EXHIBIT M
GMP AMENDMENT TO AGREEMENT BETWEEN OWNER AND
CONSTRUCTION CONTRACTOR
AMENDMENT NO. 1 TO AGREEMENT BETWEEN OWNER AND
CONSTRUCTION CONTRACTOR FOR Cross Keys High School
AGREEMENT NO. 423.71.04.00.214423.752.0000
Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
(“Agreement”), dated 11/19/2018 , between The School Board of DeKalb County, Georgia
(“Owner”) and Evergreen Construction
(“Construction Contractor”), with respect to the construction of Owner’s
New Cross Keys High School (“Project”), Owner and Construction
Contractor hereby agree to amend and modify the Agreement by this Amendment No. 1 and
establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
unless otherwise noted.
ARTICLE 1
SCOPE OF WORK
The scope of the Work consists of the construction of a Renovation and Modernization to the
existing Cross Keys High School , in accordance with the Agreement, this
Amendment and the other Contract Documents listed as Attachments 1 through 5 below, which
are hereby incorporated into and made a part of the Amendment by this reference:
Attachment No. Description Pages Date
List of Drawings, Specifications and Addendums
1. Allowances 1
_____ through _____
1 4/8/24
2. Assumptions and Clarifications _____
1 through _____
1 4/8/24
3. Completion Schedule _____
1 through _____
1 4/8/24
4. Schedule of Values _____
1 8
through _____ 4/8/24
5. List of Itemized General Conditions _____
1 9
through _____ 4/8/24
6. List of Subcontractors and _____ through _____
Major Suppliers
7. Alternates _____ through _____
M-1
ARTICLE 2
GUARANTEED MAXIMUM PRICE
2.1 Construction Contractor’s Guaranteed Maximum Price (“GMP”) for the Work,
including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
Construction Management Fee as defined in Section defined in Section
4 of the 4 of the
Agreement, is Forty four million
four hundred nineteen thousand seventy seven dollars. ($ 44,419,077 ).
2.2 The Construction Management Fee for the entire Work anticipated on this Project
is hereby established as a lump sum amount of One million three hundred thousand six hundred five
($_ 1,300,605 ), said lump sum amount is included within the above noted GMP.
2.3 The general condition expenses for the entire Work anticipated on this Project are
hereby established as a lump sum amount of Three million four hundred thirty thousand two hundred eighty one
($ 3,430,281 ), said lump sum amount is included within the above noted GMP (“General
Conditions Expenses”). The items included as General Condition Expenses are listed in the List
of Itemized General Conditions attached hereto and incorporated herein as Attachment No. 5 .
Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
Change Order or Construction Change Directive, Construction Contractor acknowledges and
agrees that Owner shall have no liability for any General Condition expenses beyond payment of
the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
to receive any additional compensation from Owner for the General Conditions beyond the above
lump sum amount. There shall be no additional General Conditions Expenses payable to
Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
Change Directive Work). Further, there shall be no mark-up for a subcontractor’s General
Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
Change Order and Construction Change Directive Work to be performed by such subcontractor.
2.4 Monthly installment payment of the Construction Management Fee and the General
Condition Expenses shall be based upon the percent completion of the designated portion of the
Work for each particular month.
2.5 In order to efficiently and timely address any unknown or unanticipated conditions
that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
of the Work, but excluding all items that are to be reimbursed under the lump sum General
Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
One millon nine hundred eighty two
contingency within the GMP in an amount not-to-exceed amount of thousand four hundred thirty six and
/100 Dollars ($ 1,982,436 ) (“Owner’s Contingency”). Owner’s Contingency
funds shall be used to cover costs that may result from incomplete design and unanticipated costs
that arise during construction that are not identified by the construction documents. Construction
M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner’s Contingency without first obtaining Owner’s express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner’s Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor’s Work compensated within the
GMP and not chargeable against Owner’s Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner’s Contingency expenditures. Further, the work that
is the subject of any Owner’s Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner’s Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner’s Contingency.
2.6 In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above,Onethe parties have agreed to
millon nine hundred
establish a contingency within the GMP in an amount not-to-exceed hundred thirty six
eighty two thousand four
and /100
Dollars ($1,982,436 ) (“Contractor’s Contingency”). Construction Contractor shall not proceed
with any portion of the Work which it intends to charge against the Contractor’s Contingency
without first obtaining Owner’s express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor’s
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor’s Work compensated within the GMP and not chargeable against
Contractor’s Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor’s Contingency expenditures. Further, the work that is the subject of any Owner’s
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor’s Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor’s Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of % of
the Cost of the Work charged against the Contractor’s Contingency.
2.7 The parties have agreed to establish an allowance within the GMP for
See allowances log in the amount of and /100 Dollars ($ 12,841,687 ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance (“Allowance Work”) without first obtaining Owner’s express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments 1 through. Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenever costs are more
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.
M-3
2.8 Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
payment is made to Construction Contractor the total Cost of the Work has been increased by
approved Change Orders in an amount causing the original GMP as set forth in this Amendment
to be exceeded by more than and /100 Dollars ($ ), then
Construction Contractor shall be entitled to an increase in the Construction Management Fee in
the amount of and /100 Dollars ( %) of the amount exceeding the sum of
and /100 Dollars ($ _) plus that original GMP amount.
2.9 Construction Contractor recognizes that the Contract includes work for trench
excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
set forth by all federal, state and local requirements. Construction Contractor certifies that the
required trench safety standards will be in effect during the period of construction of the Project
and Construction Contractor agrees to comply with all such required trench safety standards.
2.10.1 The amount of Zero and /100 Dollars
($ 0 ) has been separately identified for the cost of compliance with the required trench
safety standards; said amount is included within the GMP.
2.10 At the completion of the Work, should the actual amount of “General
Requirements” expenses be less than the amount included therefor in the Schedule of Values
approved by Owner, the resulting “savings” shall accrue to the benefit of Owner and a deductive
Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
separate guaranteed maximum price for such expenses and any overruns in General Requirements
