Agenda Item
i. Approval to Utilize the Indefinite Quantity Construction (EZIQC) Services Georgia Statewide Contract for an amount not to exceed $3,000,000
Summary: Presented by: Mr. Richard Boyd, Interim Chief Operations Officer, Division of Operations
Request: It is requested that the Board of Education authorize the District to approve the following contractors utilizing the Georgia statewide contract to provide services for repairs, alterations and minor construction projects: Albion Scaccia Enterprises, LLC, (99999-SPD-S20200901-0001); Equix Holdings, Inc. dba Astra Construction Services (99999-SPD-S20200901-0026A); Bayne Development Group, LLC, (99999-SPD-S20200901-00024); Brown & Root Industrial Services, LLC, (99999-SPD-S20160216-010); Centennial Contractors Enterprises, Inc., (99999-SPD-S20200901-0003); Crown Retail Services (99999-SPD-S20200901-0004); Engineering Design Technologies, Inc., ( 99999-SPD-S20200901-0006); F.H. Paschen, S.N. Nielsen & Associates (99999-SPD-S20200901-0007); HCR Construction, Inc., (99999-SPD-S20200901-0009); HITT Construction, Inc., ( 99999-SPD-S20200901-00010); Jewels of the South (99999-SPD-S20200901-00012); JOC Construction (99999-SPD-S20200901-00013); Lichty Commercial Construction, Inc., (99999-SPD-S20200901-00023); Osprey Management LLC, (99999-SPD-S20200901-00014); Paryani Construction (99999-SPD-S20200901-00020); Place Services, Inc., (99999-SPD-S20200901-00016); Prime Contractors (99999-SPD-S20200901-00015); Striker Contracting LLC (99999-SPD-S20200901-00019); Ujamma Construction SE LLC (99999-SPD-S20200901-00028); and Ward Humphrey Incorporated (99999-SPD-S20200901-00027) in accordance with the State of Georgia Indefinite Quantity Construction (EZIQC) statewide contract through June 30, 2023, for an amount not to exceed $3,000,000. This contract has an option to renew each fiscal year through June 30, 2024.
Why: This request is to establish a pool of pre-qualified general contractors to support the Facilities Department in addressing the issues identified in the state-issued corrective action plan to complete repairs, maintenance, and minor construction projects as competitively solicited prices utilizing the State of Georgia Indefinite Quantity Construction Services contract. Under this contract, the Contractor will furnish management, labor, materials, equipment, and incidental design support needed to perform the work.
Details: The use of this contact will provide access to twenty (20) general contractors to assist the Facilities Department in addressing maintenance and repair issues in various facilities throughout the district. This contract will not be used for construction projects that exceed $100,000. However, it may be used for non-construction projects that exceed $100,000. The Board will be notified of all projects that exceed $100,000.
Financial impact: The total budget for these services is allocated from the cost code (100.2600.543013.00011.7520.9990.8013.040.0000) and (100.2600.543009.00011.7520.9990.8013.040.0000) under the Operations’ Division General Fund Budget in the amount not-to-exceed $3,000,000.
Contact: Mr. Richard Boyd, Interim Chief Operations Officer, Division of Operations, 678.676.1483
Mr. Bobby Moncrief, Director of Facilities, Division of Operations, 678.676.1478
Effective: Upon Board Approval
Status: Approved by General Counsel
CONTRACT MODIFICATION AND EXERCISE OF OPTION
made by and between
Striker Contracting
2859 Paces Ferry Road
Suite 1750
Atlanta, GA 30339
(“Contractor”)
and
Sourcewell
202 12th Street NE
PO Box 219
Staples, MN 56479
Phone: (218) 894-1930 or (888) 894-1930
Contractor and Sourcewell have entered into an Indefinite Quantity Construction Contract, Contract
Number: GA-A04-040820-SCL, with an effective date of April 20, 2020, an initial term of one year, and
three (3) bilateral options to extend the term for an additional term.
The parties agree that certain terms within Contract Number GA-A04-040820-SCL will be modified, and
that the option to extend for a one-year term will be exercised.
IN CONSIDERATION OF the mutual covenants and agreements described in this Contract Modification
and Exercise of Option, the parties agree as follows:
MODIFICATION: FIRST RENEWAL OPTION PERIOD
Pursuant to the Contract, a new Construction Task Catalog® will be furnished on the anniversary of the
solicitation and will be in effect for the twelve (12) month period after the anniversary of the award
date. The following is the Construction Task Catalog® for the next option period:
April 2021: Sourcewell Georgia, Northern
Pursuant to the agreement between the parties, the Adjustment Factors shall remain fixed for the
duration of the contract and are as follows:
#GA-A04-040820-SCL Adjustment Factor
Non Pre-priced 1.2595
Normal Working Hours – Non Secure Areas 1.1622
Normal Working Hours - SecureAreas 1.2000
Other Than Normal Working Hours - Non Secure Areas 1.2324
Other Than Normal Working Hours - Secure Areas 1.2649
EXERCISE OF OPTION: EXTENSION
Contractor and Sourcewell hereby desire and agree to extend and renew the above defined contract,
with the above identified amendment and modifications, for the period of April 20, 2021 through April
19, 2022.
Sourcewell
By:____________________________________, Its: __________Chief Procurement Officer___________
Name printed or typed: _____________Jeremy Schwartz____________________________
Date: ________________________________
Striker Contracting - #GA-A04-040820-SCL
By:____________________________________, Its: _______________________________________________
Name printed or typed: ________________________________________________________
Date: ________________________________
If you do not want to extend the contract, please sign below and return this agreement.
Discontinue: We desire to discontinue the contract.
Signature:___________________________________________ , Date:__________________________
ANNUAL RENEWAL AND MODIFICATION OF CONTRACT
Striker Contracting, LLC (“Vendor”)
2859 Paces Ferry Road Suite 1750
Atlanta, Georgia 30339
and
Sourcewell
202 12th Street NE
Staples, MN 56479
Whereas: Vendor and Sourcewell have entered into Contract GA-A04-040820-SCL with an effective date of
April 20, 2020, a maturity date of April 19, 2024, and which is subject to annual renewal at the option of both
parties.
MODIFICATION: OPTION PERIOD 4/20/22 – 4/19/23
Pursuant to the agreement between the parties, a Construction Task Catalog® (CTC) will be furnished on the
anniversary of the solicitation and will be in effect for the twelve (12) month period after the anniversary of
the award date. The following is the CTC for the option period April 20, 2022 through April 19, 2023:
April 2022 - Sourcewell, Georgia Northern Area
Pursuant to the agreement between the parties, the Adjustment Factors remain fixed for the duration of the
contract.
Now Therefore:
Vendor and Sourcewell hereby desire and agree to extend and renew the Contract and with the above
identified modification for the period of April 20, 2022 through April 19, 2023.
Sourcewell Striker Contracting, LLC
By: __________________________ By: __________________________
Jeremy Schwartz
Title: Chief Procurement Officer Title:
Date: ________________________
Date: ________________________