NCES_Exhibit M_3.12.2024

AID 1633874 · View on Simbli

Agenda Item

x. E-SPLOST V Project 35335 Nancy Creek Facility Major Building System Replacement Guaranteed Maximum Price Approval (Not to exceed $12,375,659) ~ Updated 5.2.2024

Summary: Presented by: Erick Hofstetter, Chief Operations Officer, Division of Operations
Request: It is requested that the Board of Education establish a Guaranteed Maximum Price of $12,375,659 for work included in the E-SPLOST V Nancy Creek Facility project per the terms set forth in the Construction Manager at Risk contract previously awarded to Balfour-Beatty.
Why: To amend the agreement with Balfour-Beatty for the work and to establish a Guaranteed Maximum Price (GMP) as $12,375,659.00.
Details: On December 11, 2023, the Board of Education approved the award of a Construction Management at Risk (CM@R) contract to Balfour Beatty for Pre-Construction Services in the amount of $50,000.00.

Pursuant to that agreement the Design Professional (SSOE), CM@R (Balfour Beatty), Program Manager (ACERM), and DCSD Operations have collaborated to generate a design, a safe construction phasing plan and a GMP in the best interest of the DeKalb County School District.

This action establishes a Phase I Guaranteed Maximum Price and Contract Time for all the Work set forth in the attached NCES_Exhibit M_03-12-24.
Financial impact: This project will be funded from E-SPLOST V Project 35335 - Nancy Creek Facility Major Building Systems Replacement. If approved, the construction cost code will require a budget reallocation of $5,371,073 from Program Contingency (SP5FACCON.35335.GENCONTR).
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678-676-1475

Mr. Hans Williams, Dir. Planning & E-SPLOST Programming, Division of Operations, 678-676-1588
Effective: Upon Board Approval
Status: Approved by General Counsel
                                                           EXHIBIT M
        GMP AMENDMENT TO AGREEMENT BETWEEN OWNER AND
                  CONSTRUCTION CONTRACTOR

             AMENDMENT NO. 1 TO AGREEMENT BETWEEN OWNER AND
           CONSTRUCTION CONTRACTOR FOR Nancy Creek School Facility Major Building Systems Replacement and Renovations
                         AGREEMENT NO. SP6CIP.24836.GENCONTR.1063
        Pursuant to Sections 4.B and 7.A of the Construction Management Agreement
 (“Agreement”), dated        1/18//2024 , between The School Board of DeKalb County, Georgia
 (“Owner”) and      Balfour Beatty

 (“Construction Contractor”), with respect to the construction of Owner’s
 Nancy Creek School Facility Major Building Systems Replacement and Renovations
                                                        (“Project”), Owner and Construction
 Contractor hereby agree to amend and modify the Agreement by this Amendment No. 1 and
 establish a Guaranteed Maximum Price and Contract Time for all the Work as set forth below. All
 capitalized terms not defined herein shall have the meaning ascribed to them in the Agreement,
 unless otherwise noted.

                                                             ARTICLE 1


                                                       SCOPE OF WORK
 The scope of the Work consists of the construction of a Major Building Systems Replacement
  and Renovation                                   , in accordance with the Agreement, this
 Amendment and the other Contract Documents listed as Attachments 1 through 7 below, which
 are hereby incorporated into and made a part of the Amendment by this reference:

Attachment No.                 Description                                        Pages                 Date

List of Drawings, Specifications and Addendums
1.                             Allowances                                           1 through _____
                                                                                  _____        1        3/12/2024

2.                             Assumptions and Clarifications                       2 through _____
                                                                                  _____        9        3/12/2024

3.                             Completion Schedule                                 10
                                                                                  _____          12
                                                                                        through _____   1/26/2024

4.                             Schedule of Values                                   13 through _____
                                                                                  _____         13      3/12/2024

5.                                                                   14 through _____
                               List of Itemized General Conditions _____          14                    2/28/2024

6.                             List of Subcontractors and                          15 through _____
                                                                                  _____        15       2/28/2024
                               Major Suppliers
7.                             Alternates                                           16 through _____
                                                                                  _____          16     3/12/2024




                                                                        M-1
                                                 ARTICLE 2


                                 GUARANTEED MAXIMUM PRICE


            2.1        Construction Contractor’s Guaranteed Maximum Price (“GMP”) for the Work,
including the estimated Cost of the Work as defined in Section 5 of the Agreement and the
Construction Management Fee as defined in Section 4 of the Agreement, is Twelve million, three hundred
seventy-five thousand, six hundred fifty nine dollars ($ 12,375,659 ).

        2.2   The Construction Management Fee for the entire Work anticipated on this Project
is hereby established as a lump sum amount of six hundred forty five thousand, one hundred seventy seven dollars
($_645,177.00 ), said lump sum amount is included within the above noted GMP.

        2.3     The general condition expenses for the entire Work anticipated on this Project are
hereby established as a lump sum amount of one million, one hundred ninety-three thousand, one hundred and five dollars
($ 1,193,105.00 ), said lump sum amount is included within the above noted GMP (“General
Conditions Expenses”). The items included as General Condition Expenses are listed in the List
of Itemized General Conditions attached hereto and incorporated herein as Attachment No. 5 .
Except as said lump sum amount for General Condition Expenses may be expressly adjusted by
Change Order or Construction Change Directive, Construction Contractor acknowledges and
agrees that Owner shall have no liability for any General Condition expenses beyond payment of
the above noted lump sum amount and Construction Contractor agrees that it shall not be entitled
to receive any additional compensation from Owner for the General Conditions beyond the above
lump sum amount. There shall be no additional General Conditions Expenses payable to
Construction Contractor on the first Five Hundred Thousand and No/100 Dollars ($500,000.00)
of Change Order or Construction Change Directive Work (i.e. the lump sum amount specified in
this Subsection includes consideration for up to $500,000.00 of Change Order and/or Construction
Change Directive Work). Further, there shall be no mark-up for a subcontractor’s General
Conditions expenses on the first One Hundred Thousand and No/100 Dollars ($100,000.00) of
Change Order and Construction Change Directive Work to be performed by such subcontractor.

       2.4    Monthly installment payment of the Construction Management Fee and the General
Condition Expenses shall be based upon the percent completion of the designated portion of the
Work for each particular month.