expenses shall be borne by Construction Contractor without reimbursement from Owner.
2.11 By executing this Amendment and furnishing Owner with a GMP based on a
detailed Schedule of Values and a Master Project Schedule, Construction Contractor represents
and warrants that the Contract Documents, including the Construction Documents, as well as other
materials, and information furnished Construction Contractor as of the date of this Amendment
have described the scope, construction requirements, and design intent of the Work in detail
sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
Project Schedule. To the extent that the Construction Documents are anticipated to require further
development, Construction Contractor has provided in the GMP for such further development
consistent with the Contract Documents and reasonably inferable therefrom.
2.12 Savings will be computed as of the date of final completion of the Work and shall
consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
benefit of Owner.
M-4
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
GENERAL
G0.00 COVER SHEET 3/28/2024
G0.01 DRAWING INDEX 3/28/2024
G0.02 GENERAL INFORMATION 3/28/2024
G1.01 MEANS OF EGRESS PLAN - LEVEL 1 3/28/2024
G1.02 MEANS OF EGRESS PLAN - LEVEL 2 & 3 3/28/2024
G2.00 CONSTRUCTION PHASING DIAGRAMS 3/28/2024
CIVIL
C1.0 COVER SHEET & GENERAL NOTES 3/28/2024
SURVEY I SITE SURVEY I 3/28/2024
SURVEY II SITE SURVEY II 3/28/2024
C3.0 OVERALL LAYOUT & STAKING PLAN 3/28/2024
C3.1 LAYOUT & STAKING PLAN I 3/28/2024
C3.2 LAYOUT & STAKING PLAN II 3/28/2024
C4.0 GRADING PLAN 3/28/2024
C4.1 GRADING PLAN I 3/28/2024
C4.2 GRADING PLAN II 3/28/2024
C4.3 DRAINAGE PLAN I 3/28/2024
C4.4 DRAINAGE PLAN II 3/28/2024
C5.0 UTILITY PLAN 3/28/2024
C5.1 UTILITY PLAN I 3/28/2024
C5.2 UTILITY PLAN II 3/28/2024
C6.0 PROFILE PLAN 3/28/2024
C6.1 PROFILE PLAN 3/28/2024
C7.0 CONSTRUCTION DETAILS 3/28/2024
C7.1 CONSTRUCTION DETAILS 3/28/2024
C7.2 CONSTRUCTION DETAILS 3/28/2024
C7.3 CONSTRUCTION DETAILS 3/28/2024
C7.4 CONSTRUCTION DETAILS 3/28/2024
C7.5 CONSTRUCTION DETAILS 3/28/2024
C7.6 CONSTRUCTION DETAILS 3/28/2024
C7.7 CONSTRUCTION DETAILS 3/28/2024
LANDSCAPE
L0.00 GENERAL NOTES 3/28/2024
L1.01 OVERALL HARDSCAPE PLAN 3/28/2024
L1.02 HARDSCAPE PLAN 3/28/2024
L1.03 HARDSCAPE PLAN 3/28/2024
L1.04 HARDSCAPE PLAN 3/28/2024
L1.05 HARDSCAPE PLAN 3/28/2024
L1.06 HARDSCAPE ENLARGEMENT PLAN 3/28/2024
L1.07 HARDSCAPE ENLARGEMENT PLAN 3/28/2024
L2.01 HARDSCAPE DETAILS 3/28/2024
L2.02 HARDSCAPE DETAILS 3/28/2024
L3.00A TREE REMOVAL PLAN 3/28/2024
L3.00B TREE REMOVAL SCHEDULE 3/28/2024
L3.01 OVERALL LANDSCAPE PLAN 3/28/2024
L3.02 LANDSCAPE PLAN 3/28/2024
L3.03 LANDSCAPE PLAN 3/28/2024
L3.04 LANDSCAPE PLAN 3/28/2024
L3.05 LANDSCAPE PLAN 3/28/2024
L3.06 LANDSCAPE PLAN 3/28/2024
L3.07 LANDSCAPE PLAN 3/28/2024
1 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
L4.00 LANDSCAPE NOTES AND DETAILS 3/28/2024
DEMOLITION
D1.00 DEMOLITION SITE PLAN 3/28/2024
D2.01 OVERALL LEVEL 1 DEMOLITION PLAN 3/28/2024
D2.04 DEMOLITION ROOF PLAN 3/28/2024
D2.11D DEMOLITION FLOOR PLAN - 100 WING 3/28/2024
D2.11E DEMOLITION FLOOR PLAN - 200 WING 3/28/2024
D2.11F DEMOLITION FLOOR PLAN - 300 WING + 400 WING 3/28/2024
D2.11J DEMOLITION FLOOR PLAN - GYMNASIUM 3/28/2024
D2.11K DEMOLITION FLOOR PLAN - GYMNASIUM 3/28/2024
D6.01 DEMOLITION SECTIONS & DETAILS 3/28/2024
ARCHITECTURE
A1.00 ARCHITECTURAL SITE PLAN 3/28/2024
A2.01 OVERALL LEVEL 1 FLOOR PLAN 3/28/2024
A2.02 OVERALL LEVEL 2 & 3 FLOOR PLAN 3/28/2024
A2.04 ROOF PLAN 3/28/2024
A2.11A LEVEL 1 FLOOR PLAN - AREA A 3/28/2024
A2.11B LEVEL 1 FLOOR PLAN - AREA B 3/28/2024
A2.11C LEVEL 1 FLOOR PLAN - AREA C 3/28/2024
A2.11D LEVEL 1 FLOOR PLAN - AREA D 3/28/2024
A2.11E LEVEL 1 FLOOR PLAN - AREA E 3/28/2024
A2.11F LEVEL 1 FLOOR PLAN - AREA F/G 3/28/2024
A2.11H LEVEL 1 FLOOR PLAN - AREA H 3/28/2024
A2.11J LEVEL 1 FLOOR PLAN - AREA J 3/28/2024
A2.11K LEVEL 1 FLOOR PLAN - AREA K/L 3/28/2024
A2.11M LEVEL 1 FLOOR PLAN - AREA M 3/28/2024
A2.11N LEVEL 1 FLOOR PLAN - AREA N 3/28/2024
A2.12A LEVEL 2 FLOOR PLAN - AREA A 3/28/2024
A2.12B LEVEL 2 FLOOR PLAN - AREA B 3/28/2024
A2.12C LEVEL 2 FLOOR PLAN - AREA C 3/28/2024
A2.13A LEVEL 3 FLOOR PLAN - AREA A 3/28/2024
A2.13B LEVEL 3 FLOOR PLAN - AREA B 3/28/2024
A2.13C LEVEL 3 FLOOR PLAN - AREA C 3/28/2024
A2.14A ROOF PLAN - AREA A 3/28/2024
A2.14B ROOF PLAN - AREA B 3/28/2024
A2.14C ROOF PLAN - AREA C 3/28/2024
A2.14H ROOF PLAN - AREA H 3/28/2024
A2.14K ROOF PLAN - AREA K 3/28/2024
A2.14M ROOF PLAN - AREA M 3/28/2024
A2.14N ROOF PLAN - AREA N 3/28/2024
A2.40A OVERALL LEVEL 1 REFLECTED CEILING PLAN 3/28/2024
A2.40B OVERALL LEVEL 2 AND 3 REFLECTED CEILING PLANS 3/28/2024
A2.41A LEVEL 1 REFLECTED CEILING PLAN - AREA A 3/28/2024
A2.41B LEVEL 1 REFLECTED CEILING PLAN - AREA B 3/28/2024
A2.41C LEVEL 1 REFLECTED CEILING PLAN - AREA C 3/28/2024
A2.41D LEVEL 1 REFLECTED CEILING PLAN - AREA D 3/28/2024
A2.41E LEVEL 1 REFLECTED CEILING PLAN - AREA E 3/28/2024
A2.41F LEVEL 1 REFLECTED CEILING PLAN - AREA F/G 3/28/2024
A2.41H LEVEL 1 REFLECTED CEILING PLAN - AREA H 3/28/2024
A2.41J LEVEL 1 REFLECTED CEILING PLAN - AREA J 3/28/2024
A2.41K LEVEL 1 REFLECTED CEILING PLAN - AREA K/L 3/28/2024
A2.41M LEVEL 1 REFLECTED CEILING PLAN - AREA M 3/28/2024
2 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
A2.41N LEVEL 1 REFLECTED CEILING PLAN - AREA N 3/28/2024
A2.42A LEVEL 2 REFLECTED CEILING PLAN - AREA A 3/28/2024
A2.42B LEVEL 2 REFLECTED CEILING PLAN - AREA B 3/28/2024
A2.42C LEVEL 2 REFLECTED CEILING PLAN - AREA C 3/28/2024
A2.43A LEVEL 3 REFLECTED CEILING PLAN - AREA A 3/28/2024
A2.43B LEVEL 3 REFLECTED CEILING PLAN - AREA B 3/28/2024
A2.43C LEVEL 3 REFLECTED CEILING PLAN - AREA C 3/28/2024
A2.50A FINISH SCHEDULES 3/28/2024
A2.50B TYPICAL INTERIOR DETAILS 3/28/2024
A2.51A LEVEL 1 FINISH PLAN - AREA A 3/28/2024
A2.51B LEVEL 1 FINISH PLAN - AREA B 3/28/2024
A2.51C LEVEL 1 FINISH PLAN - AREA C 3/28/2024
A2.51D LEVEL 1 FINISH PLAN - AREA D 3/28/2024
A2.51E LEVEL 1 FINISH PLAN - AREA E 3/28/2024
A2.51F LEVEL 1 FINISH PLAN - AREA F/G 3/28/2024
A2.51H LEVEL 1 FINISH PLAN - AREA H 3/28/2024
A2.51J LEVEL 1 FINISH PLAN - AREA J 3/28/2024
A2.51K LEVEL 1 FINISH PLAN - AREA K/L 3/28/2024
A2.51M LEVEL 1 FINISH PLAN - AREA M 3/28/2024
A2.51N LEVEL 1 FINISH PLAN - AREA N 3/28/2024
A2.52A LEVEL 2 FINISH PLAN - AREA A 3/28/2024
A2.52B LEVEL 2 FINISH PLAN - AREA B 3/28/2024
A2.52C LEVEL 2 FINISH PLAN - AREA C 3/28/2024
A2.53A LEVEL 3 FINISH PLAN - AREA A 3/28/2024
A2.53B LEVEL 3 FINISH PLAN - AREA B 3/28/2024
A2.53C LEVEL 3 FINISH PLAN - AREA C 3/28/2024
A2.61A LEVEL 1 FURNITURE PLAN - AREA A 3/28/2024
A2.61B LEVEL 1 FURNITURE PLAN - AREA B 3/28/2024
A2.61C LEVEL 1 FURNITURE PLAN - AREA C 3/28/2024
A2.61D LEVEL 1 FURNITURE PLAN - AREA D 3/28/2024
A2.61E LEVEL 1 FURNITURE PLAN - AREA E 3/28/2024
A2.61F LEVEL 1 FURNITURE PLAN - AREA F/G 3/28/2024
A2.61H LEVEL 1 FURNITURE PLAN - AREA H 3/28/2024
A2.61J LEVEL 1 FURNITURE PLAN - AREA J 3/28/2024
A2.61K LEVEL 1 FURNITURE PLAN - AREA K/L 3/28/2024
A2.61M LEVEL 1 FURNITURE PLAN - AREA M 3/28/2024
A2.61N LEVEL 1 FURNITURE PLAN - AREA N 3/28/2024
A2.62A LEVEL 2 FURNITURE PLAN - AREA A 3/28/2024
A2.62B LEVEL 2 FURNITURE PLAN - AREA B 3/28/2024
A2.62C LEVEL 2 FURNITURE PLAN - AREA C 3/28/2024
A2.63A LEVEL 3 FURNITURE PLAN - AREA A 3/28/2024
A2.63B LEVEL 3 FURNITURE PLAN - AREA B 3/28/2024
A2.63C LEVEL 3 FURNITURE PLAN - AREA C 3/28/2024
A3.00 PLUMBING FIXTURES 3/28/2024
A3.01 ENLARGED RESTROOM PLANS 3/28/2024
A3.02 ENLARGED RESTROOM PLANS 3/28/2024
A3.03 ENLARGED RESTROOM PLANS 3/28/2024
A3.04 ENLARGED RESTROOM PLANS 3/28/2024
A3.05 ENLARGED RESTROOM PLANS 3/28/2024
A3.06 ENLARGED RESTROOM PLANS 3/28/2024
A3.11 ENLARGED CLASSROOM PLANS 3/28/2024
A3.12 ENLARGED CHEMISTRY LAB 3/28/2024
3 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
