Contractor CO 7 Lefko - McNair HS signed

AID 1574714 · View on Simbli

Agenda Item

i. E-SPLOST V Project 11535 Group A Security Vestibule – Change Order No. 7 to Lefko Construction (Not to exceed $234,918.24)

Summary: Presented by: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations
Request: It is requested that the Board of Education approve a budget reallocation in the amount of $234,918.24.

It is also requested that the Board of Education approve the Lefko Construction Change Order No. 7 for Security Vestibule in the amount of $234,918.24.
Why: Per the recommendations in the Comprehensive Master Plan the security vestibule project at Ronald E. McNair High School was put on hold by DCSD on March 4, 2022. Due to the lack of action on the CMP’s recommendations, DCSD asked for the security vestibule on hold to be re-activated on August 16, 2023. The additional cost is due to the increase in material costs since the initial contract award and the added general conditions of installing one security vestibule after the others in the group are complete. The approval of Change Order No. 7 will allow Lefko Construction to proceed with ordering material and installation of a security vestibule at Ronald E. McNair High School.
Details: Specific details related to the scope of work for this project can be found on the District’s solicitation website at https://dekalbschoolsga.ionwave.net/.

On November 15, 2021, the Board of Education approved the award of RFP No. RFP #22-752-001 for Group A Security Vestibule to Lefko Construction. The scope of work for this project includes Group A Security Vestibules.
Financial impact: A budget adjustment of $234,918.24 will be necessary to cover the additional cost of Change Order No. 7 to the construction services contract with Lefko Construction.

The budget adjustment would move $234,918.24 from E-SPLOST V Project 60236: Program Contingency (cost code: SP5MANG.60235.PRGCONTIN to E-SPLOST V Project 11535:Group A Security Vestibule (cost code:SP5SAFSEC.11535.GENCONTR).
Contact: Mr. Erick Hofstetter, Chief Operating Officer, Division of Operations, 678.676.1475
Status: Approved by General Counsel (Gregory Doyle Calhoun & Rogers)
                                THE DEKALB COUNTY BOARD OF EDUCATION
                                    CONSTRUCTION CONTRACT CHANGE ORDER
                                                       (General Contractor)



Project Name: Security Vestibule (Group A)
Project No.: 115-35
Change Order No: 07
Date: October 6, 2023

Contractor: LEFKO Construction
              105 Mansell Circle
              Roswell, GA 30075
              (the “Contractor”)

Project Description: Security Vestibule at Ronald McNair HS

Reason for Change:

Owner request, reinstate Ronald McNair High School security vestibule into scope of work. Due to materials
escalation and additional mobilization additional cost was associated.


Scope of Work (for this change):

Provide and install Security Vestibule in accordance with the contract documents. $234,918.24 additional to
previously approved amount.


Contract Amount:            Original Contract Price:                              $2,519,202.55
                            Previous Change Orders:                               $ 21,572.17
                            Current Contract Price (with Change(s):               $2,540,774.72
                            Amount of this Change Order:                          $ 234,918.24
                            Revised Contract Price:                               $2,775,692.96

Contract Time:              Original Substantial Completion Date: December 19, 2022.
                            Increase/(Decrease) in calendar days by previous Change Order(s): 0
                            Increase/(Decrease) in calendar days by this Change Order: 0
                            Revised Substantial Completion Date:

Attachments (Incorporated by Reference): Contractors change order request dated 9/12/23.

CLAIM IDENTIFICATION OR WAIVER
The Contractor has no claims arising out of or related to the Project for any (i) costs, expenses, profit, overhead, direct
damages, consequential damages or increase in the Contract Price or (ii) delay or impact to the Contractor or the Project
except as identified as follows:



and any and all claims that are not identified hereinabove by the Contractor are hereby waived by the Contractor.




                              Signatures are included on the following page.




Contractor Change Order (10/2023)                                                                                      1
Change Order No. 07
As changed hereinabove, the Contract for the above-referenced Project 115-35 shall continue in full force and
effect.


Agreed to by the Contractor:


                                                      10/05/2023
Marc Lefkovits                                        Date
President


Recommended for Acceptance by Architect:


                                                      10/05/2023
Sebastian Archer                                      Date
Project Manager

Recommended for Acceptance by Program Manager & Owner:



Mel Butler                                            Date
Program Director



Richard Boyd                                          Date
Director of Design and Construction



Erick Hofstetter                                      Date
Chief Operating Officer




Approved by The DeKalb County Board of Education:



Dr. Devon Q. Horton                                   Date
Superintendent



Mr. Diijon DaCosta, Sr.                               Date
Board Chair




Board of Education Approval:        Date:               Item No.:
(Required Over $100,000)




Contractor Change Order (10/2023)                                                                         2
Change Order No. 07