        2.5     In order to efficiently and timely address any unknown or unanticipated conditions
that are within the scope of the Work and are otherwise reimbursable without duplication as a Cost
of the Work, but excluding all items that are to be reimbursed under the lump sum General
Condition expense amount noted in Subsection 2.4 above, the parties have agreed to establish a
contingency within the GMP in an amount not-to-exceed amount of              zero               and
 0 /100 Dollars ($      0.00                ) (“Owner’s Contingency”). Owner’s Contingency
funds shall be used to cover costs that may result from incomplete design and unanticipated costs
that arise during construction that are not identified by the construction documents. Construction

                                                          M-2
Contractor shall not proceed with any portion of the Work which it intends to charge against the
Owner’s Contingency without first obtaining Owner’s express written authorization to proceed.
Construction Contractor acknowledges and agrees that any portion of the Work which is to be
charged against the Owner’s Contingency that does not receive such prior written approval from
Owner shall be deemed to be part of Construction Contractor’s Work compensated within the
GMP and not chargeable against Owner’s Contingency. Owner reserves the right, at its sole
discretion, to withhold its consent on Owner’s Contingency expenditures. Further, the work that
is the subject of any Owner’s Contingency expenditures shall be deemed part of the Work. The
GMP shall be reduced by unused Owner’s Contingency remaining at the completion of the Work.
Construction Contractor has no entitlement to any portion of any unused Owner’s Contingency.

                2.6     In order to efficiently and timely address any unknown or unanticipated
conditions that are within the scope of the Work and are otherwise reimbursable without
duplication as a Cost of the Work, but excluding all items that are to be reimbursed under the lump
sum General Condition expense amount noted in Subsection 2.4 above, the parties have agreed to
                                                                           six hundred sixty five thousand, six hundred seventy four
establish a contingency within the GMP in an amount not-to-exceed                                and         /100
Dollars ($665,674.00) (“Contractor’s Contingency”). Construction Contractor shall not proceed
with any portion of the Work which it intends to charge against the Contractor’s Contingency
without first obtaining Owner’s express written authorization to proceed. Construction Contractor
acknowledges and agrees that any portion of Work which is to be charged against the Contractor’s
Contingency that does not receive such prior written approval from Owner shall be deemed to be
part of Construction Contractor’s Work compensated within the GMP and not chargeable against
Contractor’s Contingency. Owner reserves the right, at its sole discretion, to withhold its consent
on Contractor’s Contingency expenditures. Further, the work that is the subject of any Owner’s
Contingency expenditures shall be deemed part of the Work. The GMP shall be reduced by unused
Contractor’s Contingency remaining at the completion of the Work. Construction Contractor has
no entitlement to any portion of any unused Contractor’s Contingency. Construction Contractor
shall be entitled to an increase in the Construction Management Fee in the amount of 5.5 % of
the Cost of the Work charged against the Contractor’s Contingency.

         2.7    The parties have agreed to Threeestablish       an allowance within the GMP for
                                                    hundred ninety-one thousand, seven
   miscellaneous allowances  in the amount of hundred sixty-eightand
                                                                  dollars /100 Dollars ($ 391,768.00 ).
Construction Contractor shall not proceed with any portion of the Work associated with the
aforesaid allowance (“Allowance Work”) without first obtaining Owner’s express written
authorization to proceed with said Allowance Work. Allowance Amounts are reflected in
Attachments 1 through . Unless otherwise provided in the Contract Documents: (a)
allowances amounts shall cover the cost to Construction Contractor of materials and equipment
delivered at the site and all required taxes, less applicable trade discounts; (b) Construction
Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit
and other expenses contemplated for stated allowance amounts shall be included in the GMP but
not in the allowances, unless otherwise stated in the allowance; and (c) whenever costs are more
than or less than allowances, the GMP shall be adjusted accordingly by Change Order.




                                                            M-3
                2.8     Pursuant to Subsection 12.3 of Exhibit A to the Agreement, if at the time final
     payment is made to Construction Contractor the total Cost of the Work has been increased by
     approved Change Orders in an amount causing the original GMP as set forth in this Amendment
     to be exceeded by more than five hundred thousand and      /100 Dollars ($ 500,000.00      ), then
     Construction Contractor shall be entitled to an increase in the Construction Management Fee in
     the amount of and /100 Dollars (                  5.5       %) of the amount exceeding the sum of
five hundred thousand and   /100 Dollars ($ 500,000.00 _) plus that original GMP amount.

          2.9     Construction Contractor recognizes that the Contract includes work for trench
  excavation in excess of five feet deep. Construction Contractor acknowledges the requirements
  set forth by all federal, state and local requirements. Construction Contractor certifies that the
  required trench safety standards will be in effect during the period of construction of the Project
  and Construction Contractor agrees to comply with all such required trench safety standards.

                 2.10.1 The amount of                     zero                 and /100         Dollars
  ($    0.00        ) has been separately identified for the cost of compliance with the required trench
  safety standards; said amount is included within the GMP.

          2.10 At the completion of the Work, should the actual amount of “General
  Requirements” expenses be less than the amount included therefor in the Schedule of Values
  approved by Owner, the resulting “savings” shall accrue to the benefit of Owner and a deductive
  Change Order or Construction Change Directive shall be issued reducing the GMP by the amount
  of such savings. For the avoidance of doubt, any savings obtained General Requirements expenses
  may not be moved to contingency or be used to offset cost overruns in other items within the GMP.
  Further, the line item for General Requirements expenses in the Schedule of Values constitutes a
  separate guaranteed maximum price for such expenses and any overruns in General Requirements
  expenses shall be borne by Construction Contractor without reimbursement from Owner.

          2.11 By executing this Amendment and furnishing Owner with a GMP based on a
  detailed Schedule of Values and a Master Project Schedule, Construction Contractor represents
  and warrants that the Contract Documents, including the Construction Documents, as well as other
  materials, and information furnished Construction Contractor as of the date of this Amendment
  have described the scope, construction requirements, and design intent of the Work in detail
  sufficient to enable Construction Contractor to establish firmly the GMP, Contract Time and the
  Project Schedule. To the extent that the Construction Documents are anticipated to require further
  development, Construction Contractor has provided in the GMP for such further development
  consistent with the Contract Documents and reasonably inferable therefrom.

          2.12 Savings will be computed as of the date of final completion of the Work and shall
  consist of the difference between (i) the Guaranteed Maximum Price (as it may be adjusted in
  accordance with the terms of the Contract Documents) and (ii) the total aggregate sum of the
  Cost of the Work plus the Construction Management Fee paid by Owner shall accrue to the sole
  benefit of Owner.



                                                      M-4
                                          ARTICLE 3


                                      CONTRACT TIME
        3.1     The Construction Phase Commencement Date for the Work is 4/15/2024 . The
total period of time beginning with the Construction Phase Commencement Date through the date
required for Substantial Completion of the Work is four hundred and sixty-sixdays ( 466     )
days ("Contract Time"). THE SUBSTANTIAL COMPLETION DATE IS THEREFORE
ESTABLISHED AS 7/25/2025                               .