A3.13 ENLARGED BIOLOGY LAB 3/28/2024
A3.14 ENLARGED PHYSICS LAB 3/28/2024
A3.16 ENLARGED TEACHER PLANNING ROOMS 3/28/2024
A3.22 ENLARGED HOME LIVING CENTER & LTSE CLASSROOM 3/28/2024
A3.23 ENLARGED SAFE CENTER 3/28/2024
A3.31 ENLARGED BAND SUITE 3/28/2024
A3.32 ENLARGED ORCHESTRA SUITE 3/28/2024
A3.34 ENLARGED KEYBOARD & PRACTICE ROOMS 3/28/2024
A3.37 ENLARGED BLACK BOX THEATER, CONCESSIONS & TICKETING 3/28/2024
A3.38 ENLARGED ART CLASSROOM 3/28/2024
A3.40 ENLARGED CAREER CENTER 3/28/2024
A3.43 ENLARGED ENGINEERING LAB 3/28/2024
A3.44 ENLARGED JROTC SUITE 3/28/2024
A3.47 ENLARGED FOOD SCIENCE LAB 3/28/2024
A3.50 ENLARGED MEDIA CENTER 3/28/2024
A3.51 INTERIOR ELEVATIONS - MEDIA CENTER 3/28/2024
A3.52 INTERIOR ELEVATIONS - MEDIA CENTER 3/28/2024
A3.60 ENLARGED GYMNASIUM 3/28/2024
A3.61 INTERIOR ELEVATIONS - GYMNASIUM 3/28/2024
A3.62 ENLARGED AUX. GYMNASIUM 3/28/2024
A3.63 ENLARGED GYMNASIUM LOCKER ROOMS & TRAINING ROOM 3/28/2024
A3.64 ENLARGED WRESTLING ROOM 3/28/2024
A3.65 ENLARGED WEIGHT ROOM 3/28/2024
A3.71 ENLARGED DINING/COMMONS 3/28/2024
A3.72 INTERIOR ELEVATIONS - DINING / COFFEE BAR LOUNGE 3/28/2024
A3.90 ENLARGED AUDITORIUM 3/28/2024
A3.91 ENLARGED AUDITORIUM ELEVATIONS 3/28/2024
A3.92 ENLARGED AUDITORIUM DRESSING ROOMS 3/28/2024
A3.93 ENLARGED SCENE SHOP 3/28/2024
A3.94 ENLARGED STUDENT COLLABORATION SPACES 3/28/2024
A4.01 EXTERIOR ELEVATIONS 3/28/2024
A4.02 ENLARGED EXTERIOR ELEVATIONS - GYMNASIUM 3/28/2024
A4.03 ENLARGED EXTERIOR ELEVATIONS - AUDITORIUM & CAFETERIA 3/28/2024
A4.04 ENLARGED EXTERIOR ELEVATIONS - MEDIA CENTER 3/28/2024
A5.01 BUILDING SECTIONS 3/28/2024
A5.02 EXTERIOR PERSPECTIVES - AUDITORIUM 3/28/2024
A5.03 INTERIOR PERSPECTIVES - AUDITORIUM 3/28/2024
A5.04 INTERIOR PERSPECTIVES - MEDIA CENTER 3/28/2024
A5.05 EXTERIOR PERSPECTIVES - BACKSDIE /CAFETERIA 3/28/2024
A5.06 EXTERIOR PERSPECTIVES - PARENT DROP-OFF 3/28/2024
A6.00 EXTERIOR ASSEMBLIES 3/28/2024
A6.01 EXTERIOR WALL SECTIONS 3/28/2024
A6.02 EXTERIOR WALL SECTIONS 3/28/2024
A6.03 EXTERIOR WALL SECTIONS 3/28/2024
A6.04 EXTERIOR WALL SECTIONS 3/28/2024
A6.10 PLAN DETAILS 3/28/2024
A7.01 STAIR PLANS & SECTIONS 3/28/2024
A7.02 STAIR PLANS & SECTIONS 3/28/2024
A7.03 STAIR PLANS & SECTIONS 3/28/2024
A7.08 METAL PAN STAIR & RAILING DETAILS 3/28/2024
A7.10 ELEVATOR PLANS, ELEVATIONS, SECTIONS & DETAILS 3/28/2024
A8.10 DOOR SCHEDULE AND TYPES 3/28/2024
4 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
A8.11 DOOR SCHEDULE AND TYPES 3/28/2024
A8.12 DOOR DETAILS (STEEL STUD PARTITIONS) 3/28/2024
A8.13 DOOR DETAILS (CMU PARTITIONS) 3/28/2024
A8.14 DOOR DETAILS (CMU PARTITIONS) 3/28/2024
A9.01 INTERIOR PARTITIONS 3/28/2024
A9.02 INTERIOR PARTITIONS 3/28/2024
A9.03 INTERIOR PARTITIONS 3/28/2024
A9.04 INTERIOR PARTITIONS (CMU) 3/28/2024
A9.10 FIRE PROTECTION DETAILS 3/28/2024
A9.11 FIRE PROTECTION DETAILS 3/28/2024
FOOD SERVICE
QF0.0 FOODSERVICE GENERAL NOTES 3/28/2024
QF0.1 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.2 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.3 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.4 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.5 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.6 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF0.7 FOODSERVICE EQUIPMENT PLAN STANDARD DETAILS 3/28/2024
QF1.0 FOODSERVICE EQUIPMENT PLAN - OVERALL 3/28/2024
QF1.1 FOODSERVICE EQUIPMENT PLAN - OVERALL KITCHEN 3/28/2024
QF1.2 FOODSERVICE EQUIPMENT PLAN - KITCHEN NORTH 3/28/2024
QF1.3 FOODSERVICE EQUIPMENT PLAN - KITCHEN SOUTH 3/28/2024
QF1.4 FOODSERVICE EQUIPMENT SCHEDULE 3/28/2024
QF6.01 FOODSERVICE EQUIPMENT ELECTRICAL PLAN – KN 3/28/2024
QF6.02 FOODSERVICE EQUIPMENT ELECTRICAL PLAN - KS 3/28/2024
QF6.03 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.04 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.05 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.06 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.07 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.08 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.09 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.10 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.11 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.12 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
QF6.13 FOODSERVICE EXHAUST HOOD VENDOR DETAILS 3/28/2024
STRUCTURAL
S0.00 GENERAL NOTES 3/28/2024
S0.01 GENERAL NOTES 3/28/2024
S0.02 3D VIEWS 3/28/2024
S1.01 TYPICAL SECTIONS AND DETAILS 3/28/2024
S1.02 TYPICAL SECTIONS AND DETAILS 3/28/2024
S1.03 TYPICAL CMU WALL DETAILS 3/28/2024
S1.04 TYPICAL CMU WALL DETAILS 3/28/2024
S1.05 TYPICAL COMPOSITE SLAB DETAILS 3/28/2024
S1.06 TYPICAL COMPOSITE SLAB DETAILS 3/28/2024
S1.07 TYPICAL COMPOSITE SLAB DETAILS 3/28/2024
S1.08 TYPICAL STEEL BEAM DETAILS 3/28/2024
S1.09 TYPICAL STEEL JOIST DETAILS 3/28/2024
S1.10 TYPICAL ROOF DETAILS 3/28/2024
S2.01 OVERALL LEVEL 1 FOUNDATION PLAN 3/28/2024
S2.02 OVERALL LEVEL 2 FRAMING PLAN 3/28/2024
S2.03 OVERALL LEVEL 3 FRAMING PLAN 3/28/2024
5 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
S2.04 OVERALL ROOF FRAMING PLAN 3/28/2024
S2.11A LEVEL 1 FOUNDATION PLAN - NEW BUILDING SOUTH 3/28/2024
S2.11C LEVEL 1 FOUNDATION PLAN - NEW BUILDING NORTH 3/28/2024
S2.11H LEVEL 1 & ROOF PLANS - HALLWAY 3/28/2024
S2.11M LEVEL 1 FOUNDATION PLAN - MUSIC SUITES 3/28/2024
S2.11N LEVEL 1 FOUNDATION PLAN - AUDITORIUM 3/28/2024
S2.12A LEVEL 2 FRAMING PLAN - NEW BUILDING SOUTH 3/28/2024
S2.12C LEVEL 2 FRAMING PLAN - NEW BUILDING NORTH 3/28/2024
S2.12M ROOF PLAN - MUSIC SUITES 3/28/2024
S2.12N ROOF PLAN - AUDITORIUM 3/28/2024
S2.13A LEVEL 3 FRAMING PLAN - NEW BUILDING SOUTH 3/28/2024
S2.13C LEVEL 3 FRAMING PLAN - NEW BUILDING NORTH 3/28/2024
S2.14A ROOF PLAN - NEW BUILDING SOUTH 3/28/2024
S2.14C ROOF PLAN - NEW BUILDING NORTH 3/28/2024
S3.01 FOUNDATION SECTIONS AND DETAILS 3/28/2024
S3.02 FOUNDATION SECTIONS AND DETAILS 3/28/2024
S4.01 NEW BUILDING NORTH COLUMN SCHEDULE 3/28/2024
S4.02 NEW BUILDING SOUTH STEEL COLUMN SCHEDULE 3/28/2024
S4.03 AUDITORIUM STEEL COLUMN SCHEDULE 3/28/2024
S4.04 AUDITORIUM STEEL COLUMN SCHEDULE 3/28/2024
S4.05 BRACED FRAME TYPICAL DETAILS 3/28/2024
S4.06 BRACED FRAME ELEVATIONS 3/28/2024
S5.00 SECTIONS AND DETAILS 3/28/2024
S6.00 NEW BUILDING CANOPIES 3/28/2024
MECHANICAL
M0.01 HVAC GENERAL NOTES & LEGEND 3/28/2024
M1.01 HVAC DEMO WORK - LEVEL 1 - AREA A 3/28/2024
M1.02 HVAC DEMO WORK - LEVEL 1 - AREA B 3/28/2024
M1.03 HVAC DEMO WORK - LEVEL 1 - AREA C 3/28/2024
M1.04 HVAC DEMO WORK - LEVEL 1 - AREA D 3/28/2024
M1.05 HVAC DEMO WORK - LEVEL 1 - AREA E 3/28/2024
M1.06 HVAC DEMO WORK - LEVEL 1 - AREA F 3/28/2024
M1.07 HVAC DEMO WORK - LEVEL 1 - AREA G 3/28/2024
M1.08 HVAC DEMO WORK - LEVEL 1 - AREA H 3/28/2024
M1.09 HVAC DEMO WORK - LEVEL 1 - AREA J 3/28/2024
M1.10 HVAC DEMO WORK - MEZZANINE - AREA J 3/28/2024
M1.11 HVAC DEMO WORK - LEVEL 1 - AREA K 3/28/2024
M1.12 HVAC DEMO WORK - LEVEL 1 - AREA L 3/28/2024
M1.13 HVAC DEMO WORK - LOW ROOF - AREA A, B, & C 3/28/2024
M1.14 HVAC DEMO WORK - LOW ROOF - AREA D & E 3/28/2024
M1.15 HVAC DEMO WORK - LOW ROOF - AREA F, G, H 3/28/2024
M1.16 HVAC DEMO WORK - MID ROOF - AREA J, K, & L 3/28/2024
M1.17 PIPING DEMO WORK - LEVEL 1 - AREA A 3/28/2024
M1.18 PIPING DEMO WORK - LEVEL 1 - AREA B 3/28/2024
M1.19 PIPING DEMO WORK - LEVEL 1 - AREA C 3/28/2024
M1.20 PIPING DEMO WORK - LEVEL 1 - AREA D 3/28/2024
M1.21 PIPING DEMO WORK - LEVEL 1 - AREA E 3/28/2024
M1.22 PIPING DEMO WORK - LEVEL 1 - AREA F 3/28/2024
M1.23 PIPING DEMO WORK - LEVEL 1 - AREA G 3/28/2024
M1.24 PIPING DEMO WORK - LEVEL 1 - AREA H 3/28/2024
M2.01 HVAC NEW WORK - LEVEL 1 - AREA A 3/28/2024
M2.02 HVAC NEW WORK - LEVEL 1 - AREA B 3/28/2024
M2.03 HVAC NEW WORK - LEVEL 1 - AREA C 3/28/2024
M2.04 HVAC NEW WORK - LEVEL 1 - AREA D 3/28/2024
M2.05 HVAC NEW WORK - LEVEL 1 - AREA E 3/28/2024
6 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
