E-SPLOST V - Nancy Creek Faciity GMP Tracking May 2024

AID 1641065 · View on Simbli

Agenda Item

x. E-SPLOST V Project 35335 Nancy Creek Facility Major Building System Replacement Guaranteed Maximum Price Approval (Not to exceed $12,375,659) ~ Updated 5.2.2024

Summary: Presented by: Erick Hofstetter, Chief Operations Officer, Division of Operations
Request: It is requested that the Board of Education establish a Guaranteed Maximum Price of $12,375,659 for work included in the E-SPLOST V Nancy Creek Facility project per the terms set forth in the Construction Manager at Risk contract previously awarded to Balfour-Beatty.
Why: To amend the agreement with Balfour-Beatty for the work and to establish a Guaranteed Maximum Price (GMP) as $12,375,659.00.
Details: On December 11, 2023, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Balfour Beatty for Pre-Construction Services in the amount of $50,000.00.

Pursuant to that agreement the Design Professional (SSOE), CM@R (Balfour Beatty), Program Manager (ACERM), and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and a GMP in the best interest of the DeKalb County School District.

This action establishes a Phase I Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached NCES_Exhibit M_03-12-24.
Financial impact: This project will be funded from E-SPLOST V Project 35335 - Nancy Creek Facility Major Building Systems Replacement. If approved, the construction cost code will require a budget reallocation of $5,371,073 from Program Contingency (SP5FACCON.35335.GENCONTR).
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1475

Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by General Counsel
35335. Nancy Creek
                                                                Revised Construction
Facility Major       Major building systems replacement with
                                                               Estimate at Completion    $12,375,659.00
Building Systems     emphasis on HVAC.
Replacement                                                          April FY24
                                                                                                                                Estimated Date
                     Brief Description                                                  New Value Pending   Estimate of Final
       Phase                                Funding Source        Approved Value                                                    of Board        Notes
                     of Phase Package                                                       Approval             GMP
                                                                                                                                   Approval

                      Pre-Construction
 Pre-Construction                              E-SPLOST V           $50,000.00                                                                   12/11/2023
                          Services
   Early Release            N/A                   N/A                   N/A                    NA                 N/A                N/A             N/A
                       Full Scope as                                                                                                             On May 2024
       Final          defined in GMP           E-SPLOST V                                $12,375,659.00     $12,375,659.00        5/6/2024          Board
                        Documents                                                                                                                  Agenda