E-SPLOST V - Cross Keys HS GMP Tracking May 2024 Board

AID 1641070 · View on Simbli

Agenda Item

ii. E-SPLOST V Project New Addition and Modernization at Cross Keys High School – Component Guaranteed Maximum Price #01 Early Release Package Approval (Not to exceed $44,419,077) ~ Updated 5.2.2024

Summary: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education establish an Initial Guaranteed Maximum Price of $44,419,077 for the construction of the Addition and Modernization of Cross Keys High School SPLOST V project per the terms set forth in the Construction Manager at Risk contract previously awarded to The Evergreen Construction Company.
Why: It is requested that the Board of Education establish an Initial Guaranteed Maximum Price of $44,419.077 for construction of the Addition and Modernization of Cross Keys High School SPLOST V project per the terms set forth in the Construction Manager at Risk contract previously awarded to Evergreen Construction Company.
Details: On November 5, 2018, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Evergreen Construction Company for the completion of the Addition and Modernization of the Cross Keys High School project and Pre-Construction Services in the amount of $90,000.00.

Pursuant to that agreement, the Design Professional (Cooper Carry), CM@R (Evergreen), Program Manager (ACERM), multiple DCSD Departments and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and an Initial GMP in the best interest of the DeKalb County School District.

This action establishes an Initial Guaranteed Maximum Price and Contract Time for all the work set forth in the attached Evergreen Initial GMP Amendment.
Financial impact: This project will be funded by SPLOST V Project 21435 - New Addition and Modernization at Cross Keys High School. If approved, a budget of $44,419,077.00 will be created in the construction cost code (SP5NEWSCH.21435.GENERALCONTRACTOR) under the voter-approved E-SPLOST VI program.
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1475

Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by General Counsel
                                                                           Revised Construction
21435. Cross     Construction of Addition and Modernization (Extensive
                                                                          Estimate at Completion    $124,581,415.00
Keys HS          Renovation) of Cross Keys HS
                                                                                April FY24

                   Brief Description of Phase                                                      New Value Pending                           Estimated Date of
     Phase                                               Funding Source      Approved Value                            Estimate of Final GMP                            Notes
                            Package                                                                    Approval                                 Board Approval

                                                                                                                                                                    Approved at
    Pre-
                   Pre-Construction Services               E-SPLOST V          $90,000.00                                                                          November 2018
 Construction
                                                                                                                                                                   Board Meeting

                  Site work, foundations, bus
                       loop, stormwater                                                                                                                            On May 2024
 Early Release                                             E-SPLOST V                               $44,419,077.00                                 5/6/2024
                    management, long lead                                                                                                                          Board Agenda
                       items/equipment

                    CR Addition, Building                                                                                                                           SD Pricing. DD
     Final        Modernization, Auditorium,             E-SPLOST V/TBD                             $80,162,338.00       $124,581,415.00          9/14/2024        Pricing expected
                     Athletics Upgrade                                                                                                                              May 10, 2024