M2.06 HVAC NEW WORK - LEVEL 1 - AREA F 3/28/2024
M2.07 HVAC NEW WORK - LEVEL 1 - AREA G 3/28/2024
M2.08 HVAC NEW WORK - LEVEL 1 - AREA H 3/28/2024
M2.09 HVAC NEW WORK - LEVEL 1 - AREA J 3/28/2024
M2.10 HVAC NEW WORK - MEZZANINE - AREA J 3/28/2024
M2.11 HVAC NEW WORK - LEVEL 1 - AREA K 3/28/2024
M2.12 HVAC NEW WORK - LEVEL 1 - AREA L 3/28/2024
M2.13 HVAC NEW WORK - LEVEL 1 - AREA M 3/28/2024
M2.14 HVAC NEW WORK - LEVEL 1 - AREA N 3/28/2024
M2.15 HVAC NEW WORK - LEVEL 2 - AREA A 3/28/2024
M2.16 HVAC NEW WORK - LEVEL 2 - AREA B 3/28/2024
M2.17 HVAC NEW WORK - LEVEL 2 - AREA C 3/28/2024
M2.18 HVAC NEW WORK - LEVEL 3 - AREA A 3/28/2024
M2.19 HVAC NEW WORK - LEVEL 3 - AREA B 3/28/2024
M2.20 HVAC NEW WORK - LEVEL 3 - AREA C 3/28/2024
M2.21 HVAC NEW WORK - HIGH ROOF - AREA A, B, & C 3/28/2024
M2.22 HVAC NEW WORK - LOW ROOF - AREA D & E 3/28/2024
M2.23 HVAC NEW WORK - LOW ROOF - AREA F, G, & H 3/28/2024
M2.24 HVAC NEW WORK - MID ROOF - AREA J, K, & L 3/28/2024
M2.25 HVAC NEW WORK - MID ROOF - AREA M & N 3/28/2024
M3.01 PIPING NEW WORK - LEVEL 1 - AREA A 3/28/2024
M3.02 PIPING NEW WORK - LEVEL 1 - AREA B 3/28/2024
M3.03 PIPING NEW WORK - LEVEL 1 - AREA C 3/28/2024
M3.04 PIPING NEW WORK - LEVEL 1 - AREA D 3/28/2024
M3.05 PIPING NEW WORK - LEVEL 1 - AREA E 3/28/2024
M3.06 PIPING NEW WORK - LEVEL 1 - AREA F 3/28/2024
M3.07 PIPING NEW WORK - LEVEL 1 - AREA G 3/28/2024
M3.08 PIPING NEW WORK - LEVEL 1 - AREA H 3/28/2024
M3.09 PIPING NEW WORK - LEVEL 1 - AREA J 3/28/2024
M3.10 PIPING NEW WORK - LEVEL 1 - AREA K 3/28/2024
M3.11 PIPING NEW WORK - LEVEL 1 - AREA L 3/28/2024
M3.12 PIPING NEW WORK - LEVEL 1 - AREA M 3/28/2024
M3.13 PIPING NEW WORK - LEVEL 2 - AREA A 3/28/2024
M3.14 PIPING NEW WORK - LEVEL 2 - AREA B 3/28/2024
M3.15 PIPING NEW WORK - LEVEL 2 - AREA C 3/28/2024
M3.16 PIPING NEW WORK - LEVEL 3 - AREA A 3/28/2024
M3.17 PIPING NEW WORK - LEVEL 3 - AREA B 3/28/2024
M3.18 PIPING NEW WORK - LEVEL 3 - AREA C 3/28/2024
M4.01 HVAC DETAILS 3/28/2024
M4.02 HVAC DETAILS 3/28/2024
M4.03 HVAC DETAILS 3/28/2024
M4.05 HVAC LARGE SCALE PLANS 3/28/2024
M5.01 HVAC SCHEDULES 3/28/2024
M5.02 HVAC SCHEDULES 3/28/2024
M6.01 HVAC CONTROLS 3/28/2024
M6.02 HVAC CONTROLS 3/28/2024
M6.03 HVAC CONTROLS 3/28/2024
M6.04 HVAC CONTROLS 3/28/2024
M6.05 HVAC CONTROLS 3/28/2024
PLUMBING
P0.01 PLUMBING NOTES & SCHEDULES 3/28/2024
P0.02 PLUMBING DETAILS 3/28/2024
P0.03 PLUMBING DETAILS 3/28/2024
P1.00-1 PLUMBING OVERALL DEMOLITION PLAN - LEVEL 1 3/28/2024
P1.01 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA A 3/28/2024
7 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
P1.02 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA B 3/28/2024
P1.03 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA C 3/28/2024
P1.04 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA D 3/28/2024
P1.05 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA E 3/28/2024
P1.06 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA F & G 3/28/2024
P1.07 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA H 3/28/2024
P1.08 PLUMBING DEMOLITION PLAN - LEVEL 1 - AREA J, K & L 3/28/2024
P1.09 PLUMBING DEMOLITION PLAN - ROOF - AREA A, B & C 3/28/2024
P1.10 PLUMBING DEMOLITION PLAN - ROOF - AREA D & E 3/28/2024
P1.11 PLUMBING DEMOLITION PLAN - ROOF - AREA F, G & H 3/28/2024
P1.12 PLUMBING DEMOLITION PLAN - ROOF - AREA J, K & L 3/28/2024
P2.00-1 PLUMIBNG OVERALL NEW WORK PLAN - LEVEL 1 3/28/2024
P2.01 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA A 3/28/2024
P2.02 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA B 3/28/2024
P2.03 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA B 3/28/2024
P2.04 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA C 3/28/2024
P2.05 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA D 3/28/2024
P2.06 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA E 3/28/2024
P2.07 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA F & G 3/28/2024
P2.08 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA H 3/28/2024
P2.09 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA J, K & L 3/28/2024
P2.10 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA M 3/28/2024
P2.11 PLUMBING NEW WORK PLAN - LEVEL 1 - AREA N 3/28/2024
P2.12 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA A 3/28/2024
P2.13 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA B 3/28/2024
P2.14 PLUMBING NEW WORK PLAN - LEVEL 2 - AREA C 3/28/2024
P2.15 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA A 3/28/2024
P2.16 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA B 3/28/2024
P2.17 PLUMBING NEW WORK PLAN - LEVEL 3 - AREA C 3/28/2024
P2.18 PLUMBING NEW WORK PLAN - ROOF - AREA A, B & C 3/28/2024
P2.19 PLUMBING NEW WORK PLAN - ROOF - AREA D & E 3/28/2024
P2.20 PLUMBING NEW WORK PLAN - ROOF - AREA F, G & H 3/28/2024
P2.21 PLUMBING NEW WORK PLAN - ROOF - AREA M & N 3/28/2024
P3.01 PLUMBING PART PLANS - KITCHEN DRAINAGE 3/28/2024
P3.02 PLUMBING PART PLANS - KITCHEN SUPPLY 3/28/2024
P3.03 PLUMBING PART PLANS - AREA A 3/28/2024
P3.04 PLUMBING PART PLANS - AREA B 3/28/2024
P3.05 PLUMBING PART PLANS - AREA C 3/28/2024
FIRE PROTECTION
FP0.01 FIRE PROTECTION NOTES & DETAILS 3/28/2024
FP1.00 FIRE PROTECTION OVERALL PLAN 3/28/2024
FP2.01 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA A, B, D & E 3/28/2024
FP2.02 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA J, K & L 3/28/2024
FP2.03 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA C, F, G & H 3/28/2024
FP2.04 FIRE PROTECTION NEW WORK PLAN - LEVEL 1 - AREA M & N 3/28/2024
FP2.11 FIRE PROTECTION NEW WORK PLAN - LEVEL 2 - AREA A, B & C 3/28/2024
FP2.12 FIRE PROTECTION NEW WORK PLAN - LEVEL 3 - AREA A, B & C 3/28/2024
ELECTRICAL
E1.00 ELECTRICAL LEGEND, NOTES, SCHEDULES AND DETAILS 3/28/2024
E3.11A ELECTRICAL LIGHTING PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E3.11B ELECTRICAL LIGHTING PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E3.11C ELECTRICAL LIGHTING PLAN – LEVEL 1 – NEW ADDITION NORTH 3/28/2024
E3.11D ELECTRICAL LIGHTING PLAN – LEVEL 1 – 100 WING 3/28/2024
E3.11E ELECTRICAL LIGHTING PLAN – LEVEL 1 – 200 WING 3/28/2024
E3.11F ELECTRICAL LIGHTING PLAN – LEVEL 1 – 300/400 WING 3/28/2024
8 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
E3.11H ELECTRICAL LIGHTING PLAN – LEVEL 1 – CTAE WING 3/28/2024
E3.11J ELECTRICAL LIGHTING PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E3.11K ELECTRICAL LIGHTING PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E3.11M ELECTRICAL LIGHTING PLAN – LEVEL 1 – MUSIC SUITE 3/28/2024
E3.11N ELECTRICAL LIGHTING PLAN – LEVEL 1 – AUDITORIUM 3/28/2024
E3.12A ELECTRICAL LIGHTING PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E3.12B ELECTRICAL LIGHTING PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E3.13A ELECTRICAL LIGHTING PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E3.13B ELECTRICAL LIGHTING PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E3.21 ELECTRICAL ENLARGED LIGHTING PLANS 3/28/2024
E4.11A ELECTRICAL POWER PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E4.11B ELECTRICAL POWER PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E4.11C ELECTRICAL POWER PLAN – LEVEL 1 – NEW ADDITION NORTH 3/28/2024
E4.11D ELECTRICAL POWER PLAN – LEVEL 1 – 100 WING 3/28/2024
E4.11E ELECTRICAL POWER PLAN – LEVEL 1 – 200 WING 3/28/2024
E4.11F ELECTRICAL POWER PLAN – LEVEL 1 – 300/400 WING 3/28/2024
E4.11H ELECTRICAL POWER PLAN – LEVEL 1 – CTAE WING 3/28/2024
E4.11J ELECTRICAL POWER PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E4.11K ELECTRICAL POWER PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E4.11M ELECTRICAL POWER PLAN – LEVEL 1 – MUSIC SUITE 3/28/2024
E4.11N ELECTRICAL POWER PLAN – LEVEL 1 – AUDITORIUM 3/28/2024