        3.2     Pursuant to the Agreement, the parties have established liquidated damage rates for
reasons stated therein, which the parties acknowledge and agree apply to this Amendment and
Construction Contractor’s responsibility to substantially complete the Work within the Contract
Time as stated herein and finally complete the Work within the time prescribed in the Contract.
Accordingly, the liquidated damage rates established in the Agreement shall be assessed against
Construction Contractor for each calendar day Construction Contractor fails to achieve Substantial
Completion of the Work within the Contract Time or final completion of the Work within the time
prescribed in the Contract.

                                          ARTICLE 4


                                      MISCELLANEOUS
4.1 Except as expressly modified herein, the terms and conditions of the Agreement remain
unchanged. All terms not specifically defined herein shall have the meaning ascribed to them in
the Agreement. In the event of a conflict between the terms of this Amendment and those of the
Agreement, Owner and Construction Contractor agree that the terms of this Amendment shall
prevail and control. This Amendment may be executed in counterparts, each of which shall be
deemed to be an original, but all of which shall constitute one and the same instrument.

Owner                                        Construction Contractor

By:                                                  By:

Its:                                                 Its:

Date:                                                Date:

Attest:                                              Attest:




                                                  M-5
  ATTACHMENT 1 - ALLOWANCES
  Nancy Creek Elementary School                                         GMP
  Atlanta, GA                                                           March 12, 2024



Estimate / Owner Allowances (Included in Budget)
Allowance amounts listed below are the direct cost amounts and do not include Contractor overhead, fees,
insurances, or other indirect costs. Allowances are for the Owner and will be reconciled by change order. Contractor
assumes no cost exposure for the assigned value of the indicated Allowances.

    1. Allowance for Furniture, Fixture & Equipment relocation = $36,000
    2. Allowance for Temporary Restrooms = $200,000
    3. Allowance for structural steel/lintels at new openings in existing CMU walls = $30,000
    4. Allowance for patching existing spray fireproofing where required = $20,000
    5. Allowance for ERRCS testing = $17,628
    6. Allowance for installation and commissioning of an ERRCS system = $88,140




                                         Page 1
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                         GMP
                                                                         March 12, 2024
  Nancy Creek Elementary School


Assumptions & Clarifications
The following clarifications and assumptions, organized by CSI division, are included as part of the Agreement.

General Notes
   1. This GMP Estimate for Nancy Creek Elementary School is based upon the following documents, unless
       otherwise stated in Clarifications below:
             a.   Project Manual Issued for Bid dated Jan.20,2023 by SSOE
             b. Plans Issued for Bid dated Jan.20,2023 by SSOE
             c.   Addendum #1 – Not provided
             d. Addendum #2 dated March 8,2023 by SSOE
             e. RFI log #1 (see attached)


This estimate includes:
    1. Construction Manager will furnish and maintain General Liability Insurance through a GL/Excess BBC’s
        master insurance program. The General Liability Insurance will be billed at a fixed rate of 1.10% of the GMP
        with the first Payment Application. Direct bills from the master program are not available as the fixed rate is
        based on the entire portfolio of US projects and calculated as a fixed rate.
    2. Balfour Beatty P&P Bond will be provided at a fixed rate of 0.561% of the GMP. Bond costs will be billed
       100% with the first Payment Application.
    3. Builder’s Risk policy will be provided by Contractor and be billed at actual cost with the first Payment
       Application at a value equal to the cost of work. Owner shall maintain property insurance for facility.
    4. Construction Manager will furnish and maintain Subcontractor Default Insurance (SDI) through BBC’s master
       insurance program. SDI will be billed at fixed rate of 1.52% of the cost of work. Direct bills from the master
       program are not available as the fixed rate is based on the entire portfolio of US projects and calculated as a
       fixed rate. Construction Manager will purchase, maintain, and enroll all eligible and prequalified
       subcontractors, suppliers, and vendors into a SDI program at a fixed amount which shall be billed in total at
       the outset of the project. Any subcontractors who do not meet SDI prequalification requirements who have
       subcontractors over $250,000 will be bonded at the contractor’s discretion.


Division 1                       General Requirements
This estimate includes:
    1. Digital Documents: All documents including closeouts will be transmitted digitally. No provisions for hard
       copies are included.
    2. Potential Trade Escalation: Should the award of certain Trade Contracts not allow for a fixed-price structure
       where the Trade Contractor would bear all or part of the responsibility for future inflation and/or cost
       escalation for the entire scope and value of the Trade Contract due to either (1) market conditions (supply
       chain, etc.) that won’t allow for firm fixed price commitments at time of Trade Contract award and/or (2) at the
       request of the Owner who wants to remove such Escalation Allowances or Escalation Contingencies for
       anticipated or potential future inflation and/or cost escalation from the initial Trade Contract amount and fully
       bear that future risk, the Expenditure Authorization Letter will capture such details and outline the mutually
       agreed-upon timeline and process for which the material escalation items will be measured and later

                                          Page 2
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                          GMP
                                                                          March 12, 2024
  Nancy Creek Elementary School

        reconciled. Upon reconciliation of any material escalation item from Trade Contracts, the GMP contract
        amount will be adjusted accordingly via Change Order. Should the Owner elect to deviate from the agreed-
        upon timeline for reconciling the escalation as outlined in the Expenditure Authorization Letter, any further
        cost or schedule impacts resulting from that change will cause the GMP to be adjusted via the Change Order
        process outlined in the Agreement.
    3. General Conditions: Are established as a lump sum that shall be paid in equal installments on a monthly basis
       over the course of the project.
    4. Construction Contingency: Our GMP Proposal contains 7 percent (7.00%) of Cost of the Work construction
       contingency (based on the 100% CD’s). The Construction Contingency will be used at the reasonable
       discretion of the Contractor to address unexpected circumstances and expenses incurred to: (a) pay for
       purchase of subcontracts, suppliers and vendors in excess of budgeted line item(s) within the GMP; (b) fill
       scope gaps between trade subcontractors; (c) repair un-assignable damaged work; and (d) settle minor
       disputes with trade subcontracts at the completion of the Project. In essence, these are expenses which are
       ordinary and customary that does not constitute a change in the Work as defined in the Agreement. The
       Construction Contingency can be used to offset cost overruns incurred by the Contractor for General
       Conditions or General Requirements. Conversely, any savings will flow into the Construction Contingency.
    5. Pandemic/ Supply Chain Issues: Any delays in deliveries, unavailability of materials or equipment, labor
       shortages and/or cost escalation attributable to, pandemic or public health emergencies as well as supply chain
       issues will constitute compensable delays or change events.
    6. An assumption that to the extent the specifications do not involve design elements performed by different trades
       and is otherwise a customary proprietary design or engineered component requiring a professional engineer’s
       stamp on shop drawings such as fire suppression systems, fire alarm systems and other similar activities,
       Construction Manager’s liability for design errors and omissions is limited to amounts we recover from the
       subcontractor or its insurance carriers.
    7. An allowance for Temporary Restrooms. See Allowances.
This estimate excludes:
    8. Repairs to existing structure(s) other than as provided on the Contract Documents.
    9. Security guards, security cameras, or security services.
    10. Any code updating of existing facility not specifically shown or identified on the documents.
    11. Utility consumption fees, except temporary construction power due to this being occupied campus.
    12. Design responsibility inherent in performance specifications that involve assemblies or interfaces among
        design elements performed by different trades or are otherwise not customary proprietary specifications
        obtained from single manufacturers.
    13. Specifications that state the following or something substantively similar to the following 1) “delegated design:
        design assembly or interface, including comprehensive engineering analysis by a qualified professional
        engineer, using performance requirements and design criteria indicated”; 2) requirements for code
        compliance and design features “whether or not indicated on the drawings,” and 3) references to design “by
        others” on the drawings.
    14. All Testing


