork                       $                       -     $                    142,114   $                   142,114
07B Roofing                                      $                   166,516   $                        -     $                   166,516
07C Fireproofing                                 $                    27,000   $                        -     $                    27,000
08A Doors, Frames & Hardware (Turnkey)           $                    23,525   $                  1,001,800   $                 1,025,325
08H Storefronts                                  $                       -     $                  1,072,591   $                 1,072,591
09A Drywall / Metal Framing                      $                   613,352   $                    112,547   $                   725,899
09D Painting / Wallcovering                      $                    70,765   $                    266,990   $                   337,755
09E Flooring                                     $                    17,232   $                    502,358   $                   519,590
09P Acoustic Room Treatments                     $                       -     $                     70,659   $                    70,659
10A Toilet Partitions / Accessories              $                     6,373   $                    295,074   $                   301,447
10C Signage                                      $                       -     $                     50,000   $                    50,000
12A Window Treatments                            $                       -     $                     90,000   $                    90,000
21A Fire Protection                              $                   564,044   $                        -     $                   564,044
22A Plumbing                                     $                   428,281   $                    175,860   $                   604,141
23A HVAC                                         $                 5,720,614   $                    245,389   $                 5,966,003
26A Electrical                                   $                 3,888,341   $                    125,000   $                 4,013,341
26B Electrical Bid Spread Allowance              $                 1,200,000   $                        -     $                 1,200,000
31D Sitework Package                             $                   192,924   $                  1,114,743   $                 1,307,667
32A Paving / Curb & Gutter                       $                       -     $                    206,930   $                   206,930
32C Site Concrete                                $                       -     $                    102,800   $                   102,800
32F Site Fencing                                 $                    14,227   $                        -     $                    14,227
32G Athletic Field Construction                  $                       -     $                  1,102,777   $                 1,102,777
32O Landscaping & Irrigation                     $                       -     $                     75,000   $                    75,000


Subtotal                                         $                17,050,465   $                  8,212,905   $                25,263,370
      General Conditions                         $                 2,766,781   $                 1,074,599    $                 3,841,380
      General Liability                          $                   250,572   $                   128,952    $                   379,524
      SDI                                        $                   259,167   $                   122,565    $                   381,732
      Builder's Risk                             $                    46,230   $                    21,492    $                    67,722
      Performance and Payment Bond               $                   127,792   $                    61,252    $                   189,044
      Preconstruction Services                   $                       -     $                    37,611    $                    37,611
      Construction Contingency                   $                 1,193,533   $                   410,645    $                 1,604,178
      Escalation Contingency                     $                       -     $                   164,258    $                   164,258
Subtotal                                         $                21,694,539   $                10,234,280    $                31,928,819
      Fee                                        $                 1,084,727   $                   511,714    $                 1,596,441
GRAND TOTAL                                      $              22,779,266     $               10,745,994     $               33,525,260




                                                          Page 31 of 33
ATTACHMENT 5 – List of Itemized General Conditions
                                                       GMP
Champion Theme Middle School
                                                       Feb.28, 2024
Stone Mountain, GA




                                       Page 32 of 33
  ATTACHMENT 7 - Alternates
   Champion Theme Middle School                                        GMP
  Stone Mountain, GA                                                   March 8, 2024



Alternates
Alternate amounts listed below are the direct cost amounts and do not include Contractor overhead, fees, insurances,
or indirect costs. Alternates may be incorporated by future Change Order. Alternate pricing is good for twenty (20)
days.

    1. N/A




                                                 Page 33 of 33