E4.12A ELECTRICAL POWER PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E4.12B ELECTRICAL POWER PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E4.13A ELECTRICAL POWER PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E4.13B ELECTRICAL POWER PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E5.11A ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E5.11B ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E5.11C ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – NEW ADDITION NORTH 3/28/2024
E5.11D ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – 100 WING 3/28/2024
E5.11E ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – 200 WING 3/28/2024
E5.11F ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – 300/400 WING 3/28/2024
E5.11H ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – CTAE WING 3/28/2024
E5.11J ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E5.11K ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E5.11M ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – MUSIC SUITE 3/28/2024
E5.11N ELECTRICAL HVAC/PLUMB PLAN – LEVEL 1 – AUDITORIUM 3/28/2024
E5.12A ELECTRICAL HVAC/PLUMB PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E5.12B ELECTRICAL HVAC/PLUMB PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E5.13A ELECTRICAL HVAC/PLUMB PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E5.13B ELECTRICAL HVAC/PLUMB PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E6.11A ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E6.11B ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – NEW ADDITION SOUTH 3/28/2024
E6.11C ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – NEW ADDITION NORTH 3/28/2024
E6.11D ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – 100 WING 3/28/2024
E6.11E ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – 200 WING 3/28/2024
E6.11F ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – 300/400 WING 3/28/2024
E6.11H ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – CTAE WING 3/28/2024
E6.11J ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E6.11K ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – GYMNASIUM 3/28/2024
E6.11M ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – MUSIC SUITE 3/28/2024
E6.11N ELECTRICAL LOW VOLTAGE PLAN – LEVEL 1 – AUDITORIUM 3/28/2024
E6.12A ELECTRICAL LOW VOLTAGE PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E6.12B ELECTRICAL LOW VOLTAGE PLAN – LEVEL 2 – NEW ADDITION SOUTH 3/28/2024
E6.13A ELECTRICAL LOW VOLTAGE PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
E6.13B ELECTRICAL LOW VOLTAGE PLAN – LEVEL 3 – NEW ADDITION SOUTH 3/28/2024
9 of 10
List of Drawings, Specifications, and Addenda
DESCRIPTION DATED
SPECIFICATIONS
GA DOE Preliminary Review Narrative prepared by Cooper Carry dated November 17, 2023
10 of 10
Cross Keys High School 4/8/2024
Attachment 1 - Allowances Log
Value
1 Utilities Demolition $ 200,000.00
2 Storm Sewer Replacement $ 1,500,000.00
3 Underground Detention System $ 1,500,000.00
4 Roof Leaders $ 150,000.00
5 Sanitary Sewer $ 450,000.00
6 Water & Fire $ 450,000.00
7 Rock & Unsuitable Soils $ 1,000,000.00
8 Striping & Signage $ 15,000.00
9 Plumbing Underground for Classroom Addition $ 731,368.00
10 HVAC Equipment for Classroom Addition $ 2,354,785.00
11 Electrical Underground and Switchgear for Classroom Addition $ 1,801,007.00
12 Modular Classrooms $ 1,275,600.00
13 Plumbing Underground for Performing Arts Addition $ 173,279.00
14 HVAC Equipment for Performing Arts Addition $ 624,644.00
15 Electrical Underground and Switchgear for Performing Arts Addition $ 480,040.00
Cross Keys High School
Enabling, Sitework, and Initial Structure GMP
Attachment 2 – Assumptions and Clarifications
April 8, 2024
1. General
1.1 The Enabling, Sitework, and Initial Structure GMP is based on the Design Development
documents dated March 28, 2024 by Cooper Carry.
1.2 The Enabling, Sitework, and Initial Structure GMP includes estimated monies for the
following work: grading and utilities, asphalt paving, curb & gutter, site retaining walls,
concrete paving and sidewalks, classroom addition concrete, CMU, and structural steel,
below grade waterproofing, hollow metal door frames, food service equipment,
plumbing underground rough-in, HVAC equipment, electrical underground rough-in, bus
drop-off canopy, performing arts addition concrete, CMU, and structural steel, below
grade waterproofing, hollow metal door frames, food service equipment, plumbing
underground rough-in, HVAC equipment, electrical underground rough-in, and
temporary modular classrooms.
1.3 A construction contingency of 5% is included.
1.4 A design contingency of 5% is included.
1.5 We have not included builders risk insurance for the existing school.
1.6 We have not included any costs for building permit fees, water meter and tap fees or
impact fees.
1.7 The Structure GMP does not include the following:
a) Building permit fees
b) NPDES filing fees
c) Tree Survey
d) Water meter and tap fees
e) Impact fees
f) Testing & inspection including NPDES monitoring
g) Landscaping
h) Fencing
i) Athletic Field Improvements
j) Demolition of the existing school
k) Asbestos abatement or other hazardous remediation
Page 1 of 1
Attachment 3 - Cross Keys High School Addition and Modernization Schedule
Jun 1 - Jul 31
P1 - Enabling / Bus Drop-off
Aug 1 - Nov 25
P2 - New 3 Story Building
Aug 1 - Oct 1
P2.1 - New Auditorium
Jun 1 - Jul 31
P3 - Classroom Wing Renovation 1
Jun 1 - Jul 31
P3.1 - Classroom Wing Renovation 2
Dec 15 - Jan 3
Move
Jan 5 - May 1
P4 - Demo of Admin, Media, Cafeteria, Special Ed
May 4 - May 3
P5 - 3 Story Connection
Jun 1 - Aug 1
P6 - Resurface Track and Resod Field
Jun 1 - Aug 1
P6.1 - Classroom Wing Renovation 3 & 4
Jun 1 - Aug 1
P6.2 - Gym Renovation
2024 2025 2026 2027
Jun Sep Dec Mar Jun Sep Dec Mar Jun Sep Dec Mar 2027
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
GENERAL NOTES - SITE PLAN
A.
B.
REFER TO CIVIL DRAWINGS FOR LIMITS OF CONSTRUCTION.
REFER TO CIVIL DRAWINGS FOR SITE DEMOLITION, GRADING & DRAINAGE, PAVING DIMENSIONS,
COOPER CARRY
THE CENTER FOR CONNECTIVE ARCHITECTURE
UTILITY EXTENSIONS AND CONNECTIONS.
C. REFER TO LANDSCAPE ARCHITECTURAL DRAWINGS FOR GROUNDCOVER, PLANTING AND 191 Peachtree Street NE
IRRIGATION.
Suite 2400
P
P
D. REFER TO ELECTRICAL DRAWINGS FOR EXTERIOR AND SITE LIGHTING. Atlanta, GA 30303-1770
(404) 237-2000
coopercarry.com
KEYED NOTES - SITE PLAN
1. NEW ASPHALT BUS DROP-OFF; REFER TO CIVIL DRAWINGS. ©2023 COOPER CARRY
2. NEW ASPHALT PARENT DROP-OFF; REFER TO CIVIL DRAWINGS.
SCOPE DOCUMENTS
N
N
3. NEW SITE RETAINING WALL; REFER TO CIVIL AND STRUCTURAL DRAWINGS.
The Contract Documents Issued for [Conceptual Design, Schematic
4. NEW ASPHALT PARKING LOT; REFER TO CIVIL DRAWINGS. Design, Design Development, Partial Construction Documents or Other
Issuance up to Issued for Construction] are intended to be at that level of
5. EXISTING COURTYARDS TO BE REMODELED; REFER TO CIVIL AND LANDSCAPE DRAWINGS. development and as such, may be neither complete nor coordinated. The
[Construction Manager, Contractor, Design/Builder] is responsible for
6. EXISTING TRACK AND FIELD TO BE RESURFACED; REFER TO CIVIL AND LANDSCAPE DRAWINGS. complete and coordinated pricing [and execution] of the Work, and shall
include items necessary for the proper execution and completion of the
7. NEW TURF PRACTICE FIELD. REFER TO CIVIL AND LANDSCAPE DRAWINGS. Work, as shown, specified, reasonably inferred or required for a complete
Project. For Work of delegated designs; systems, assemblies,
8. NEW CONCRETE JROTC PRACTICE PAD; REFER TO CIVIL DRAWINGS. components and materials shall comply with national, state and local code
NORTH CLIFF VALLEY W AY requirements. The [Construction Manager, Contractor, Design/Builder]
9. NEW CONCRETE TENNIS COURTS; REFER TO CIVIL DRAWINGS. shall inform the Owner and Architect, in timely fashion, of any discovered
M
M
omissions, inconsistencies or errors in the Contract Documents.