Division 2                       Demolition
This estimate includes:
    1. All Selective demolition as indicated on the contract documents.

                                          Page 3
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                           GMP
                                                                           March 12, 2024
  Nancy Creek Elementary School

    2. An allowance for removal of all Furniture, Fixtures & Equipment (FF&E) prior to commencement of
       construction work. See Allowances.




This estimate excludes:
    1. Any bracing/shoring or engineering of such as required for demolition.
    2. Removal of all existing nails, brackets, plastic shield, hooks, clips, tape, screws etc. from walls, floors or
       ceilings.




Division 3                       Concrete
This estimate includes:
    1. Modifications to existing equipment pads as required.
This estimate excludes:
    1. N/A


Division 4                       Masonry
This estimate includes:
    1. N/A


This estimate excludes:
    2. Patching pre-existing holes/penetrations on existing masonry walls
    3. Patching holes in masonry walls, made by the removal of any existing FF&E and any wall mounted
       accessories.
    4. Grouting of existing masonry walls



Division 5                       Metals
This estimate includes:
    1. All structural steel as indicated on the contract documents.
    2. An allowance for structural steel/lintels at new openings in existing CMU walls. See allowances.


This estimate excludes:
    3. New stair & foundation (General Note K on Sheet S0.00) as none is shown
    4. AISC certification.
    5. Recycled materials requirement
                                          Page 4
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                          GMP
                                                                          March 12, 2024
  Nancy Creek Elementary School


Division 7                       Thermal and Moisture Protection
This estimate includes:
    6. 500 lf of new walkway pads
    7. 60 mil PVC KEE roof
    8. An allowance for patching existing spray fireproofing. See Allowances.


This estimate excludes:
    9. New roof hatch
    10. Testing for roofing


Division 8                       Doors and Windows
This estimate includes:
    1. All doors, frames and hardware as indicated on the door schedule in the contract documents.




This estimate excludes:
    1. Replacement of any existing doors, frames, and hardware not specifically indicated on the contract
       documents.
    2. Replacement of any existing glazing, windows, storefronts, or louvers not specifically indicated on contract
       documents.



Division 9                       Finishes
This estimate includes:
    1. Painting only at new interior hollow metal frames.
    2. Painting only ‘corner to corner’ at existing walls where patching will occur for new construction activities.
This estimate excludes:
    1. R13 insulation.
    2. Abuse-resistant gypsum wallboard
    3. Scraping all peeling paint from existing walls and repainting all walls
    4. Patching and painting pre-existing holes and penetrations on walls, floors or ceilings.
    5. Patching holes in the masonry walls, made by the removal of any existing FF&E and any wall mounted
       accessories and finishing/painting of the same
    6. Seismic bracing


                                          Page 5
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                         GMP
                                                                         March 12, 2024
  Nancy Creek Elementary School


Division 10                     Specialties
This estimate includes:
    1. .N/A




This estimate excludes:
    2. N/A


Division 21, 22 & 23                    Mechanical Systems (Plumbing, Fire Protection, HVAC)
This estimate includes:
    1. This proposal includes HVAC equipment & systems as R-410A per the Contract Documents. This proposal
       does not include the forthcoming legal mandated changes to refrigerants. The proposal assumes that HVAC
       equipment will be included in early release and all submittals completed and approved in a timely fashion for
       all HVAC equipment to be ordered before May 1, 2024.
    2. HVAC life safety dampers as indicated on the Construction Drawings. This proposal assumes the Mechanical
       Designer has shown all dampers required by code.


This estimate excludes:
    3. This proposal assumes the existing gas service is sufficient and excludes any upgrades to the existing
       service.
    4. Temporary equipment for heating/cooling. This proposal only includes running permanent units for temp
       heat/cooling once installed.
    5. Delegated-design of hangers & supports.
    6. Seismic bracing requirements.
    7. Fire Pumps. This proposal assumes the provided Flow Test analysis is sufficient.
    8. Any repair of existing to remain pipe, insulation or equipment.




Division 26                     Electrical Systems
This estimate includes:
    1.   New raceways installed below ceiling will be surface mounted.
    2.   Allowance for ERRCS testing and installation. See Allowances.
    3.   Salvage and reinstallation of low voltage devices mounted to ceiling as noted on Contract Documents.
This estimate excludes:
    4.   Installation of new Tele/data/AV systems including Smartboards.

                                         Page 6
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                          GMP
                                                                          March 12, 2024
  Nancy Creek Elementary School

    5.   Any repair or adjustment for existing to remain feeders or equipment.




Division 31 &32                          Sitework & Fencing
This estimate includes:
    3. Salvaging and reinstalling existing granite curbs at installation of new Fire Line.
    4. Paving and striping only at areas disturbed by the new Fire Line installation.
    5. Fencing includes a 6’ black 6-gauge chain link fence.
This estimate excludes:
    6. New granite curbs
    7. Excavation, removal, and or replacement of unsuitable soils/ rock.
    8. Re-surfacing or re-striping existing parking lot which is outside the limits of the scope of work




                                          Page 7
  ATTACHMENT 2 – ASSUMPTIONS AND
  CLARIFICATIONS                                                        GMP
                                                                        March 12, 2024
  Nancy Creek Elementary School

Alternates
Alternate amounts listed below are the direct cost amounts and do not include Contractor overhead, fees, insurances,
or indirect costs. Alternates may be incorporated by future Change Order. Alternate pricing is good for twenty (20)
days.

     N/A

Estimate / Owner Allowances (Included in Budget)
Allowance amounts listed below are the direct cost amounts and do not include Contractor overhead, fees,
insurances, or other indirect costs. Allowances are for the Owner and will be reconciled by change order. Contractor
assumes no cost exposure for the assigned value of the indicated Allowances.

