Agenda Item
b. Capital Improvement & Facilities Update
Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676-1475
DeKalb County School District
Capital Improvement Program – Construction Update Report
Report Date: July 14, 2025
1. New Dresden Elementary School
Project Number: 21836
Principal: Dr. Lauren Pells
Architect: BRPH
Contractor: Winter Construction
Scope: New 134,420 sq ft elementary school with 59 instructional units and 900-seat capacity
Construction Budget: $72,323,774
Project Timeline:
• Design Completion: March 2024
• Construction Start: June 2024
• Construction End: August 2027
Current Status:
Construction is actively underway with structural and sitework progressing.
4-Week Look Ahead:
• Steel erection began June 17, 2025.
• Masonry mock-up wall to be completed by June 27, 2025.
• Excavation and reinforcement for Retaining Wall A ongoing.
• Underground storm line (Line A) installation continues.
• Masonry subcontractor returned July 7, 2025, for CMU wall erection.
• Backfilling ongoing along basement foundation walls.
• Georgia Power granted Right of Entry on June 9, 2025, for utility installations.
Photos:
2. Cross Keys High School
Project Number: 21435
Principal: Dr. B. Cunningham
Architect: Cooper Carry
Contractor: Evergreen Construction
Scope: 290,288 of new temporary classroom facilities, bus loop, building additions, and
renovation.
Construction Budget: $81,369,443 Phase 1
Project Timeline:
• Construction Start: June 2024
• Construction Completion: August 2028
Current Status:
• Water line pressure tests and chlorination mostly complete.
• Accessible ramps to modular classrooms nearly finished.
• Grading and backfill around the new bus loop area underway.
4-Week Look Ahead:
• Retaining wall construction and roadway preparation near the bus loop to begin.
3. New Sequoyah Middle & High School
Project Number: 10136
Principal: Tiffany Sims
Architect: GMC Architects
Contractor: Gilbane
Scope: 480,000 GSF of new construction of middle and high school campus
Construction Budget: $235,000,000
Project Timeline:
• Design Completion: January 2025
• Contractor Procurement: February 2025
• Construction Start: February 2025
• Construction End: August 2028
Current Status:
• Underground domestic and fire lines being installed.
• Erosion control measures nearly complete.
• Concrete pours ongoing for footings and slabs-on-grade.
4-Week Look Ahead:
• Complete aggregate piers.
• Begin excavation for shallow foundations.
• Continue concrete pours and begin steel erection.