10. NEW ASPHALT SERVICE DRIVE AND TURN-AROUND; REFER TO CIVIL DRAWINGS.
11. NEW UNDERGROUND STORMWATER DENTENTION SYSTEM; REFER TO CIVIL DRAWINGS.
STOP
ROAD
12. NEW PREFABRICATED ALUMINUM CANOPY; REFER TO STRUCTURAL DRAWINGS.
ISSUANCES
3 STOP
No. Drawing Issue Description Date
NEW LOADING DOCK
LEGEND 1
2
SCHEMATIC DESIGN
GA DOE PRELIMINARY PLANS
10/31/2023
11/17/2023
& SERVICE YARD EXISTING PARKING
R 36.0'
3 DESIGN DEVELOPMENT 03/28/2024
99 SPACES
L
L
180.0'
R 240.0
NEW PARENT
'
EXISTING BUILDING TO REMAIN
DROP-OFF
2
P6
VAN
NEW BUILDING ADDITION
'
R 120.0
NEW PARKING
58 SPACES
VAN
STOP
180.0'
P2 4
R540.0
'
STOP
LS
GROSS BUILDING AREAS
K
K
HIL
P6.1 EXISTING
400 WING
Name Area
100 WING 20,347 SF
P4 - 200 WING 19,239 SF
P1
EXISTING 3
CTAE WING 300 WING 16,311 SF
400 WING 7,591 SF
Demo COURTYARD
CTAE WING 32,281 SF
D
5
UI
GYMNASIUM 41,546 SF
J
J
DR
EXISTING/RENOVATION 137,316 SF
& COURTYARD
5
3 AUDITORIUM & MUSIC SUITES 33,759 SF
P6.1 EXISTING
300 WING
LEVEL 1
LEVEL 2
64,729 SF
20,709 SF
P1
6 -F
TF
P5 - LEVEL 3 28,330 SF
UT
UR
ES
/W
COURTYARD
EXISTING TRACK NEW CONSTRUCTION 147,527 SF
& PRACTICE FIELD
TH
5 TOTAL GROSS BUILDING AREA 284,843 SF
Build
R
H
H
7
O
N
COURTYARD
5
P1
EXISTING PARKING
14 SPACES
COURTYARD
P3.1 EXISTING
G
G
200 WING
5
P2.1 P1 11
H
G
NEW BUS COURTYARD
DROP-OFF
5 F
1 C N
CU
P3
EXISTING
F
F
RT 100 WING
3
M
IS B E
DR
IV
E K
A D J
12 L
10
EXISTING PARKING FUTURE
41 SPACES FIELD
HOUSE
P1
E
E
3
8
EXISTING 9
CROSS KEYS HIGH SCHOOL
P6.2 GYMNASIUM
Facility Code: 644-4054-1165.01
D
D
DCSD Project Number: 214-35
EXISITING FTE: 1776 PROPOSED FTE: 1400
Autodesk Docs://20220185 - Cross Keys High School/20220185_2023_CKHS_arch.rvt
VAN
VAN
EXISTING IUs: 64 PROPOSED IUs: 74
VAN
EXISTING AREA: 167,167 GSF PROPOSED AREA: 283,664 GSF
VAN
3
4 NEW PARKING
94 SPACES
1626 NORTH DRUID HILLS ROAD
ATLANTA, GA 30319
♦
C
C
DEKALB CO. SCHOOL DISTRICT
PROJECT NUMBER: 20220185 PROJECT NAME: CROSS KEYS HIGH SCHOOL
STOP
10
ARCHITECTURAL SITE PLAN
EXISTING PARKING
27 SPACES
SHEET NUMBER: A1.00 - ARCHITECTURAL SITE PLAN
B
B
SOPHIA TARKHAN 20220185
Principal-in-Charge Project No.
03/28/2024
Project Designer Date
3/28/2024 10:22:26 AM
CHRISSY PEREZ
N Project Architect
JOHN BITTINGER
Architect
A1.00
A
A
JENNY PARK
1 ARCHITECTURAL SITE PLAN Staff Architect / Designer
A1.00 SCALE: 1" = 50'-0"
EVONNE CONNALLY
Staff Interior Architect Drawing No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 NOT ISSUED FOR CONSTRUCTION
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Initial GMP Summary
Summary Sheet Total $
1 Sitework Subtotal $ 10,861,737
2 Athletics Subtotal $ -
3 3 Story Addition Subtotal $ 24,648,548
4 Performing Arts Subtotal $ 7,248,859
5 Gym Renovation Subtotal $ -
6 Classroom Renovation Subtotal $ 127,688
7 CTAE Renovation Subtotal $ -
8 Modular Classrooms $ 1,532,244
PROJECT TOTAL $ 44,419,077
Page 1 of 8
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Sitework Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Demolition
Curb & Gutter 2,338 LF $ 10.00 $ 23,380.00
Asphalt Paving 28,251 SF $ 3.00 $ 84,753.00
Sidewalks 35,060 SF $ 3.00 $ 105,180.00
Utilities 1 ALLW $ 200,000.00 $ 200,000.00
Retaining Walls 123 LF $ 150.00 $ 18,450.00
Tennis Courts 12,362 SF $ 3.00 $ 37,086.00
Fencing 770 LF $ 10.00 $ 7,700.00
Modulars 12 EA $ 15,000.00 $ 180,000.00
Miscellaneous 1 LS $ 250,000.00 $ 250,000.00
Grading
Erosion & Sedimentation Control 12 Acres $ 13,045.66 $ 150,025.09
Clearing 1.54 Acres $ 20,000.00 $ 30,800.00
Sidewalks 13,668 SF $ 3.00 $ 41,004.00
Mass Grading Included
Strip Topsoil 2,930 CY $ 14.00 $ 41,020.00
Export Excess 1,953 CY $ 35.00 $ 68,366.67
Cut Fill 18,553 CY $ 10.00 $ 185,533.33
Fine Grade 288,746 SF $ 1.25 $ 360,932.50
Respread Topsoil 977 CY $ 10.00 $ 9,766.67
Backfill Foundation Walls / Retaining Walls 1,738 CY $ 55.00 $ 95,608.33
Import 1,245 CY $ 35.00 $ 43,586.67
Storm Sewer 1 ALLW $ 1,500,000.00 $ 1,500,000.00
Underground Detention System 1 ALLW $ 1,500,000.00 $ 1,500,000.00
Roof Leaders 1 ALLW $ 150,000.00 $ 150,000.00
Sanitary Sewer 1 ALLW $ 450,000.00 $ 450,000.00
Water & Fire 1 ALLW $ 450,000.00 $ 450,000.00
Water Meter By Owner
Tap Fees By Owner
Impact Fees By Owner
Rock & Unsuitable Soils 1 ALLW $ 1,000,000.00 $ 1,000,000.00
NPDES Monitoring 39 Mos $ 500.00 $ 19,500.00
Asphalt Paving
Light Duty 6,937 SY $ 45.00 $ 312,165.00
Heavy Duty 1,991 SY $ 55.00 $ 109,505.00
Sealcoat Existing 4,049 SY $ 4.00 $ 16,196.00
Curb & Gutter
Curb & Gutter 5,559 LF $ 22.00 $ 122,298.00
Roll Curb 35 LF $ 22.00 $ 770.00
Fences & Gates (Partial Fencing Allowance) 1,115 LF $ 60.00 $ 30,000.00
Gates Included
Hardscapes
Concrete Paving 14,880 SF $ 20.00 $ 297,600.00
Sidewalks 22,580 SF $ 3.00 $ 67,740.00
Auditorium Sidewalk 9,615 SF $ 5.00 $ 48,075.00
HC Ramps 5 EA $ 1,000.00 $ 5,000.00
Page 2 of 8
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Sitework Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
HD Conc. Loading Dock Paving 4,265 SF $ 18.50 $ 78,902.50
Loading Dock & Ramp 1,110 SF $ 18.50 $ 20,535.00
Site Stairs 993 LF $ 85.00 $ 84,405.00
JROTC Practice Pad 6,335 SF $ 8.00 $ 50,680.00
Concrete Site Retaining Walls 7,554 SF $ 75.00 $ 566,550.00
Pavement Striping & Signage (Bus Loop and Street Parking) 322 Spaces $ 144.00 $ 15,000.00
Sitework Total $ 8,828,113.76
General Conditions $ 305,941.00
General Requirements $ 37,982.00
Builders Risk Insurance $ 12,712.48
Liability Insurance $ 15,531.08
Subcontractor Default Insurance $ 132,421.71
Payment & Performance Bonds $ 72,545.11
Construction Manager's Fee $ 371,294.12
Total $ 9,776,541.25
Contingency
Design (5%) $ 488,827.06
Construction (5%) $ 488,827.06
Subtotal $ 10,754,195.38
Escalation (1%) $ 107,541.95
Total $ 10,861,737.33
Page 3 of 8
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
3 Story Addition Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Subsoil Termite Treatment 68,035 SF $ 0.05 $ 3,401.75 $ 0.03
Concrete Foundations & SOG 68,035 SF $ 25.00 $ 1,700,875.00 $ 13.81
Foundation Wall 6,906 SF $ 55.00 $ 379,830.00 $ 3.08
Elevated SOD 53,105 SF $ 13.09 $ 695,144.45 $ 5.65
Masonry
CMU Walls 142,974 SF $ 17.54 $ 2,507,763.96 $ 20.37
Structural & Misc. Metals 603 Tons $ 7,953.00 $ 4,793,790.05 $ 38.93
Joist & Deck 108 Tons $ 7,871.00 $ 848,084.51 $ 6.89
AESS 63 Tons $ 11,929.50 $ 752,751.45 $ 6.11
Stairs & Rails 7 Flights $ 30,000.00 $ 210,000.00 $ 1.71
Lobby Stair Premium 1 LS $ 35,700.00 $ 35,700.00 $ 0.29
Guardrails at Retaining Walls 719 LF $ 300.00 $ 215,700.00 $ 1.75
Waterproofing, Damproofing, and Caulking
Waterproofing
Elevator Pit 1 EA $ 2,500.00 $ 2,500.00 $ 0.02
Foundation Wall 6,906 SF $ 7.50 $ 51,795.00 $ 0.42
Doors, Frames, & Finish Hardware (Long Lead Items) 148 LVS $ 3,392.00 $ 125,504.00 $ 1.02
Parent Drop Off Canopy 1,069 SF $ 59.00 $ 63,071.00 $ 0.51
Food Service Equipment 1 LS $ 1,250,000.00 $ 1,250,000.00 $ 10.15
Plumbing (Underground Allowance) 123,126 SF $ 18.00 $ 731,368.44 $ 5.94