    1. Allowance for Furniture, Fixture & Equipment relocation = $36,000
    2. Allowance for Temporary Restrooms = $200,000
    3. Allowance for structural steel/lintels at new openings in existing CMU walls = $30,000
    4. Allowance for patching existing spray fireproofing where required = $20,000
    5. Allowance for ERRCS testing = $17,628
    6. Allowance for installation and commissioning of an ERRCS system = $88,140




                                    END OF CLARIFICATIONS AND ASSUMPTIONS




                                         Page 8
                                                   DCSD Nancy Creek Elementary School
                                                   RFI Log #1 - 02-08-2024

BBC RFI # Discipline       Drawing & Detail #      Issue / Question                                                                      Answer
         1 Civil                                   Please provide detail for replacing Asphalt paving                                    NCES - refer to "Typical Patch and Resurfacing Detail" detail on C6.0; CTMS - "8" Reinforced Concrete Paving" detail shown for handicapped parking and
                                                                                                                                         "Typical Patch and Resurfacing Detail" shown for fire line on C-6.
         2 Architectural   A1.20                   Is the roofing removal and replacement to be included as an add alternate or is to    Include the roofing removal and replacement as an add alternate per the documents
                                                   be included in base bid pricing ?
         3 Mechanical                              Please clarify if Commissioning agent will be hired (and paid for) by the owner     DCSD will not hire or pay for a commissioning agent
                                                   directly
         5 Electrical      E6.01                   Please clarify if we are to provide new generator or if we are to reuse existing    Provide a new generator for NCES per the documents
                                                   generator (per the one-line diagram, it seems that we are to provide new generator)

         6 Architectural   A1.10                   Please advise on the rating for walls shown in Red at Building #2020 as it is not     The walls in question are existing conditions (1 hour rated masonry) that should be maintained.
                                                   shown on the Drawing Conventions Legend
         7 Architectural                           Please provide a finish schedule                                                      Other than new acoustical panel ceiling systems throughout the building, the finishes scope of work is limited to new construction in electrical and
                                                                                                                                         mechanical rooms (ERRCS CLOSET 604.4 and MAIN ELECTRICAL 504.4). New walls should be painted. The floors in those spaces will be sealed
                                                                                                                                         concrete.
         8 Electrical                   284621.11 Please advise if Simplex is an acceptable/approved vendor for Fire Alarm               Yes, Simplex is an acceptable/approved manufacturer.
        12 Electrical                   284621.11 Champion specifications does not note FireLite as an approved FA manufacturer,         Yes, Firelite is an acceptable/approved manufacturer.
                                                  but Nancy creek specifications include FireLite. Please advise if FireLite is an
                                                  acceptable/approved vendor for Fire Alarm for both schools.




                                                                                                                                       Page 9
Activity ID              Activity Name                                           OD    RD       % Start           Finish                                     2024                                                                 2025                                              2026
                                                                                                                               Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
                                                                                 558   466          29-Dec-23 A 28-Nov-25                                                                                                                                            Nancy Creek ES Preliminary Schedule 2024-01-26
   Nancy Creek ES Preliminary Schedule 2024-01-26
    Milestones                                                                   491   398          23-Jan-24 A   22-Aug-25                                                                                                                      Milestones

     M050                Executed Precon Agreement                                0     0    100% 23-Jan-24 A                     Executed Precon Agreement
     M100                Project Kick-off Meeting DCSD/SSOE/BB                    0     0      0% 29-Jan-24                        Project Kick-off Meeting DCSD/SSOE/BB
     M110                NTP - Preconstruction                                    0     0      0% 29-Jan-24*                       NTP - Preconstruction
     M120                NTP - Construction                                       0     0      0% 15-Apr-24                                       NTP - Construction
     M150                Construction Duration (calendar days)                   467   467     0% 15-Apr-24       25-Jul-25                                                                                                                 Construction Duration (calendar days)
     M200                Start Summer 2024 Work                                   0     0      0% 24-May-24                                              Start Summer 2024 Work
     M250                Summer 2024 Work Complete                                0     0      0%                 26-Jul-24*                                           Summer 2024 Work Complete
     M300                Start Summer 2025 Work                                   0     0      0% 02-Jun-25                                                                                                                      Start Summer 2025 Work
     M350                Summer 2025 Work Complete                                0     0      0%                 25-Jul-25*                                                                                                                Summer 2025 Work Complete
     M900                Project Substantial Completion                           0     0      0%                 25-Jul-25                                                                                                                 Project Substantial Completion
     M950                Final Completion                                         0     0      0%                 22-Aug-25                                                                                                                      Final Completion

    School Calendar                                                              420   420          01-Apr-24     28-Nov-25                                                                                                                                          School Calendar

     CAL100              Spring Break 2024                                        5     5      0% 01-Apr-24*      05-Apr-24                     Spring Break 2024
     CAL150              Teacher Last Day 2023-2024                               1     1      0% 23-May-24*      23-May-24                              Teacher Last Day 2023-2024
     CAL200              Teacher First Day 2024-2025                              1     1      0% 29-Jul-24*      29-Jul-24                                            Teacher First Day 2024-2025
     CAL250              Thanksgiving Break 2024                                  5     5      0% 25-Nov-24*      29-Nov-24                                                                   Thanksgiving Break 2024
     CAL300              Winter Break 2024-2025                                   12    12     0% 23-Dec-24*      03-Jan-25                                                                          Winter Break 2024-2025
     CAL360              February Break 2025                                      5     5      0% 17-Feb-25*      21-Feb-25                                                                                  February Break 2025
     CAL350              Spring Break 2025                                        5     5      0% 07-Apr-25*      11-Apr-25                                                                                             Spring Break 2025
     CAL400              Teacher Last Day 2024-2025                               1     1      0% 30-May-25*      30-May-25                                                                                                     Teacher Last Day 2024-2025
     CAL450              Teacher First Day 2025-2026                              1     1      0% 28-Jul-25*      28-Jul-25                                                                                                                 Teacher First Day 2025-2026
     CAL510              Fall Break 2025                                          5     5      0% 13-Oct-25*      17-Oct-25                                                                                                                                   Fall Break 2025
     CAL500              Thanksgiving Break 2025                                  5     5      0% 24-Nov-25*      28-Nov-25                                                                                                                                          Thanksgiving Break 2025

    Preconstruction/CM Package/Board Submission                                  171    79          29-Dec-23 A 15-May-24                               Preconstruction/CM Package/Board Submission

