3. Updates on Ongoing Audits Updated 4.15.2024
Summary: Presented by: Dr. Joel Thibodeaux, Director of Audit & Compliance, Office of Audit & Compliance
DeKalb County Board of Education
Audit Committee Meeting
April 11, 2024
Update of Internal Audit Activity
Presented by: Joel Thibodeaux, CIA – Director of Audits & Compliance
ESSER Audit Update
FORVIS, LLP
• Scheduled completion has been moved to May 2024
• Cost to Date: $519,201 of $877,000 project budget
• Q3 Audit Status Summary (October - December 2023)received
• Current Status:
• Working through final information requests related to approval workflows in
materials procurement and payroll reclassifications
• Draft report is being developed as data is collected and analyzed
• Draft report delivery is expected late April 2024 with final report delivered in
May 2024, contingent upon DCSD’s response to draft report.
2
ESSER Audit Update
FORVIS, LLP
• Current Status:
• Working through Munis contractor access issues
• DIIT and Munis contractor team engaged in resolution
• Draft report is being developed as data is collected and analyzed
• Draft report delivery is expected late April 2024 with final report delivered in
May 2024, contingent upon DCSD’s response to draft report.
3
SPLOST IV & V Audit Update
Plante Moran, PLLC
• Projected completion remains May 31, 2024.
• Project status meetings are now weekly
• Cost to Date: $668,897 of $761,000
• Change Order request of $320,000 presented and submitted for approval
• Additional manpower hours needed for document collection and analysis
• Total budgeted expense: $1,081,000
• Data gathering and Analysis of SPLOST V projects managed and paid in Munis is near
completion.
• Working through data requirements for SPLOST IV and SPLOST V projects managed in
CrossPointe.
• Inter-Divisional and contractor collaboration efforts are being managed through
Audits& Compliance and Chief of Staff Office.
• Noted improvements in turnaround time and data quality
4
School Audits
• Audits were completed at SW DeKalb and Redan High Schools.
• Audit reports were transmitted to Principals and the HS Area Office.
• Lakeside HS required expanded scope. Additional analysis and reporting
underway.
• Audits at Cedar Grove, Dunwoody, and Lithonia High Schools were
initiated during March.
• Full cooperation is being reported from the field
• Finance has provided the Internal Audits team will full data access to
Munis Student Activity and archived SchoolBooks data – enhancing
IA’s ability to retrieve and analyze school financial activity.
5
School Audits
Current School Audit Listing for FYTD 2024
Southwest DeKalb High School – Exit Lithonia High School – Fieldwork near
Mtg completion
Dunwoody High School – Fieldwork
Redan High School – Exit Mtg
ongoing
Cedar Grove High School – Fieldwork
Lakeside High School - Reporting
ongoing
6
Fleet Services & Inventory
• Delivery of the draft report on Inventory is scheduled for April 30, 2024.
• Audit Area Updates:
• Vehicle Purchases –
• Other departments purchasing vehicles: Plant Services, Public Safety, Transportation, Superintendent’s
Office
• Departmental fleet managers interviewed regarding procurement procedures
• Vehicle inventory being reconciled to Munis
• Fuel – Purchase contract management, fuel distribution management and access
procedures
• Vehicle Maintenance – Completed interviews with service advisors and currently evaluating
maintenance scheduling, inspections, and repair
• Vehicle Disposal procedures – Capital Assets Manager interviewed and engaged for
additional information, including inventory reconciliation
7
Follow-Up Questions or Concerns?
Audit Committee Requests for Additional Information
Office of Internal Audits & Compliance
Joel B Thibodeaux, CIA – Director
joel_b_thibodeaux@dekalbschoolsga.org
8
Item Updates:
Internal Audits & Compliance
1. ESSER Audit
2. SPLOST IV & V Audit
3. Internal Audit Activity
9