HVAC (Equipment Allowance) 123,126 SF $ 38.25 $ 2,354,784.75 $ 19.13
Test & Balance Included
Controls Included
Electrical (Underground & Switchgear Allowance) 123,126 SF $ 44.33 $ 1,801,006.97 $ 14.63
3 Story Addition Total $ 18,523,071.33 $ 150.44
General Conditions $ 1,962,381.00 $ 15.94
General Requirements $ 312,431.00 $ 2.54
Builders Risk Insurance $ 26,673.22 $ 0.22
Liability Insurance $ 31,488.98 $ 0.26
Subcontracor Default Insurance $ 277,846.07 $ 2.26
Payment & Performance Bonds $ 124,042.02 $ 1.01
Construction Manager's Fee $ 710,469.41 $ 5.77
Total $ 21,968,403.02 $ 178.42
Contingency
Design (5%) $ 1,098,420.15 $ 8.92
Construction (5%) $ 1,098,420.15 $ 8.92
Subtotal $ 24,165,243.32 $ 196.26
Page 4 of 8
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
3 Story Addition Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Escalation (2%) $ 483,304.87 $ 3.93
Total $ 24,648,548.18 $ 200.19
Page 5 of 8
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Performing Arts Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Subsoil Termite Treatment 36,921 SF $ 0.05 $ 1,846.05 $ 0.06
Concrete Foundations & SOG 36,921 SF $ 25.00 $ 923,025.00 $ 28.13
Masonry
CMU Walls 53,966 SF $ 17.54 $ 946,563.64 $ 28.84
Structural & Misc. Metals 112 Tons $ 7,953.00 $ 890,736.00 $ 27.14
Joist & Deck 82 Tons $ 7,871.00 $ 645,422.00 $ 19.67
AESS 20 Tons $ 11,929.50 $ 244,256.51 $ 7.44
Doors, Frames, & Finish Hardware (Long Lead Items) 21 LVS $ 3,392.00 $ 23,506.56 $ 0.72
Plumbing (Underground Allowance) 32,818 SF $ 16.00 $ 173,279.04 $ 5.28
HVAC (Equipment Allowance) 32,818 SF $ 38.25 $ 627,644.25 $ 19.13
Test & Balance Included
Controls Included
Electrical (Underground & Switchgear Allowance) 32,818 SF $ 44.33 $ 480,040.34 $ 14.63
Performing Arts Total $ 4,956,319.39 $ 151.02
General Conditions $ 1,161,959.00 $ 35.41
General Requirements $ 109,239.00 $ 3.33
Builders Risk Insurance $ 7,137.10 $ 0.22
Liability Insurance $ 9,158.10 $ 0.28
Subcontractor Default Insurance $ 74,344.79 $ 2.27
Payment & Performance Bonds $ 46,823.13 $ 1.43
Construction Manager's Fee $ 159,644.62 $ 4.86
Total $ 6,524,625.13 $ 198.81
Contingency $ -
Design (5%) $ 326,231.26 $ 9.94
Construction (5%) $ 326,231.26 $ 9.94
Subtotal $ 7,177,087.65 $ 218.69
Escalation (1%) $ 71,770.88 $ 2.19
Total $ 7,248,858.52 $ 220.88
Page 6 of 8
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Classroom Renovation Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Bus Loop Canopy 1,796 SF $ 59.00 $ 105,964.00 $ 1.71
Classroom Renovation Total $ 105,964.00 $ 1.71
General Conditions (None Included) $ -
General Requirements (None Included) $ -
Builders Risk Insurance $ 152.59 $ 0.00
Liability Insurance $ 1,174.42 $ 0.02
Subcontractor Default Insurance $ 1,589.46 $ 0.03
Payment & Performance Bonds $ 14,838.44 $ 0.24
Construction Manager's Fee $ 3,969.41 $ 0.06
Total $ 127,688.32 $ 2.06
Contingency
Design (5%) (None Included) $ -
Construction (5%) (None Included) $ -
Subtotal $ 127,688.32 $ 2.06
Escalation (5%) (None Included) $ -
Total $ 127,688.32 $ 2.06
Attachment 4 - Schedule of Values
Dekalb County Schools 4/8/2024
Cross Keys High School Modernization
Modulars Estimate
Trade Quantity UM Unit $ Total $ $/SqFt
Modulars
Setup 3 EA $ 288,400.00 $ 865,200.00
Rental 24 Mos $ 17,100.00 $ 410,400.00
Sitework Total $ 1,275,600.00
General Conditions $ -
General Requirements $ -
Builders Risk Insurance $ 1,836.86
Liability Insurance $ 3,099.64
Subcontractor Default Insurance $ 19,134.00
Payment & Performance Bonds $ 24,260.16
Construction Manager's Fee $ 55,227.12
Total $ 1,379,157.78
Contingency
Design (5%) $ 68,957.89
Construction (5%) $ 68,957.89
Subtotal $ 1,517,073.56
Escalation (1%) $ 15,170.74
Total $ 1,532,244.29
Page 8 of 8
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Sitework
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 147,306 $ 54,358 $ 201,664
Assistant Project Manager (100%) 30 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Engineer (100%) 12 Weeks $ -
Project Coordinator (100%) 12 Weeks $ -
Assistant Superintendent (100%) 18 Weeks $ -
Assistant Superintendent (100%) 13 Weeks $ -
Purchasing Agent (100%) 5 Weeks $ 1,920 $ 709 $ 13,143
Project Secretary (100%) 12 Weeks $ 720 $ 266 $ 11,828
Project Accountant (100%) 12 Weeks $ 1,750 $ 646 $ 28,749
Supervision Vehicles - Months $ 1,866 $ -
Superintendent Vehicle Fuel & Repair - Months $ 2,500 $ -
Superintendent Vehicle Insurance - Months $ 385 $ -
Safety Program & Inspections 1 LS $ 7,500 $ 7,500
Safety Signage 1 LS $ 4,000 $ 1,500 $ 6,500 $ 12,000
Drug Testing 1 LS $ 1,060 $ 1,060
Hard Hats & Safety Vests 1 LS $ 2,650 $ 2,650
Raingear & Boots 1 LS $ 636 $ 636
Eye & Ear Protection 1 LS $ 106 $ 106
Safety Harnesses and Lifelines 1 LS $ 1,605 $ 1,605
First Aid Supplies - Months $ 100 $ -
Office Trailer Rental - Months $ 2,250 $ -
Tool Trailer Rental - Months $ 250 $ -
Office Equipment - LS $ 5,000 $ -
Computer Equipment - LS $ 10,000 $ -
Project Software - Procore - Months $ 116,500 $ -
Office Supplies & Postage - Months $ 250 $ -
Office Furniture - LS $ 5,000 $ -
Drawings & Printing - LS $ 10,000 $ -
CAD Files - LS $ 5,000 $ -
Web Cam - OxBlue - Months $ 815 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 105 $ -
Closeout Documents & As-Builts - LS $ 3,500 $ -
Traffic Control/Flagman - Weeks $ 1,375 $ 507 $ -
Setup Field Office - LS $ 1,580 $ 583 $ 1,070 $ -
1 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Sitework
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Remove Field Office - LS $ 1,050 $ 387 $ 1,070 $ -
Setup Tool Trailer - LS $ 500 $ 185 $ 852 $ -
Remove Tool Trailer - LS $ 250 $ 92 $ -
Project Signs - LS $ 200 $ 74 $ 535 $ -
Radios - LS $ 2,500 $ 923 $ 4,770 $ -
Temp/Permanent Power & Gas - Months $ 4,825 $ -
Temporary Power - Months $ 648 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat - Months $ 4,253 $ -
Temporary Water - Months $ 343 $ -
Holding Tank - Months $ 300 $ -
Temporary Toilets - Months $ 962 $ -
Sanitary Supplies - Months $ 159 $ -
Ice, Cups, and Water - Months $ 159 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 1,274 $ -
-
Barricades 1 LS $ 25,000 $ 25,000
Protect New Work 1 LS $ - $ -
Ceremonies 1 LS $ - $ -
TOTAL $ 305,941
2 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Sitework
General Requirments Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers - EA $ 100 $ -
Temporary Fence 2,109 LF $ 5 $ 2 $ 6.24 $ 27,596
Continuous Cleanup - Weeks $ 1,862 $ 687 $ -
Dump Fees 18 Pulls $ 577 $ 10,386
Street Sweeper - Months $ 1,610 $ -
Skid Steer - Months $ 2,862 $ -
Equipment Rental - Months $ 2,100 $ -
Fuel & Lubricant - Months $ 250 $ -
Small Tools - Months $ 1,000 $ -
SF $ 0.35 $ -
TOTAL $ 37,982
3 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Three Story Classroom Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 869,882 $ 321,000 $ 1,190,882
Senior Project Manager (100%) 39 Weeks $ -