     PRE100              Subcontractor Solicitation                               38    2 94.74% 29-Dec-23 A 29-Jan-24             Subcontractor Solicitation
     PRE200              Subcontractor Bid Date                                   1     1      0% 29-Jan-24       29-Jan-24        Subcontractor Bid Date
     PRE300              GMP Package to DCSD                                      1     1      0% 26-Feb-24       26-Feb-24             GMP Package to DCSD
     PRE400              DCSD Board Approval                                      1     1      0% 15-Apr-24       15-Apr-24                       DCSD Board Approval
     PRE500              Subcontractor Buyout                                     23    23     0% 15-Apr-24       15-May-24                             Subcontractor Buyout

    Procurement                                                                  293   293          15-Apr-24     12-Jun-25                                                                                                        Procurement

     Electrical                                                                  293   293          15-Apr-24     12-Jun-25                                                                                                        Electrical
      PROC1000           Prep Electrical Submittals                               20    20     0% 15-Apr-24       10-May-24                            Prep Electrical Submittals
      PROC1010           BBC Review/Submit Electrical Submittals                  3     3      0% 13-May-24       15-May-24                             BBC Review/Submit Electrical Submittals
      PROC1020           Review/Approve Electrical Submittals                     10    10     0% 16-May-24       30-May-24                                 Review/Approve Electrical Submittals
      PROC1030           Fab/Del Panelboards (30 weeks)                          150   150     0% 31-May-24       07-Jan-25                                                                          Fab/Del Panelboards (30 weeks)
      PROC1040           Fab/Del Natural Gas Generator (52 weeks)                260   260     0% 31-May-24       12-Jun-25                                                                                                        Fab/Del Natural Gas Generator (52 weeks)
      PROC1050           Fab/Del 1200A Switchgear (52 weeks)                     260   260     0% 31-May-24       12-Jun-25                                                                                                        Fab/Del 1200A Switchgear (52 weeks)
     Mechanical                                                                  148   148          15-Apr-24     11-Nov-24                                                                Mechanical
      PROC2000           Prep Mechanical Submittals                               10    10     0% 15-Apr-24       26-Apr-24                         Prep Mechanical Submittals
      PROC2010           BBC Review/Submit Mechanical Submittals                  3     3      0% 29-Apr-24       01-May-24                          BBC Review/Submit Mechanical Submittals
      PROC2020           Review/Approve Mechanical Submittals                     10    10     0% 02-May-24       15-May-24                             Review/Approve Mechanical Submittals
      PROC2030           Fab/Del Above Ceiling Mechanical Equipment (10 weeks)    50    50     0% 16-May-24       26-Jul-24                                            Fab/Del Above Ceiling Mechanical Equipment (10 weeks)


              Remaining Level of Effort               Milestone                                                                                                                                                                                                                    Page 1 of 3
              Actual Level of Effort
              Remaining Work
                                                      Summary       Nancy Creek ES Preliminary Schedule 2024-01-                                                                                                                                                         Data Date: 26-Jan-24
                                                                                                                                                                                                                                                                         Print Date: 29-Feb-24
              Actual Work
              Critical Remaining
                                                                                         26

                                                                                                                                      Page 10
Activity ID              Activity Name                                              OD    RD     % Start        Finish                           2024                                                                 2025                                           2026
                                                                                                                            Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
      PROC2060           Fab/Del Cooling Towers (12 weeks)                           60    60   0% 16-May-24    09-Aug-24                                     Fab/Del Cooling Towers (12 weeks)
      PROC2050           Fab/Del Heat Exchangers (14 weeks)                          70    70   0% 16-May-24    23-Aug-24                                        Fab/Del Heat Exchangers (14 weeks)
      PROC2090           Fab/Del ERU (14 weeks)                                      70    70   0% 16-May-24    23-Aug-24                                        Fab/Del ERU (14 weeks)
      PROC2100           Fab/Del MAU (14 weeks)                                      70    70   0% 16-May-24    23-Aug-24                                        Fab/Del MAU (14 weeks)
      PROC2070           Fab/Del RTU's (except RTU-1) (18 weeks)                     90    90   0% 16-May-24    23-Sep-24                                                   Fab/Del RTU's (except RTU-1) (18 weeks)
      PROC2080           Fab/Del RTU-1 (25 weeks)                                   125   125   0% 16-May-24    11-Nov-24                                                           Fab/Del RTU-1 (25 weeks)

    Construction                                                                    294   294       24-May-24   25-Jul-25                                                                                                       Construction

     Summer 2024                                                                     44    44       24-May-24   26-Jul-24                                  Summer 2024

      Sitework                                                                       44    44       24-May-24   26-Jul-24                                  Sitework
       A1000             Mobilize and MEP Safe-off                                   3     3    0% 24-May-24    29-May-24                       Mobilize and MEP Safe-off
       A1010             Install Erosion Controls                                    3     3    0% 30-May-24    03-Jun-24                        Install Erosion Controls
       A1020             Site Demo                                                   5     5    0% 04-Jun-24    10-Jun-24                         Site Demo
       A1030             Install Fire Line Extension                                 15    15   0% 11-Jun-24    01-Jul-24                             Install Fire Line Extension
       A1040             FRP Curb and Gutter                                         5     5    0% 02-Jul-24    09-Jul-24                               FRP Curb and Gutter
       A1050             Asphalt Pavement and Striping                               8     8    0% 10-Jul-24    19-Jul-24                                 Asphalt Pavement and Striping
       A1060             BBC Punch and Clean                                         5     5    0% 22-Jul-24    26-Jul-24                                  BBC Punch and Clean
      Building 2020 - Gym                                                            26    26       30-May-24   05-Jul-24                               Building 2020 - Gym
       B6000             Install Protection and Selective Demo                       5     5    0% 30-May-24    05-Jun-24                        Install Protection and Selective Demo
       B6010             Electrical and Fire Protection Overhead Rough               5     5    0% 06-Jun-24    12-Jun-24                         Electrical and Fire Protection Overhead Rough
       B6020             Install Ceiling Grid                                        3     3    0% 13-Jun-24    17-Jun-24                          Install Ceiling Grid
       B6030             Electrical and Fire Protection Drops into Grid Ceiling      3     3    0% 18-Jun-24    20-Jun-24                           Electrical and Fire Protection Drops into Grid Ceiling
       B6040             Electrical and Fire Protection Cover-up Inspection          2     2    0% 21-Jun-24    24-Jun-24                            Electrical and Fire Protection Cover-up Inspection
       B6050             Install Ceiling Tile                                        3     3    0% 25-Jun-24    27-Jun-24                            Install Ceiling Tile
       B6060             BBC Punch and Clean                                         5     5    0% 28-Jun-24    05-Jul-24                               BBC Punch and Clean
      Building 2010 - Roof (Add Al ternate)                                          30    30       30-May-24   11-Jul-24                               Building 2010 - Roof (Add Alternate)
       A2000             Replace/Repair Roof (not including at mechanical units)     15    15   0% 30-May-24    19-Jun-24                           Replace/Repair Roof (not including at mechanical units)
       A2010             Install Gutters and Downspouts                              10    10   0% 20-Jun-24    03-Jul-24                              Install Gutters and Downspouts
       A2020             BBC Punch and Clean                                         5     5    0% 05-Jul-24    11-Jul-24                               BBC Punch and Clean
      Mechanical/Electrical Yards                                                    20    20       30-May-24   26-Jun-24                            Mechanical/Electrical Yards
       A3000             Selective Demo (Not Including Existing Chiller)             5     5    0% 30-May-24    05-Jun-24                        Selective Demo (Not Including Existing Chiller)
       A3010             MEP Underground Rough (Gas Piping)                          5     5    0% 06-Jun-24    12-Jun-24                         MEP Underground Rough (Gas Piping)
       A3020             FRP Concrete Footings                                       5     5    0% 13-Jun-24    19-Jun-24                           FRP Concrete Footings
       A3030             FRP Cooling Tower Support Wall                              5     5    0% 20-Jun-24    26-Jun-24                            FRP Cooling Tower Support Wall
     Summer 2025                                                                     39    39       02-Jun-25   25-Jul-25                                                                                                       Summer 2025

      Building 2010 - School                                                         39    39       02-Jun-25   25-Jul-25                                                                                                       Building 2010 - School
       Area 1                                                                        39    39       02-Jun-25   25-Jul-25                                                                                                       Area 1
        B1000            Mobilize and MEP Safe-off                                   2     2    0% 02-Jun-25    03-Jun-25                                                                                             Mobilize and MEP Safe-off
        B1010            Install Protection and Selective Demo                       5     5    0% 04-Jun-25    10-Jun-25                                                                                              Install Protection and Selective Demo
        B1020            MEPF Overhead Rough                                         15    15   0% 11-Jun-25    01-Jul-25                                                                                                  MEPF Overhead Rough
        B1030            Set/Connect Above Ceiling Mechanical Equipment              5     5    0% 25-Jun-25    01-Jul-25                                                                                                  Set/Connect Above Ceiling Mechanical Equipment
        B1040            Install Ceiling Grid                                        5     5    0% 30-Jun-25    07-Jul-25                                                                                                    Install Ceiling Grid
        B1050            MEPF Drops into Grid Ceiling                                5     5    0% 02-Jul-25    09-Jul-25                                                                                                    MEPF Drops into Grid Ceiling
        B1060            MEPF Cover-up Inspection                                    2     2    0% 10-Jul-25    11-Jul-25                                                                                                    MEPF Cover-up Inspection
        B1070            Install Ceiling Tile                                        5     5    0% 14-Jul-25    18-Jul-25                                                                                                      Install Ceiling Tile
        B1080            MEPF Tr im- out                                             5     5    0% 15-Jul-25    21-Jul-25                                                                                                      MEPF Tr im- out


              Remaining Level of Effort                Milestone                                                                                                                                                                                                      Page 2 of 3
              Actual Level of Effort
              Remaining Work
                                                       Summary             Nancy Creek ES Preliminary Schedule 2024-01-                                                                                                                                     Data Date: 26-Jan-24
                                                                                                                                                                                                                                                            Print Date: 29-Feb-24
              Actual Work
              Critical Remaining
                                                                                                26