Project Manager (100%) 39 Weeks $ -
Assistant Project Manager (100%) 39 Weeks $ -
Assistant Project Manager (100%) 39 Weeks $ -
Project Engineer (100%) 39 Weeks $ -
Project Coordinator (100%) 39 Weeks $ -
Project Coordinator (100%) 39 Weeks $ -
General Superintendent (25%) 39 Weeks $ -
Project Superintendent (100%) 39 Weeks $ -
Assistant Superintendent (100%) 39 Weeks $ -
Assistant Superintendent (100%) 39 Weeks $ -
Surveyor (100%) 1 LS $ 50,000 $ 50,000
Purchasing Agent (100%) 26 Weeks 1920 $ 709 $ 68,341
Project Secretary (100%) 39 Weeks 720 $ 266 $ 38,442
Project Accountant (100%) 39 Weeks 1750 $ 646 $ 93,435
Supervision Vehicles 9 Months $ - $ 1,866 $ 16,794
Superintendent Vehicle Fuel & Repair 9 Months $ - $ 2,500 $ 22,500
Superintendent Vehicle Insurance 9 Months $ - $ 443 $ 3,985
Safety Program & Inspections 1 LS $ 7,500 $ 7,500
Safety Signage 1 LS $ 4,000 $ 1,500 $ 6,500 $ 12,000
Drug Testing 1 LS $ 1,060 $ 1,060
Hard Hats & Safety Vests 1 LS $ 2,650 $ 2,650
Raingear & Boots 1 LS $ 636 $ 636
Eye & Ear Protection 1 LS $ 106 $ 106
Safety Harnesses and Lifelines 1 LS $ 1,605 $ 1,605
First Aid Supplies 9 Months $ 100 $ 900
Office Trailer Rental 9 Months $ 2,250 $ 20,250
Tool Trailer Rental 9 Months $ 250 $ 2,250
Office Equipment 1 LS $ 5,000 $ 5,000
Computer Equipment 1 LS $ 10,000 $ 10,000
Project Software - Procore 1 LS $ 116,500 $ 116,500
Office Supplies & Postage 9 Months $ 250 $ 2,250
Office Furniture 1 LS $ 5,000 $ 5,000
Drawings & Printing 1 LS $ 10,000 $ 10,000
CAD Files 1 LS $ 5,000 $ 5,000
Web Cam - OxBlue 9 Months $ 815 $ 7,337
4 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Three Story Classroom Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Daily Photos - Cupix 9 Months $ 755 $ 6,799
Aerial Photograghy 9 Months $ 105 $ 945
Closeout Documents & As-Builts 1 LS $ 3,500 $ 3,500
Traffic Control/Flagman 39 Weeks $ 1,375 $ 507 $ 73,413
Setup Field Office 1 LS $ 1,580 $ 583 $ 1,070 $ 3,233
Remove Field Office 1 LS $ 1,050 $ 387 $ 1,070 $ 2,507
Setup Tool Trailer 1 LS $ 500 $ 185 $ 852 $ 1,537
Remove Tool Trailer 1 LS $ 250 $ 92 $ 342
Temporary Ladders 3 EA $ 200 $ 74 $ 535 $ 2,426
Project Signs 1 LS $ 2,500 $ 923 $ 4,770 $ 8,193
Radios 1 LS $ 3,500 $ 3,500
Temp/Permanent Power & Gas - Months $ 14,365 $ -
Temporary Power 9 Months $ 2,000 $ 18,000
Temporary Power Setup (Georgia Power) 1 LS $ 25,000 $ 25,000
Temporary Heat 4 Months $ 4,253 $ 17,012
Temporary Water 9 Months $ 500 $ 4,500
Holding Tank 9 Months $ 450 $ 4,050
Temporary Toilets 9 Months $ 1,250 $ 11,250
Sanitary Supplies 9 Months $ 200 $ 1,800
Ice, Cups, and Water 9 Months $ 200 $ 1,800
Telecom System & Installation (Internet) 1 LS $ 650 $ 650
Telecom Service (Internet & Cell Phones) 9 Months $ 2,500 $ 22,500
Barricades 1 LS $ 25,000 $ 25,000
Ceremonies 1 LS $ 30,000 $ 30,000
TOTAL $ 1,962,381
5 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Three Story Classroom Addition
General Requirments Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 25 EA $ 100 $ 2,463
Temporary Fence 1,274 LF $ 5 $ 2 $ 6.24 $ 16,670
Continuous Cleanup 39 Weeks $ 1,862 $ 687 $ 99,415
Dump Fees 53 Pulls $ 577 $ 30,391
Street Sweeper 9 Months $ 1,610 $ 14,490
Skid Steer 9 Months $ 2,862 $ 25,758
Equipment Rental 9 Months $ 2,100 $ 18,900
Fuel & Lubricant 9 Months $ 250 $ 2,250
Small Tools 9 Months $ 1,000 $ 9,000
Multivista 123,126 SF $ 0.35 $ 43,094
Protect New Work 1 LS $ 50,000 $ 50,000
TOTAL $ 312,431
6 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Performing Arts Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Project Team 1 LS $ 566,087 $ 208,895 $ 774,982
Senior Project Manager (100%) 39 Weeks
Project Manager (100%) 39 Weeks
Assistant Project Manager (100%) 39 Weeks
Project Engineer (100%) 39 Weeks
Project Engineer (100%) 39 Weeks
Project Coordinator (100%) 39 Weeks
General Superintendent (25%) 39 Weeks
Project Superintendent (100%) 39 Weeks
Assistant Superintendent (100%) 39 Weeks
Surveyor (100%) 1 LS $ 50,000 $ 50,000
Purchasing Agent (100%) 20 Weeks 1920 $ 709 $ 52,570
Project Secretary (100%) 39 Weeks 720 $ 266 $ 38,442
Project Accountant (100%) 39 Weeks 1750 $ 646 $ 93,435
Supervision Vehicles - Months $ 1,866 $ -
Superintendent Vehicle Fuel & Repair - Months $ 2,500 $ -
Superintendent Vehicle Insurance - Months $ 385 $ -
Safety Program & Inspections 1 LS $ 7,500 $ 7,500
Safety Signage 1 LS $ 4,000 $ 1,500 $ 6,500 $ 12,000
Drug Testing 1 LS $ 1,060 $ 1,060
Hard Hats & Safety Vests 1 LS $ 2,650 $ 2,650
Raingear & Boots 1 LS $ 636 $ 636
Eye & Ear Protection 1 LS $ 106 $ 106
Safety Harnesses and Lifelines 1 LS $ 1,605 $ 1,605
First Aid Supplies - Months $ 100 $ -
Office Trailer Rental - Months $ 2,250 $ -
Tool Trailer Rental - Months $ 250 $ -
Office Equipment - LS $ 5,000 $ -
Computer Equipment - LS $ 10,000 $ -
Project Software - Procore - Months $ 116,500 $ -
Office Supplies & Postage - Months $ 250 $ -
Office Furniture - LS $ 5,000 $ -
Drawings & Printing 1 LS $ 10,000 $ 10,000
CAD Files 1 LS $ 5,000 $ 5,000
Web Cam - OxBlue - Months $ 815 $ -
Daily Photos - Cupix - Months $ 755 $ -
Aerial Photograghy - Months $ 105 $ -
7 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Performing Arts Addition
General Conditions Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Closeout Documents & As-Builts 1 LS $ 3,500 $ 3,500
Traffic Control/Flagman - Weeks $ 1,375 $ 507 $ -
Setup Field Office - LS $ 1,580 $ 583 $ 1,070 $ -
Remove Field Office - LS $ 1,050 $ 387 $ 1,070 $ -
Setup Tool Trailer - LS $ 500 $ 185 $ 852 $ -
Remove Tool Trailer - LS $ 250 $ 92 $ -
Temporary Ladders 1 EA $ 200 $ 74 $ 535 $ 809
Project Signs 1 LS $ 2,500 $ 923 $ 4,770 $ 8,193
Radios - LS $ 3,500 $ -
Temp/Permanent Power & Gas 4 Months $ 14,365 $ 57,459
Temporary Power - Months $ 2,000 $ -
Temporary Power Setup (Georgia Power) - LS $ 25,000 $ -
Temporary Heat 4 Months $ 4,253 $ 17,012
Temporary Water - Months $ 500 $ -
Holding Tank - Months $ 450 $ -
Temporary Toilets - Months $ 1,250 $ -
Sanitary Supplies - Months $ 200 $ -
Ice, Cups, and Water - Months $ 200 $ -
Telecom System & Installation (Internet) - LS $ 650 $ -
Telecom Service (Internet & Cell Phones) - Months $ 2,500 $ -
Barricades 1 LS $ 25,000 $ 25,000
Ceremonies - LS $ 30,000 $ -
TOTAL $ 1,161,959
8 of 9
Attachement 5 - List of Itemized General Conditions
Cross Keys High School 4/8/2024
Performing Arts Addition
General Requirments Estimate
Qty Unit Labor Labor Burden Material Equipment Sub Total
Fire Extinguishers 7 EA $ 100 $ 656
Temporary Fence 924 LF $ 5 $ 2 $ 6.24 $ 12,091
Continuous Cleanup - Weeks $ 1,862 $ 687 $ -
Dump Fees 20 Pulls $ 577 $ 11,540
Street Sweeper 3 Months $ 1,610 $ 4,830
Skid Steer 3 Months $ 2,862 $ 8,586
Equipment Rental 3 Months $ 2,100 $ 6,300
Fuel & Lubricant 3 Months $ 250 $ 750
Small Tools 3 Months $ 1,000 $ 3,000
Multivista 32,818 SF $ 0.35 $ 11,486
Protect New Work 1 LS $ 50,000 $ 50,000
TOTAL $ 109,239
9 of 9