                                                                                                                                  Page 11
Activity ID              Activity Name                                             OD   RD    % Start        Finish                           2024                                            2025                                                2026
                                                                                                                         Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
        B1090            BBC Punch and Clean                                        5    5   0% 21-Jul-25    25-Jul-25                                                                                  BBC Punch and Clean
        B1100            HVAC Controls                                              5    5   0% 21-Jul-25    25-Jul-25                                                                                  HVAC Controls
       Area 2                                                                      37   37       04-Jun-25   25-Jul-25                                                                                  Area 2
        B2000            Install Protection and Selective Demo                      5    5   0% 04-Jun-25    10-Jun-25                                                                         Install Protection and Selective Demo
        B2010            MEPF Overhead Rough                                       15   15   0% 11-Jun-25    01-Jul-25                                                                             MEPF Overhead Rough
        B2020            Set/Connect Above Celing Mechanical Equipment              5    5   0% 25-Jun-25    01-Jul-25                                                                             Set/Connect Above Celing Mechanical Equipment
        B2100            Set/Connect Mechanical Equipment in Mechanical Room       15   15   0% 25-Jun-25    16-Jul-25                                                                                 Set/Connect Mechanical Equipment in Mechanical Room
        B2030            Install Ceiling Grid                                       5    5   0% 30-Jun-25    07-Jul-25                                                                               Install Ceiling Grid
        B2040            MEPF Drops into Grid Ceiling                               5    5   0% 02-Jul-25    09-Jul-25                                                                               MEPF Drops into Grid Ceiling
        B2050            MEPF Cover-up Inspection                                   2    2   0% 10-Jul-25    11-Jul-25                                                                               MEPF Cover-up Inspection
        B2060            Install Ceiling Tile                                       5    5   0% 14-Jul-25    18-Jul-25                                                                                 Install Ceiling Tile
        B2070            MEPF Tr im- out                                            5    5   0% 15-Jul-25    21-Jul-25                                                                                 MEPF Tr im- out
        B2090            HVAC Controls                                              5    5   0% 18-Jul-25    24-Jul-25                                                                                  HVAC Controls
        B2080            BBC Punch and Clean                                        5    5   0% 21-Jul-25    25-Jul-25                                                                                  BBC Punch and Clean
       Area 3                                                                      37   37       04-Jun-25   25-Jul-25                                                                                  Area 3
        B3000            Install Protection and Selective Demo                      5    5   0% 04-Jun-25    10-Jun-25                                                                         Install Protection and Selective Demo
        B3010            MEPF Overhead Rough                                       15   15   0% 11-Jun-25    01-Jul-25                                                                             MEPF Overhead Rough
        B3020            Set/Connect Above Ceiling Mechanical Equipment             5    5   0% 25-Jun-25    01-Jul-25                                                                             Set/Connect Above Ceiling Mechanical Equipment
        B3030            Install Ceiling Grid                                       5    5   0% 27-Jun-25    03-Jul-25                                                                             Install Ceiling Grid
        B3040            MEPF Drops into Grid Ceiling                               5    5   0% 01-Jul-25    08-Jul-25                                                                               MEPF Drops into Grid Ceiling
        B3050            MEPF Cover-up Inspection                                   2    2   0% 09-Jul-25    10-Jul-25                                                                               MEPF Cover-up Inspection
        B3060            Install Ceiling Tile                                       5    5   0% 11-Jul-25    17-Jul-25                                                                                 Install Ceiling Tile
        B3070            MEPF Tr im- out                                            5    5   0% 14-Jul-25    18-Jul-25                                                                                 MEPF Tr im- out
        B3090            HVAC Controls                                              5    5   0% 18-Jul-25    24-Jul-25                                                                                  HVAC Controls
        B3080            BBC Punch and Clean                                        5    5   0% 21-Jul-25    25-Jul-25                                                                                  BBC Punch and Clean
       Mechanical/Electrical Yards                                                 28   28       04-Jun-25   14-Jul-25                                                                                Mechanical/Electrical Yards
        B4000            Install Cooling Tower Support Steel                        5    5   0% 04-Jun-25    10-Jun-25                                                                         Install Cooling Tower Support Steel
        B4060            Selective Demo                                             5    5   0% 04-Jun-25    10-Jun-25                                                                         Selective Demo
        B4020            Paint Support Steel                                        3    3   0% 11-Jun-25    13-Jun-25                                                                         Paint Support Steel
        B4010            Set/Connect Generator                                     10   10   0% 13-Jun-25    26-Jun-25                                                                            Set/Connect Generator
        B4030            Set/Connect Mechanical Equipment                          10   10   0% 16-Jun-25    27-Jun-25                                                                            Set/Connect Mechanical Equipment
        B4040            Install New Fencing                                        5    5   0% 30-Jun-25    07-Jul-25                                                                               Install New Fencing
        B4050            BBC Punch and Clean                                        5    5   0% 08-Jul-25    14-Jul-25                                                                                BBC Punch and Clean
       Building 2010 - Roof                                                        37   37       04-Jun-25   25-Jul-25                                                                                  Building 2010 - Roof
        B7000            Selective Demo                                             5    5   0% 04-Jun-25    10-Jun-25                                                                         Selective Demo
        B7010            MEP Rough-in (Gas Piping)                                 10   10   0% 11-Jun-25    24-Jun-25                                                                           MEP Rough-in (Gas Piping)
        B7020            Install Support Steel for Mechanical Equipment             8    8   0% 13-Jun-25    24-Jun-25                                                                           Install Support Steel for Mechanical Equipment
        B7030            Set/Connect Mechanical Equipment                          15   15   0% 24-Jun-25    15-Jul-25                                                                                Set/Connect Mechanical Equipment
        B7050            Repair/Replace Roof at Mechanical Units                    5    5   0% 14-Jul-25    18-Jul-25                                                                                 Repair/Replace Roof at Mechanical Units
        B7040            BBC Punch and Clean                                        5    5   0% 21-Jul-25    25-Jul-25                                                                                  BBC Punch and Clean
        Add Alternate: New Roofing System - Building 2010                          20   20       13-Jun-25   11-Jul-25                                                                               Add Alternate: New Roofing System - Building 2010
         B8000           Install New PVC Roofing System (Add Alternate)            20   20   0% 13-Jun-25    11-Jul-25                                                                               Install New PVC Roofing System (Add Alternate)
       Test and Balance HVAC Equipment                                              5    5       21-Jul-25   25-Jul-25                                                                                  Test and Balance HVAC Equipment
        B4900            Test and Balance HVAC Equipment                            5    5   0% 21-Jul-25    25-Jul-25                                                                                  Test and Balance HVAC Equipment
       Electrical Room                                                             10   10       12-Jul-25   21-Jul-25                                                                                 Electrical Room
        B5000            Set/Connect Switchgear                                    10   10   0% 12-Jul-25    21-Jul-25                                                                                 Set/Connect Switchgear


              Remaining Level of Effort              Milestone                                                                                                                                                                                 Page 3 of 3
              Actual Level of Effort
              Remaining Work
                                                     Summary              Nancy Creek ES Preliminary Schedule 2024-01-                                                                                                               Data Date: 26-Jan-24
                                                                                                                                                                                                                                     Print Date: 29-Feb-24
              Actual Work
              Critical Remaining
                                                                                               26

                                                                                                                               Page 12
ATTACHMENT 4 – Schedule of Values
Nancy Creek Elementary School
                                                               GMP
Atlanta, GA
                                                               March 12, 2024




                           Item of Work                        GMP Total




01G General Requirements                                   $        233,093

01H Furniture Relocation Allowance                         $          36,000
01R Temp Restroom Allowance                                $        200,000
02A Demolition                                             $        216,741
05A Structural & Miscellaneous Steel (Turnkey)             $        164,441
07B Roofing                                                $        1,299,302

07C Fireproofing                                           $         20,000
08A Doors, Frames & Hardware (Turnkey)                     $         10,916
09A Drywall / Metal Framing                                $        214,025
09D Painting / Wallcovering                                $         28,237
09X Final Clean                                            $         40,000

21A Fire Protection                                        $        283,029
22A Plumbing                                               $         64,316
23A HVAC                                                   $      3,848,242
26A Electrical                                             $      2,636,518
31D Sitework Package                                       $        202,244
32F Site Fencing                                           $         12,528
General Conditions                                         $      1,193,105
General Liability                                          $        136,132
SDI                                                        $        144,546
Builder's Risk                                             $         11,965
Performance and Payment Bond                               $         69,427
Contractor’s Contingency                                   $        665,674
Fee                                                        $        645,177

GRAND TOTAL                                                $   12,375,659



                                                 Page 13
ATTACHMENT 5 – List of Itemized General Conditions
Nancy Creek Elementary School                        GMP
Atlanta, GA                                          Feb.28, 2024




                                         Page 14
ATTACHMENT 6 – List of Subcontractors
Nancy Creek Elementary School                                 GMP
Atlanta, GA                                                   Feb.28, 2024




                               Item of Work                           Subcontractor



 02A Demolition                                             Alpha Omega

 05A Structural & Miscellaneous Steel (Turnkey)             Silver Oak Contracting

 07B Roofing                                                Innovative Roofing

 08A Doors, Frames & Hardware (Turnkey)                     Tal-Kno

 09A Drywall / Metal Framing                                Baker Building Services

 09D Painting / Wallcovering                                Ortiz Painting

 21A Fire Protection                                        Amber Fire

 22A Plumbing                                               Cat Plumbing

 23A HVAC                                                   Paulson Cheek

 26A Electrical                                             J&I Cordon / Penco Electrical

 31D Sitework Package                                       MHI

 32F Site Fencing                                           D & D Fence




                                                  Page 15
  ATTACHMENT 7 – Alternates
  Nancy Creek Elementary School                                        GMP
  Atlanta, GA                                                          March 12, 2024



Alternates
Alternate amounts listed below are the direct cost amounts and do not include Contractor overhead, fees, insurances,
or indirect costs. Alternates may be incorporated by future Change Order. Alternate pricing is good for twenty (20)
days.

      N/A




                                               Page 16